IBM Maximo Asset Management Scheduler 7.5.1
Release Date: July 27, 2012
Pedro Solfa Spadacini - Test Software Engineer
IBM Software Group, Tivoli
Phone: +55-11-2927-1229
E-mail: [email protected]
© 2012 IBM Corporation2
Agenda
� What Makes Up Scheduler 7.5.1
� Scheduler – Revised Approach to Work Management
� Introduction to Maximo Scheduler
� The Planner & Scheduler
� Graphical Assignment
� Field Work Management the Dispatcher
� Project Summary
� Customer Interaction
� Work Management
� Scheduler -Relevant Roles
� Time Phased Functional Utilization
� Dispatcher Use Cases
� Field Technician Use Cases
� Conclusion
� Questions
© 2012 IBM Corporation3
What Makes Up Scheduler 7.5.1
Investing in the natural evolution of our current products in a direction desired by
our customers
Enhancements to Scheduler
– Graphical Assignment/Dispatching
– Provision of standard Work Order actions
– Additional Resources
• Assets/Locations
• Labor
• Tools
• Materials
– Schedule Compliance
Enhancements to Maximo
– Service Addresses
– Public Map UI Control
– Crews
Maximo Everyplace role based templates
All included as Maximo Scheduler 7.5.1
© 2012 IBM Corporation4
Scheduler – Revised Approach to Work Management
� It is a means for labor assignments to be made
� It is a Dispatching application where the location of Crews and Labor, and the progress of work can all be monitored
� It is Maximo Everyplace templates designed to make the job of the field technician all that much easier
Not just a Planning & Scheduling Tool !
© 2012 IBM Corporation5
Maximo Scheduler 7.5.1 - Introduction
� Extends work management in Maximo satisfying the needs of Planners, Schedulers, Dispatchers and Mobile Field Technicians.
� Target market: Utilities, oil & gas, municipal governments or any customers requiring EAM with work management tools.
� Key differentiator: No integration with third party products. EAM, Planning and Scheduling integrated in just one solution, reducing time to value.
� Efficient work scheduling and execution based on: availability of asset, tools, materials and graphical assignment.
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Maximo
Maximo Scheduler
Installed when Maximo 7.5 is installed
• Enabled by the Scheduler license key• Pre-req of 7.5.0.3 fix pack
What is Maximo Scheduler?
Scheduler is anadd-on product to Maximo
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
The Planner & SchedulerThe Planner & Scheduler
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Schedule Compliance
The ability to show Target, Scheduled and Actual Dates on the Gantt chart
� Allows Planners & Schedulers to get a view of how work is progressing, and the affect of the
progress on related work
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Asset & Location Availability
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Material AvailabilityOther Resource Availability tab shows:
� Maintenance/Operational/Calendar availability of Asset and Location
� Material Availability for planned materials
� Shows required quantity vs available quantity
� Green bar shows materials are available, red bar shows materials are unavailable
� Planners & Schedulers know when not to schedule work based on material availability
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Additional Actions Work Order Actions
– Allow status changes on multiple
work orders/tasks
Additional Toolbar Buttons
– Zoom to Week
– Go To Day
– Constrain horizontal scrolling to the
date range containing work
– Filter resources based on selected
work orders
– Show/Hide Compliance
– Full Screen
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Schedule Cost Tab
Calculate costs within schedule by week, month and year
� Illustrate Committed and Saved Estimated Labor, Materials, Services and Tools, as well
as Actual Labor, Materials, Service and Tools
� Allows budget adherence
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Graphical AssignmentGraphical Assignment
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Graphical AssignmentNew application aimed at the process of assigning work to people
– Similar UI to Scheduler Gantt view for consistency
– Helps the Planner & Scheduler see non work time for a resource, as well as assignments made by other Foremen
beyond the bounds of their schedule… eliminates duplicate labor assignments
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Making an AssignmentAllows the Foreman to:
� Split Work According to Shifts, might be used if extending duration of the assignment across an
end of shift
� Split Work, once split can drag second assignment to add a time gap
� Split Work into Three Records, creates two additional assignments
� Create Assignment
� Delete Assignment
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Field Work ManagementField Work ManagementThe DispatcherThe Dispatcher
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential17
Scheduler Features for Field Work Management
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Dispatch View
� Dispatcher views the map with applicable Crew or Resource routes as defined by assignments.
Calendar View Map View
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Map Overview� New Map Control
– Configurable
– Everyplace enabled
� Map Providers
– Google Maps
– Bing Maps
– ESRI with Maximo Spatial
� Map tools
– Unassigned WOs
– Nearby labors and crews
– Layer/symbology selection
� Geolocation
– Labor / Crew tracking
Route
Work Order
Crew
Maptip
Actions
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential20
Labor & Crew Geo-location Tracking
� Browser geo-location API tracks the user
� based on Crew or Labor “Location Refresh” field
� data stored in LBSLOCATION table
� OOTB user is only tracked when in one of the Scheduler
Everyplace applications.
Red last update accuracy is over the limit
Yellow last update outside 60 mins
Blue when last update was within 60 mins
Configurable on these system properties:
mxe.lbs.lastupdate.tolerance
mxe.lbs.maximumAccuracy
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
The Mobile Field TechnicianThe Mobile Field Technician
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Field Technician Application
Field Technician’s Work Order Route
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Field Technician Application – My Work
Field Technician’s Street Level Route
Field Technician’s Material Requirements
Field Technician’s Tool Requirements
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Field Technician Application – Details
Toolbar Actions:• Query Tools• New / Follow-up Work Order• Status Change• Stop / Start Timers• Attach Documents
View work order details
Template version: SWG IPD V5.5.1 (Jul 2010)
SWG CPA DCP Template
IBM Confidential
Field Technician Application – ResultsLabor, Materials,
Tools, Failure Reporting and Work
Log results.
© 2012 IBM Corporation26
Project Summary
Customer Interaction with product validation
11 customers, 5 Business Partners, ISST & GBS, Sprint demos, Business Partner Meetings, User Group Conferences, Hosted and on-site Beta program.
Revenue: Projected $4M in incremental Scheduler revenue over next 5 years, plus significant Maximo drag revenue.
Pricing: Increase from $1060 to $1590 per authorized user.
Competitive Posture
4 gaps addressed; on par or leading in all Scheduler areas except Appointment Booking and CRM integration (strategically not planning to address).
What was delivered
Map ControlService AddressesCrewsMobile applications with mapping and work details (w/ Maximo Everyplace)
Graphical AssignmentSchedule ComplianceDispatchingAsset, Location AvailabilityWork order actions in Scheduler
Gaps addressed
� Map Control - GIS
� Graphical Assignment
� Viewing of work, route, directions, by planner, foreman, field technician
� Schedule and resource optimization
Focus on product usability
© 2012 IBM Corporation27
Customers
Customer Demand
Maximo customers have requested advanced planning & scheduling tools to eliminate the need for third party product integrations (CIM, Akwire, Click, Servigistics, TOA, etc.)
Where customers have attempted to meet their requirements with a true FSM product (Click, TOA), they have had to invest inreducing it’s functionality to meet their business requirements.
Positioning
Where a customers requirements demand a true FSM product, we will defer to Click Software.
We do not ever intend to include the FSM specific elements into our solution, or compete in true FSM opportunities. We have onlytaken the steps to expand the footprint of our existing product in ways demanded by our customers.
Agile Client Interaction List
� City of Henderson
� City of Cambridge
� City of Corpus Christi
� City of Lakeland
� Baltimore Gas & Electric
� DTE Energy
� Salt River Project (SRP)
� Portland General Electric
� Deutsche Telekom
� Eli Lilly
� General Mills
Customer Checkpoints
� Sprint demos
� Dev. Partner Meetings
� User Group Conferences
� Beta workshops
© 2012 IBM Corporation28
Work ManagementLogical Hands-off
Schedule Created
Project, demand, & forecasted work
Assignments made
Crafts & skills validated
Absences & vacation respected
Field tech sees assigned route on a map
See locations of neighboring crews
Feedback on work status & progress
Assigned routes visible on a map
New work may easily be assigned based on proximity of labor
Scheduler
Graphical Assignmen
t
Dispatching
Maximo Everyplace
© 2012 IBM Corporation29
Scheduler - Relevant Roles
Planner/Scheduler
Dispatcher
Mobile Workforce
� Receive work orders in the field
� Provide real time status updates to dispatch
� Request supplementary information from the
back-office
� Review work orders on the mobile map, along
with optimal driving directions
� Notify dispatch of potentially dangerous
situations
� Complete, edit and approve work orders
� Sequence and route work
assignments based on
geography
� Monitor technician and work
order progress and status
� Monitor the location of field
resources compared to open
work orders
� Dispatch emergent work to
the proper resource.
� Define and adjust
technician/crew availability
along with resource
leveling
� Capacity Planning
� Assign work orders to
technicians
� Continuously optimize the
schedule as the operational
environment changes
� Sequence and route work
assignments based on
geography
© 2012 IBM Corporation30
Time Phased Functional Utilization
PM Forecasting
WO Scheduling
ResourceAssignment
DispatchingField
Technician
Years to Months Weeks 1-7 Days 1-3 Days
Forecast Schedule MobileDispatch
PM Application
Scheduler and
Graphical Assignment
Graphical Assignment
Everyplace Applications
© 2012 IBM Corporation31
Dispatcher Use Cases
Dispatcher
� Assignment of work for crews and labors has been completed for the following week.
� On Monday morning Bill calls in sick – Ford is re-assigned Bill’s work for the day
� View progress of work out in the field as it becomes completed throughout the day.
� New emergent work comes in – Determine who is in the area of the emergency work and is available.– Assign the work to a crew – it automatically becomes part of their route.
© 2012 IBM Corporation32
Field Technician Use Cases
Mobile Field Technician
� View list of Work Orders assigned on a tablet device– View street-level route and the driving directions– View nearby labor/crews
� Display streamlined Work Order information along with start/stop timer to complete work.
� New emergent work is assigned to the field technician– View updates to the work list along with a new SLR for the day
� The work day is not going as planned – (a) Finished assigned work early – need to find other work in area to fill rest of day– (b) Unexpected delay in an assignment - not going to finish all of today’s assigned work– need to collaborate with dispatch to reassign the rest of work.
© 2012 IBM Corporation33
Future
� Schedule optimization (Integration with ILOG)
− On-going work with Watson and Haifa Research teams.
� Routing optimization based on weather feeds, manual input, environment changes
− Use case: when a road gets blocked by snow, route should adapt
� Linear assets and linear referencing integration
� Network Tracing (Ex: Which area is affected if I close a valve)
� GIS analytics and geo processing
Service Area
Ex: areas reached in 1min, 2min and 3min drive
Linear referencing
Viewshed analysis
Ex: areas that can be seen from observation points
© 2012 IBM Corporation34
DEMO
� Let's see a quick demo !
� http://ibm-931cf5a1b7d:7001/maximo/webclient/login/login.jsp
© 2012 IBM Corporation35
Conclusion
� Maximo Scheduler was created to
� Plan, Scheduling and Assign future work taking in consideration relationships, restrictions, availability and skills.
� Drag & Drop work assignments, quick and easy
� Visualize field crews
� Using a new map control to visualize and execute actions from the map.
� To monitor on going work
� Manage crews, work and their routes
� Improve crew and labor efficiency
� Using maps to visualize the route for the daily work
� Dynamic work list based on manual or automatic assignment (optimization)
� Improve near by labors communication
� Update work orders from the field, with mobile devices
© 2012 IBM Corporation36
Questions?