Presented at ACCU 2014 (accu.org) Are estimates an essential part of project planning and delivery or a waste of everybody's time? As is so often the case the answer is neither and both. In this session we discover that there is more than one kind of estimate and examine how they are typically used in an agile context. We look at what some of the great minds have said on the subject, from Steve McConnell to Demarco and Lister. We'll also consider the need for estimates from the viewpoint of the business people who have to decide whether a project proposal should receive budget. Picking up the 'No Estimates' discussion from Twitter, we'll see if there's a case to be made for always refusing to provide estimates or whether there are times that some sorts of estimation is valuable. I may not change your mind, but I intend to widen your perspective.

Citation preview

Page 1: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Lies, damn lies and estimates

Seb RoseClaysnow Limited

www.claysnow.co.uk

@sebrose

Tuesday, 15 April 14

Page 2: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 3: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

DISRAELI

Tuesday, 15 April 14

Page 4: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 5: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 6: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 7: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 8: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 9: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

I’ll be back tomorrow to finish off

You’ll be in by Christmas

That will be fixed before we

leave

All our previous customers are

completely satisfied

We don’t make mistakes like other

builders

You won’t notice we’re there

Tuesday, 15 April 14

Page 10: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Your companyNEEDS

that estimatesoonnowyesterday

(Of course we won’t hold you to it)

Tuesday, 15 April 14

Page 11: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

The project status is still green

We’re 90% doneWe will deliver

with zero defects

On time, on budget every project

It’s working in the test environment

Integration takes hardly any

time

Tuesday, 15 April 14

Page 12: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Prediction is very difficult,

especially about the future.

Niels Bohr, physicistTuesday, 15 April 14

Page 13: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 14: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

The primary purpose of an estimate is not to predict a project’s outcome;

it is to determine whether a project’s targets are realistic enough to allow the project to be controlled to meet them.

Steve McConnell, Software Estimation (2006)

Tuesday, 15 April 14

Page 15: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

6. Introduction to Estimation Techniques7. Count, Compute, Judge8. Calibration and Historical Data9. Individual Expert Judgement10. Decomposition and Recomposition11. Estimation by Analogy12. Proxy-Based Estimates13. Expert Judgement in Groups14. Software Estimation Tools15. Use of Multiple Approaches16. Flow of Software Estimates on a Well-

Estimated Project17. Standardized Estimation Procedures

Part II - Fundamental Estimation Techniques

Tuesday, 15 April 14

Page 16: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 17: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 18: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

The Cone of Uncertainty in Project Management

Tuesday, 15 April 14

Page 19: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 20: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Overconfidence

Tuesday, 15 April 14

Page 21: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

For each of the next 10 quantitative questions, give a lower and an upper bound,

such that you believe with about 90% certainty that the

correct answer lies within the interval given.

This means that you should expect to guess correctly for about 9 questions out of 10.

Laurent Bossavit, www.bossavit.com, @morendil

Tuesday, 15 April 14

Page 22: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Example:

Q. How many people are in this room?

You ‘guess’ an interval:Low: 30, High: 100

Tuesday, 15 April 14

Page 23: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What was the date of birth of Bram Stoker, author of Dracula?

Question 1:

Tuesday, 15 April 14

Page 24: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What is the population of the Republic of Brazil?

Question 2:

Tuesday, 15 April 14

Page 25: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What is the height, in meters, of the tallest living redwood tree?

Question 3:

Tuesday, 15 April 14

Page 26: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How many standardized (ISO 6346) steel shipping containers exist in the world?

Question 4:

Tuesday, 15 April 14

Page 27: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How many Boeing 747 (all models) have been built at this date?

Question 5:

Tuesday, 15 April 14

Page 28: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What is the total number of human deaths attributed to H5N1 “avian” flu?

Question 6:

Tuesday, 15 April 14

Page 29: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How many Syrian conflict refugees were registered by UNHCR as of 1 Nov 2012?

Question 7:

Tuesday, 15 April 14

Page 30: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What was the total wine production of France in 2009, in hectolitres?

Question 8:

Tuesday, 15 April 14

Page 31: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How many Olympics medals altogether have been won to date by Austrian athletes?

Question 9:

Tuesday, 15 April 14

Page 32: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

What is the half-life, in years, of the isotope Plutonium 239?

Question 10:

Tuesday, 15 April 14

Page 33: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

1) 18472) 199 million3) 115 meters4) 20 million5) 14866) 3797) 286,0008) 45 million hectolitres9) 30410) 24 thousand years

Tuesday, 15 April 14

Page 34: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How did you do?

Tuesday, 15 April 14

Page 35: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

"We aren't really bad at estimating.

What we are really bad at is enumerating all the assumptions that lie behind our estimates."

-Paul Rook

Tuesday, 15 April 14

Page 36: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014 Why do we estimate?

Tuesday, 15 April 14

Page 37: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Forecasting

Tuesday, 15 April 14

Page 38: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tracking

Tuesday, 15 April 14

Page 39: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 40: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

“A boundary object is a concept in sociology to describe information used in different ways by different communities. They are plastic, interpreted differently across communities but with enough immutable content to maintain integrity”

--Wikipedia

Estimates are Boundary Objects

Tuesday, 15 April 14

Page 41: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

“They are weakly structured in common use, and become strongly structured in individual-site use. They may be abstract or concrete.

They have different meanings in different social worlds but their structure is common enough to more than one world to make them recognizable means of translation.

The creation and management of boundary objects is key in developing and maintaining coherence across intersecting social worlds.”

-- Leigh & Griesemer

Tuesday, 15 April 14

Page 42: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

http://leadinganswers.typepad.com/leading_answers/files/original_waterfall_paper_winston_royce.pdf

The original “waterfall” paper - Winston Royce, 1970

Tuesday, 15 April 14

Page 43: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 44: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 45: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 46: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 47: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

How long is a piece of string?

Tuesday, 15 April 14

Page 48: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 49: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

120 cm100 cm70 cm60 cm40 cm

E.D.C.A.B.

Tuesday, 15 April 14

Page 50: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

... these studies which have for a few years now given rise to the claim that "research shows that people are better at relative than absolute estimation" do not in fact seem to square with that claim.

This doesn't entail that relative estimation doesn't work - only that it is not proven.

http://guide.agilealliance.org/guide/relative.html

Tuesday, 15 April 14

Page 51: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 52: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

12 cm10 cm7 cm6 cm4 cm

E.D.C.A.B.

Tuesday, 15 April 14

Page 53: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Is it small, or just far away?

Tuesday, 15 April 14

Page 54: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 56: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

“If a project has no risks, don’t do it.”

“Waltzing with bears”, DeMarco & Lister, 2003

Tuesday, 15 April 14

Page 57: Lies, damn lies, estimates

There are known knowns; there are things we know that we know.

There are known unknowns; that is to say there are things that, we now know we don't know.

But there are also unknown unknowns – there are things we do not know we

don't know.

Tuesday, 15 April 14

Page 58: Lies, damn lies, estimates

ASSUME YOU'RE

IGNORANTTuesday, 15 April 14

Page 59: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

“... during an inception, when we aremost ignorant

about most aspects of the project,the best use

we can possibly make of the time available is to attempt to

identify and reduceour ignorance”

http://dannorth.net/2010/08/30/introducing-deliberate-discovery/

Deliberate discovery

Tuesday, 15 April 14

Page 60: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

1. Just about everyone in the world has done this.

2. Lots of people have done this, including several people in the company.

3. Someone in our company has done this.4. Someone in the world did this, but not in

our organisation (and probably at a competitor).

5. Nobody has ever done this before.

http://lizkeogh.com/2013/07/21/estimating-complexity/

Estimating Complexity

Tuesday, 15 April 14

Page 61: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Dave Snowden, released under CC BY 3.0

Cynefin

Tuesday, 15 April 14

Page 62: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

http://www.tylerjanderson.com/case-study-roi-of-facebook-advertising/Tuesday, 15 April 14

Page 63: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

ROI = x 100(Investment Gain - Investment Cost)

(Investment Cost)

Tuesday, 15 April 14

Page 64: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Impact mapping

http://impactmapping.org/about.php

Tuesday, 15 April 14

Page 65: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Tuesday, 15 April 14

Page 66: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Cost of delay

http://blackswanfarming.com/cost-of-delay/

... is a way of communicating the impact of time on value.

Tuesday, 15 April 14

Page 67: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Cost of delay

http://blackswanfarming.com/cost-of-delay/

1.Better Decision-making – by making the economic trade-offs visible

2.Better Prioritisation – by using CD3 (Cost of Delay Divided by Duration) we deliver more total value

3.By changing the focus – from efficiency and cost (which encourages the wrong behaviours), to speed and value

Tuesday, 15 April 14

Page 68: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

#NoEstimates

http://neilkillick.com/2013/02/08/noestimates-part-2-contract-negotiation-and-the-old-banger/

http://neilkillick.com/2013/01/31/noestimates-part-1-doing-scrum-without-estimates/

Remove the unknownsEstimating sprint velocity is wasteIterate, don’t estimateShift focus to “small”

Agile team, same old contractQuality is variable, not fixedDon’t deliver requirements, deliver what the customer wants

Tuesday, 15 April 14

Page 69: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

... crying “No estimates,

no backlogs, no deadlines”

... [is] not very effective nor efficient.

http://xprogramming.com/articles/artifacts-are-not-the-problem/

Tuesday, 15 April 14

Page 70: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Done conventionally, software projects offer almost no information, and almost no control, to those who are given the responsibility to manage them.

... the people in charge of spending money to get software really do need control and information.

Saying “no” doesn’t help them.

http://xprogramming.com/articles/artifacts-are-not-the-problem/

Tuesday, 15 April 14

Page 71: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Giving software projects an API

... [is] about “yes, yes, yes”.

http://xprogramming.com/articles/artifacts-are-not-the-problem/

Tuesday, 15 April 14

Page 72: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

All models are wrong,

but some are useful

George Box, statisticianTuesday, 15 April 14

Page 73: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Dear Customer

... when we start an IT project, we don’t know how much time and effort it will take to complete.

Consequently, we don’t know how much it will cost.

http://www.agileconnection.com/article/dear-customer-truth-about-it-projects?page=0%2C0Tuesday, 15 April 14

Page 74: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Dear Customer

http://www.agileconnection.com/article/dear-customer-truth-about-it-projects?page=0%2C0

... the more details you try to give us beforehand, the more likely your desires are to change.

Each time you give us more detail, you are offering more hostages to fortune.

Tuesday, 15 April 14

Page 75: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

“Old fogies knowyour estimates will be bogus.

They know youwon’t

get them right.

They know youwon’t

hit the deadline with full scope”

http://xprogramming.com/articles/artifacts-are-not-the-problem/

Tuesday, 15 April 14

Page 76: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Challenge the use of estimates - understand its value

Estimates are not commitments - make this crystal clear

Is it small or just far away - ignorance is the major constraint

Take aways

Tuesday, 15 April 14

Page 77: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

-JVM

Seb Rose,

Availa

ble 20

14

(hopef

ully)

Tuesday, 15 April 14

Page 78: Lies, damn lies, estimates

Seb  Rose

Twi$er:     @sebrose

Blog:       www.claysnow.co.uk

E-­‐mail:     [email protected]

Tuesday, 15 April 14

Page 79: Lies, damn lies, estimates

© C

lays

now

Lim

ited

2014

Estimates produced before a project starts are lies about how much something will cost, usually tailored depending on whether the source of the estimate wants the project to go ahead or not.

Estimates produced once a project has started are lies that compensate for the inaccuracies of earlier estimates.

Both contribute towards an illusion of control that is no more real in software than it is in civil engineering.

http://accu.org/index.php/journals/1836