of 27 /27
COST CONCEPTS AND DESIGN ECONOMICS INSPIRING CREATIVE AND INNOVATIVE MINDS

Lecture2

Embed Size (px)

DESCRIPTION

for nordin omar"s student(UTM)

Text of Lecture2

  • 1. COST CONCEPTS AND DESIGN ECONOMICS INSPIRING CREATIVE ANDINNOVATIVEMINDS

2. COST ESTIMATING USED TO

  • Provide information used in setting a selling price for quoting, bidding, or evaluating contracts
  • Determine whether a proposed product can be made and distributed at a profit (EG: price = cost + profit)
  • Evaluate how much capital can be justified for process changes or other improvements
  • Establish benchmarks for productivity improvement programs

3. COST ESTIMATING

  • Used to describe the process by which the present and future cost consequences of engineering designs are forecast

4. COST ESTIMATING APPROACHES

  • Top-down Approach
  • Bottom-up Approach

5. TOP-DOWN APPROACH

  • Uses historical data from similar engineering projects
  • Used to estimate costs, revenues, and other parameters for current project
  • Modifies original data for changes in inflation / deflation, activity level, weight, energy consumption, size, etc
  • Best use is early in estimating process

6. BOTTOM-UP APPROACH

  • More detailed cost-estimating method
  • Attempts to break down project into small, manageable units and estimate costs, etc.
  • Smaller unit costs added together with other types of costs to obtain overall cost estimate
  • Works best when detail concerning desired output defined and clarified

7.

  • Fixed cost : unaffected by changes in activity level
  • Variable cost : vary in total with the quantity of output (or similar measure of activity)
  • Incremental cost : additional cost resulting from increasing output of a system by one (or more) units

Costs can be categorized in several different ways. 8.

  • Direct : can be measured and allocated to a specific work activity
  • Indirect : difficult to attribute or allocate to a specific output or work activity (alsooverheadorburden )
  • Standard cost : cost per unit of output, established in advance of production or service delivery

9.

  • Opportunity cost : the monetary advantage foregone due to limited resources.The cost of the best rejected opportunity.
  • Life-cycle cost : the summation of all costs related to a product, structure, system, or service during its life span.

10.

  • Cash cost: a cost that involves a payment of cash.
  • Book cost: a cost that does not involve a cash transaction but is reflected in the accounting system.
  • Sunk cost: a cost that has occurred in the past and has no relevance to estimates of future costs and revenues related to an alternative course of action.

11.

  • Investment Costor capital investment is the capital (money) required for most activities of the acquisition phase;
  • Working Capitalrefers to the funds required for current assets needed for start-up and subsequent support of operation activities;
  • Operation and Maintenance Costincludes many of the recurring annual expense items associated with the operation phase of the life cycle;
  • Disposal Costincludes non-recurring costs of shutting down the operation;

CAPITAL ANDINVESTMENT 12.

  • Overheadconsists of plant operating costs that are not direct labor or material costs
    • indirect costs, overhead and burden are the same;
  • Prime Cost is a common method of allocating overhead costs among products, services and activities in proportion the sum of direct labor and materials cost ;

DIRECT, INDIRECT AND OVERHEAD COSTS 13. STANDARD COSTS

  • Representative costs per unit of output that are established in advance of actual production and service delivery;
  • Standard Cost Element Sources of Data
  • Direct Labor Process routing sheets,+ standard times, standardlabor rates;
  • Direct Material Material quantities per+ unit, standard unitmaterials cost;
  • Factory Overhead Costs Total factory overheadcosts allocated based onprime costs;

14. Figure 2-1 15. The Life Cycle Cost

  • The Life Cycle divided into 2 general time period
  • Acquisition Phase
  • Operation Phase

16. Acquisition Phase

  • Analysis of economic need
  • Conceptual design
    • Defined technocal and operational requirements
    • Development of feasible alternatives
    • Advance development and prototype-testing

17. Acquisition Phase

  • 3. Detailed design
    • -activities to prepare, acquire and make ready for operation

18. Operation Phase

  • Production, delivery or construction of the end item
  • Operation and customer use
  • Retirement from active operation or use

19. Fixed and Variable Cost

  • AFixed Cost (FC)is any cost that does not vary in proportion to the quantity of output.
    • Examples include rent, depreciation, lighting,and supervisor salaries.
    • Fixed Costs are commonly fixed only over a certain range of production, called therelevant range .
    • For example supervisor salaries or lighting are fixed for one shift operation but step to a new higher level for two shift operation.
    • Successive relevant ranges are often represented graphically as a step function.

20. Fixed and Variable Cost

  • AVariable Cost (VC)is a cost that varies in proportion to the quantity of output.
    • Common examples include direct materials and direct labor.
    • Variable Costs are often represented as a linear function of output
      • VC(q) = rate * q; where q is the level of production
  • Total Costis the sum of fixed costs and variable costs
    • TC(q) = FC + VC(q)

21. Total Costs

  • Adding the same amount of total fixed cost to every level of total variable cost yields total cost.
  • For this reason, the total cost curve has the same shape as the total variable cost curve; it is simply higher by an amount equal toTC .
  • TC(q) = FC + VC(q)

22. Revenue

  • Price x Quantity
  • P x q

23. Breakeven

  • Total Revenue (TR)is the sum of revenues received for the units sold.
  • Total Revenue is often represented as a linear function of units sold.
      • TR(q) = price * q; where q is the number of units sold
  • If steady state inventory is assumed then units sold will be equal to the units produced.
  • The point ofBreakeven , where total costs equal total revenues, can be found by solving:
    • TR(q) = FC + VC(q)

24. Breakeven Graph Profit Loss 25. Significance of Breakeven

  • If production (sales) is less than breakeven, a loss will occur.
  • If production (sales) is greater than breakeven, a profit will occur.
  • Lower values of the breakeven quantity are generallydesirable.
  • Lower values can be achieved by:
    • increasing the revenue rate (the slope of the revenue line),
    • decreasing the variable cost rate (the slope of the total cost line),
    • reducing the fixed cost (the intercept of the total cost line).
  • Engineering Economy projects frequently target one of these areas for improvement

26. Example

  • Determination of breakeven value
  • R(q) = $5.00(q)
  • FC = $300
  • VC(q) = ($2.50+$1.00)(q) = $3.50(q)
  • Breakeven:
    • R(q) = FC + VC(q)
    • $5.00(q) = $300 + $3.50(q)
    • x = 200 units

27.

  • Net Profit for a lot size of 1,000 units
  • Profit (Loss) = TR(q) TC(q)
    • = TR(q) (FC + VC(q))
    • = TR(q) FC VC(q)
    • = $5.00(q) - $300 - $3.50(q)
    • = $5.00(1,000) - $300 - $3.50(1,000)
    • = $1,200 profit