% Complet Task Name Finish Resource Names 100% XYZ Company Data Center Re-Location to CO-LO Facility Sat 5/18/13 100% Order MPLS betwwen HQ & CO-LO Facility Tue 1/1/13 XYZ Emp.#1 100% MPLS Installed & Tested Fri 3/1/13 Carrier 100% Order Router Tue 1/1/13 XYZ Emp #2 100% Router Installed, Configured & Tested at CO-LO Facility Fri 3/8/13 XYZ Emp.#1 100% Create From and To Hardware & Network Plan Sat 1/26/13 XYZ Emp.#1 100% Create RFP for Hardware Movers and send out Sun 2/3/13 TKO,Sr. MGMT 100% Project Team Kickoff Fri 2/8/13 Mover,Physical Movers,Sr. MGMT,XYZ Emp #2,XYZ Emp.#1,TKO 100% Evaluate and Execute Hardware Mover Contract Wed 2/27/13 Sr. MGMT,TKO 100% Moving Company Internal Mobilization Wed 3/6/13 Physical Movers 100% Moving Company XYZ Company DC Relocation Materials Order & Receipt Tue 3/5/13 Physical Movers 100% Design Patch Matrix/BOM Development Complete Sat 3/9/13 Physical Movers 100% Order BOM and Delivered for Installation Complete Sun 3/10/13 Physical Movers 100% Destination Site Cable Pre Deployment Complete Fri 3/15/13 Physical Movers 100% QA Patch Matrix (20%) Mon 1/14/13 XYZ Emp.#1,TKO Task Split Milestone Summary Project Summary External Tasks External Milestone Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only Deadline Progress Page 1 Project: XYZ Company Data Cente Date: Thu 6/9/16

Keith odom sample microsoft project template data center move

Embed Size (px)

Citation preview

%

Complete

Task Name Finish Resource Names

100% XYZ Company Data Center Re-Location to CO-LO Facility Sat 5/18/13

100% Order MPLS betwwen HQ & CO-LO Facility Tue 1/1/13 XYZ Emp.#1

100% MPLS Installed & Tested Fri 3/1/13 Carrier

100% Order Router Tue 1/1/13 XYZ Emp #2

100% Router Installed, Configured & Tested at CO-LO Facility Fri 3/8/13 XYZ Emp.#1

100% Create From and To Hardware & Network Plan Sat 1/26/13 XYZ Emp.#1

100% Create RFP for Hardware Movers and send out Sun 2/3/13 TKO,Sr. MGMT

100% Project Team Kickoff Fri 2/8/13 Mover,Physical

Movers,Sr.

MGMT,XYZ Emp

#2,XYZ Emp.#1,TKO

100% Evaluate and Execute Hardware Mover Contract Wed 2/27/13 Sr. MGMT,TKO

100% Moving Company Internal Mobilization Wed 3/6/13 Physical Movers

100% Moving Company XYZ Company DC Relocation Materials Order

& Receipt

Tue 3/5/13 Physical Movers

100% Design Patch Matrix/BOM Development Complete Sat 3/9/13 Physical Movers

100% Order BOM and Delivered for Installation Complete Sun 3/10/13 Physical Movers

100% ‐Destination Site Cable Pre Deployment Complete Fri 3/15/13 Physical Movers

100% QA Patch Matrix (20%) Mon 1/14/13 XYZ Emp.#1,TKO

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 1

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Customer 1 Operation Backup, Down/UP Processes Tue 3/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 2 Operation Backup, Down/UP Processes Thu 3/7/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 3 Operation Backup, Down/UP Processes Sat 3/2/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 4 Operation Backup, Down/UP Processes Sat 3/9/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 5 Operation Backup, Down/UP Processes Fri 3/8/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 6, 7, 8, 9, and 10 Homed on same system Backup,

Operation Down/UP Processes

Sun 3/17/13 XYZ Emp.#1,XYZ

Emp #2

100% Order Redundant Firewall Fri 2/8/13 XYZ Emp.#1

100% Redundant Firewall Delivered Thu 2/14/13 XYZ Emp.#1

100% Install and Configure Redundant Firewall Fri 3/15/13 XYZ Emp.#1

100% Tue 1/1/13

100% Customer Migrations Tue 1/1/13

100% Tue 1/1/13

100% Customer 1 Migration - Also see XYZ

Migration 1 schedule at bottom of this plan

Fri 3/15/13

100% Notify Customer 1 Client of Plans Sat 1/26/13 Sr. MGMT,TKO

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 2

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Schedule Customer 1 Client Resources Fri 3/15/13 Sr. MGMT,TKO

100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Syms Backup Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% HMC Power Down all LPARS Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 1 Physical Migration Fri 3/15/13 Physical Movers

100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Run All "Missed" Jobs during Offline Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 1 Migration Window Complete Fri 3/15/13 Entire Team

100% Tue 1/1/13

100% Customer Migrations <continue> Tue 1/1/13

100% Customer 4 Migration Fri 3/22/13 Entire Team,TKO,Mon

1/14/13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 3

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO

100% Schedule Client Resources Sat 1/26/13 XYZ Emp.#1,XYZ

Emp #2

100% Operations: Backup, Power Down/Power Up Procedures Fri 3/22/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Backup Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2

100% End all System Processes and verify all jobs are stopped prior to shutdownFri 3/22/13 XYZ Emp.#1,XYZ Emp #2

100% Power down Customer 4 IDEAS/GUI Server Tue 1/1/13 XYZ Emp.#1

100% HMC Power Down all LPARS Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2

100% Customer 4 Physical Migration Fri 3/22/13 Physical Movers

100% Power Up Systems Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2

100% Test Conectivity and OPS Consoles Fri 3/22/13 XYZ Emp.#1,XYZ Emp #2

100% Verify "Stable State" Fri 3/22/13 XYZ Emp #2,Chris H.,XYZ Emp.#1

100% Customer 4 Migration Window Complete Fri 3/22/13 Entire Team

100% Run Missed Jobs – MSGSDIMSG and EOD Process Fri 3/22/13 XYZ Emp #2

100% Qinter Up – System available to users Fri 3/22/13 XYZ Emp #2

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 4

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Customer 2 Migration/Implementation Tue 4/2/13

100% Notify Client of Plans Sat 1/26/13 Sr. MGMT

100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT,XYZ

Emp.#1

100% Operations: Backup, Power Down Power Up Procedures Tue 4/9/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Full System Backup 1:00 am Monday Mon 4/1/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Intel Backups Mon 4/1/13 XYZ Emp.#1

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Sat 4/27/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Incremental backup Mon 4/1/13 XYZ Emp #2

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 5

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Power Down VMs Tue 4/2/13 XYZ Emp.#1

100% Power Down VM Host Tue 4/2/13 XYZ Emp.#1

100% Power Down AS400 System Tue 4/2/13 XYZ Emp.#1,XYZ

Emp #2

100% Power Down Network Equipment Tue 4/2/13 XYZ Emp.#1

100% Customer 2 Physical Migration Tue 4/2/13 Physical Movers

100% Power up Network Equipment Tue 4/2/13 XYZ Emp.#1

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 6

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Power up San Device Wed 4/3/13 XYZ Emp.#1

100% Power up FD-Bckup Server (Check San is up & Check network is

up)

Wed 4/3/13 XYZ Emp.#1

100% Power UP VM Host Wed 4/3/13 XYZ Emp.#1

100% Power up VM's Wed 4/3/13 XYZ Emp.#1

100% Power on the HMC Managed Server Wed 4/3/13 XYZ Emp #2

100% Power on the Systems – FLDMMS first- Wait for *NWS – others

can go

Wed 4/3/13 XYZ Emp #2

100% Power on Tape Drives Wed 4/3/13 XYZ Emp #2

100% Test Conectivity and OPS Consoles Wed 4/3/13 XYZ Emp.#1,XYZ

Emp #2

100% Run missed schedules on FLD side (E3) Wed 4/3/13 Customer 2

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 7

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Run All "Missed" Jobs during Offline Wed 4/3/13 XYZ Emp.#1,XYZ

Emp #2

100% Verify "Stable State" Wed 4/3/13 XYZ Emp.#1,XYZ

Emp #2

100% Custome 2 Migration/Implementation Window Complete Wed 4/3/13 Entire Team

100% Customer 5 Migration Wed 3/20/13

100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 8

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Schedule Client Resources Mon 1/14/13 TKO,Sr. MGMT

100% Operations: Backup, Power Down/Power Up Procedures Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Backup Thu 4/4/13 XYZ Emp.#1,XYZ

Emp #2

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% HMC Power Down all LPARS Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 5 Physical Migration Fri 4/5/13 Physical Movers

100% Test Conectivity and OPS Consoles Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Run All "Missed" Jobs during Offline Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Run HW Test for Drives, Connect, etc. Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Verify "Stable State" Fri 4/5/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 5 Migration Window Complete Tue 3/19/13 Entire Team

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 9

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Customer 3 Migration Sun 4/28/13

100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO

100% Order Client Links Mon 1/21/13 XYZ Emp.#1,XYZ

Contact

100% Links Installed & Ready Sat 3/16/13 Carrier

100% CO-LO Cross Connect Sat 3/23/13 Data Center Co_Lo

100% Schedule Carrier for Migration Date Sat 3/2/13 TKO,XYZ Emp.#1

100% Schedule Client Resources Fri 3/15/13 TKO,Sr. MGMT

100% Operations: Backup, Power Down/Power Up Procedures Sat 4/27/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Backup Sat 4/6/13 XYZ Emp.#1,XYZ

Emp #2

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Sun 4/7/13 XYZ Emp.#1,XYZ

Emp #2

100% HMC Power Down all LPARS Mon 4/8/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 3 Physical Migration Sun 4/7/13 Physical Movers

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 10

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Test Conectivity and OPS Consoles Mon 4/8/13 XYZ Emp.#1,XYZ

Emp #2

100% Run All "Missed" Jobs during Offline Sun 4/7/13 XYZ Emp.#1,XYZ

Emp #2

100% Run HW Test for Drives, Connect, etc. Sun 4/7/13 XYZ Emp.#1,XYZ

Emp #2

100% Verify "Stable State" Sun 4/7/13 XYZ Emp.#1,XYZ

Emp #2

100% Customer 3 Migration Window Complete Sun 4/7/13 Entire Team

100% Shared Equipment (SE) Migration (Customers 6, 7, 8, 9 and

10)

Wed 5/1/13

100% Notify Client of Plans Sat 1/26/13 Sr. MGMT,TKO

100% Schedule Client Resources Tue 1/1/13 XYZ Emp.#1,XYZ

Emp #2

100% Operations: Backup, Power Down Power Up Procedures Tue 4/30/13 XYZ Emp.#1,XYZ

Emp #2

100% Perform Backup Thu 4/11/13 XYZ Emp.#1,XYZ

Emp #2

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Fri 4/12/13 XYZ Emp.#1,XYZ

Emp #2

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 11

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% HMC Power Down all LPARS Fri 4/12/13 XYZ Emp.#1,XYZ

Emp #2

100% SE Physical Migration Sat 4/13/13 Physical Movers

100% Test Conectivity and OPS Consoles Sat 4/13/13 XYZ Emp.#1,XYZ

Emp #2

100% Run All "Missed" Jobs during Offline Sat 4/13/13 XYZ Emp.#1,XYZ

Emp #2

100% Run HW Test for Drives, Connect, etc. Sat 4/13/13 XYZ Emp.#1,XYZ

Emp #2

100% Verify "Stable State" Sat 4/13/13 XYZ Emp.#1,XYZ

Emp #2

100% (SE) Migration Window Complete Sat 4/13/13 Entire Team

100% Customer XYZ Migration #2 Sun 4/21/13

100% Notify Client of Plans / Normal Change Management Processes

Used

Fri 1/25/13 Sr. MGMT,TKO

100% Order Client Links (Megapath 3 T1's) Mon 1/21/13 XYZ Contact,TKO

100% Schedule Carrier for Migration Date Mon 1/21/13 Jay R.

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 12

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Schedule Client Resources Fri 2/22/13 John D.,Jay R.,Sr.

MGMT,TKO,XYZ

100% Links Installed & Ready Wed 3/20/13 Carrier

100% Co-Lo Cross Connect Wed 3/20/13 Data Center Co_Lo

100% Network Testing Complete Thu 3/21/13 John Doe

100% Perform AS400 Backup Fri 4/19/13 John Doe

100% FRMMS full backup Fri 4/19/13 XYZ

100% FRRI full backup Fri 4/19/13

100% Perform Windows Backup Fri 4/19/13 Jane May

100% Scheduled Windows Backup Fri 4/19/13 Jane May

100% End all System Processes and verify all jobs are stopped prior to

shutdown

Fri 4/19/13 John Doe,Jane May

100% Graceful Powerdown AS400 System Fri 4/19/13 Jay R.,John D.

100% Robot Jobs Identified - held Fri 4/19/13 John Doe

100% Outside Windows FTP servers Fri 4/19/13 John Doe

100% Windows Scheduled Jobs Off Fri 4/19/13 John Doe

100% Shutdown FRMMS/FRRI Fri 4/19/13 John Doe

100% Power down managed system (FRMMS) Fri 4/19/13 John Doe

100% Power down managed system (FRRI) Fri 4/19/13 John Doe

100% Power down HMC Fri 4/19/13 John Doe

100% Power down 2 Tape Libraries Fri 4/19/13 John Doe

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 13

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Graceful Powerdown Windows System Fri 4/19/13 Jane May

100% Power down VMs (5 mins to power down each VM) a. .18 subnet = XYZCenteraldev, XYZ-DNS,XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SALLOFri 4/19/13 Jane May

100% Power down physical VM Server (5 mins to power down each VM Host) a. Host 1 & Host2Fri 4/19/13 Jane May

100% Power down xyzintprod.servers.xyz 192.168.X.X IBM 3850 Fri 4/19/13 Jane May

100% Power Down xyzallocation.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 Jane May

100% Power down xyzentralprod.servers... 192.168.X.X System x3550 Fri 4/19/13 Jane May

100% Power down xyzinttest.servers.xyz 192.168.X.X System x3550

Fri 4/19/13 XYZ Emp.#1

100% Power down xyz-emn1-bk1.servers.xyz 192.168.X.X Fri 4/19/13 XYZ Emp.#1

100% Power down SAN devices (5 mins to power down SAN devices)Fri 4/19/13 XYZ Emp.#1

100% Physical Migration to Co-Lo except Credit Auth Fri 4/19/13 Physical Movers

100% Power down xyzisd.servers.xyz 192.168.0.X System x3550 Fri 4/19/13 XYZ Emp.#1

100% Power down xyzsdhot.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1

100% Power down xyzisdwarm.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1

100% Power down SAN devices (5 mins to power down SAN devices) Fri 4/19/13 XYZ Emp.#1

100% Power down xyzisdbkup.servers.xyz 192.168.X.X System x3550 Fri 4/19/13 XYZ Emp.#1

100% Power Down XYZ network equipment Fri 4/19/13 XYZ Emp.#1

100% XYZ 2nd Physical Migration to Co-Lo ( Credit Auth ) Fri 4/19/13 Physical Movers

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 14

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Power UP AS400 System Sat 4/20/13

100% Power up Tape Library Sat 4/20/13 XYZ Emp #2

100% Power up HMC Sat 4/20/13 XYZ Emp #2

100% Power up managed system (FRMMS) Sat 4/20/13 XYZ Emp #2

100% Power up managed system (FRRI) Sat 4/20/13 XYZ Emp #2

100% TCP001 job started - FRMMS Sat 4/20/13 XYZ Emp #2

100% Outside Windows FTP servers communicating Sat 4/20/13 XYZ Emp #2

100% Windows Scheduler Started Sat 4/20/13 XYZ Emp #2

100% Startup Robot Sat 4/20/13 XYZ Emp #2

100% Release Missed jobs Sat 4/20/13 XYZ Emp #2

100% Power UP Windows System Sat 4/20/13

100% Power on SAN devices (15 mins to power on SAN devices) Sat 4/20/13 XYZ Emp.#1

100% Power UP xyzisdbkup.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1

100% Power UP 1st- xyz-emn1-bk1.servers.xyz 192.168.X.X Sat 4/20/13 XYZ Emp.#1

100% Power on physical Windows Servers (10-15 min to power on each server) Exact boot order for A-ESat 4/20/13 XYZ Emp.#1

100% Power on VMs (2 mins to power on each VM) a. XYZCenteraldev, XYZ-DNS, XYZ-CRM, XYZ-GUI, XYZ-IDEAS, XYZ-SALLOSat 4/20/13 XYZ Emp.#1

100% Power UP a. xyzintprod.servers.xyz 192.168.X.X IBM 3850 Sat 4/20/13 XYZ Emp.#1

100% Power UP b. xyzisd.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1

100% Power UP b. xyzentralprod.servers... 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1

100% Power UP d. xyzisdhot.servers.xyz 192.168.X.X System x3550

Sat 4/20/13 XYZ Emp.#1

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 15

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Power UP e. xyzisdwarm.servers.xyz 192.168.X.X System x3550

Sat 4/20/13 XYZ Emp.#1

100% Power UP f. xyzallocation.servers.xyz 192.168.X.X System x3550 Sat 4/20/13 XYZ Emp.#1

100% Power UP h. xyzinttest.servers.xyz 192.168.X.X System x3550Sat 4/20/13 XYZ Emp.#1

100% Power on physical VM Server (10-15 mins to power down each VM Host) a. Host 1 & Host2Sat 4/20/13 XYZ Emp.#1

100% Test Conectivity and OPS Consoles Sat 4/20/13 XYZ Emp.#1,XYZ

Emp #2

100% Run All "Missed" Jobs during Offline Sat 4/20/13 XYZ Emp.#1,XYZ

Emp #2

100% Run HW Test for Drives, Connect, etc. Sat 4/20/13 XYZ Emp.#1,XYZ

Emp #2

100% Operations Post-Move Checklist Sat 4/20/13 XYZ Emp.#1,XYZ

Emp #2

100% Power up system at Co-Lo Sat 4/20/13 XYZ Emp #2

100% Start the HMC Sat 4/20/13 XYZ Emp #2

100% Start the partitions Sat 4/20/13 XYZ Emp #2

100% Verify Communications to Iseries/Client Access Sat 4/20/13 XYZ Emp #2

100% Windows server/s to system verification Sat 4/20/13 XYZ Emp.#1

100% Subsystems up Sat 4/20/13 XYZ Emp #2

100% Netserver running Sat 4/20/13 XYZ Emp.#1

100% Client Checkpoint – (network and communications ok) Sat 4/20/13 XYZ Emp.#1

100% Qinter Up Sat 4/20/13 XYZ Emp #2

100% Users allowed back onto the system Sat 4/20/13 XYZ Emp #2

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 16

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% Retail Ideas – IDE210CL released and running (was initially on hold) Sat 4/20/13 XYZ Emp #2

100% Verify any Jobs/applications that need to be running – exa: Logagent, TCP001, etc Sat 4/20/13 XYZ Emp #2

100% Jwalk up – if necessary Sat 4/20/13 XYZ Emp #2

100% JOBQ’s released Sat 4/20/13 XYZ Emp #2

100% Robot Started Sat 4/20/13 XYZ Emp #2

100% Robot jobs released and caught up to Current time Sat 4/20/13 XYZ Emp #2

100% Release IBM scheduler if necessary Sat 4/20/13 XYZ Emp #2

100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1

100% Release Windows scheduled jobs Sat 4/20/13 XYZ Emp.#1

100% Verify "Stable State" Sat 5/18/13 XYZ Emp.#1,XYZ

Emp #2

100% XYZ Migration Window Complete Sat 4/20/13 Entire Team

100% XYZ Test Systems Sat 4/20/13 XYZ Contact

100% Run End of Day Processes Sat 4/20/13 XYZ Emp #2

100% XYZ Company Migration #1 Fri 3/15/13

100% Notify Client of Plans Tue 1/1/13 Sr. MGMT,TKO

100% Operations : Backups, Power Down/Power Up Procedures Fri 3/15/13 XYZ Emp.#1

100% Perform XYZ Company Backup Fri 3/15/13 XYZ Emp.#1

100% End all System Processes and applications prior to shutdown Fri 3/15/13 XYZ Emp.#1

100% System and Network Equipment Power Down Fri 3/15/13 XYZ Emp.#1

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 17

Project: XYZ Company Data CenteDate: Thu 6/9/16

%

Complete

Task Name Finish Resource Names

100% XYZ Company Physical Migration Fri 3/15/13 Physical Movers

100% Breakdown/Packing Fri 3/15/13 Physical Movers

100% Travel Fri 3/15/13 Physical Movers

100% Rack & Stack Fri 3/15/13 Physical Movers

100% Cable Services Fri 3/15/13 Physical Movers

100% Power up Network and Systems Tue 1/1/13 XYZ Emp.#1,Cisco

Engineer

100% Test Conectivity and OPS Consoles Fri 3/15/13 XYZ Emp.#1

100% Verify VMs, WEB, Blackberry back ONLINE Fri 3/15/13 XYZ Emp.#1

100% Run HW Test for Drives, Connect, etc. Fri 3/15/13 XYZ Emp.#1

100% Verify "Stable State" Fri 3/15/13 XYZ Emp.#1,XYZ

Emp #2

100% XYZ Company Migration Window Complete Fri 3/15/13 Entire Team

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 18

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Lead by TKO

Week of March 11th

Week of March 11th

Week of March 11th

1/1

Carrier

XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1

TKO,Sr. MGMT

2/8

Sr. MGMT,TKO

Physical Movers

Physical Movers

3/9

Physical Movers

Physical Movers

XYZ Emp.#1,TKO

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 19

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Scheduled for March 21st

Scheduled: March 15th

9:00am Est. / BOM and Cable

order dependancy

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

2/8

XYZ Emp.#1

XYZ Emp.#1

3/15

Sr. MGMT,TKO

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 20

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Customer 1 Power Down

Tasks...

Start of Maintenance Window

- 9:00am

3:00 pm Est.

Scheduled: March 22nd/

BOM and Cable order

dependancy

3/15

3/15

XYZ Emp.#1,XYZ Emp #2

3/15

3/15

Physical Movers

3/15

3/15

3/15

XYZ Emp.#1,XYZ Emp #2

Entire Team

Entire Team,TKO,Mon 1/14/13

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 21

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Power Down Tasks...

08:00 PM – 2 hours

10:00 PM

10:00PM

10:10PM (9:36pm)

10:10PM (9:36pm) - (Turn

over to Moving Company) - 7

hours to move (3:36am 6

hours)

5:10am April 2nd (3:36am)

5:10am April 2nd

5:30am April 2nd

5:30am April 2nd

3 hours

8:30am EST (6:52am EST)

Sr. MGMT,TKO

XYZ Emp.#1,XYZ Emp #2

3/22

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

Physical Movers

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp #2,Chris H.,XYZ Emp.#1

Entire Team

XYZ Emp #2

XYZ Emp #2

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 22

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Scheduled : April 2nd

(TUESDAY) - 2:30pm Est.

Power Down Tasks...

1:30PM - 2:30PM

2:30pm

2:30pm - FLDE3 – 1hr,

FLDITG – 1hr 45min,

FLDMMS – 1hr 30min,

FLDRI – 10min ( all at the

same time so (2hrs max for

all))

4/2

Sr. MGMT

TKO,Sr. MGMT,XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

XYZ Emp #2

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 23

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

FD-CentralProd – power

down 2:30pm, FD-INTProd –

power down 2:31pm,

FD-CRMDEV power down

2:33pm, FD-CRMProd Power

down 2:35pm,

FD-IDEASProd power down

2:36pm, FD-SilvonProd

power down 2:38pm

ESX Host1 power down

2:45pm, ESX Host2 power

down 2:45pm, FD-Bkup

power down 2:50pm,

FD-IBMSAN power down

2:50

4:30PM

4:30PM

5:15PM (4:31) (Turn over

to Moving Company) - 10

hours to move

3:15AM April 3rd (12:00am)

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1

Physical Movers

XYZ Emp.#1

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 24

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

3:15am April 3rd (12:03am)

3:30am April 3rd (12:03 am)

3:45AM April 3rd (12:03 am)

4:00AM April 3rd (12:03

am)

4:15am (10 min) (12:30am -

HMC Internal Drive Failure -

IBM Dispatched)

4:25am (20 min) (5:45am)

4:45am (5 min) (12:30am)

4:45AM April 3rd (6:00am)

4:45AM April 3rd (6:28am)

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Customer 2

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 25

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

FLDRI – None, FLDE3

-ASR_SWAP SCD USER

DEF 05:35:00 *WEEKLY,

AWR_SKUOUT SCD USER

DEF 05:30:00 *WEEKLY ,

AWR_SWAP SCD

USER,DEF 05:35:00

*WEEKLY, RUNALLPO

SCD *ALL 21:45:00

*WEEKLY, RUNAMPO SCD

USER DEF 06:15:00

*WEEKLY , RUNASR SCD

USER DEF 05:00:00

*WEEKL

4:45AM (6:45am)

Target Completion : 5:00am

April 3rd (6:45am)

Schedule : April 5th - 9:00am

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Entire Team

3/20

Sr. MGMT,TKO

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 26

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Power Down Tasks...

10:30 AM April 5th (Turn

over to Moving Company) 10

hours to move

9:00 PM April 5th

TKO,Sr. MGMT

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

4/5

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Entire Team

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 27

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Scheduled April 7th 1:00 AM

Open ticket with Carrier for

Migration times

Power Down Tasks...

12:15AM April 7 (Turn over

to Moving Company) 9.5

hours to move (see Move

Plan)

Sr. MGMT,TKO

XYZ Emp.#1,XYZ Contact

Carrier

Data Center Co_Lo

3/2

TKO,Sr. MGMT

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Physical Movers

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 28

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

12:00PM April 7 (per Move

Plan)

Schedule : April 12th -

10:00pm to 6:00am

Power Down Tasks...

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Entire Team

Sr. MGMT,TKO

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 29

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

10:30PM - (Turn over to

Moving Company) - 7 hours

to move

5:30am April 13th

6:00am April 13

Open ticket with Carrier for

Migration Window

XYZ Emp.#1,XYZ Emp #2

Physical Movers

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

Entire Team

Sr. MGMT,TKO

XYZ Contact,TKO

1/21

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 30

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Date and Time Verified

Upon Formal Approval - Start

of Maintenance Window -

2:00am

Power Down Tasks...

John D.,Jay R.,Sr. MGMT,TKO,XYZ

Carrier

Data Center Co_Lo

3/21

XYZ

Jane May

John Doe,Jane May

John Doe

John Doe

John Doe

John Doe

John Doe

John Doe

John Doe

John Doe

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 31

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Power Down Tasks...

Except Credit Auth Servers -

Est 14 hours

Estimated 2 hours

Jane May

Jane May

Jane May

Jane May

Jane May

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

Physical Movers

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

Physical Movers

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 32

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Power Up starts

Power Up starts

Credit Auth

Credit Auth

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 33

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Credit Auth

Post Move ...

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp.#1,XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp.#1

XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp #2

XYZ Emp #2

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 34

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

Estimated 3.5 Hours after

Maint. Window

XYZ Company Power Down

Tasks...

Start of Maintenance Window

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp #2

XYZ Emp.#1

XYZ Emp.#1

XYZ Emp.#1,XYZ Emp #2

Entire Team

XYZ Contact

XYZ Emp #2

3/15

Sr. MGMT,TKO

3/15

XYZ Emp.#1

3/15

3/15

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 35

Project: XYZ Company Data CenteDate: Thu 6/9/16

Notes

9.5 hour Estimate (Total)

3 hours

1 hour

2 hours

3.5 hours

Physical Movers

Physical Movers

Physical Movers

Physical Movers

XYZ Emp.#1,Cisco Engineer

3/15

3/15

3/15

Entire Team

16 23 30 6 13 20 27 3 10 17 24 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30

Dec '12 Jan '13 Feb '13 Mar '13 Apr '13 May '13 Jun '13

Task

Split

Milestone

Summary

Project Summary

External Tasks

External Milestone

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Deadline

Progress

Page 36

Project: XYZ Company Data CenteDate: Thu 6/9/16