Interlachen Of Pelican Bay Pool Project Update

Interlachen Pool Presentation 2009 Blog

  • Upload
    atgrove

  • View
    295

  • Download
    0

Embed Size (px)

DESCRIPTION

 

Citation preview

Page 1: Interlachen Pool Presentation 2009 Blog

InterlachenOf Pelican BayPool Project Update

Page 2: Interlachen Pool Presentation 2009 Blog

The Condition of the Pool

• The following slides will show the deterioration of the pool deck and wooden bulkheads

• The sand fill under the deck is leaking through the bulkheads into the pool which is causing the deck to crack and slope

Page 3: Interlachen Pool Presentation 2009 Blog

SLOPING DECK

Page 4: Interlachen Pool Presentation 2009 Blog

CAULKED DECK CRACKS

Page 5: Interlachen Pool Presentation 2009 Blog

SHIFTING DECK CRACK

Page 6: Interlachen Pool Presentation 2009 Blog

DECK AND BULKHEAD DETERIORATION

Page 7: Interlachen Pool Presentation 2009 Blog

DECK AND BULKHEAD DETERIORATION

Page 8: Interlachen Pool Presentation 2009 Blog

DECK AND BULKHEAD DETERIORATION

Page 9: Interlachen Pool Presentation 2009 Blog

Pool Committee Considerations

• Five options were reviewed by the pool committee

• These five options were further reduced to two final considerations

Page 10: Interlachen Pool Presentation 2009 Blog

Options Considered by the Pool Committee

A. New deck, bring existing pool & deck to compliance

• Doing nothing was not an option

B. New 16’ deck & bulkhead, bring old pool to compliance

C. New pool & Spa, new 14.5’ deck & new bulkhead

• Additional cost for 16’ deck was minimal

D. New pool & Spa, new 16’ deck & new bulkhead

E. Include new bulkhead at both ends of bridge

• In these economic times this additional cost was not advisable

Page 11: Interlachen Pool Presentation 2009 Blog

Pool Committee Estimated Costs for Plan B or Plan D

2009 Interlachen Pool Project

Plan B Plan DSame as Plan A Renovation New Pool/Spa 16' DeckPlus 16' Deck & Composite Sheet Piles New Pool /Spa Equipment PkgeNew Spa Package

Site Prep $11,100.00 $11,100.00Basic Demolition $5,050.00 $5,050.00additional demolition of pool/spa $6,850.00Basic Paver Deck $31,476.80 $28,268.00thin set paver on lanai additional to 16' $1,833.75 additional to 16' $1,833.75Pool work spa work with spa equipment $99,750.00New Pool / Spa & Equipment $175,703.00Electic Allowance - Lighting & fixture $6,000.00 $6,000.00Fence & Gates $16,875.00 $14,625.00Additional Back Fill $8,478.75 $8,478.78SUB TOTAL $180,564.30 $257,908.53

Sheet Pile Composite Bulkhead $171,200.00 $171,200.00Manta Ray Tie Backs $15,360.00SUB TOTAL $367,124.30 $429,108.53

Page 12: Interlachen Pool Presentation 2009 Blog

Additional Costs Not Considered by Pool Committee

2009 Interlachen Pool Project

New Vac Pac & Piping $16,500.00 includedMove Existing Pool Heater Equipment est add to scope of work $2,000.00 add to scope of work $2,000.00Retro Fit Existing Ladders to new Deck est $500.00 $500.00SUB TOTAL $386,124.30 $431,608.53

Contingency fund @ % 5% $19,181.22 2% $8,582.17Construction Manager $10,000.00 $10,000.00Pelican Bay & DOH Permits $2,400.00 $2,400.00Engineering Contract est $4,500.00 $4,500.00Legal Preperation & Documents est $1,500.00 $1,500.00

$423,705.52 $458,590.70

Reserve Fund Contribution ($75,000.00) ($75,000.00)$348,705.52 $383,590.70

The following slides will portray the need for an additional vac-pac for the reconditioned old pool in option B

Note: A vac-pac is a complete pump and filter package

Page 13: Interlachen Pool Presentation 2009 Blog

PUMP ROOM FLOOR

Page 14: Interlachen Pool Presentation 2009 Blog

PUMP ROOM ELECTRICAL

Page 15: Interlachen Pool Presentation 2009 Blog

PUMP ROOM SPA CONTROLS

Page 16: Interlachen Pool Presentation 2009 Blog

PUMP ROOM FLOOR

Page 17: Interlachen Pool Presentation 2009 Blog

Final Costs with Additional Costs Included

2009 Interlachen Pool Project

New Vac Pac & Piping $16,500.00 includedMove Existing Pool Heater Equipment est add to scope of work $2,000.00 add to scope of work $2,000.00Retro Fit Existing Ladders to new Deck est $500.00 $500.00SUB TOTAL $386,124.30 $431,608.53

Contingency fund @ % 5% $19,181.22 2% $8,582.17Construction Manager $10,000.00 $10,000.00Pelican Bay & DOH Permits $2,400.00 $2,400.00Engineering Contract est $4,500.00 $4,500.00Legal Preperation & Documents est $1,500.00 $1,500.00

$423,705.52 $458,590.70

Reserve Fund Contribution ($75,000.00) ($75,000.00)$348,705.52 $383,590.70

Plan B (old pool) Final Cost Estimate all in = $348,705.52

Plan D (new pool) Final Cost Estimate all in = $383,590.70

Difference between old and new pool = $34,872

Page 18: Interlachen Pool Presentation 2009 Blog

Financial Model

PlanB Plan D Differential

Total Estimated Costs 348,705.00$ 383,590.00$ 34,872.00$

Cost per Unit 3,750.00$ 4,125.00$ 375.00$

Assessment Model

Assessment 3,000.00$ 3,000.00$

3 Quarterly Maintenance 3 x 250=750 3 x 375=1125 375.00$ Increments

Per Quarter 250.00$ 375.00$ 125.00$

Page 19: Interlachen Pool Presentation 2009 Blog

Board of Directors Recommendations

• The Interlachen Board of Directors has unanimously decided to proceed with Option D (new pool, spa, bulkhead and 16’ deck)

• Requests for quotation and accurate pricing for this package will be let immediately.

• The Board of Directors will present the final cost and unit assessments, along with a suggested financial plan as soon as the quotation process is complete.