Bottom-Up (Micro)

• Single-Point Estimation • Three-Point Estimates • Multiple Estimators • Delphi Technique

Page 2: Bottom-up time estimations techiques

1. Have people familiar with the tasks make the estimate.

2. Use several people to make estimates.

3. Base estimates on normal conditions, efficient methods, and a normal level of resources.

4. Use consistent time units in estimating task times.

5. Treat each task as independent, don’t aggregate.

6. Don’t make allowances for contingencies.

7. Adding a risk assessment helps avoid surprises to stakeholders.

Estimating Guidelines for Times, Costs, and Resources

Page 3: Bottom-up time estimations techiques

Single Point Estimation

30 Days to Complete

How long will Task A take to complete?

Bottom-up (Micro)

Page 4: Bottom-up time estimations techiques

Three-Point EstimatesHow long will Task A take to complete?

Optimistic (a) 20 daysMost Likely (m) 30 daysPessimistic (b) 58 days

Page 5: Bottom-up time estimations techiques

Three-Point Estimates

Optimistic (a) 20 daysMost Likely (m) 30 daysPessimistic (b) 58 days

How long will Task A take to complete?

20 Days + 30 Days + 58 Days3 Estimates

= 36 days

Triangular Distribution or simple average

Page 6: Bottom-up time estimations techiques

Activity Time Calculations

weighted average activity time

=Te

Page 7: Bottom-up time estimations techiques

Activity Time Calculations

Te a + 4m + b 6

=

Page 8: Bottom-up time estimations techiques

Three-Point EstimatesHow long will Task A take to complete?

te 20+ 4*30 + 58 6

=

Optimistic (a) 20 daysMost Likely (m) 30 daysPessimistic (b) 58 days

Page 9: Bottom-up time estimations techiques

Three-Point EstimatesHow long will Task A take to complete?

te = 33.00 days

Optimistic (a) 20 daysMost Likely (m) 30 daysPessimistic (b) 58 days

Page 10: Bottom-up time estimations techiques

Beta Distribution

Optimistic (a)

Like

lines

s or

Pro

babi

lity

—>

Most Likely (m)

Pessimistic (b)

te

Page 11: Bottom-up time estimations techiques

Beta Distribution

Optimistic (a)

Like

lines

s or

Pro

babi

lity

—>

Most Likely (m)

Pessimistic (b)

33.00 days

Page 12: Bottom-up time estimations techiques

Three-Point Estimates

Estimated Project Duration: 243 days

Probably that project will be done in 250 days: 74%

PERT Analysis

Page 13: Bottom-up time estimations techiques

Multiple EstimatorsBottom Up Estimating

Estimator 1 Estimator 2 Estimator 33

20 Days 30 Days 50 Days

Bottom-up (Micro)

Page 14: Bottom-up time estimations techiques

Multiple EstimatorsBottom Up Estimating

Estimator 1 Estimator 2 Estimator 33

20 Days 30 Days 50 Days

Bottom-up (Micro)

Page 15: Bottom-up time estimations techiques

Multiple EstimatorsBottom Up Estimating

20 Days

Estimator 1 Estimator 2 Estimator 33

20 Days + 30 Days + 50 Days3 Estimators

= 33.3 Days

Bottom-up (Micro)

30 Days 50 Days

Page 16: Bottom-up time estimations techiques

Delphi Technique

Page 17: Bottom-up time estimations techiques

Multiple Estimators

Estimator 1 Estimator 2 Estimator 3

30 days

3

Bottom-up (Micro)

Page 18: Bottom-up time estimations techiques

Bottom-Up (Micro)

• Single-Point Estimation • Three-Point Estimates • Multiple Estimators • Delphi Technique