The Big Bang! Upgrading to Banner 8.1
Presented by: TJ Rains, PMP
Associate CIO, Enterprise SystemsEmporia State University
April 12, 2010
Session ID 0042
2
Session Rules of Etiquette
• Please turn off your cell phone/pager
• If you must leave the session early, please do so as discreetly as possible
• Please avoid side conversation during the session
Thank you for your cooperation!
Session ID 0042
3
Introduction
• Purpose: To review Emporia State University’s Banner 8.1 upgrade project focusing on the following core elements:—Project Planning and Management—Scope and Resource Requirements—Business Process Analysis and System Testing—Lessons Learned
• Benefits: —Obtain information and materials on planning and
managing a Banner major release upgrade. —Learn from our successes and mistakes.
Session ID 0042
4
Agenda
• ESU’s Banner Environment
• Enterprise Systems Team Structure
• Banner 8.1 Upgrade Project Planning and Management—Scope, Resources, Schedule
• Business Process Analysis and System Testing
• Issues Encountered
• Lessons Learned
• Presentation Supplements
Session ID 0042
ESU’s Banner Environment
UDC Vision Realized at ESU
6
ESU’s Banner Environment
• Core Systems —Luminis Portal (Buzz In)
• Banner Channels, SSB Integration, Single-Sign-On—Banner Advancement—Banner Finance—Banner Financial Aid—Banner Student
• *Enrollment Management to be launched July 6, 2010.—Operational Data Store/Enterprise Data Warehouse—Cognos 8 BI—RMS Housing
Session ID 0042
7
Supporting Software
• Evisions Form Fusion and Intellecheck
• E~Print
• Touchnet Payment Gateway
• UC4 (Appworx)
• Runner Technologies Clean Address
• Platforms —Hardware – Sun v490 Based Architecture w/ StorageTek
SAN—Primary OS - Sun Solaris 10—Oracle 9i
Session ID 0042
8Session ID 0042
ESUStaff
Sungard HE Banner
Buzz In Portal / Self Service Banner
General Person
Finance
Human Resources
Financial Aid
Student
Advancement
General Portal Content
Student/Financial Aid Self Service
Finance Self Service
HR/Payroll Self Service
Advancement Self Service
Cognos/e~Print Reporting
Blackboard
Onbase – Document Imaging
GroupWise – Email Calendar
Operational Data Store /Enterprise Data Warehouse
Students, Alumni, Faculty
and Staff
Identity Management Services - Novell eDirectory
TCS Support– Helpdesk, Infrastructure, Enterprise Systems, Client Services, Academic and Multimedia
Enterprise Systems Team Structure
10
Enterprise Systems Team
• Enterprise Infrastructure—Oracle DBA/Team Lead (1 FTE)—Banner Application Administrator/DBA (1 FTE)—Luminis System Administrator (1 FTE)—Web Tailor/SSB Administrator/Developer (1 FTE)—Systems Integrator/EM Specialist (1 FTE)—Banner Security Administrator/UC4 Administrator (1 FTE)—ODS/EDW/Cognos Administrator (1 FTE)—Systems Administrator/Sun Hardware Support (1 FTE)
Session ID 0042
Enterprise Systems Team (cont.)
• Banner Student, Financial Aid Technical Team —Application Development Supervisor (1 FTE)—Primary Student Application Support (1 FTE)—Primary Financial Aid Support (1 FTE)
• Banner Finance, HR, Payroll, Advancement Technical Team —Application Development Supervisor (1 FTE)—Primary HR/Payroll/Finance Support (1 FTE)—Primary Advancement Support (1 FTE)
11Session ID 0042
Banner 8.1 Project Management
Scope, Resources, Schedule
Project Management
• Project Management Methodology—Kansas Information Technology Office (KITO) Project
Management Methodology.—Publicly available at http://www.da.ks.gov/kito/ITPMM.HTM
• Project Planning—Project was chartered and planned collaboratively with
administration, system owners and central IT staff. —Schedule and budget developed by central IT and vetted
through administration and system owners.
• Project Execution—Central IT resource (Associate CIO) managed, monitored
and controlled the execution phase of the project. —Bi-Weekly status update meetings held with system
owners to verify functional testing progress.
13Session ID 0042
Project Scope (In Scope)
• Evaluate, procure, install and configure new server and storage hardware to support the Banner 8 environment.
• Upgrade to Oracle 10g (UTF8).
• Upgrade all Banner systems (INB and SSB) to latest releases (8.1x).
• Upgrade ODS and EDW to latest release (8).
• Upgrade to Luminis 4.2.
• Upgrade Cognos 8 BI to version 8.3 SP2.
• Upgrade UC4 to latest release.
14Session ID 0042
Project Timeline
15Session ID 0042
Project Schedule
• 8 Months of Bliss! —September 2008 – October 2008
• Development of Functional and Technical Test Plans—Student, Financial Aid, Finance, HR/Payroll,
Advancement Banner Systems—September 2008 – November 2008
• Hardware Installation and Configuration—Sun T25220 and Sunfire x4500 servers, StorageTek
SAN Environment and Tape Library.
16Session ID 0042
Project Schedule (cont.)
—September 2008 – March 2009• Installation of Banner Test and Production
Environments—Netbackup—Oracle Database and Application Servers—ODS and EDW— INB and SSB—Luminis IV—Cognos 8 BI—ePrint —UC4—Evisions Form Fusion and Intellecheck
• System Integration Testing Readiness
17Session ID 0042
Project Schedule (cont.)
—January 2009 – March 2009• System and Integration Testing (All Systems)• Execution of Defined Test Plans
—March 2009 – Early April 2009• End User Training Development and Delivery (All
Systems)— April 24, 2009 – April 26, 2009 GO LIVE!!!
• Complete Final Data Migration• Complete Final Production Testing • Cutover to Production
18Session ID 0042
Business Process Analysis – Student
Business Process Analysis
• Significant business process changes in Registration, Undergraduate Admissions, Graduate Admissions and International Admissions occurred as a result of our initial Banner implementation. —Changes were never documented! — Impacted test plan development for the Student system.
• Decided to conduct Business Process Analysis work sessions to document business process changes to ensure test plan alignment.
• Output: Business Process Diagrams, Formal Test Plan and Checklists
20Session ID 0042
Output: Business Process Diagram
21Session ID 0042
Output: Testing Checklist
22Session ID 0042
Banner 8.1 Upgrade Graduate Office Testing Tasks
Results/Comments section indicates results of simulation.
Task Responsibility Done Test Results/Comments General Tasks TCS Ensure Job Submission is running Nikki Barnes Ensure Sleep/Wake Printers/Procedures are Set up Nikki Barnes Ensure Luminus is functional Brian Morgan Ensure Cognos is accessible Review Common Matching Rules Jim Moore,
Sandy Crofoot Nikki Barnes
Ensure fsaAtlas DIT is functional Brian Morgan Sandy Crofoot
Review all General Person Validation Tables Technical Team Review all Student Validation Tables Sandy Crofoot 1/28 All populated – looked fine Task Responsibility Done Test Results/Comments Ongoing Grad Admissions Tasks Graduate (Mary
Sewell, Peggy Anderson)
Please admit at least one student of each scenario you have
Verify Admissions Checklist Rules (SAACHKB) Peggy Anderson Review Curriculum Rules/Program Code Definitions Peggy Anderson GOAMATCH Mary Sewell SPAIDEN Mary Sewell SAAADMS Mary Sewell SOAPCOL Mary Sewell SOAHOLD Mary Sewell SGAADVR Mary Sewell Admission Letter procedure
Test Plans
Test Plan Development
• Conducted test plan development work sessions with functional and technical support staff. —Lead by technical support staff
• Used test plans developed during our initial Banner implementation as a starting point.
• Finalized plans were vetted with system owners and documented as ready for execution.
• Student System – Business Process Analysis, testing checklists and formal test plan.
24Session ID 0042
Student Test Plan
Issues Encountered
Issues Encountered
• Luminis Middle Tier – ID/PIN/LDAP synchronization.
• LDI role assignment for targeted content delivery.
• ODS changes in fields and data types caused significant issues with existing reports.
• Form changes and additions – testing and training.
• Lack of thorough understanding of business process supported by the student system caused difficulties in test plan development.
• Touchnet Payment Gateway configuration.
• Active Directory printing.
• Pro-C Compiler support change
26Session ID 0042
Lessons Learned
Lessons Learned
• Functional and technical team collaboration is necessary for a successful upgrade.—Project planning, scheduling, test plan development and
issue resolution.
• Remain open and honest about issues and attach each issue in a pragmatic and deliberate manner.
• Plan for the worst, hope for the best.
• Be open to change in schedule if necessary for project success.
28Session ID 0042
Presentation Supplements
Presentation Supplements
• Project Documents—Banner 8.1 Project Work Breakdown Structure—Banner 8.1 Go Live Check List—Banner 8.1 INB Form Observations
• Test Plans—Test Plans and Testing Check Lists
30Session ID 0042
Questions and Answers
Thank You!TJ Rains, PMP
Associate CIO, Enterprise Systems
Emporia State University
Please complete the online class evaluation form
Session ID 0042
32