    PROJECT COST

    ESTIMATE

    SUBMITTED AS

    OF

    DATE APPROVED PR DATE

    1. Proposed Student KIOSK at CED P 92,609.74 Jan. 26, 2012 Feb. 13, 2012 Feb. 13, 2012 PR# 067,068

    (ab

    2. Proposed Student Center at CED P 255,913.70 Feb. 22, 2012 Released

    3. Prposed Water Distribution System at CHE P 84,127.55 Jan. 31, 2012 Feb. 14, 2012 Feb. 14, 2012 PR# 071, 0

    4. Major Repair at Social Hall CED P 1,700,000.00 Feb. 08, 2012

    5. Propose repair/ renovation of the CPD P 10,433.50 Feb. 23, 2012 released

    (Partition) (center for Peace and Dev't.)

    6. Construction of Multipurpose at CN P 503,969.84 Feb. 22, 2012 May 8, 2012 Proposed Source

    7. ICRIM building P 293,259.60 July 9, 2012 July 12, 2012 Release

    Prepared by;

    ENGR. AQUILINO V. PEREZ

    Director for Physical Plant

    NAME OF PROJECT

    STATUS REPORT

  • 7/30/2019 Status of Project Implementation

    2/12

    PROJECT COST

    ESTIMATE

    SUBMITTED AS

    OF

    DATE APPROVED PR DATE

    8. Proposed Renovation of Office of the President , P 229,180 April 25, 2012

    Conference room, Staff Area at the Abitona bldg.

    9. Uprgrading of Transformer sub 1 to 3 uts 167KVA P 3,479,040.19 released to B

    PR Approved Ju

    10. Repair and Renovation of Old Boys Dormitory P 800,000.00 June 6, 2011 June 9, 2011 ALTOS CONSTR

    to Classroom , College of Agriculture as o

    11. Concreting of Road Network,College of Agriculture P 2,000,000.00 Jun6 10, 2011 July 14, 2011 ARDENT CON

    for Inspectio

    12. Proposed two(2) storey CSM Lecture room P 1,220,264.85 May 25, 2011 June 9, 2011 FJ CONST

    Phase I,and Proposed CSM comfort room for (A

    male and Female (CLUSTER)

    13. Repair and repainting of two(2) comfort rooms at P 169,431.12 Aug. 08, 20111 Aug. 15, 2011 VAF CONST

    Academic building, San Ramon Zbga. City (As of O

    14. Proposed Lactation Room 56,400.36 Sept. 27, 2012 Oct.11, 2012 Released to S

    NAME OF PROJECT

    Prepared by;

    ENGR. AQUILINO V. PEREZ

    Director for Physical Plant

  • 7/30/2019 Status of Project Implementation

    3/12

    Projects for Implementation

    APP 2012- batch 1

    PROJECT COST

    ESTIMATE

    SUBMITTED AS

    OF

    DATE APPROVED PR DATE

    1. Major Renovation of at CN Annex building P 2,075,000.00 Aug. 13,2012 Aug. 15, 2012 Aug. 28, 2012 For

    2. Two Storey CSM Lecture Room and Comfort rooms P 2,500,000.00 Oct. 05,2012 Oct. 11, 2012 For Post-q

    (Phase II)

    3. Concreting Road Network San Ramon Campus P 2,500,000.00 Oct. 11,2012 Oct. 11, 2012 For Post-q

    (Phase II)

    4. Repair and Renovation of High school Building and P 1,300,000.00 Sept. 25, 2012 Oct. 11, 2012 For Post-q

    Concreting Pathways

    5. WMSU Gate 1, Security Services Office and P 1,000,000.00 Oct. 05,2012 Oct. 11, 2012 For Post-q

    Guard House

    6. Expansion of Food Court P 500,000.00 Oct. 5, 2012 Oct. 11, 2012 For Post-q

    7. Construction of Septic tank and Plumbing System at P 48, 675.00 Oct. 5, 2012 Oct. 11, 2012

    Prepared by;

    ENGR. AQUILINO V. PEREZ

    Director for Physical Plant

    NAME OF PROJECT

  • 7/30/2019 Status of Project Implementation

    4/12

    APP 2012 -BATCH 2

    PROJECT COSTESTIMATE

    SUBMITTED AS

    OF

    DATE APPROVED PR DATE

    8. CSS Extension Building P 2,000,000.00 For Pre P

    9. Repair and Renovation of ILS- Buildings P 1,000,000.00 Es

    10. Repair and Renovation of Admin. Building (Abitona bldg.) P 970,820.00 Es

    11. Repair and renovation of College of Forestry P 800,000.00 Nov. 6,2012 Es

    12. Repair and Renovation of University KIOSK to house the P 800,000.00 Es

    Admission Office, Scholarship and MISTO

    13. Repair and Renovation of Old Engineering building P 700,000.00 Nov. 7, 2012 Es

    14. Repair Parking Lot , Main Campus P 500,000.00 Es

    15. Repair roofing/ Ceiling and repainting of interior/exterior P 500,000.00 Oct. 17, 2012 Oct. 22,2012

    walls at University New Library (revised estimate)

    Prepared by;

    NAME OF PROJECT

  • 7/30/2019 Status of Project Implementation

    5/12

    Director for Physical Plant

  • 7/30/2019 Status of Project Implementation

    6/12

  • 7/30/2019 Status of Project Implementation

    7/12

    DATE SUBJECT FROM ACTION TAKEN ESTIMATED BY

    8/17/2012 High School OUA For Estimate Sannyboy

    Major Renovation at CN Annex bldg. OUA For Purchase Request Sannyboy Released to Accounting 8/28/2012

    Proposed WMSU Main Gate OUA For re- estimate Sannyboy

    Renovation of Old Engineering building OUA

    Proposed 22 stalls at Pepsi Canteen OUA Alvin Silagan

    Proposed renovation of CSM Physics Laboratory room (211) OUA Alvin Silagan

    Proposed renovation of CSM Biology Laboratory room (107) OUA Alvin Silagan

    Proposed renovation of Chemistry Laboratory room (101) OUA Alvin SilaganRepair of Frontage of Admission Office OUA

    Floor Filing and repair of Comfort room (MISTO) OUA

    Septic tank at lot 2 OUA Edwin

    8/28/2012 Power rehabilitation of steel water tank OUA

    Major Repair and renovation of Gymnasium OUA Alvin Silagan

    Proposed 2-storey Lecture room at CSM OUA Sannyboy

    PLAN Received for Estimate

  • 7/30/2019 Status of Project Implementation

    8/12

    DATE SUBJECT FROM ACTION TAKEN REMARKS

    COMMUNICATIONS out-going

  • 7/30/2019 Status of Project Implementation

    9/12

    DATE RECEIVED SUBJECT REMARKS DATE RELEASED TO

    COA Inspection report w/ attached requirements: Nov. 08, 2012 Accounting

    Repaiting of two(2) Comfort rooms at Academic building of College a.) Estimates

    of Agriculture ( VAF Construction) b.) APP

    c.) Blue print

    d.) Scope of wor

    e.) Contractors Bid Estimates

    Request Assistance in the Const. of the Proposed Major Nov. 08, 2012 VP-PAF

    repair of Social hall of the College of Education

    (FJ Construction)

    100% Completion of works " Proposed Two (2) Storey Lecture attachment of requirements for Payment Oct. 31, 2012 Accounting

    room (Phase I) and Proposed Comfort room for Male and female a.) Affidavit (Payment of Laborer/mat'L)

    b.) Cert. of Completion /Final Acceptance

    c.) Certification from Supply Office

    COA Inspection report Oct. 29, 2012 VP-PAF

    (Concreting of Road Network )

    75% Completion of works Oct. 23, 2012 VP-PAF

    Power Rehabilitation lot 1 and 2

    (ASIA PHIL.)

    Memorandum- Communication (In Coming)/ out going

  • 7/30/2019 Status of Project Implementation

    10/12

    Certification of Completion and Acceptance For Signature Oct. 18, 2012 OP

    Proposed two(2) storey lecture room (PhaseI) and

    CR for Male and Female -FJ Construction

    Bill of Materials/Estimates Repair Ceiling/ Repaiting of int./ext. Oct. 18, 2012 Librarywalls at University New Library VP-PAF

    Request Approval for Extension of Two Draftsman Oct. 15, 2012 HRMO

    ( Arch. Rodriguez/ Arch. Mijarez)

    Plan- Repair and Concreting of Road Network Phase II for changes Oct. 09, 2012 OUA

    ZAMCELCO /application letter for Electrical Permit Oct. 08, 2012 OP

    (WMSU- Power Rehabilitation lot 1 and 2

    Bill of Estimates/Materials for Proposed Lactation Room Oct. 1, 2012 VP-PAF

    w/ Plan attached (5 pages)

    Bill of Estimates/materials for Concreting of Road Network CA Oct. 01, 2012 VP-PAF

    phase II (with Plan attached) 2pages

    Released of Payment 100% Completion of works for the Proposed Sept. 28, 2012 VP-PAF

    two (2) storey Lecture room (Phase I) and Proposed Comfort roomfor Male and Female

    Bill of Estimated materials for the Sept. 27, 2012 VP-PAF

    Proposed Lactation Room

    9/3/2012

    (COA) Documents to Facilitate inspection doc. Submitted Sept. 25,2012 COA

  • 7/30/2019 Status of Project Implementation

    11/12

    ((Concreting of Road Network- ARDENT CONSTRUCTION) (SWA, Insp. Report,before and after

    concreting of road, Cert. of Completion

    8/28/2012 Request for Final Inspection -Proposed 2 storey CSM Lecture room For Final Inspection Sept. 28, 2012 VP-PAF

    (Finance Office) and Proposed Comfort room for male and Female (Cluster) at (Accomplishment attached) for Payment

    College of CSM (FJ Construction and Enterprises)

    8/28/2012 Billing No.1- Power Rehabilitation of Lot 1 and Lot 2

    (Finance Office) (AsiaPhil. Manufacturing Industries Inc.)

    8/29/2012 Rehabilitation of Street lights along the hallway between No Funding/

    (Finance Office) High School and CSM bldgs. And along the Parking area of lot I No source of Fund

  • 7/30/2019 Status of Project Implementation

    12/12


Recommended