ACKNOWLEDGEMENTS
It was a great opportunity to me for completing my industrial training in one of Sri Lanka’s
most important establishments such as Sri Lanka Air Force which is South Asia’s one and only
establishment overhauling helicopters. It was even more enthusiastic to work with a group of very
highly skilled professionals, who were very friendly from the commencement of my training session.
First of all I must thank Industrial Training and Career Guidance Unit (ITCGU) of faculty of
Engineering, University of Peradeniya and National Apprentice and Industrial Training Authority
(NAITA) for conducting the training program and allowing us to get the required industrial exposure
for achieving challenges which should overcome by engineers in the industrial environment.
Then I offer my sincere thanks to the Commanding Officer of Mechanical Transport Repair and
Overhaul Wing (MTR&OW) Group Captain Eng. Senarathna who was in-charge of us during the
training session and to Squadron Leader Eng N.S. Dikkumburage, Flight Lieutenant Eng. Chamila
Mallawarachchi, Squadran Leader Eng. Chamila Kahadakoralage who were in-charge of the training
session and also to Squadron Leader Eng. G.G.I.D. Viraj who was in-charge of workshop Engineer.
I must further thank, all workers who were at Air Craft Engineering wing, General Engineering
Wing, Mechanical Transport Repair & Overhaul Wing for helping me without any hostility to improve
my knowledge. Actually it was a strange experience for me at the beginning of the training period and
I could spend valuable and pleasurably 11 weeks with aid of all the personnel who has given the
support and the assistance in completing my industrial training session.
E.M.K.S. Edirisooriya
Faculty of Engineering
University of Peradeniya
iii
CONTENTS
Acknowledgements i
Contents iii
List of Figures v
List of Abbreviations vi
Chapter 1 INTRODUCTION
1.1 Introduction to Sri Lanka Air Force 1
1.2 SLAF’s vision & mission 1
1.3 Rank Structure 3
1.4 Decorations & medals 3
1.5 Sri Lanka Air force base, Katunayaka 4
Chapter 2 DISASSEMBLY OF A DEFFENDER TDI ENGINE
2.1 Disassembling process 8
2.2 Important points to be considered 8
Chapter 3 ASSEMBLY OF DEFENDER TDI ENGINE
3.1 Assembling process 10
3.2 Settling tappet clearance 11
3.3 Important points to be considered 12
Chapter 4 DISASSEMBLY OF DEFENDER TDI GEAR BOX
4.1 Disassembling process 14
4.2 Important points to be considered 15
Chapter 5 ASSEMBLY OF DEFENDER TDI GEAR BOX
5.1 Assembling process 16
5.2 Important points to be considered 17
Chapter 6 THE TRANSFER BOX
6.1 Function of a transfer box 18
iv
Chapter 7 LATHE MACHINES
7.1 Main parts of lathe machine 19
7.2 General operation of lathe machine 20
7.3 External Threads cutting operation 21
7.4 Important points to be consider 21
Chapter 8 WELDING
8.1 Metal inert gas welding (MIG) 23
8.2 Gas welding 23
8.3 Tungsten Inert gas welding (TIG) 24
Chapter 9 NON DESTRUCTIVE TESTING
9.1 Radiographic testing 26
9.2 Magnetic particle testing 26
9.3 Ultrasonic testing 26
9.4 Eddy current testing 27
9.5 Penetrate testing 27
Chapter 10 CONCLUSIONS 28
v
LIST OF FIGURES
Figure 2.1 Cross section of a diesel V engine 8
Figure 2.2 Cross section of a Pushrod and overhead cam engine 9
Figure 3.1 Measuring by using a dial gauge 10
Figure 3.2 Measuring gap of a piston ring 10
Figure 3.3 A piston ring compressor(Ring Clamp) 11
Figure 3.4 Adjusting tappet clearance 11
Figure 3.5 Setting tappet clearance 12
Figure 3.6 The Engine head 13
Figure 4.1 The components of a gearbox 13
Figure 4.2 Separation of the gearbox 14
Figure 4.3 Dog teeth in a gearbox 14
Figure 5.1 Components of the Gearbox 15
Figure 5.2 Components of the hub 15
Figure 6.1 Components of a transfer box 16
Figure 6.2 Components of a transfer box 17
Figure 7.1 Main Components of a Lathe Machine 17
Figure 7.2 A Lathe Machine 19
Figure 8.1 The welding process 20
Figure 8.2 Welding process 21
Figure 8.3 The diagram of the MIG welding 21
Figure 8.4 The diagram of the Gas welding 22
Figure 8.5 The diagram of the TIG welding 22
Figure 9.1 NDT testing 23
Figure 9.2 Ultrasonic testing 24
Figure 9.3 Eddy current testing 25
vi
LIST OF ABBREVIATIONS
AEW AIRCRAFT ENGINEERING WING
GEW GENERAL ENGINEERING WING
LROW LAND ROVER OVERHAUL WING
MTR&OW MECHANICAL TRANSPORT REPAIR & OVERHAUL WING
SLAF SRI LANKA AIR FORCE
TDI TURBOCHAEGED DIRECT INJECTION
1
Chapter 1 INTRODUCTION
1.1 INTRODUCTION TO SRI LANKA AIR FORCE
Sri Lanka Air Force has been reputed to occupy the most advanced technology and machinery
in the country out of the three military forces operating in Sri Lanka at present. It has 16 base stations
covering the entire island, and 3 training bases. There are 5 stations which carry out Flying Formation
- Katunayake, Rathmalana, Higuraggoda, Anuradhapura and Vauniya. The 12 squadrons are situated at
these 5 bases. Housing flying formations are where they carry out day to day flying activities.
SLAF is a child of Royal Air Force in United Kingdom. Before the independence Royal Air
Force was carrying operation in Sri Lanka. SLAF was established by an act of parliament in 1949, act
number 41 of 1949. The exact date of the formation of the Air Force is however, taken as 3rd
March
1951. The first commander of the Air Force, Air Commodore G. C. Blaydon and Royal Air Force was
appointed to command the Royal Ceylon Air Force. On 22nd
may 1972, when Sri Lanka was declared
a republic, the name of the Royal Ceylon Air Force was changed to the Sri Lanka Air Force.
In our training period, the commander of the Sri Lanka Air Force is Air Chief Marshal Roshan
Gunathilake who is a son of the former Air Commander Air Vice Marshal W.D.H.S.W Gunathilake.
As well as Sri Lanka Air Force is dedicating for welfare activities. The objectives of those
activities are offering support to service personnel and their families to improve their living conditions
and morale.
1.2 SLAF’S VISION & MISSION
1.2.1 Vision
TO ESTABLISH AN AIR FORCE OF HIGH OPERATIONAL EFFICIENCY
TO PRESERVE THE SOVEREIGNTY
OF SRI LANKA
2
1.2.2 Mission
TO PROVIDE HEAVY MAINTENANCE FACILITIES FOR
THE AIRCRAFT OPERATIONAL FORMATIONS. FURTHER, THE RESOURCES
AVAILABLE MAY ALSO BE USED TO UNDERTAKE COMMERCIAL PROJECTS WITH
PRIOR
1.2.3 Vision of DAE
To achieve flight safety and aircraft serviceability to its
highest standard, through improved competency and
work perfection.
3
1.3 RANK STRUCTURE
1.3.1 Commissioned Officers
Air Chief
Marshal Air
Marshal Air Vice
Marshal Air
Commodore Group
Captain Wing
Commander Squadron
Leader Flight
Lieutenant Flying
Officer Pilot
Officer
1.3.2 Other Ranks
Warrant Officer Flight Sergeant Sergeant Corporal Leading Aircraftman
1.4 DECORATIONS & MEDALS
Parama Weera
Vibushanaya
Weerodhara Vibhushanaya
Weera Wickrama
Vibhushanaya
Rana Wickrama Padakkama
Rana Sura
Padakkama
Vishishta Seva Vibhushanaya
Utthama Seva
Padakkama
Videsha Seva Padakkama
Republic Of Sri
Lanka Armed
Services Medal -
1972
Sri Lanka Air Force 25th
Anniversary medal - 1976
Queen Elizabeth II
Coronation
Medal - 1953
Ceylon Armed Services Long
Service Medal - 1968
Sri Lanka Armed
Services
Long Service
Medal-1979
President's Inauguration
Medal - 1978
50th Independence
Anniversary
Commemoration
Desha Putra Sammanaya
North & East
Operations Medal
Purna Bhumi Padakkama
Vadamarachchi
Operation Medal
Sri Lanka Air Force 50th
Anniversay Medal
Riviresa Campaign
Service Medal
Ceylon Armed Services
Inauduration Medal -1956
United Nations' Service
Medal (CONGO)
4
1.5 SRI LANKA AIR FORCE BASE, KATUNAYAKE
The Sri Lanka Air Force Base Katunayake,
the largest Air Force Base in Sri Lanka , is situated in
close proximity to the Bandaranayke International
Airport. The Base provides administrative, logistical,
general and civil engineering services to all lodger
formations located within the Base. The following
flying Squadrons are among the major lodger
formations in the base
No. 04 Helicopter Squadron
No. 05 Jet Squadron
No. 10 Fighter Ground Attack Squadron
No. 14 Squadron
In addition to the above flying formations the following formations are also located within the Base.
Supply & Maintenance Depot
Electronic & Communication
Command Argo Unit
Runway Maintenance Wing
Aeronautical Engineering Wing
General Engineering Wing
Aircraft Spares Depot
Air Defence Cmd & Control Center
Hospital
Radar Maintenance Wing
Motor Transport Repair Operating Wing
No 26 Regiment Wing
Air Field Construction Wing
No 43 Color Wing
No 62 Intelligence Wing
Parachute Training School
Mechanical & Electrical Wing
Dental Unit
SLAF Band
No 01 Air Defence Radar Squadron
Special Project Unit
Equipment Provisioning and Accounting Unit
5
A fully equipped gymnasium, a swimming pool and a cinema are among the many recreational and
sports facilities offered by the Base for its personnel. The housing complex located within the Base
provides accommodation to several hundred families of the AF personnel serving at the SLAF Base
Katunayake.
6
ORGANIZATION OF SLAF
3 O
F 7
CO AP &
SU
BASE
COMMANDERS
CO’S OF
SQUADRONS
CO
AEW
OCM
NO 2 (HTS)
SQUADRON
OCM
NO 1 (FTW)
SQUADRON
OCM
NO 3 (MARI)
SQUADRON
OCM
NO 14 (JET)
SQUADRON
OCM
NO 11
(UAV)
SQUADRON
OCM
NO 7 (HELI)
SQUADRON
OCM
NO 4 (HELI)
SQUADRON
OCM
NO 9 (AHS)
SQUADRON
OCM
NO 10 (KFIR)
SQUADRON
OCM
NO 5 (JET)
SQUADRON
OCM
NO 6 (HELI)
SQUADRON
OCM
NO 8 (LTS)
SQUADRON PILOTS
COMMANDER OF SRI LANKA AIR FORCE
DAE DIRECTOR OF
AERONAUTICAL
ENGINEERING
CHIEF OF STAFF
DGE DIRECTOR OF
GENERAL
ENGINEERING
DOPPS DIRECTOR OF
AIRCRAFT
OPERATIONS
DHS DIRECTOR
OF HEALTH
SERVICES
DW DIRECTOR
OF
WELFARE
DP
DIRECTOR OF
PLANNING
DETE DIRECTOR OF
ELECTRICAL &
TELECOMMUNICATION
ENGINEERING
DA DIRECTOR OF
ADMINISTRATION
DT DIRECTOR
OF
TRAINING
DCE DIRECTOR OF
CIVIL
ENGINEERING
DL DIRECTOR
OF
LOGISTICS
MINISTER OF DEFENSE
PRESIDENT OF SRI LANKA
7
ORGANIZATION OF AEW
SNCO I/C
CIVIL
CONTROL
SNCO I/C
DISCIPLIN
ARY
SNCO I/C
ORDERL
Y ROOM
OC
SPECIAL
PROJECT
WIN
G
WAR
RAN
COMMANDING OFFICER
OC TECH
PLANNING
&
CONTROL
OC
ADMINISTRATION
OC
AR &
SS
OC
PSES
OC
AVIONICS
OC
LOGIST
IC
WO I/C
SAFETY BAY
WO I/C
COMPO
NENT
BAY
WO I/C
NDT LAB
WO I/C
ROTOR
BAY
WO I/C
AR &
SS
WO I/C
SPECIAL
PROJECT
WO I/C
ENGINE
BAY
WO I/C
ELECTRICAL
BAY
WO I/C
INSTRUMENT
BAY
SNCO
I/C
FORWA
RD
SNCO I/C
ORDERLY
ROOM
WING
WARRAN
T
OFFICER
WO I/C
COMPONEN
T BAY
WO I/C
ROTOR
BAY
WO I/C
AR & SS
WO I/C
TECH
PLANNING
& CONTROL
WO I/C
SPECIAL
PROJECT
WO I/C
ENGINE BAY
SNCO I/C
FORWAR
D SUPPLY
UNIT
8
Chapter 2 : DISASSEMBLY OF A DEFENDER TDI ENGINE
Figure 2.1: Cross section of a diesel V engine
2.1 Disassembling process
The procedure is initiated by removing the oil sump by removing purge nut sump. Next attempted the
drain water in the cooling system, but since the drain nut system is corroded cooling becomes difficult
and there the water in the system that was in the system without removing. Then the injector pump,
vacuum pump, oil filter and the front cover were removed. After that the pressure plate, clutch plate,
inlet and exhaust manifolds were removed. Then the flywheel, the tappet cover, rocker shaft, push
rods, intor nozzles, heater plugs, valve tips, engine head and the cam followers were removed. After
the motor is turned upside down and the crankcase oil filter end bearings and main bearings were
removed and the pistons were removed. Next the cam shafts and the oil swans were removed.
All components except the engine head, injection pump, oil pump, water pump and front cover washed
using Auta and was cleaned with pressurized water components jet. Finally well dried with
compressed air and They were oiled to prevent rusting.
2.2 Important points to be considered
1. Engine heads are never washed using Auta. If not the gasket will perish and sealing the engine
head to the engine block want happen properly.
2. As soon as the components are dried, it should be oiled to prevent the formation of rust. But
not all need to be oiled. Finally component surfaces and surfaces with fine surface finish.
Eg: cylinder bores, cam faces, bearing sleeves, cam rollers and crank shafts are the components
that need to be oiled. After that the engine block was washed using Auta and was cleaned and
dried. Finally, the cylinder bores were oiled.
9
3. Banjo bolts should not be tightened using excessive torques. If so they will fail under torsion
4. Nuts and bolts smaller M10 tight are must always be removed using a hexagon socket.
(Open end wrenches can be used. But tend to slip damaging the hexagonal nut or bolt. When
this repetition, gradually impossible to be removed or secured with a key becomes.)
Figure 2.2: Cross section of a Pushrod and overhead cam engine
10
Chapter 3: ASSEMBLY OF A DEFENDER TDI ENGINE
3.1 Assembling process
The assembly process began by fixing the swans. Next oil hoses main bearings and thrust bearings
were fitted and were oiled. Then, the crankshaft is placed in place and the remaining halves of bearings
(bearings main) is attached and bearing caps were fixed. The end-play of the crankshaft was checked
using a dial gauge.
Figure 3.1: Measuring by using a dial guage
The final game is usually set to 7 min. After the gap of piston rings were measured. This as is done by
inserting a ring into the hole, pushing the piston and then measure the gap using thicknesses gauges.
The process was repeated three rings. (the gap for the compression ring should be 0.6mm, whereas for
compression and rings should be 0.4 mm.)
Figure 3.2: Measuring gap of a piston ring
Then, the piston rings inserted into the pistons using a circlip plier. Next pistons inserted into the hole
using a clamp ring and piston were pushed into place using a hammer and a wooden pole. Then
11
bearings were inserted head and covered it attached. The carrying handle is rotated after setting each
piston in order to ensure that there are no obstructions and the crank rotates continuously.
Figure 3.3: A piston ring compressor (Ring Clamp)
Then the camshaft is mounted and the feed pump and vacuum pumps fixed. Then the bell was
attached. After that the gears were set and the timing belt was overlooked and so tense using suitable
matrix tensioner .Then the cover was fixed and the damper pulley, pulley fan, power steering pump
pulley attached. Then the wheel set and twice crankshaft is rotated to ensure obstructions. After
absence of ant oil filter and drain cap were fixed. Next the cam followers were fixed. Then the motor
head and push rods were inserted. After noticed that the rocker was placed correctly and was fixed.
The game Valves set to 0.2 mm using the 'nine method'. After the cover pusher respite unit, injection
pump, injectors and glow plugs were fixed. Finally the inlet and exhaust manifolds were fixed.
Figure 3.4: Adjusting tappet clearance
3.2 Settling tappet clearance
First rocker arm adjuster adjuster is loosened completely. Next decreased to almost touch the valve
end. Then the valve tip and 0.2 mm thickness gauge is placed over the valve was placed to tip. After
the adjuster is reduced to gauge. Finally touched firmly held probe adjuster closed place by tightening
the screw.
12
Figure 3.5: Setting tappet clearance
The Nine methods
This method is used only for the defender TDI engine. The process involve four steps.
1. Turn the crank and observe the valves to see which valve is rising.
2. Turn the crank continuously until the rising valve stops its motion(At the beginning of the
‘Dwell” of the valve cam)
3. If the valve is the nth
valve then tappet clearance is set to the (9-n)th
valve.
4. Tappet clearance is set as mentioned above
3.3 Important points to be considered
When tightening bolts a torque wrench should be used(Specially in fixing the flywheel,
connecting rods and the engine head)
1. A torque of 40 Nm is used for flywheels.
2. A torque of about 40 Nm is used for the connecting rods.
13
At the top of the engine; Initially all nuts are tightened with a torque of 40 Nm. Next whole nut is
rotated by 60 0 .After all nuts are rotated once again by the two central rows 60
0.Finally nuts is further
rotated by other 20 0(This is done in order to ensure that the nuts are tightened to the proper torque). If
not at times due to the presence of rust etc. the actual torque may be less than the value set in the
torque wrench.
Figure 3.6: The Engine head
3. When fastening the nuts of the connecting rods and the engine head a diagonal pattern ( Nuts
are tightened alternatively, starting at the middle and progressing to the ends.)should be used in
order to prevent distortion.(The reverse of the pattern must be used in removing the nuts)
14
Chapter 4 DISASSEMBLY OF DEFENDER TDI GEAR BOX
4.1 Disassembling process
Figure 4.1 : The components of a gearbox
First the transfer case is removed from the gearbox. Then the gear selector switch and four-wheel drive
was removed. Then the bush in the gearbox is removed by heating using an oxyacetylene cutter and
lever out of position using two types levers. After that the accommodation and the gear assembly was
taken retired out. Next shaft top, main shaft, lay shaft and idler wheel removed. Then reverse forks
hubs. Next withdrew from the security rings, brushes, O-rings, needle bearings and tapered roller
bearings possible were removed and the main shaft It was taken to the hydraulic pressure. Bearing
larger tapered roller was not removed and the gears were eliminated one after the other. Next to dogs
and retaining springs are eliminated.
Figure 4.2 :Separation of the gearbox
15
4.2 Important points to be considered
1. When removing the bush, care should be taken not to damage the edges.(If the edges get
damaged the oil seals at the ends of the bush will get turn off)
2. After removal of the components, dog teeth of the hubs and gears should be checked. If that
have disappeared and have been rounded pointy teeth, the wheel or the axle has to be replaced.
If not want to participate adequately gears. Also the tip of the gear teeth should be checked for
cracks or fractures. If a crack or a broken gear wheel is located, should be replaced
Figure 4.3: Dog teeth in a gearbox
16
Chapter 5 ASSEMBLY OF A DEFENDER TDI GEARBOX
Figure 5.1: Components of the Gearbox
5.1 Assembling process
First retaining springs are fixed to the hub and the struts (tooth struts / Dogs) held in a person place.
While all three keys simultaneously pressed into the sleeve is inserted into position by another. Both
hubs were assembled similarly. Next sprockets cones brass, bronze and slippers cone centers are
arranged in order in the splined shaft and the components were Locke in place with security rings
when needed. Then the completed main shaft was placed in the holder and the other hub was inserted
onto the shaft. Next the forks of that hub was fixed. Then the reverse ideal wheel was mounted on the
shaft and the link slides in and out of position fixed. After the shaft holding the forks fixed in position
after placing the upper shaft forks. Next remained place and the lay shaft was fixed. Then the gear
assembly was inserted into the housing properly and the screws were tightened. After the oil seal,
guides, and the bell were fixed. Finally the gear selector was fixed and coupling speed checked.
Figure 5.2: Components of the hub
17
5.2 Important points to be considered
1. Care must be taken in setting the tapered roller bearings in the middle, and in the end. They
never be beaten. Should be placed using a hydraulic press. Even in the process, the force must
be applied with intense care. (Applying pressure should be stopped if you feel an obstruction
to waive force. If bearing damage.)
2. It should be clear that the two fork slots and slot the shifter idle must be aligned before
inserting the set of gears in the housing. (If not certain gears may not engage)
18
Chapter 6 THE TRANSFER BOX
Figure 6.1 : Components of a transfer box
The transfer case is connected to the transmission and the front and real axles per unit means of shafts.
This also known as "gearbox transfer", “Transfer Case "," Jockey box "or" T-box ")
6.1 Function of a transfer box
1. Power transmission is received and sends it to the front and rear axles. This can be done either
by gears or chain drivers. In some transfer cases operating mode can be switched between "four
wheels" and "two-wheel drive "through a shifter, while others are operated using switches. The
guy who left is not selectable transfer boxes (box Defender transfer is selectable transfer box
with a driven gear shifter,)
2. In the transfer path boxes synchronize the rotation difference between the front and rear
wheels. This necessary when front and rear types rotate at different speeds because of the
difference in tire sizes. (In simple terms transfer boxes act as central differential gear)
3. In off-road vehicles, transfer boxes acts as differential locks.
Figure 6.2 : Components of a transfer box
19
Chapter 7 LATHE MACHINES
Around a power driven, general purpose machine tool used for production of the cylindrical work
piece. As the metal piece to be machined is rotated on the lathe, a single tool cutting point is advanced
radially into the work piece a specified depth and longitudinally moved along the axis of the work
piece, the removal of metal in the form of chips. Both inside and outside surfaces can be machined on
a lathe. By using attachments and accessories, other operations such as drilling, boring, and the conical
shape and angle of rotation, screw thread persecution, knurling, milling, grinding and polishing can be
done.
Figure 7.1: Main Components of a Lathe Machine
7.1 Main parts of lathe machine
1. Headstock
The head is attached on the left side of the bed, which is formed by the spindle drive gear and
shift levers. Three jaw chuck jaws and four plate are most commonly used to hold or clamp the
work piece to be cut.
2. Tailstock
The counterpoint is on the right side of the bed. It can be locked in any position along the bed
of the lathe tailstock clamp. It can be used to support long work piece during the cutting
process. Counterpoint spindle is used to receive the deadlock, which provides support for the
far right of the work.
3. Bed
The bed is a heavy, rugged casting made to support the working parts of the lathe. On its top
section are machined ways that guide and align the major parts of the lathe.
20
4. Lathe carriage
Around the truck carrying the cutter (tool post) and precisely controls the movement is parallel
to the ways called turning straight or right angle to form, called front. The car mount has three
main parts, the compound rest, and an apron.
5. Face Plate
A faceplate is used to drive a lathe dog which in turn is firmly attached to the work piece.
Contains more open slots or grooves in T so that the bolts or screws T can be used to secure the
work piece to the face plate. Many types of work that can not be kept in baboons may
conveniently be machined when mounted on the faceplate.
6. Three jaw universal Chuck
A three jaw chuck work holding cylindrical or hexagonal. The three jaws move together to
bring the work in the center. Two sets of interchangeable jaws are provided. These are called
inside and outside jaws.
7. Four Jaw independent Chuck
The four-jaw independent chuck is used to hold most of the work for which a mandrel is
required. The jaws of hardened steel are reversible and sustain work of different sizes and
shapes. Each jaw can be moved independently of the others so that the work pieces can be
delivered accurately to run. A four-jaw independent chuck has several circular grooves around
the face of the body. The jaws can be approximately centered by adjusting the jaws to these
slots. The work piece is then inserted and tightened jaws enough to hold the job instead.
Reverse the tool, tighten finger tight only, and make it until it touches the work piece. Rotate
the dish by hand to locate the high or low point of the work piece. Adjust the jaws until the
work piece runs true. If more precision is required, using a test indicator.
7.2 General Operation of Lathe Machine
Turning Operation : Turning operation is used to reduce the diameter of a cylindrical work piece. A
single cutting tool removes the material from a rotating work piece to generate a
cylindrical shape.
Facing operation : Tool is fed radially inward direction and facing the work piece. Normal facing is
done from outer edge to the center of the work piece.
Taper Turning : The diameter of a work piece changes uniformly from one end to other.
21
Chamfering : Cutting edge cuts an angle on the corner of the cylinder forming a chamfer.
Figure 7.2: A Lathe Machine
7.3 External Threads cutting operation
First, the cutting of the thread is mounted on the tool post at right angles to the work that was aligned
correctly using a screw cut meter. Then a slow turn had to be selected so that the need for sufficient to
reverse or remove the cross slide and turn off the machine at the end of the thread time. The work
piece is turned required outer diameter and a beveled edge was machined on the free end of the work
piece. Each thread was cut in several steps. The depth of cut can not be great if you can not overload
the motor may fall or tip the tool. Turn back or remove the cross slide at the end of each cut, the motor
is reversed to bring the tool to the starting position. The tool is adjusted to a new cutting depth by
using reading hand wheel cross slide. Lastly, cleaning the cut thread profile he was done and cleaned
up the thread.
7.4 Important points to be considered
1. The cutting depth should be adjusted around 1mm per one step
2. After the cutting outline of the threads, it should be checked whether the cut is on desired pitch
by using a thread pitch gauge.
3. When the tool reaches the end of the cut quickly tool is turned to away from the work piece
using the cross slide crank.
22
Chapter 8 WELDING
Figure 8.1 : The welding proces
Figure 8.2 Welding process
WELDING
PROCESS
Fusion welding
process
Gas welding
Oxy acetylene
Oxy hydrojen
Arc welding
Unshielded arc Inert gas shield
arc
MIG welding
TIG welding
Atomic hydrogen arc
Submerged arc
Other processes
Pressure welding process
Black smith's forge welding
Electric Resistance
welding
Spot welding
Projection welding
Seam welding
Butt welding
Flash Butt welding
Cold pressure welding
Friction welding
23
8.1 Metal Inert Gas Welding (MIG)
First the machine was turned on and the CO2 cylinder valve was opened. Next metal strips are held in
place with a little space between them. The ends were then labeled. Finally he completed welding
accordingly
Figure 8.3:A diagram of MIG welding
8.2 Gas welding
First the oxygen cylinder valve and acetylene cylinders opened and the gas in the cylinders were
confirmed. Next both pressure adjusting screws (ie, oxygen and acetylene) were completely oxygen
valves closed. Then and acetylene cylinder valve is opened needle respectively. Next acetylene torch
was opened. the screw pressure was adjusted to obtain the desired pressure and the needle valve was
closed. The same was repeated with the needle valve. Then oxygen needle valve acetylene opened a
swing and ignited using a spark igniter or flame. After the oxygen needle valve was slowly opened
until the flame oxidant obtained. Finally strips metal were marked at the extreme ends are welded
accordingly
Figure 8.4: A diagram of Gas welding
24
8.3 Tungsten Inert Gas Welding (TIG)
First the tungsten electrode was checked to confirm that the tip is in good condition, Next machine
became a cylinder valve argon opened. Then settings were chosen to adapt accordingly the material to
be welded. Next the metal strips were kept in place with a diameter equal to the gap filler wire. After
labels are placed on the welding was completed ends.
Figure 8.5: A diagram of TIG welding
25
Chapter 9 NON DESTRUCTIVE TESTING
Non-destructive testing (NDT) is a new synthetic scientific technology that is a powerful tool for
reducing costs, improving product quality, and maintaining quality levels. It is a test that includes all
possible methods of detection or measurement of the properties or performance capabilities of
materials, parts, assemblies or structures, which don’t impair their serviceability. There are six
methods using in NDT lab of AEW.
Visual testing
Radiographic testing
Ultrasonic testing
Eddy current testing
Magnetic particle testing
Liquid penetrant testing
Procedure of NDT.
Inspection
Measurement
Monitoring
Figure 9.1: NDT testing
26
9.1 Radiographic testing (RT)
When rays pass through the matter, some of these rays are absorbed. The amount of absorption
depends upon the thickness and density of the matter; therefore, the intensity of the rays emerging
from the matter varies. The intensity of rays at the point where there is no defect is greater than that
where defect exists. When this variation is detected, the quality of the matter can be determined.
9.2 Magnetic particle testing
When there exists a discontinuity in the material, magnetic force line will make a detour round the
discontinuity. If the flaw is on or near the surface of material, some magnetic force line will run out of
the material, and magnetic leakage field is produced. Then when you spray some magnetic particles or
liquid on surface, the leakage field will adsorb particles and form a flaw indication. From the magnetic
indication, flaws can be easily determined
9.3 Ultrasonic testing
Ultrasonic wave can enter into material, and it will be reflected at the interface between two agents.
Ultrasonic waves are generated and accepted by probe, which is one part of the ultrasonic detector and
includes straight probe and slope probe. The piezoelectric crystal of them is the key unit for energy
transducer, the function of it is generating longitudinal wave and finishing conversion between
acoustic energy and electric energy.
Figure 9.2 Ultrasonic testing
27
9.4 Eddy current testing
Eddy current is produced in the tested material. And for different material or in different state, the
eddy current is different. If there lies a flaw, the eddy current field at the flaw will be different from
that at the other place. So we can determine whether or where the flaw lies.
Figure 9.3 Eddy current testing
9.5 Penetrate testing
Color liquid or fluorescent liquid suck into the out crack in the work piece. Then clear the surface of
work piece. If you use a sorbent to suck out the liquid, the image of crack will appear
28
Chapter 10 CONCLUSIONS
Engineering is not an easy task as a career. It is essential to have good practical knowledge and also
experience to do the task effectively. As engineers we are responsible to do several occupations. He
must play various characters once he is an advisor, once he is a manager, once he is a manager
likewise an engineer should have good personality to handle everything properly. As an engineer he
should be able to associate with every person in the site as well. He should be able to create good
communication with each other to enhance the work in the site. And he has the ability of labor
handling.
The efficiency of the SLAF was incredibly high and the quality of the outputs were unmatchable any
other production. But massive scale safety of the workers were questionable. Workers were safety
shoes and eye protection but hardly wear hearing protection and better masks. In some arrangements
can do to complete workers to use safety equipment.