Title Slide
MONTHLY STATUS REPORT– September 2014 LOS ALAMITOS UNIFIED SCHOOL DISTRICT
Oak Middle School Modernization Project
September 9, 2014
Los Alamitos, California
ACTIVITY SUMMARY
Progress 21
• Track • Grow-Out Period On-Going
Track and Field
Field Area
ACTIVITY SUMMARY
Progress 21
• Building N Entry • Demolition Complete
Southern View Building N Entry
Southern View Building N Entry
ACTIVITY SUMMARY
Progress 21
• Building N Entry • Demolition Complete
Plumbing Pipe Supporting Entry Doors
Entry Section Not Tied Into Building
ACTIVITY SUMMARY
Progress 21
• Classroom Building M • Complete
Building M Southern Facade
Building M Typical Classroom Interior
ACTIVITY SUMMARY
Progress 21
• Building N • Complete – Pending Multi-Purpose Room Turn-Over
New Kitchen Hood and Finishes
New Kitchen Pass Through and Railings
ACTIVITY SUMMARY
Progress 21
• Building N • Choir Room Complete
Choir Room View to Office Spaces
Choir Room View to Main Entry
ACTIVITY SUMMARY
Progress 21
• Buildings E and N • Complete
Building N, Multi-Purpose Room
New Classroom Building E
ACTIVITY SUMMARY
Progress 21
• Band Room and Outpost - Building L • Demolition Complete – Rough-Ins On-Going
Exterior Preparation - Ongoing
Rough Framing for New Offices
Schedule
Phase 7
• Buildings L & N
• Complete Multipurpose Room, Building N
• Complete Entry of Building N
• Complete Classroom Building L
• Continue Remediation of Track
• Continue Grow-Out Period
SCHEDULE