Langdon SVC Replacement g pAPIC 2010
Colin Clark
APIC Power & Energy Innovation Forum
Varun Chhibbar
OutlineOutline
• DefinitionsDefinitions• Purposes of the Langdon SVC
Th L d SVC R l t P j t• The Langdon SVC Replacement Project• Design Improvements• Lessons learned• HighlightHighlight
APIC Power & Energy Innovation Forum
DefinitionsDefinitions
• Static Var Compensator (SVC)Static Var Compensator (SVC)– Controls reactive power with conventional
Inductors and CapacitorsInductors and Capacitors– Acts as a variable shunt impedance
• Thyristor or SCR Silicon Controlled• Thyristor or SCR – Silicon Controlled RectifierV l b k t b k th i t i ith• Valve – a back to back thyristor pair with snubber circuit
APIC Power & Energy Innovation Forum
Definitions ContDefinitions Cont…• TCR – Thyristor Controlled ReactorTCR Thyristor Controlled Reactor• TSC – Thyristor Switched Capacitor
6 Pulse SVC fires 6 times per cycle• 6 Pulse SVC fires 6 times per cycle• 12 Pulse SVC fires 12 times per cycle
APIC Power & Energy Innovation Forum
12 Pulse SVC(Old Langdon SVC)
240 kV
20 kV20 kV
TCR TSC TCR TSC13th11th 23th 13th11th 23th
APIC Power & Energy Innovation Forum
Langdon SVC FunctionallityLangdon SVC Functionallity• Voltage control of the 240 kV bus (253 kV)
S t di t b• System disturbance response• Reduce overvoltages for 1201L energization
t ior trip• Improve system performance during load
h ddishedding• Increase stability limit of the network• Assist operators with dispatch of switched
capacitor banks
APIC Power & Energy Innovation Forum
Main Project DriversMain Project Drivers• Control system no longer supported (1985)• Few thyristor spares remaining• UV damage and checking of main air coreUV damage and checking of main air core
reactors• Inherent cooling issues that limited output• Inherent cooling issues that limited output
• Reactor valve overheating due to cooling system failure – June 2nd 2008
APIC Power & Energy Innovation Forum
Langdon Project RequirementsLangdon Project Requirements
• Like for like replacementLike for like replacement• AESO request - capability to control
remote mechanically switched capacitorsremote mechanically switched capacitors• Same physical location (P&L for fence)
APIC Power & Energy Innovation Forum
2 x 3” AL FLAT BUS2 x 3 AL FLAT BUS
1/2” COPPER TUBING1/2” COPPER TUBING
APIC Power & Energy Innovation Forum
The Langdon ProjectThe Langdon Project+ Two Phases+ Phase One – complete December 19th 2008
- 4 months to replace TCR valves etc4 months to replace TCR valves, etc. Different cooling pressure and firing signalsThree control systems (CWC-85, VarMach-99, Mach2-08)y ( , , )
+ Phase Two – complete November 26th 2009Replace remaining equipment- Replace remaining equipment
APIC Power & Energy Innovation Forum
Actual VI CurveActual VI Curve• Rating
± 250 MVAr @ 1.0pu± 302.5 MVAr @ 1.1 pu473 MVAr Rx, 10 min overload
APIC Power & Energy Innovation Forum
12 Pulse SVC(New Langdon SVC)
240 kV
20 kV20 kV
TCR TSC TCR TSC12th 12th
31 MVAr 31 MVAr156 MVAr 94 MVAr 94 MVAr156 MVAr
APIC Power & Energy Innovation Forum
156 MVAr 94 MVAr 94 MVAr156 MVAr
Design Improvementsg p• Simplified filter design• Elimination of legacy air switches • Bus protection without groundingBus protection without grounding
transformers• Enhanced surge protection• Enhanced surge protection• Thyristor replacement without draining
licooling
APIC Power & Energy Innovation Forum
Design Improvementsg p• Lifecycle sparing approach – 220 line items• Cooling: fewer piping connections, SS
versus PVC, pump HMI, p p• Controls over DNP with hardwire backup• Low noise design• Low noise design• Bird and rodent ‘resistant’
APIC Power & Energy Innovation Forum
Langdon SVCProtection Block Diagram
240 kV
20 kV20 kV
TCR TSC TCR TSC12th 12th
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned
• Design ReviewsDesign Reviews
86-1 Breaker TC1Trip
86-2 Breaker TC2Trip
Trip Logic
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned• Clear outage plans• Study models• Never assumeNever assume• Involvement of field technicians
O li f i ti• Open lines of communication• On-site supervision• Clear Interface points
APIC Power & Energy Innovation Forum
Lessons LearnedLessons Learned• On-site involvement of ACC operator• Burn-in period• Local project managementLocal project management• Complications due to phase approach
K l d bl i i i t ff• Knowledgeable commissioning staff• Built in fault recording system
APIC Power & Energy Innovation Forum
HighlightHighlight
Trip the inter-tie with BC (1201L) underTrip the inter tie with BC (1201L) under different import and export conditions
Operate the SVC at its thermal limit
APIC Power & Energy Innovation Forum