NMDOT FNMDOT FORMSORMS M MANAGEMENTANAGEMENT S SOLUTIONOLUTION PPROJECTROJECT

PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN (PMP)(PMP)

EXECUTIVE SPONSOR – TOM CHURCH, NMDOT CABINET SECRETARY, DESIGNATE

BUSINESS OWNER – BRUCE OAKELEY, NMDOT ISM BUREAU CHIEF

PROJECT MANAGER – SAL HERNANDEZ, INTEGRATUS SOLUTIONS

ORIGINAL PLAN DATE: DECEMBER 13, 2013REVISION DATE: JANUARY 2, 2014

REVISION: 2.2

REVISION HISTORY.............................................................................................................................................. 3

1.0 PROJECT OVERVIEW...................................................................................................................................... 4

1.2 FUNDING AND SOURCES...........................................................................................................................................41.3 CONSTRAINTS........................................................................................................................................................51.4 DEPENDENCIES.......................................................................................................................................................51.5 ASSUMPTIONS...................................................................................................................................................61.6 INITIAL PROJECT RISKS IDENTIFIED...........................................................................................................................7

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE.............................................................................8

2.1 STAKEHOLDERS......................................................................................................................................................82.2 PROJECT GOVERNANCE STRUCTURE...........................................................................................................................9

2.2.1 Describe the organizational structure – Org Chart.....................................................................................92.2.2 Describe the role and members of the project steering committee...........................................................92.2.3 Organizational Boundaries, interfaces and responsibilities.......................................................................9

2.3 EXECUTIVE REPORTING..........................................................................................................................................10

3.0 SCOPE......................................................................................................................................................... 10

3.1 PROJECT OBJECTIVES............................................................................................................................................103.1.1 Business Objectives..................................................................................................................................103.1.2 Technical Objectives................................................................................................................................10

3.2 PROJECT EXCLUSIONS............................................................................................................................................113.3 CRITICAL SUCCESS FACTORS...................................................................................................................................11

4.0 PROJECT DELIVERABLES AND METHODOLOGY.............................................................................................12

4.1 PROJECT MANAGEMENT LIFE CYCLE........................................................................................................................124.1.1 Project Management Deliverables...........................................................................................................134.1.2 Deliverable Approval Authority Designations..........................................................................................154.1.3 Deliverable Acceptance Procedure...........................................................................................................19

4.2 PRODUCT LIFE CYCLE.......................................................................................................................................194.2.1 Technical Strategy...................................................................................................................................204.2.2 Product and Product Development Deliverables......................................................................................214.2.3 Deliverable Approval Authority Designations..........................................................................................224.2.4 Deliverable Acceptance Procedure...........................................................................................................22

5.0 PROJECT WORK........................................................................................................................................... 23

5.1 WORK BREAKDOWN STRUCTURE (WBS)..................................................................................................................235.2 SCHEDULE ALLOCATION -PROJECT TIMELINE..............................................................................................................245.3 PROJECT BUDGET.................................................................................................................................................245.4 PROJECT TEAM....................................................................................................................................................25

5.4.1 Project Team Structure, Roles and Responsibilities..................................................................................255.5 STAFF PLANNING AND RESOURCE ACQUISITION................................................................................................26

5.5.1 Project Staff.............................................................................................................................................265.5.2 Non-Personnel resources.........................................................................................................................26

5.6 PROJECT LOGISTICS.........................................................................................................................................265.6.1 Project Team Training..............................................................................................................................27

6.0 PROJECT MANAGEMENT AND CONTROLS....................................................................................................27

6.1 RISK AND ISSUE MANAGEMENT..............................................................................................................................276.1.1 Risk Management Strategy......................................................................................................................276.1.2 Project Risk Identification........................................................................................................................286.1.3 Project Risk Mitigation Approach............................................................................................................28

PAGE | 1

6.1.4 Risk Reporting and Escalation Strategy...................................................................................................286.1.5 Project Risk Tracking Approach................................................................................................................296.1.6 ISSUE MANAGEMENT..............................................................................................................................29

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&V...........................................................................................296.3 SCOPE MANAGEMENT PLAN..................................................................................................................................30

6.3.1 Change Control........................................................................................................................................306.5 COMMUNICATION PLAN........................................................................................................................................31

6.5.1 Communication Matrix............................................................................................................................316.5.2 Status Meetings.......................................................................................................................................316.5.3 Project Status Reports..............................................................................................................................31

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS).....................................................................................326.7 QUALITY OBJECTIVES AND CONTROL..............................................................................................................32

6.7.1 quality Standards.....................................................................................................................................336.7.2 Project and Product Review AND ASSESSMENTS.....................................................................................336.7.3 Agency/Customer Satisfaction.................................................................................................................346.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS......................................................................................34

6.8 CONFIGURATION MANAGEMENT...................................................................................................................386.8.2 Project Repository (Project Library).........................................................................................................38

7. 0 PROJECT CLOSE........................................................................................................................................... 39

7.1 Administrative Close...................................................................................................................................397.2 Contract Close.............................................................................................................................................39

PAGE | 2

REVISION HISTORYREVISION HISTORY

REVISION NUMBER DATE COMMENT

1.0 July 27th, 2007 DoIT Project Management Plan template

2.0 December 30th, 2013 Initial creation of PMP from DoIT template

2.1 January 2nd, 2014 Revised to add rough scheduling and project task details

2.2 January 3, 2014 Revised to add Section 6 specifics and other content updates

2.3

PAGE | 3

1.0 PROJECT OVERVIEW The New Mexico Department of Transportation relies thoroughly on the forms catalog it presently has implemented within its agency. The information management practices around the usage of these documents are essential to the functioning of its business. There have been over three hundred forms identified as used for different areas within the agency.

These forms are currently created using an older methodology, which makes the information management practices cumbersome, manual-intensive and prone to human errors and delays. The manual process calls for forms to be printed and then delivered (via mail or fax) to the agency. The form submission process is decoupled from the process flow.

Furthermore, These forms reside on an aging system that requires it to be replaced before it begins to degrade service within the agency.

NMDOT has chosen to modernize and substantially improve the form submission process. Modernization Improvements will include digitizing the document submission process as well as improving the form submission lifecycle, this will reduce process times and errors. The intrinsic benefits include creating a more productive and responsive agency thereby increasing customer satisfaction.

1.2 FUNDING AND SOURCES

SOURCE AMOUNT ASSOCIATED RESTRICTIONS

APPROVERS

NM STATE ROAD FUND

$500,000

PAGE | 4

1.3 CONSTRAINTSThe following factors can potentially restrict the project by scope, resource, or schedule.

NUMBER DESCRIPTION

1Time – Project will need to be closed out by June 30th 2014

2Budget – Project not to exceed $500K

3Scope – Project scope need not exceed existing project estimates and increased scope be addressed/approved or denied by Project Steering Committee

4Software – Project technical deliverables need to be developed with Adobe LiveCycle software and related tools

5Resources - Project will need to be completed with a mix of NMDOT and Contractor resources

6Budget – Project cannot cause a dramatic shift in operational cost.

7Process – Project will adhere to applicable DoIT methodology

8Agency – Project will adhere to applicable NM State and NMDOT policies and regulations.

9Agency – Project technical deliverables to meet existing service agreements and response times.

10Infrastructure – Software must be configured and operate alongside existing NMDOT infrastructure without disrupting ongoing business service.

1.4 DEPENDENCIES Mandatory dependencies are dependencies that are inherent to the work being done. D- Discretionary dependencies are dependencies defined by the project management

team. This may also encompass particular approaches because a specific sequence of activities is preferred, but not mandatory in the project life cycle.

E-External dependencies are dependencies that involve a relationship between project activities and non-project activities such as purchasing/procurement

NUMBER

DESCRIPTION TYPE M,D,E

1 ACTIVE DIRECTORY - ENSURE A PROPER MANAGEMENT INTERFACE EXISTS FOR THE ACTIVE DIRECTORY MANAGEMENT AS WELL AS ENSURE CONTENT IS UP TO DATE

M, E

2 TRAINING - DELIVER PROPER DEVELOPMENT TRAINING FOR FORMS AND PORTAL DEVELOPERS

M

3 INSTALLATION AND CONFIGURATION - ENSURE THE PROPER HARDWARE, SOFTWARE AND INFRASTRUCTURE IS MADE AVAILABLE

M, E

PAGE | 5

NUMBER

DESCRIPTION TYPE M,D,E

4 ORGANIZATIONAL BUY-IN - ENSURE EXECUTIVE AND SME BUY-IN FOR NEW TECHNOLOGY AND PROCESS

M

5 TECHNOLOGICAL - ENSURE PROPER IMPLEMENTATION OF TBD APPROACH (ELECTRONIC V DIGITAL SIGNITURES)

M

6 ORGANIZATIONAL - ENSURE SUBJECT MATTER EXPERTS ARE EXCESSIBLE – BOTH FUNCTIONAL AND TECHNICAL SME’S ARE REQUIRED

M

1.5 ASSUMPTIONS

NUMBER DESCRIPTION

1All system users exist in NMDOT’s Active Directory. All system users are internal to the agency.

2Business rules for form data and routing relating to existing forms are known and fixed.

3Servers and client workstations meet or exceed the minimum requirements of the technology stack.

4The form templates will be developed using a proper common format. If such a format is not possible, then the form will be provided in an alternative format and will be served as fill and print forms.

5Project team will have access to functional and technical SMEs

PAGE | 6

1.6 INITIAL PROJECT RISKS IDENTIFIED

[Risk 1 Active Directory]

Description – Active Directory entries are incorrect thus effecting forms with workflow

Probability EXPECTED Impact HIGH

Mitigation Strategy – 2 fold strategy Initial and On-going1. Initial – There is an initial effort to clean up Active Directory

entries in bulk, especially for those Users/Groups identified as prospects for forms with workflow.

2. On-going – An interface will be developed for the Human Resources department to actively monitor and update Active Directory entries. Major Events (Hire to Fire) will trigger an resource to update the Active Directory.

Contingency Plan1. Continuous efforts to clean up the Active Directory entries on

a regular interval

[Risk 2 – Software Features]

Description - Features and capabilities of the product may be wrong, incomplete, or too complex and that may not satisfy the requirement.

Probability LOW Impact MEDIUM

Mitigation Strategy1. Complex scenarios were given to Vendor during a Proof of

Concept initiative when evaluating software.2. Additionally, ensure that all functionality is defined before

development begins.Contingency Plan

1. Co-Develop more difficult scenarios with Vendor or engage them for support as needed

2. Extend product, as needed with custom integration layers.

[Risk 3 – Software Training]

Description – Resource training on software is inadequate or has not taken place

Probability LOW Impact MEDIUM

Mitigation Strategy1. Training Plan to be developed for technical developers and

support staff2. Engage Vendor for development as needed

Contingency Plan1. Engage Vendor for development or support as needed and

engage in over-the-shoulder development until adequate training plan can be established.

PAGE | 7

[Risk 4 – End User Adoption]

Description – End users are slow to adopt forms development

Probability LOW Impact HIGH

Mitigation Strategy1. Continuously involve end users at the appropriate level of

detail.Contingency Plan

1. Executive mandate of solution set

2.0 PROJECT AUTHORITY AND ORGANIZATIONAL STRUCTURE

2.1 STAKEHOLDERS

NAME STAKE IN PROJECT ORGANIZATION TITLE

Bruce Oakeley Responsible for the modernization of the Forms Portal and the replacement of the existing legacy system.

NMDOT Information Systems Bureau Chief

Gilbert Archuleta Key actor in regard to all forms relating to employee information

NMDOT Human Resources Bureau Chief

Julie Atencio Responsible for oversight of NMDOT forms, and managing changes and additions to NMDOT’s forms catalog.

NMDOT Acting Inspector General

PAGE | 8

2.2 PROJECT GOVERNANCE STRUCTURE2.2.1 DESCRIBE THE ORGANIZATIONAL STRUCTURE – ORG CHART

2.2.2 DESCRIBE THE ROLE AND MEMBERS OF THE PROJECT STEERING COMMITTEE

N/A

2.2.3 ORGANIZATIONAL BOUNDARIES, INTERFACES AND RESPONSIBILITIES

Main communication interface is between Project Managers from Integratus Solutions (Contracting Vendor) and the assigned Team Leaders..  The primary methods utilized will be the Status Report/Briefing, ad-hoc meetings, electronic mail, and phone conversations.  Interaction may occur directly between the technical components of all teams.  However, overall task direction can only come from the Project Manager.  Final decisions will be made at the Steering Committee or Executive Level.

PAGE | 9

2.3 EXECUTIVE REPORTINGProject status will be communicated to the Executive level on a weekly basis, reports will be at an aggregate level and outline any major risk and or issues. Executives can contact project management at any time for ad-hoc reporting as it relates to project status.

3.0 SCOPE

3.1 PROJECT OBJECTIVES3.1.1 BUSINESS OBJECTIVES

NUMBER DESCRIPTION

Bus. Objective 1 Reduce cost associated to support and maintenance of Legacy Forms Portal.

Bus. Objective 2 Replace the manual-intensive Legacy Forms Portal with a modern more robust digitized form system.

Bus. Objective 3 Reduce human errors and delays with an improved process and forms workflow.

Bus. Objective 4 To provide electronic routing and signature for our agency’s most widely and frequently-used forms.

Bus. Objective 5 Create a more productive and responsive agency by reducing form processing cycle times, thereby increasing customer satisfaction.

3.1.2 TECHNICAL OBJECTIVES

NUMBER DESCRIPTION

Tech. Objective 1 To put a solid framework in place for managing forms and form data, electronic or digital signatures, and reporting needs.

Tech. Objective 2 Modernization of Legacy Forms Portal falls in line with agency effort to modernize systems.

Tech. Objective 3 Minimize business impact and make transition to a new system as seamless as possible

Tech Objective 4 Integrate new Forms portal into existing architecture

Tech Objective 5 Create a mechanism for the Human Resources organization to manage Active Directory entries.

3.2 PROJECT EXCLUSIONS

PAGE | 10

Number of reports to be converted to digital workflow is not yet defined, during the planning phase the final number of conversion eligible reports will be defined and project plan will be adjusted accordingly.

3.3 CRITICAL SUCCESS FACTORSIdentify the critical success factors for achieving success in this project. Metric are key to understanding the ability of the project to meet the end goals of the Executive Sponsor and the Business Owner, as well as the ability of the project team to stay within schedule and budget. See also section 6.7 Quality Objectives and Controls.

NUMBER DESCRIPTION

CSF - 1 AGREEMENT ON PROJECT SCOPE, GOALS AND TIMELINE

CSF – 2 MANAGE SCOPE AND CHANGES EFFECTIVELY

CSF – 3 MANAGE RISKS AND ISSUES TO RESOLUTION/REMIDIATION

CSF – 4 EFFECIVELY MANAGE RESOURCES (RIGHT RESOURCE FOR THE JOB)

CSF – 5 PROMOTE USER INVOLVEMENT

CSF – 6 EFFECTIVELY MANAGE PROJECT TIMELINE

CSF – 7 FACILITATE EXECUTIVE INVOLVEMENT

CSF – 8 REMOVE POLITICAL AND TECHNICAL BARRIERS

CSF – 9 QUICKLY RESOLVE TECHNICAL BREAK-FIX

CSF – 10 FACILITATE USER ACCEPTANCE

CSF – 11 EFFECTIVELY MANAGE PROJECT BUDGET

CSF – 12 PROMOTE EFFECTIVE COMMUNICATIONS

PAGE | 11

4.0 PROJECT DELIVERABLES AND METHODOLOGY

4.1 PROJECT MANAGEMENT LIFE CYCLE

Phase Summary of Phase Key Deliverables

Initiation Evaluation of business problem domain; research of potential solutions

Project Charter

Project Scope

Business Requirements – Business Case

Assumptions

Constraints

Authorization to proceed with planning

Planning Identification and documentation of specific business and technical requirements

Project Management Plan

Critical success factors

Work Break down Structures

Project Schedule

JAD Session

System Requirements Specification,

Implementation Installation of hardware and software for the solution; development of specific forms to implement workflow and e-signatures

Working installation of LiveCycle ES Server (test environment, production environment)

LiveCycle forms Migration and Development

End-user documentation

End-user training

Technician and form designer training

Closeout Evaluation of new solution. Deliverable or Product Acceptance

Lessons Learned

PAGE | 12

4.1.1 PROJECT MANAGEMENT DELIVERABLES

Project Deliverables are work products or artifacts that are driven by the project management methodology requirements and standard project management practices regardless of the product requirements of the project.

4.1.1.1 Project CharterProject Charter Document Deliverable Acceptance Criteria – Follow NM DoIT

Standards and review by project management and project business owners.

Standards for Content and Format – NM DoIT Standards

Quality Review –Initial document creation followed by project management, executive and business owner review

4.1.1.2 Project Status ReportsBi-weekly Project Status Reports, one to internal team members, and one to project stakeholders and oversight bodies.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review. Subsequently, reviewed by project team as a whole.

4.1.1.3 Risk Assessment ReportInitial Risk Assessment report, which will be reviewed and approved by all stakeholders.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review. Subsequently, reviewed by project team as a whole.

PAGE | 13

4.1.1.4 Business Continuity PlanA specification describing what methods the project team will employ to ensure uninterrupted service to customers during the implementation phase.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review. Subsequently, reviewed by project team as a whole.

4.1.1.5 Project Operations and Support PlanA document outlining the governance structure for the project, as well as team roles, responsibilities, and scheduling.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review. Subsequently, reviewed by project team as a whole.

4.1.1.6 Project Test Plan & StrategyA document outlining the plan and strategies to be used to test functionality in the new system.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review. Subsequently, reviewed by project team as a whole.

PAGE | 14

4.1.1.7 Project Management PlanInitial Project Management Plan, to be reviewed by all stakeholders and the PCC.

Deliverable Acceptance Criteria - Follow NM DoIT Standards and review by project management and project business owners.

Standards for Content and Format - NM DoIT Standards

Quality Review - Initial document creation followed by project management, executive and business owner review.

4.1.2 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-001Initiation - Project Initiation and Scope Focus Meetings

Bruce Oakeley

PRJ-DEL-002Initiation - Initiation Phase Certification Form

Bruce Oakeley

PRJ-DEL-003 Initiation - Project Charter Bruce Oakeley

PRJ-DEL-004Initiation - Initiation Phase Certification

Bruce Oakeley

PRJ-DEL-005Initiation - Form Evaluation and Enumeration

Bruce Oakeley

PRJ-DEL-006

Initiation - Identification of forms for electronic workflow & signature

Bruce Oakeley

PRJ-DEL-007Initiation - Change Management process for implementation phase

Bruce Oakeley

PRJ-DEL-008

Initiation - Identification of workflow end points for top 30 priority forms.

Bruce Oakeley

PRJ-DEL-009Initiation - Identification of workflow participant categories

Bruce Oakeley

PAGE | 15

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-010 Initiation - Project JAD Session Bruce Oakeley

PRJ-DEL-011Initiation - System Requirement Specification (SRS)

Bruce Oakeley

PRJ-DEL-012

Initiation - System Requirement Specification (SRS) Evaluation and Review - Round 1

Bruce Oakeley

PRJ-DEL-013Initiation - Project Status Reports (Internal)

Bruce Oakeley

PRJ-DEL-014Initiation - Initial Risk Assessment Report

Bruce Oakeley

PRJ-DEL-015Initiation - Initial Business Continuity Plan

Bruce Oakeley

PRJ-DEL-016Initiation - Initial Project Communication Plan

Bruce Oakeley

PRJ-DEL-017Initiation - Initial Project Operations and Support Plan

Bruce Oakeley

PRJ-DEL-018Initiation - Initial Project Test Plan and Strategy

Bruce Oakeley

PRJ-DEL-019Initiation - Initial Project Management Plan

Bruce Oakeley

PRJ-DEL-020Initiation - Initial Active Directory Update Plan

Bruce Oakeley

PRJ-DEL-021Planning - Planning Phase Certification Form

Bruce Oakeley

PRJ-DEL-022Planning - Revise Project Management Plan

Bruce Oakeley

PRJ-DEL-023Planning - IV&V Selected and Contract Negotiated

Bruce Oakeley

PRJ-DEL-024Planning - Project Status Reports (Internal)

Bruce Oakeley

PAGE | 16

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-025

Planning - System Requirement Specification (SRS) Evaluation and Review - Round 2

Bruce Oakeley

PRJ-DEL-026Planning - Technical Architecture Document

Bruce Oakeley

PRJ-DEL-027Planning - Revise Risk Assessment Report

Bruce Oakeley

PRJ-DEL-028Planning - Revise Business Continuity Plan

Bruce Oakeley

PRJ-DEL-029Planning - Revise Project Communication Plan

Bruce Oakeley

PRJ-DEL-030Planning - Revise Project Operations and Support Plan

Bruce Oakeley

PRJ-DEL-031Planning - Revise Project Test Plan and Strategy

Bruce Oakeley

PRJ-DEL-032Planning - Revise Active Directory Update Plan

Bruce Oakeley

PRJ-DEL-033 Planning - Initial Cutover Plan Bruce Oakeley

PRJ-DEL-034Planning - Evaluate Electronic or Digital Signature Solution

Bruce Oakeley

PRJ-DEL-035Planning - ELECTRONIC SIGNATURE - Signature Collection Plan Strategy

Bruce Oakeley

PRJ-DEL-036

Planning - DIGITAL SIGNATURE - operations and support plan for digital sig. services.

Bruce Oakeley

PRJ-DEL-037

Planning - Determine Active Directory fields needed for Live Cycle function

Bruce Oakeley

PRJ-DEL-038

Planning - Determine which support staff will update non-GO portions of Active Directory

Bruce Oakeley

PAGE | 17

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-039 Planning - Technical Team Training Bruce Oakeley

PRJ-DEL-040Implementation - Implementation Phase Certification Form

Bruce Oakeley

PRJ-DEL-041Implementation - Updated Project Management Plan

Bruce Oakeley

PRJ-DEL-042Implementation - IV&V Reports Submitted

Bruce Oakeley

PRJ-DEL-043Implementation - Technical Architecture Approved

Bruce Oakeley

PRJ-DEL-044Implementation - Project Status Reports (Internal)

Bruce Oakeley

PRJ-DEL-045

Implementation - LiveCycle ES4 Server Installation and Configuration

Bruce Oakeley

PRJ-DEL-046Implementation - Active Directory Updates - Mass Update

Bruce Oakeley

PRJ-DEL-047Implementation - Active Directory Updates - District Level Updates

Bruce Oakeley

PRJ-DEL-048

Implementation - ELECTRONIC SIGNATURE - Design / Develop web service interface for existing signature server

Bruce Oakeley

PRJ-DEL-049

Implementation - Design / develop scripting to extract and rename guid-named forms from OIG form server

Bruce Oakeley

PRJ-DEL-050Implementation - Existing Form Migration

Bruce Oakeley

PRJ-DEL-051Implementation - New Form Development

Bruce Oakeley

PRJ-DEL-052Implementation - Workflow Development

Bruce Oakeley

PAGE | 18

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-053

Implementation - Implement Electronic or Digital Signature Solution

Bruce Oakeley

PRJ-DEL-054

Implementation - Web Interface for Active Directory Organizational Maintenance

Bruce Oakeley

PRJ-DEL-055Implementation - End User Training for AD Web Interface

Bruce Oakeley

PRJ-DEL-056Close - Closeout Phase Certification Form

Bruce Oakeley

PRJ-DEL-057Close - Final IV&V Reports Submitted

Bruce Oakeley

PRJ-DEL-058 Close - Project Closeout Report Bruce Oakeley

PRJ-DEL-059 Close - Lessons Learned Bruce Oakeley

4.1.3 DELIVERABLE ACCEPTANCE PROCEDURE

Deliverables will be reviewed as follows1. Deliverable owner will review for completeness2. Deliverable will be peer-reviewed3. Deliverable will be reviewed by all of its dependent owners and project management

4.2 PRODUCT LIFE CYCLE The Project Management has decided to use the approved DoIT Project Process as outlined in the DoIT memorandum and project certification timeline.

PAGE | 19

4.2.1 TECHNICAL STRATEGY

Discuss the key technical strategies for achieving success in this project:

1. All new development to adhere to existing NMDOT development “Best-Practices” practices

2. All new infrastructure to adhere to existing NMDOT “Best-Practices” architecture

3. All Hardware and Software to be easily extensible to “add-on” for future requirements and encompass “tried and true” technologies

4. Vendor support will be important to this project, to assist with implementation and to provide training to staff.

5. NMDOT Staff will become proficient using LiveCycle ES4 Designer to create forms, and also in using the workflow tool to model, test, and deploy form workflows.

6. A virtualized server environment will provide fault tolerance, failover, and load-balancing (if needed).

7. Minimize technical knowledge needed by the end user

8. To develop deliverables in “waves” to allow end users to provide feedback for subsequent development

9. To ensure most complex developmental challenges are addressed and validated first

10. To ensure environment integrity (Dev, Test, Production) by having migration and/or build controls

PAGE | 20

4.2.2 PRODUCT AND PRODUCT DEVELOPMENT DELIVERABLES

At the highest level, the following are the project deliverables in terms of the work product delivered.

4.2.2.1 LiveCycle ES Server Installation and ConfigurationInstallation and configuration of the LiveCycle ES Server product and its related database (SQL Server)

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.2.2 Existing Forms MigrationInventory and Migrate existing agency forms to new Forms Server

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.2.3 New Form DevelopmentIdentify and develop new agency forms to new Forms Server

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.2.4 Work Flow DevelopmentCreate new work flows for new or migrated forms

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.2.5 Active Directory Web Interface for HR StaffLiveCycle will leverage Active Directory within the NMDOT to route form data based on

Deliverable Acceptance Criteria -

Standards for Content and Format -

PAGE | 21

organizational relationships; HR will be provided with a web interface to Active Directory to specify limited details such as Name, Email, Phone Number, and Manager.

Quality Review -

4.2.2.6 Electronic or Digital Signature SolutionSignatures will be rendered using an in-house electronic signature database or more formal PKI-based Digital Signatures.

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.2.7 Active Directory clean upClean up existing Active Directory entries and identify the entries needed for work flow

Deliverable Acceptance Criteria -

Standards for Content and Format -

Quality Review -

4.2.3 DELIVERABLE APPROVAL AUTHORITY DESIGNATIONS

DELIVERABLE NUMBER

DELIVERABLE APPROVERS (WHO CAN APPROVE)

DATE APPROVED

PRJ-DEL-002 System Requirement Specification (SRS)

Bruce Oakeley,Jeff Woodman

PRJ-DEL-003 LiveCycle ES4 Server Installation Jeff Woodman

PRJ-DEL-004 Redeveloped Electronic Forms

(New and/or existing)

Julie Atencio,Bruce Oakeley,Jeff Woodman

PRJ-DEL-005 Active Directory Organizational Relationships

Gil Archuleta,Bruce Oakeley,Jeff Woodman

PRJ-DEL-006 Electronic or Digital Signature Solution

Bruce Oakeley,Jeff Woodman

4.2.4 DELIVERABLE ACCEPTANCE PROCEDURE

TBD

PAGE | 22

5.0 PROJECT WORK

5.1 WORK BREAKDOWN STRUCTURE (WBS)

Identifier Work Package Description Definition/Objective Milestone/Deliverable

WBS-001 Form identification and prioritization

Determine total number of forms, and prioritize forms for electronic workflow

All forms are cataloged in a spreadsheet, with prioritization.

WBS-002 Software Installation / Configuration

Prepare the LiveCycle server environment to host forms.

Web portal is accessible on internal network; forms can be deployed to the web portal and accessed by end users.

WBS-003 Active Directory Clean up Clean up existing Active Directory Entries

Clean up Active Directory Entries

WBS-004 Active Directory Entry Interface Create Interface for the ongoing maintenance of Active Directory Forms

Development of interface solution.

WBS-005 Form Design Forms receiving electronic workflow / signature must be redesigned in XDF format for LiveCycle

Forms that are candidates for electronic workflow are deployed in LiveCycle format to the LiveCycle repository with electronic workflow and signature capability.

WBS-006 Workflow / Form Testing Verify that developed forms behave as expected and that workflow participants are properly notified.

Create Workflows; Test Workflows; ensure proper routing.

PAGE | 23

5.2 SCHEDULE ALLOCATION -PROJECT TIMELINE

Identifier Task/Activity Name Resource Name

Milestone (Y/N)

Effort/ Duration

Start Finish Dependent Task

SA-001 Active Directory Configuration

Conce Fresquez / District IT Staff

Y TBD TBD

SA-002 Web Interface for AD organizational relationship maintenance

Jeff Woodman Y TBD TBD

SA-003 Installation and configuration of LiveCycle ES Server

Alfred Lopez TBD TBD

SA-004 Form Development

Vendor / Implementation Team

TBD TBD

5.3 PROJECT BUDGET

Identifier Work Package or Budget Category Cost

PB-001 Professional Services 218,000

PB-002 Adobe Live Cycle Training 25,000

PB-003 Adobe Live Cycle 280,000

TOTAL 523000

PAGE | 24

5.4 PROJECT TEAM5.4.1 PROJECT TEAM STRUCTURE, ROLES AND RESPONSIBILITIES

Role RESPONSIBILITY NAME FUNCTIONAL AREA

Executive Sponsor

Provides direction at a high level based on business needs.

Bruce Oakeley ISM Bureau Chief, NMDOT

Stakeholder / Business Owner

Oversees NMDOT Forms, and manages additions and changes to the form catalog.

Julie Atencio NMDOT Acting Inspector General

Stakeholder / Business Owner

Oversees human resource operations for the agency, and is the owner of many of the forms

Gilbert Archuleta NMDOT Human Resources Bureau Chief

Technical Lead Overall supervision of technical project aspects

Jeff Woodman Supervisor – NMDOT Web Team

Implementation Tech

Develops forms and workflow logic

James Gomez NMDOT Web Team

Implementation Tech

Develops forms and workflow logic

Brian Gutierrez NMDOT Web Team

Implementation Tech

Develops forms and workflow logic

Matt Hunt NMDOT Web Team

Implementation Tech

Performs server configuration, assists with form development

Alfred Lopez NMDOT Web Team

Implementation Tech

Develops forms and workflow logic

Gabriel Vigil NMDOT I.T.

Project Manager Project Management Sal Hernandez Contractor

PAGE | 25

5.5 STAFF PLANNING AND RESOURCE ACQUISITION

5.5.1 PROJECT STAFF

Resource Cost EstimateEstimated Hours Availability Skill Set Work Product/Deliverable

Jeff Woodman 40 / week 90% Dev, Servers

James Gomez 40 / week 90% Dev

Brian Gutierrez 40 / week 90% Dev

Matt Hunt 40 / week 90% Dev / Design

Alfred Lopez 40 / week 90% Servers

Gabriel Vigil 40 / week 90% Dev

Sal Hernandez 40 / week 100% PM

5.5.2 NON-PERSONNEL RESOURCES

Use this section to list services or product (HW/SW and such) needed for project

Resource Cost EstimateEstimated units/hours Availability Source Work Product/Deliverable

LiveCycle ES4 Suite 225,000 n/a n/a Adobe

Windows 2008 R2 Standard Microsoft

Oracle WebLogic Oracle

5.6 PROJECT LOGISTICSProject will be developed onsite at the NMDOT offices. All contractors/resources will need to conduct project meetings and development work on-site.

Project Management will conduct regular meetings in relation to project status, requirements gathering, Issues and Risks and Change Control.

PAGE | 26

5.6.1 PROJECT TEAM TRAINING

The NMDOT forms project opens up the need for several areas of training as described below.

Resource Cost EstimateEstimated Hours Availability Skill Set Work Product/Deliverable

Technical Developers TBD 40 High Technical Developer

Form DevelopmentForm ManagementForm Technical SupportProduct Technical Support

End Users – Forms Application

TBD 40 Medium Forms Analyst

Form DevelopmentForm Management

End Users – HR Application TBD 8 Medium HR Analyst Active Directory Updates

Help Desk TBD 8 Medium Helpdesk Form Technical Support

6.0 PROJECT MANAGEMENT AND CONTROLS

6.1 RISK AND ISSUE MANAGEMENT6.1.1 RISK MANAGEMENT STRATEGY

There will be a formal strategy for how risks are identified, analyzed/ quantified, mitigated, reported, escalated and tracked.

Identification – Any member associated to the project, whether internal or external, at any time can raise an issue or risk. The identification of an issue/risk must reach the project manager via email or in writing of the details behind the issue/risk. The project manager will keep a log of all of the identified issues.

Analyze and Qualification – Each issue/risk will be analyzed and qualified as to its occurrence, probability of occurrence and surrounding factors needed to reproduce or identify the root cause.

Mitigation – Once Identified and Qualified, the project team will need to come together, whether during the regular status meeting or via a special meeting to discuss options for mitigation for each issue/risk. The Issue/Risk will be given a functional and technical owner responsible for resolution.

Tracking – The Project management shall keep an issue and risk log, which will be the subject conversation during the bi-weekly project status meeting.

PAGE | 27

6.1.2 PROJECT RISK IDENTIFICATION

The Project management will undertake a proactive risk management process. As part of this process we will evoke some or all of the following “Best Practice” approaches to and sources for identifying risks, which include:

SWOT analysis (strength, weakness opportunity, threat)

Working Groups and Project Meetings Agency knowledge

PESTLE (political, economic, social, technological, legal, environmental)

One-on-One Interviews Process analysis with SMEs

Brainstorming Stakeholder/Business Owner analysis Scenario Analysis/What if Analysis

The Project Management will undertake steps that will allow the project team analyze and interpreting information about the nature of each risk gathered during risk identification to determine the level of risk, based on the likelihood of it occurring, and the consequence if it were to occur.

6.1.3 PROJECT RISK MITIGATION APPROACH

Each Issue/Risk will be qualified, once qualified and it is decided that mitigation is necessary, the Functional and Technical owner will work in tandem to propose, design and advise Project Management of the

6.1.4 RISK REPORTING AND ESCALATION STRATEGY

Risks may/will change over the course of the project. Some risks may reduce or disappear altogether, others risks may increase and new risks might arise. To this end, the process of Identifying, Qualifying and Mitigating is a continual process. Project Management will hold Bi-Weekly issue/risk/resolution meetings to report and address all issues and risks. The frequency of this meeting may change based on the number or severity of issues/risks that are encountered.

Project Management will provide an escalation process and outline thresholds where risks can be escalated to the next level of management for appropriate action.

Project Management will leverage the existing Impact and Probability Hierarchies to govern the escalation process as follows

Probability Levels: Certain, Expected, Likely, Possible, Unlikely

Impact Levels: Very High, High, Medium, Low, Very Low

All risks must be reported to team leads (Functional or Technical), if these risks are deemed to have merit or are above the Possible or Low thresholds they must be reported to project management.

PAGE | 28

6.1.5 PROJECT RISK TRACKING APPROACH

Project Management will be the sole owner and thus the system of record for Issue and Risk tracking. Project Management will use the DoIT Issue and Risk Log templates. The purpose of this mechanism is to:

Provide current status of every Issue and Risk at any point in time Provide traceability of Issue and Risk information Provide information to monitor and review risks on an ongoing basis Report analysis of the risk to appropriate decision makers

Communicate risk management information to the appropriate stakeholders

DoIT templates include

Project Risk Assessment Report

Risk and Issue Log

Issue Description and Resolution Long Form

Risk Report Long Form

6.1.6 ISSUE MANAGEMENT

6.1.6.1 Internal Issue Escalation and Resolution ProcessProject Management will manage Issues and Risks in the same manner. See section 6.1.1.

Identification

Analyze and Qualification

Mitigation/Resolution

Tracking

6.1.6.2 External Issue Escalation and Resolution ProcessIssues External to the project team will be escalated according to the Entity for which the issue needs reporting – The Process shall be defined (but not limited to the following)

Contracting Resources – Contact Vendor Escalate Vendor Senior Management Hardware - Contact Vendor Escalate to Client Support Manager Escalate to Sales

Manager Escalate to Appropriate Senior Management Software - Contact Vendor Escalate to Client Support Manager Escalate to Sales

Manager Escalate to Appropriate Senior Management

6.2 INDEPENDENT VERIFICATION AND VALIDATION - IV&VProject Management will work closely with all template and resources provided by DoIT to meet the necessary requirements for the Independent Verification and Validation (IV&V) process. In

PAGE | 29

addition, Executive Ownership and Project Management will prepare a gate presentation for each phase of the project plan. Project Management will also be open to additional request as issued by the IV&V committee in an effort to be transparent and diligent.

6.3 SCOPE MANAGEMENT PLANThe Project management team will work to identify and baseline the scope of the project at the close of the imitation phase. Project management will allow changes to scope up until the end of the Planning Phase – after which scope will be base lined. If unanticipated changes in scope arise, Project Management will have a process in place to identify, assess and approve/decline the added scope.

Project management will keep all team members informed of the scope changes impact as it relates to Time, Budget and Resources.

Project Management will work closely with Business Owners, Executives and Project Team Members to address all facets of the proposed changes (Increases or Decreases) in scope.

6.3.1 CHANGE CONTROL

6.3.1.1 Change Control ProcessThis project will adopt the DoIT change control process that will work alongside the Issue and Risk management process. Once an issue/risk is identified and during the Analysis and Qualification stages, it will be uncovered if the Issue/Risk item will Increase/Decrease the scope of the project. The steps for Change Control Process are defined in the flow chart below.

****All Identified Changes must be submitted and logged the “Project Change Request” form.

6.3.1.2 Change Control Board (CCB)The Change Control Board shall comprise of the Executive Sponsor and the Business Owners

PAGE | 30

BOARD MEMBER NAME FUNCTIONAL AREA

Executive Sponsor Bruce Oakeley ISM Bureau Chief, NMDOT

Stakeholder / Business Owner

Julie Atencio NMDOT Acting Inspector General

Stakeholder / Business Owner

Gilbert Archuleta NMDOT Human Resources Bureau Chief

6.5 COMMUNICATION PLANProject Management will formalize a communication plan that will address the dissemination of information to the different needs of the stakeholders. See Communication matrix section 6.5.1 .

6.5.1 COMMUNICATION MATRIX

Please see the Project Communication Matrix.doc for details

6.5.2 STATUS MEETINGS

Project Management will facilitate the following meetings:

Weekly Project Status Meeting with Team Leads

Bi-Weekly Project Status Meetings with Full Team

Issue and Risk Meetings as needed

Change Control Board Meetings as needed.

6.5.3 PROJECT STATUS REPORTS

Project Management shall issue a Weekly Status Dashboard to all project stakeholders

PAGE | 31

6.6 PERFORMANCE MEASUREMENT (PROJECT METRICS)

6.6.1 Baselines

Common Project Issue Area Category Measure

Schedule and Progress Milestone Performance • Milestone Dates

Work Unit Progress • Component Status • Requirement Status • Test Case Status • Critical Paths Tested • Problem Report Status • Reviews Completed • Change Request Status

Incremental Capability • Build Content – Component • Build Content – Function

Resources and Cost Personnel• Effort • Staff Experience • Staff Turnover

Financial Performance• Earned Value • Cost

Availability • Resource Availability Dates • Resource Utilization

Growth and Stability Product Size and Stability• Lines of Code • Components • Database Size

Functional Size and Stability• Requirements • Function Points • Change Request Workload

Product Quality Defects• Problem Reports • Defect Density

Complexity • Cyclomatic Complexity

Rework• Rework Size • Rework Effort

Development Performance Process Maturity • Capability Maturity Model Level

Productivity • Product Size/Effort Ratio • Functional Size/Effort Ratio

6.7 QUALITY OBJECTIVES AND CONTROL

PAGE | 32

6.7.1 QUALITY STANDARDS

No. Quality Standard Tracking Tool or Measure

1 Project phase is completed by the established finish date. • Project Schedule• Project Status

2 Project is completed within budget. • Project Charter• Project Status

3 Project reviews show contractors deliver requirements specified in the contract by due dates or pay penalties.

• Vendor Contract• Final Customer Acceptance

4 Project issues are resolved and documented within 10 calendar days of identification or extensions are justified.

• Issues Tracking

5 Project will be completed based on the original project scope and approved scope changes.

• Project Charter• Project Plan• Control Change Request

6 Architecture shall conform to Best Practices or to the Agency Standard • Architecture Review

7 Business Requirements have been captured • Functional Documentation Signoff

8 Business Requirements have been meet • Project Signoff

9 Fully Trained staff • Training completion

6.7.2 PROJECT AND PRODUCT REVIEW AND ASSESSMENTSReview Type Quality Standard Tools Reviewer Reports

Functional Requirements All functional requirements have been captured

Functional Specification - SRS

Functional Team lead and Reviewed for understanding by technical team

Status Reports

Project Management Documents

All project management documents complete and made available to stakeholders

PMP and Related documents

Executive and Business Owners

Status Reports

Technical Deliverables All technical work product is compete and has been unit and system tested

Technical Specification document

Technical Team lead and Tested for completeness/accuracy by functional team

Status Reports

Testing All testing phase complete and issues mitigated

Testing Phase(s) Functional and Technical Team

Status Reports

PAGE | 33

6.7.3 AGENCY/CUSTOMER SATISFACTION

Areas of Feedback When How Often

Agency awareness Monthly Monthly

Quality of communications Monthly Monthly

Manages project tasks Monthly Monthly

Productive Meetings Monthly Monthly

6.7.4 PRODUCT DELIVERABLE ACCEPTANCE PROCESS

DELIVERABLE NUMBER

DELIVERABLE FINAL APPROVAL PROCESS CUSTOMER ACCEPTANCE CRITERIA

PRJ-DEL-001Initiation - Project Initiation and Scope Focus Meetings

Sign-Off TBD

PRJ-DEL-002Initiation - Initiation Phase Certification Form

Sign-Off TBD

PRJ-DEL-003 Initiation - Project Charter Sign-Off TBD

PRJ-DEL-004Initiation - Initiation Phase Certification

Sign-Off TBD

PRJ-DEL-005Initiation - Form Evaluation and Enumeration

Sign-Off TBD

PRJ-DEL-006

Initiation - Identification of forms for electronic workflow & signature

Sign-Off TBD

PRJ-DEL-007Initiation - Change Management process for implementation phase

Sign-Off TBD

PRJ-DEL-008

Initiation - Identification of workflow end points for top 30 priority forms.

Sign-Off TBD

PRJ-DEL-009Initiation - Identification of workflow participant categories

Sign-Off TBD

PAGE | 34

DELIVERABLE NUMBER

DELIVERABLE FINAL APPROVAL PROCESS CUSTOMER ACCEPTANCE CRITERIA

PRJ-DEL-010 Initiation - Project JAD Session Sign-Off TBD

PRJ-DEL-011Initiation - System Requirement Specification (SRS)

Sign-Off TBD

PRJ-DEL-012

Initiation - System Requirement Specification (SRS) Evaluation and Review - Round 1

Sign-Off TBD

PRJ-DEL-013Initiation - Project Status Reports (Internal)

Sign-Off TBD

PRJ-DEL-014Initiation - Initial Risk Assessment Report

Sign-Off TBD

PRJ-DEL-015Initiation - Initial Business Continuity Plan

Sign-Off TBD

PRJ-DEL-016Initiation - Initial Project Communication Plan

Sign-Off TBD

PRJ-DEL-017Initiation - Initial Project Operations and Support Plan

Sign-Off TBD

PRJ-DEL-018Initiation - Initial Project Test Plan and Strategy

Sign-Off TBD

PRJ-DEL-019Initiation - Initial Project Management Plan

Sign-Off TBD

PRJ-DEL-020Initiation - Initial Active Directory Update Plan

Sign-Off TBD

PRJ-DEL-021Planning - Planning Phase Certification Form

Sign-Off TBD

PRJ-DEL-022Planning - Revise Project Management Plan

Sign-Off TBD

PRJ-DEL-023Planning - IV&V Selected and Contract Negotiated

Sign-Off TBD

PRJ-DEL-024Planning - Project Status Reports (Internal)

Sign-Off TBD

PAGE | 35

DELIVERABLE NUMBER

DELIVERABLE FINAL APPROVAL PROCESS CUSTOMER ACCEPTANCE CRITERIA

PRJ-DEL-025

Planning - System Requirement Specification (SRS) Evaluation and Review - Round 2

Sign-Off TBD

PRJ-DEL-026Planning - Technical Architecture Document

Sign-Off TBD

PRJ-DEL-027Planning - Revise Risk Assessment Report

Sign-Off TBD

PRJ-DEL-028Planning - Revise Business Continuity Plan

Sign-Off TBD

PRJ-DEL-029Planning - Revise Project Communication Plan

Sign-Off TBD

PRJ-DEL-030Planning - Revise Project Operations and Support Plan

Sign-Off TBD

PRJ-DEL-031Planning - Revise Project Test Plan and Strategy

Sign-Off TBD

PRJ-DEL-032Planning - Revise Active Directory Update Plan

Sign-Off TBD

PRJ-DEL-033 Planning - Initial Cutover Plan Sign-Off TBD

PRJ-DEL-034Planning - Evaluate Electronic or Digital Signature Solution

Sign-Off TBD

PRJ-DEL-035Planning - ELECTRONIC SIGNATURE - Signature Collection Plan Strategy

Sign-Off TBD

PRJ-DEL-036

Planning - DIGITAL SIGNATURE - operations and support plan for digital sig. services.

Sign-Off TBD

PRJ-DEL-037

Planning - Determine Active Directory fields needed for Live Cycle function

Sign-Off TBD

PRJ-DEL-038

Planning - Determine which support staff will update non-GO portions of Active Directory

Sign-Off TBD

PAGE | 36

DELIVERABLE NUMBER

DELIVERABLE FINAL APPROVAL PROCESS CUSTOMER ACCEPTANCE CRITERIA

PRJ-DEL-039 Planning - Technical Team Training Sign-Off TBD

PRJ-DEL-040Implementation - Implementation Phase Certification Form

Sign-Off TBD

PRJ-DEL-041Implementation - Updated Project Management Plan

Sign-Off TBD

PRJ-DEL-042Implementation - IV&V Reports Submitted

Sign-Off TBD

PRJ-DEL-043Implementation - Technical Architecture Approved

Sign-Off TBD

PRJ-DEL-044Implementation - Project Status Reports (Internal)

Sign-Off TBD

PRJ-DEL-045

Implementation - LiveCycle ES4 Server Installation and Configuration

Sign-Off TBD

PRJ-DEL-046Implementation - Active Directory Updates - Mass Update

Sign-Off TBD

PRJ-DEL-047Implementation - Active Directory Updates - District Level Updates

Sign-Off TBD

PRJ-DEL-048

Implementation - ELECTRONIC SIGNATURE - Design / Develop web service interface for existing signature server

Sign-Off TBD

PRJ-DEL-049

Implementation - Design / develop scripting to extract and rename guid-named forms from OIG form server

Sign-Off TBD

PRJ-DEL-050Implementation - Existing Form Migration

Sign-Off TBD

PRJ-DEL-051Implementation - New Form Development

Sign-Off TBD

PRJ-DEL-052Implementation - Workflow Development

Sign-Off TBD

PAGE | 37

DELIVERABLE NUMBER

DELIVERABLE FINAL APPROVAL PROCESS CUSTOMER ACCEPTANCE CRITERIA

PRJ-DEL-053

Implementation - Implement Electronic or Digital Signature Solution

Sign-Off TBD

PRJ-DEL-054

Implementation - Web Interface for Active Directory Organizational Maintenance

Sign-Off TBD

PRJ-DEL-055Implementation - End User Training for AD Web Interface

Sign-Off TBD

PRJ-DEL-056Close - Closeout Phase Certification Form

Sign-Off TBD

PRJ-DEL-057Close - Final IV&V Reports Submitted

Sign-Off TBD

PRJ-DEL-058 Close - Project Closeout Report Sign-Off TBD

PRJ-DEL-059 Close - Lessons Learned Sign-Off TBD

6.8 CONFIGURATION MANAGEMENT

6.8.1 VERSION CONTROL

The Project Team will strictly enforce version and Configuration control.

All Development, Test and Production environments will have the same configuration.

Code will be packaged and follow a promotion process.

6.8.2 PROJECT REPOSITORY (PROJECT LIBRARY)All Project documentation will be saved on NMDOT File Server system. The System will be backed up on a daily basis.

All Project Management related documentation will be distributed via PDF and the Project Manager will manage changes.

PAGE | 38

7. 0 PROJECT CLOSE

7.1 ADMINISTRATIVE CLOSE

Formal Sign-off shall signify the close of each project phase and of the entire project once the work has been verified, delivered and accepted by the Business Owner.

7.2 CONTRACT CLOSE

This project will consist of multiple contracts. A contract is deemed closed upon reaching the end of the contract or when a contract is terminated before he work is completed.

PAGE | 39