DESIGN OF WATER DISTRIBUTION SYSTEM ( SVNIT CAMPUS)
FOR REVISED DEMAND
2011-2012
Submitted by Guided by
ANSHUK GARG U08CE069
RAJWANSH SINGH U08CE047
RAVI TEJA U08CE056
TAMMU TULSIRAM U08CE044
AVINASH KUMAR U08CE067
SACHIN GAUTAM U08CE006
CIVIL ENGINEERING DEPARTMENT
SARDAR VALLABHBHAI NATIONAL INSTITUTE OF
TECHNOLOGY SURAT- 395007
Dr. P.L.PATEL
Professor
CERTIFICATE
This is to certify the following students of B. Tech -IV sem. 7th
have
satisfactorily completed their project preliminary report on ―Design of
Water Distribution System (SVNIT CAMPUS) for Revised Demand‖
during academic year 2011 – 2012.
CIVIL ENGINEERING DEPARTMENT
SARDAR VALLABHBHAI NATIONAL INSTITUTE OF
TECHNOLOGY SURAT- 395007
Signature of Head of
Department
ANSHUK GARG U08CE069
RAJWANSH SINGH U08CE047
RAVI TEJA U08CE056
TAMMU TULSIRAM U08CE044
AVINASH KUMAR U08CE067
SACHIN GAUTAM U08CE006
Signature of Guide
ACKNOWLEDGEMENT
We take great opportunity to express our deep sense of gratitude and indebtedness to
―Dr.P.L.Patel‖ in Civil Engineering department, S.V.N.I.T, Surat for his valuable guidance,
useful comments and co-operation with kind and encouraging attitude at all stages of the
experimental work for the successful completion of this work.
We would like to thank Dr. P.V.Timbadiya and Viraj Sir for their help with the softwares and
guidance in the Hydrology Lab.
We would also like to thank our head of department ‗Dr. J.N. Patel‘.
We are thankful to S.V.N.I.T, Surat and its staff for providing us this opportunity which helped
in gaining knowledge and to make this Project report successful endeavour.
Thank You
TABLE OF CONTENTS
1. Introduction……………………………………………………………………………….1
2. Networking parameters…………………………………………………………………...2
3. Darcy-Weisbach equation and Newton-Raphson Method……………………………….3
4. Analysis of study area…………………………………………………………………….5
5. Analysis of Capacity and Demand……………………………………………………….6
6. Analysis of the network………………………………………………………………….7
7. Gravity network………………………………………………………………………….7
8. Pressure network…………………………………………………………………………8
9. Software support
a. LOOP 4.0………………………………………………………………………...8
b. WaterGEMS……………………………………………………………………...9
10. Nodes for Gravity Network……………………………………………………………...13
11. Gravity Network Layout………………………………………………………………..15
12. Pressure Network Layout……………………………………………………………….16
13. Results
a. Pipe Results……………………………………………………………………..17
b. Junction Results…………………………………………………………………19
14. Conclusions……………………………………………………………………………..22
INTRODUCTION
Water is a vital element in the living system and is an important component and also a key
element for the socio-economic development of a country. All living things require water for
their sustenance. In fixing the living standards of the population, the availability of water to
domestic needs plays an important role. With the increase in population in the sphere, the
demand for water and the fight to share this resource during the period of scarcity also increases
enormously. This has been true with particular reference to the recent past. In a country like
India, the rainfall is seasonal and is highly erratic in nature, leading to spatial and temporal ·
variations in the water availability. Thus, it becomes necessary for the water supply engineers to
supply pure and adequate water, equally to all the consumers. For this challenging task, the
design, and the analysis, of the pipe network system on optimization and other techniques have
been based throughout the world.
A water distribution system is an essential infrastructure in the supply of water for domestic as
well as industrial uses. It connects consumers to sources of water, using hydraulic components,
such as pipes, valves, pumps and tanks. The design of such systems is a multifarious task
involving numerous interrelated factors, requiring careful consideration in the design process.
Important design parameters include water demand, minimum pressure requirements,
topography; system reliability, economics, piping, pumping and energy use.
The primary goal of all water distribution system engineers is the delivery of water to meet the
demands on quantity and pressure. Unfortunately, as a water distribution system ages, its ability
to transport water diminishes and the demands placed upon it typically increase. In addition to
the unsatisfactory performance of a deteriorated network, there are direct economic impacts of a
failing system. Older systems ·have reduced the carrying capacity due to corrosion and
tuberculation and are more susceptible to leaks and breaks, resulting in loss of water, requiring
time and money to repair. Moreover population explosion is one of the main reasons for the
increase in the demand of water for consumption and most of the networks fail to meet this
demand.
Researchers have developed two principal approaches in pipe network design and analysis. One
is the linear programming approach and the other one is the non-linear programming approach.
The non linear optimization includes MINOs (Murtagh and Saunders 1987), GINO and GAMS.
All these packages use a constrained generalized reduced gradient technique to identify a local
optimum for the network problem. Constraints can be included explicitly in the model. Examples
include, the continuity equations, head losses around loops or between reservoirs, minimum and
maximum pressure limitations, and minimum and maximum diameters. Costs can be expressed
as any non-linear function of pipe diameter and length. The limitations of the technique are as
follows:
1. Since the pipe diameters are continuous variables, the optimal values will not necessarily
confirm to the available pipe sizes; thus a rounding off of the final solution is required.
2. Only a local optimum is obtained.
3. There is a limitation on the number of constraints and hence the size of the network that
can be handled.
The main objective of this project is to design a water distribution network for the increasing
requirement in Sardar Vallabhbhai National Institute Of Technology, Surat.
NETWORKING PARAMETERS
For the design of network there is a need for calibration of various parameters like discharge at
nodes, height requirement to acquire the desired head etc. In addition to that it also requires the
capacity of various structures, the daily demand of various buildings. The following are various
sequential networking parameters that are to be calibrated.
Configuration-It involves the location of sites for various elements such as elevated service
reservoirs, pumps, pipes, valves, and accessories. The configuration is decided by taking into
consideration the existing pattern of streets and highways, existing and planned subdivisions,
property right-of-ways, possible sites for elevated and ground service reservoirs, location and
density of demand centres, and general topography.
Pipe Lengths-The pipe lengths are obtained from the known geometrical layout of the network.
When nodes are connected by links consisting of pipes in series, in parallel, and in series-parallel
combination, such pipes are usually replaced by equivalent pipes in network analysis.
Pipe Diameters-The pipe diameters are either known or calculated for equivalent pipes.
Pipe Roughness coefficients-The pipe roughness coefficients such as Hazen-William coefficient
CHW and Manning‘s coefficient N are considered known and remains constant during the
analysis. But Darcy-Weisbach friction factor f is a function of Reynolds number and therefore of
pipe discharge, and thus must be re-evaluated when the pipe discharge changes.
Minor Appurtenances-The effect of minor appurtenances can be individually considered.
However in network analysis, it is common practice to consider equivalent pipes and
correspondingly increase the pipe length by 5-10% to account for the effect of minor
appurtenances.
Demand Pattern-The demand fluctuate with time, days and seasons. But it is common practice
to assume that demands remain constant in the analysis.
Hydraulic Gradient Levels-The hydraulic gradient levels or simply the heads are mostly
unknown and obtained from the analysis.
DARCY-WEISHBACH EQUATION
In fluid dynamics, the Darcy–Weisbach equation is a phenomenological equation, which relates
the head loss or pressure loss — due to friction along a given length of pipe to the average
velocity of the fluid flow. The equation is named after Henry Darcy and Julius Weisbach.
It is of two types
Pressure loss form:
Head loss form:
hf – head loss due to friction
L - length of pipe
D- hydraulic diameter of the pipe
V- average velocity of flow
g- acceleration due to gravity
f- dimensionless constant, darcy‘s friction coefficient
The calibrations in many software is done by using three main hydraulic equations named Darcy-
Weisbach equation, Newton-Raphson method and Manning‘s equation.
NEWTON-RAPHSON’S METHOD
In numerical analysis, Newton's method (also known as the Newton–Raphson method), named
after Issac Newton and Joseph Raphson, is a method for finding successively better
approximations to the roots (or zeroes) of a real -valued function. The algorithm is first in the
class of Householder‘s method succeeded by Halley‘s method. The method can also be extended
to complex functions and to systems of equations.
Given a function ƒ defined over the real x, and its derivative f‘, we begin with a first guess x0 for
a root of the function f. Provided the function is reasonably well-behaved a better
approximation x1 is
Geometrically, (x1, 0) is the intersection with the x-axis of a line tangent to f at (x0, f (x0)).The
process is repeated as
until a sufficiently accurate value is reached.
The idea of the method is as follows: one starts with an initial guess which is reasonably close to
the true root, then the function is approximated by its tangent line (which can be computed using
the tools of calculus), and one computes the x-intercept of this tangent line (which is easily done
with elementary algebra). This x-intercept will typically be a better approximation to the
function's root than the original guess, and the method can be iterated.
ANALYSIS OF PRESENT STUDY AREA BY ZONES
Academic zone:
This zone comprises of Administrative building and drawing hall, Civil engineering department,
Applied mechanics department, Applied sciences and humanities department, Electronics
engineering department, Electrical engineering department, Chemical engineering department,
Mechanical engineering department and Production engineering department.
Hostels :
This includes the all places other than academic area which include Bhabha bhavan, Nehru
bhavan, PG boys hostel, Raman bhavan, Gajjar bhavan, Sardar bhavan, Gandhi bhavan, New
girls hostel, Kasthuriba bhavan, Sarojini bhavan, Staff quarters.
Staff Quarters:
Include the A ,B ,C and D type quarters. Director‘s Bungalow and proposed staff quarters.
Other Institutional Buildings:
This area includes some places like Staff club, Post office, Canteen, Student activity centre and
Dispensary
ANALYSIS OF CAPACITY AND DEMAND
HOSTEL AREA NO. OF
PEOPLE
DEMAND TANK
CAPACITY
BHABHA BHAVAN 960 52800 75000 TAGORE BHAVAN 192 10560 15000 NEHRU BHAVAN 200 11000 15000 PG BOYS HOSTEL 960 52800 75000 RAMAN BHAVAN 170 9350 12000 GAJJAR BHAVAN 950 52250 60000 SARDAR BHAVAN 143 7865 9000 GANDHI BHAVAN 143 7865 9000
NEW GIRLS HOSTEL 800 44000 60000 KASTURBA BHAVAN 246 13530 15000 SAROJINI BHAVAN 126 6930 9000
80 TOTAL 268950 354000
STAFF QUARTERS
A1-6 30 4050 18000 B1-16 80 10800 21000 C1-12 60 8100 12000 C13-48 180 24300 39000 D1-48 240 32400 24000 D49-72 120 16200 12000
TOTAL 95850 126000
ACADEMIC AREA
CRC 600 3000 6000 CIVIL ENGG DEPT 300 1500 9000 TRANSPORTATION
LAB 100 500 3000
WATER RESOURCE
LAB 100 1000 6000
WATER RESOURCE
NEW LAB 100 10000 15000
WORKSHOP 200 1000 3000 AMD 200 1000 6000
CONCRETE LAB 100 2000 6000
PRODUCTION DEPT 100 500 3000 SEMINAR HALL 150 750 3000
APPLIED SCIENCES
AND HUMANITIES 300 1500 6000
CCC 200 1000 3000 COMPUTER DEPT 200 1000 6000 ADMINISTRTIVE
BUILDING 200 1000 15000
ELECTRICAL DEPT 200 1000 9000 ELECTRICAL
CIRCUITS LAB 100 500 3000
ELECTRONICS DEPT 300 1500 3000 CHEMICAL DEPT 200 1000 6000
ESTATE BUILDING 50 400 9000 GENERATOR ROOM 100 2000 6000
LIBRARY 200 1000 6000 MECHANICAL DEPT 400 2000 6000 FLUID MECHANICS
LAB 100 2000 6000
IC ENGINES LAB 100 500 3000 BOILER LAB 100 5000 3000
CAD LAB 100 500 6000
TOTAL AREA 43150 156000
OTHER AREA STAFF CLUB 100 1500 3000
BANK 200 1000 6000 POST OFFICE 200 1000 6000
CANTEEN 500 4000 6000 SAC 2000 1000 6000
DISPENSARY 100 500 3000
TOTAL 9000 30000
TOTAL CAPACITY 416950 666000
ANALYSIS OF NETWORK
After calculating the demand we need to design a pipe network.
The pipe network can be divided in two ways
1. Gravity network
2. Pumping network
There is a need to know which type of network has to adopted for our requirement, the network
methods are clearly explained in the next section.
In order to prepare the design the co-ordinates for all nodes have to be analysed, the table under
shows the co-ordinates of various nodes.
GRAVITY NETWORK
In this network, the pressure required for the water to serve our needs is provided by the gravity
head(acquired during storage in over head tank). There is no requirement of any pumping system
to be arranged at the target regions to pump the water to the over head tanks of buildings. It is
simple to design this kind of network where the additional requirement of power to pump the
water into overhead tank is not required.
In the present study area there is no need of providing any pumps provided the target building is
less than 2 storey.
The water head available at consumer door is just a minimum quantity, the remaining head is
consumed in frictional and other losses.
PUMPING NETWORK
The distribution system here includes distribution of water by using pumps. There is a power
required to pump the water , here there is a additional charge for maitainance of these pumping
systems. This system is adopted when the gravity head provided by the main tank is not
sufficient for the water to get stored in the over head tanks of the targets.
In the present study area, if the building is more than 2 storey this system is adopted. This system
supports the given network by providing the required head by mechanical means.
SOFTWARE SUPPORT
The software used in designing the water distribution system is LOOP 4.0 and WaterGEMS.
There are many other software for these purposes.
LOOP 4.0:
It is developed and distributed under the joint efforts of UNDP/World Bank. It is user friendly
software. Loop has been programmed in Microsoft quick basic 1.5. It could be used for the
design of new, partially and fully existing gravity as well as pumped water distribution system. It
allows for reservoirs(both with fixed head and variable head), valves(pressure reducing as well
as check valves) and online booster pump.
General Information sheet-wise:
Sheet-1:
Number of nodes
Number of pipes
Number of common diameter having pipes
Peak design factor
Type of formula
Units of various pipe parameters
Sheet-2:
Pipe to and fro length
Diameter
Hazen‘s pipe
Node number
Material.
Sheet-3:
Node number
Peak flow factor
Elevation
Minimum pressure
Maximum pressure.
Sheet-4:
Number of fixtures:
Number of nodes with fixed HGL
Number of nodes with variable HGL
Number of booster pumps
Number of pressure reducing valves
Number of check valves
Sheet-5:
Internal diameter of pipe
Hazen‘s constant
Cost per metre
Allowable pressure
Sheet-6:
Design Information:
Newton-Raphson stopping criterion
Minimum Pressure
Maximum Pressure
Design hydraulic gradient in km
Simulate or Design
WaterGEMS:
It can simulate Fires, pipe breaks, energy costs, power outrages, tank out of service, shutdown
for rehab or connection, unusual demands, use your imagination.
It u8ses the water use patterns, demand patterns, time scales, system-wide temporal water use to
calibrate the results.
Simulation process:
Controls:
Operational controls:
Property of a controlled element
Limited to a single condition/action
Logical(rule based) controls:
Kept with logical alternatives
Complex conditions/action
Operational rules:
Must tell mode how pumps and valves operate
Status(digital):
o Pipe: open or closed
o Pumps: on or off
o Valves: active, inactive, closed
Setting(analog):
o Pumps: relative speed factor
o Valves: pressure, flow or head loss coefficient
Data entry Initial conditions First time step Solve network
Check
controls
Last step ? results
yes
no
Logical controls:
Controls made up of conditions and actions
If(condition is true)
Then(action)
Else(action)
If(flow at p-17 >200) then (pmp-1=on) else(pmp-1=off)
Conditions:
Element ( hgl at j11>145 )
Time from start ( t>= 7 )
Clock time ( clock time < 7:00 am )
System demand(demand > 500)
Composite conditions and actions:
Flow>200 and clock time>3: 00 pm
Pmp-1=off and p-11=open
Each action and condition has label
If(cc01 and cc02) then(aa02 and aa05)
Can find references foe each action or condition
Setting logical controls:
Reporting time step(calc option)
Saves results for all steps(default)
Can save only at constant increment
Define conditions
and actions
Create controls Create
control sets
Specify control
set
Can save at variable increments
o Can skip range of time steps
o Can save at constant or all time steps in some range
Results file path:
Results saved with .mdb by default
May want to save results files elsewhere
Can specify alternative path
Some result files
o .out main results file
o .nrg energy cost results
GRAVITY NETWORK DESIGNED USING WaterGEMS:
Fig 1
Fig 2
NODES FOR GRAVITY NETWORK
NODE X Y Z
1 1594 813 7.773
2 1575 819 7.819
3 1640 862 7.609
4 1618 881 8.059
5 1627 884 8.059
6 1612 877 8.059
7 1606 906 7.508
8 1693 889 7.616
9 1676 906 7.981
10 1682 911 7.981
11 1668 905 7.981
12 1668 924 7.568
13 1748 924 7.615
14 1738 940 7.752
15 1732 938 7.752
16 1740 943 7.752
17 1729 963 7.759
18 1723 961 7.759
19 1705 1030 7.557
20 1696 1033 7.557
21 1697 1056 7.349
22 1686 1052 7.349
23 1700 1060 7.561
24 1683 1097 7.349
25 1666 1091 7.351
26 1692 1100 7.176
27 1670 1119 7.13
28 1685 1126 6.937
29 1660 1172 6.742
30 1675 1178 6.742
31 1521 935 8.095
32 1581 965 7.653
33 1564 994 7.612
34 1592 942 7.867
35 1581 940 7.867
36 1596 943 7.867
37 1636 997 7.605
38 1650 972 7.463
39 1637 966 7.463
40 1652 974 7.463
41 1626 1014 7.288
42 1437 1127 6.896
43 1477 1136 6.75
44 1538 805 7.877
45 1525 823 7.895
46 1462 777 7.892
47 1435 831 7.72
48 1395 808 7.446
49 1391 900 7.689
50 1393 875 7.682
51 1457 894 8.13
52 1374 934 7.819
53 1363 954 7.561
54 1338 954 7.737
55 1373 971 7.676
56 1320 989 7.825
57 1359 1011 7.205
58 1314 1063 7.687
59 1298 1052 7.505
60 1333 1065 7.687
61 1336 886 7.38
62 1285 959 7.77
63 1274 953 7.77
64 1252 1025 7.786
65 1245 1015 7.484
66 1244 1019 7.484
67 1217 1006 7.342
68 1268 855 7.207
69 1255 873 7.554
70 1249 845 7.743
71 1207 854 7.927
72 1220 834 7.337
73 1225 815 7.406
74 1168 800 7.327
75 1173 788 7.484
76 1144 786 7.849
77 1109 776 8.11
78 1100 855 7.802
79 1131 871 7.105
80 1077 702 7.812
81 1113 915 7.14
82 1409 741 7.183
83 1356 818 7.673
84 1336 806 7.491
85 1314 795 7.647
86 1280 777 7.563
87 1236 755 7.357
88 1243 744 7.273
89 1349 794 7.704
90 1321 780 7.718
91 1283 767 7.563
92 1298 804 7.689
93 1325 821 8.168
94 1389 725 6.944
95 1422 666 6.946
96 1301 678 7.529
97 1318 622 7.341
PRESSURE NETWORK USING WaterGEMS :
Fig3
PIPE RESULTS:
Label Length (m) Start Node Stop Node
Diameter (mm) Flow (L/day) Velocity (m/s)
P-1 19.92 J-1 J-2 152.4 144549 0.0917
P-2 77.94 J-2 J-3 152.4 73118 0.0464
P-3 29.07 J-3 J-4 152.4 16400 0.0104
P-4 27.73 J-4 J-7 152.4 5600 0.0036
P-5 9.49 J-4 J-5 152.4 5400 0.0034
P-6 7.21 J-4 J-6 152.4 5400 0.0034
P-7 59.48 J-3 J-8 152.4 56718 0.036
P-8 24.04 J-8 J-9 152.4 16800 0.0107
P-9 7.81 J-9 J-10 152.4 5600 0.0036
P-10 8.06 J-9 J-11 152.4 5600 0.0036
P-11 19.7 J-9 J-12 152.4 5600 0.0036
P-12 65.19 J-8 J-13 152.4 39918 0.0253
P-13 18.87 J-13 J-14 152.4 39918 0.0253
P-14 6.32 J-14 J-15 152.4 4628 0.0029
P-15 3.61 J-14 J-16 152.4 4628 0.0029
P-16 24.7 J-14 J-17 152.4 30662 0.0195
P-17 6.32 J-17 J-18 152.4 4628 0.0029
P-18 71.17 J-17 J-19 152.4 26034 0.0165
P-19 9.49 J-19 J-20 152.4 1350 0.0009
P-20 27.2 J-19 J-21 152.4 24684 0.0157
P-21 11.7 J-21 J-22 152.4 1350 0.0009
P-22 5 J-21 J-23 152.4 4628 0.0029
P-23 43.32 J-21 J-24 152.4 18706 0.0119
P-24 18.03 J-24 J-25 152.4 1350 0.0009
P-25 9.49 J-24 J-26 152.4 4628 0.0029
P-26 25.55 J-24 J-27 152.4 12728 0.0081
P-27 16.55 J-27 J-28 152.4 8100 0.0051
P-28 53.94 J-27 J-29 152.4 4628 0.0029
P-29 16.16 J-29 J-30 152.4 4628 0.0029
P-30 127.95 J-2 J-31 152.4 14800 0.0094
P-31 67.08 J-31 J-32 152.4 13800 0.0088
P-32 33.62 J-32 J-33 152.4 1500 0.001
P-33 25.5 J-32 J-34 152.4 5400 0.0034
P-34 11.18 J-34 J-35 152.4 2700 0.0017
P-35 4.12 J-34 J-36 152.4 2700 0.0017
P-36 63.63 J-32 J-37 152.4 6900 0.0044
P-37 28.65 J-37 J-38 152.4 5400 0.0034
P-38 14.32 J-38 J-39 152.4 2700 0.0017
P-39 2.83 J-38 J-40 152.4 2700 0.0017
P-40 19.72 J-37 J-41 152.4 1500 0.001
P-42 209.57 J-31 J-42 152.4 1000 0.0006
P-43 41 J-42 J-43 152.4 1000 0.0006
P-44 39.56 J-2 J-44 152.4 56631 0.0359
P-45 11.8 J-44 J-45 152.4 4000 0.0025
P-46 80.99 J-44 J-46 152.4 52631 0.0334
P-48 60.37 J-46 J-47 152.4 22703 0.0144
P-49 46.14 J-47 J-48 152.4 2000 0.0013
P-50 51.88 J-47 J-49 152.4 20703 0.0131
P-51 14.56 J-49 J-50 152.4 1000 0.0006
P-52 49.04 J-49 J-51 152.4 0 0
P-53 43.08 J-49 J-52 152.4 19703 0.0125
P-54 42.44 J-52 J-53 152.4 5500 0.0035
P-55 22.56 J-53 J-54 152.4 1500 0.001
P-56 15.56 J-53 J-55 152.4 0 0
P-57 58.52 J-53 J-56 152.4 4000 0.0025
P-58 20.17 J-56 J-57 152.4 1000 0.0006
P-59 67.12 J-56 J-58 152.4 3000 0.0019
P-61 19.1 J-58 J-60 152.4 3000 0.0019
P-62 66.65 J-52 J-61 152.4 14203 0.009
P-63 89.05 J-61 J-62 152.4 12500 0.0079
P-64 12.53 J-62 J-63 152.4 2000 0.0013
P-65 73.79 J-62 J-64 152.4 10500 0.0067
P-66 16.73 J-64 J-65 152.4 10500 0.0067
P-67 6.28 J-65 J-66 152.4 500 0.0003
P-68 23.1 J-65 J-67 152.4 10000 0.0063
P-69 74.73 J-61 J-68 152.4 1703 0.0011
P-70 21.08 J-68 J-69 152.4 1000 0.0006
P-71 26.93 J-68 J-70 152.4 703 0.0004
P-72 26.08 J-70 J-71 152.4 1000 0.0006
P-73 25.5 J-70 J-72 152.4 -297 0.0002
P-74 19.65 J-72 J-73 152.4 1000 0.0006
P-75 62.13 J-72 J-74 152.4 -1297 0.0008
P-76 13 J-74 J-75 152.4 1000 0.0006
P-77 27.78 J-74 J-76 152.4 -2297 0.0015
P-78 36.4 J-76 J-77 152.4 400 0.0003
P-79 81.84 J-76 J-78 152.4 1000 0.0006
P-80 34.89 J-78 J-79 152.4 0 0
P-81 53.16 J-78 J-80 152.4 1000 0.0006
P-82 29.41 J-80 J-81 152.4 0 0
P-83 64.07 J-46 J-82 152.4 29927 0.019
P-84 93.48 J-82 J-83 152.4 10300 0.0065
P-85 23.32 J-83 J-84 152.4 10300 0.0065
P-86 24.6 J-84 J-85 152.4 7800 0.0049
P-87 38.47 J-85 J-86 152.4 5300 0.0034
P-88 49.19 J-86 J-87 152.4 300 0.0002
P-89 13.04 J-87 J-88 152.4 300 0.0002
P-90 13.46 J-84 J-89 152.4 2000 0.0013
P-91 16.55 J-85 J-90 152.4 500 0.0003
P-92 11.51 J-86 J-91 152.4 5000 0.0032
P-93 13.1 J-85 J-92 152.4 2000 0.0013
P-94 13.98 J-84 J-93 152.4 500 0.0003
P-95 25.61 J-82 J-94 152.4 19627 0.0125
P-96 67.6 J-94 J-95 152.4 7865 0.005
P-97 99.76 J-94 J-96 152.4 11762 0.0075
P-98 58.52 J-96 J-97 152.4 7865 0.005
P-99 81.39 J-96 J-98 152.4 3897 0.0025
P-100 81.27 J-98 J-99 152.4 3897 0.0025
P-101 29.15 J-99 J-100 152.4 200 0.0001
P-102 26 J-99 J-101 152.4 0 0
P-103 18.19 J-1 T-1 152.4 -144549 0.0917
P-104 85.87 J-99 J-76 152.4 3697 0.0023
JUNCTION RESULTS :
Label Elevation (m) Zone Demand (L/day) HYDRAULIC GRADE (M) Pressure (kPa)
J-1 7.7 <None> 0 22.2 141.9
J-2 7.82 <None> 0 22.2 140.7
J-3 7.6 <None> 0 22.19 142.8
J-4 8.05 <None> 0 22.19 138.4
J-5 8.05 c type 5400 22.19 138.4
J-6 8.05 c type 5400 22.19 138.4
J-7 7.5 c type 5600 22.19 143.8
J-8 7.61 <None> 0 22.19 142.7
J-9 7.99 <None> 0 22.19 139
J-10 7.98 c type 5600 22.19 139.1
J-11 7.98 c type 5600 22.19 139.1
J-12 7.56 c type 5600 22.19 143.2
J-13 7.61 <None> 0 22.19 142.7
J-14 7.75 <None> 0 22.19 141.4
J-15 7.75 D-Type Staff Quarters 4628 22.19 141.4
J-16 7.75 D-Type Staff Quarters 4628 22.19 141.4
J-17 7.75 <None> 0 22.19 141.3
J-18 7.75 D-Type Staff Quarters 4628 22.19 141.3
J-19 7.55 <None> 0 22.19 143.3
J-20 7.55 A-Type 1350 22.19 143.3
J-21 7.34 <None> 0 22.19 145.4
J-22 7.34 A-Type 1350 22.19 145.4
J-23 7.56 D-Type Staff Quarters 4628 22.19 143.2
J-24 7.34 <None> 0 22.19 145.4
J-25 7.35 A-Type 1350 22.19 145.3
J-26 7.17 D-Type Staff Quarters 4628 22.19 147
J-27 7.13 <None> 0 22.19 147.4
J-28 6.93 D-Type Staff Quarters 8100 22.19 149.4
J-29 6.74 <None> 0 22.19 151.2
J-30 6.74 D-Type Staff Quarters 4628 22.19 151.2
J-31 8.09 <None> 0 22.2 138.1
J-32 7.65 <None> 0 22.2 142.4
J-33 7.61 staff club 1500 22.2 142.8
J-34 7.86 <None> 0 22.2 140.3
J-35 7.86 b type 2700 22.2 140.3
J-36 7.86 b type 2700 22.2 140.3
J-37 7.6 <None> 0 22.2 142.9
J-38 7.46 <None> 0 22.2 144.2
J-39 7.46 b type 2700 22.2 144.2
J-40 7.46 b type 2700 22.2 144.2
J-41 7.29 director bunglow 1500 22.2 145.9
J-42 6.89 <None> 0 22.2 149.8
J-43 6.75 bank 1000 22.2 151.2
J-44 7.87 <None> 0 22.2 140.2
J-45 7.89 canteen 4000 22.2 140
J-46 7.89 <None> 0 22.19 140
J-47 7.72 <None> 0 22.19 141.7
J-48 7.44 institutional buildings 2000 22.19 144.4
J-49 7.68 <None> 0 22.19 142.1
J-50 7.68 institutional buildings 1000 22.19 142.1
J-51 8.13 <None> 0 22.19 137.6
J-52 7.81 <None> 0 22.19 140.8
J-53 7.56 <None> 0 22.19 143.2
J-54 7.74 institutional buildings 1500 22.19 141.5
J-55 9.67 <None> 0 22.19 122.6
J-56 7.82 <None> 0 22.19 140.7
J-57 7.2 institutional buildings 1000 22.19 146.7
J-58 7.68 <None> 0 22.19 142
J-60 7.68 institutional buildings 3000 22.19 142
J-61 7.38 <None> 0 22.19 145
J-62 7.77 <None> 0 22.19 141.2
J-63 7.77 Labs 2000 22.19 141.2
J-64 7.78 <None> 0 22.19 141.1
J-65 7.48 <None> 0 22.19 144
J-66 7.48 Labs 500 22.19 144
J-67 7.34 Labs 10000 22.19 145.4
J-68 7.2 <None> 0 22.19 146.7
J-69 7.55 institutional buildings 1000 22.19 143.3
J-70 7.74 <None> 0 22.19 141.5
J-71 7.59 institutional buildings 1000 22.19 142.9
J-72 7.34 <None> 0 22.19 145.4
J-73 7.4 institutional buildings 1000 22.19 144.8
J-74 7.32 <None> 0 22.19 145.6
J-75 7.48 institutional buildings 1000 22.19 144
J-76 7.84 <None> 0 22.19 140.5
J-77 8.11 institutional buildings 400 22.19 137.8
J-78 7.8 <None> 0 22.19 140.9
J-79 7.1 <None> 0 22.19 147.7
J-80 7.81 institutional buildings 1000 22.19 140.8
J-81 7.14 <None> 0 22.19 147.3
J-82 7.18 <None> 0 22.19 146.9
J-83 7.67 <None> 0 22.19 142.1
J-84 7.49 <None> 0 22.19 143.9
J-85 7.64 <None> 0 22.19 142.4
J-86 7.56 <None> 0 22.19 143.2
J-87 7.35 <None> 0 22.19 145.3
J-88 7.27 <None> 300 22.19 146.1
J-89 7.7 Labs 2000 22.19 141.9
J-90 7.72 Labs 500 22.19 141.7
J-91 7.56 Labs 5000 22.19 143.2
J-92 7.69 Labs 2000 22.19 142
J-93 8.17 Labs 500 22.19 137.3
J-94 6.94 <None> 0 22.19 149.3
J-95 6.95 hostel area 7865 22.19 149.2
J-96 7.53 <None> 0 22.19 143.5
J-97 7.34 hostel area 7865 22.19 145.4
J-98 7.67 <None> 0 22.19 142.2
J-99 7.53 <None> 0 22.19 143.6
J-100 7.04 institutional buildings 200 22.19 148.3
J-101 7.1 <None> 0 22.19 147.7
CONCLUSION
The project done using watergems and loop concludes that the network designed by the team is
sufficient enough to meet the needs like demand, capacity and also the pressure heads. A
pressure network is designed where the head is not enough to carry the water to the overhead
tanks of all individual buildings i.e. where the gravity network is not adoptable The drawings and
respective tables showing capacity, demand, co-ordinates are calibrated in the project. The pipe
diameter is taken as a constant 152.6 mm, there is a flexibility to change the diameter where
there is less demand so that the overall cost of the project can be reduced. The total demand for
the study area (S.V.N.I.T Campus)is 0.416 MLD.
REFERENCES
• Jyothi Prakash and V Natarajan (June,2011), Pipe Network analysis in an educational
campus, Journal of IWWA.
• Richard Ainsworth(2004) , Managing Water Distribution Network , IWA Publishing,
London, UK.
• Shie-Yui Liong(2006), Optimal Water Distribution Network, Journal of the Institution of
Engineers, Singapore.
• Glenn O.Brown(1999) , The History of Darcy-Weishbach Equation, Paper published by
Okalahoma State University.
• Adi Ben-Israel(1990), Newton-Raphson‘s method for the solution of system of equations,
research supported by the Swope Foundation.