Transcript
Page 1: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES COSTS

by

Mary Lou Ralls, P.E., PrincipalRalls Newman, LLC

(formerly Texas State Bridge Engineer)

Page 2: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Learning Outcomes• Identify examples of ABC/PBES replacement projects that

achieved onsite construction time and cost savings, and locate project contacts

• Describe combinations of PBES and contracting strategies that achieved accelerated onsite construction timelines at lower costs

• Explain why comparison of ABC costs and conventional construction costs may not be appropriate

• Explain why moving to ABC/PBES as a standard practice will achieve cost savings

Page 3: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

• Reduced onsite construction time

• Construction cost less than engineer’s estimate

• Project details• Project owner contacts• Other contacts, e.g.:

• Contractor• Design Engineer• Prefabricator

http://www.fhwa.dot.gov/bridge/prefab/successstories/091104/index.cfm

Cost-Competitive Projects

Page 4: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Projects

• ABC/PBES Deck Elements: full-depth precast deck panels– WA – Washington State Department of

Transportation’s SR 433 Lewis & Clark Bridge over Columbia River - 2004

• ABC/PBES Pier Elements: precast caps on cast-in-place columns– TX – Texas Department of Transportation’s State

Highway 66 Bridge over Lake Ray Hubbard - 2003

Page 5: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Projects, cont’d.

• ABC/PBES Beam Elements: modular beams with decks– NJ – New Jersey Department of Transportation’s

Route 1 Bridges over Olden Avenue & Mulberry Street – 2005

• ABC/PBES Beam Elements (modular beams with decks) + Abutment Elements (precast backwalls, precast wingwalls)– CO – Colorado Department of Transportation’s State

Highway 86 Bridge over Mitchell Gulch – 2002

Page 6: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Projects, cont’d.

• ABC/PBES Beam Elements (modular beams with decks) + Pier Elements (precast pile caps) + Miscellaneous Elements (precast approach slabs, precast parapets– NY – New York City Department of Transportation’s

Belt Parkway Bridge over Ocean Parkway – 2004

Page 7: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Deck Elements (full-depth precast deck panels)

Page 8: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Replaced 3900 ft of deck using SPMTs during 124 nights plus 3 weekend closures …

… with no impact to rush-hour traffic

After deck replacement

SPMTs with frame carrying panel

State Route 433 Lewis and Clark Bridgeover Columbia River, WA/OR – 2004

Page 9: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Route 433 Lewis and Clark Bridgeover Columbia River, WA/OR – 2004

Removal of old deck section & installation of new panel in avg. 6.5 hours overnight

103 full-width, 6-inch full-depth precast lightweight concrete panels, each 36 ft wide & 20 ft to 45 ft long

Page 10: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

SR 433 Lewis and Clark Bridge over Columbia River Contract Requirements

• “A” + “B” + “C” Bidding Method to determine lowest responsible bidder– “A” = bid items – “B” = bridge closures @ $8,000– “C” = single lane closures @ $2,000

Page 11: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

SR 433 Lewis and Clark Bridge over Columbia River

Incentives for Early Completion• $100,000 for completion by April 2004• $55,000 per Weekend Bridge Closure less than 4• $4,000 per Total Bridge Closure less than number bid• $1,000 per Single Lane Closure less than number bid

Page 12: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

SR 433 Lewis and Clark Bridge over Columbia RiverLiquidated Damages

• $16,000 per Total Bridge Closure more than number bid

• $4,000 per Single Lane Closure (SLC) more than number bid

• $1,700 per 15-min period beyond times specified for Weekend or Total Closure

• $900 per 15-min period beyond SLC

Page 13: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

• Engineer’s Estimate $ 28.8 M• Number of bidders 6• 2nd lowest bid $ 29.2 M• Low Bid $ 18.0 M• Savings – 38 % = $ 10.8 M

Closures: Only 124 nights & 3 weekends

SR 433 Lewis and Clark Bridge over Columbia River – 2004 Construction Costs

Page 14: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Pier Elements:precast caps on cast-in-place columns

Page 15: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Precast bent caps saved 215 days of onsite construction

State Highway 66 Bridgeover Lake Ray Hubbard, Texas – 2003

Page 16: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 66 Bridgeover Lake Ray Hubbard, Texas – 2003

…proposed by the Contractor

43 identical precast concretebent caps …

Page 17: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 66 Bridge over Lake Ray Hubbard Contract Requirements

• Contract specified cast-in-place concrete bent caps• Contractor proposed field change to precast concrete

bent caps for eastbound bridge• TxDOT accepted proposed field change, with no

change in funding

Page 18: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 66 Bridge over Lake Ray Hubbard – 2003 Construction Costs

• Engineer’s Estimate $ 48.2 M• Number of bidders 8• 2nd lowest bid $ 43.1 M• Low Bid $ 40.9 M• Savings – 15 % = $ 7.3 M

Onsite Time Savings: 215 Days

Page 19: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Beam Elements (modular beams with decks)

Page 20: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Route 1 Bridges over Olden Avenue& Mulberry Street, New Jersey – 2005

NJDOT’s 1st Hyperbuild Project

Olden Avenue Mulberry Street

Route 1FreewaythroughCity ofTrenton

Page 21: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Replaced 3 deteriorated bridges in 3 weekends

Deteriorated Route 1 decksover Mulberry Street and Olden Avenue

Route 1 Bridges over Olden Avenue& Mulberry Street, New Jersey – 2005

New Route 1 decksover Mulberry Street

Elevation of new Route 1 Bridgesover Mulberry Street

Page 22: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

over Mulberry Street

over

Old

en A

venu

e

Route 1 Bridge Construction

Page 23: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Route 1 Bridges over Olden Avenue & Mulberry Street Contract Requirements

• For each bridge, maximum 57 hours from complete closure to 2 lanes open

• Lane Occupancy Charge up to $10K/da• Substantial Completion by November 16, 2005• All work completed by January 13, 2006

Page 24: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

• If less than 57 hours:– Bridge over Olden Avenue• $1,500 per hour• Cap of $27,000

– Each bridge over Mulberry Street• $2,000 per hour• Cap of $36,000

Route 1 Bridges over Olden Avenue & Mulberry Street Incentives

Page 25: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

• If more than 57 hours:– Bridge over Olden Avenue• $1,500 per hour

– Each bridge over Mulberry Street• $2,000 per hour

• If after Nov. 16 – $4,200 per day• If all work not completed by Jan. 13 – additional $900

per day

Route 1 Bridges over Olden Avenue & Mulberry Street Liquidated Damages

Page 26: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

• Engineer’s Estimate $ 3.8 M• Number of bidders 5• 2nd Lowest Bid $ 3.8 M• Low Bid $ 3.5 M• Savings – 8 % = $ 0.3 M

3 bridges replaced in 3 weekends

Route 1 Bridges over Olden Avenue & Mulberry Street – 2005 Construction Costs

Page 27: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Beam Elements (modular beams with decks) + Abutment Elements

(precast backwalls, precast wingwalls)

Page 28: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

46-hour weekend construction of 40-ft long, 43-ft wide single span

No impact to rush-hour traffic

State Highway 86 Bridgeover Mitchell Gulch, Colorado – 2002

Page 29: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Precast concrete abutments, wingwalls, superstructure units with railing, & steel H piles

Early Saturday morning Saturday afternoon Saturday afternoon

State Highway 86 Bridgeover Mitchell Gulch, Colorado – 2002

Page 30: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 86 Bridge over Mitchell Gulch Contract Requirements

• Contract specified 3-cell cast-in-place concrete box culvert to replace 2-span timber bridge

• Value engineering change proposal by contractor/design team– Prefabricated single-span bridge – Completion in one weekend

Page 31: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 86 Bridge over Mitchell Gulch Contract Requirements, cont’d.

• CDOT response:– Accepted VE change proposal– Implemented lane rental fee

• Lane Rental Specification– $500/hr starting 6 a.m. Monday– Fee based on user costs to occupy SH 86

Page 32: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

State Highway 86 Bridge over Mitchell Gulch – 2002 Construction Costs

• Engineer’s Estimate $ 394.2 K• Number of bidders 12• 2nd Lowest Bid $ 365.8 K• Low Bid $ 365.2 K• Savings – 7 % = $ 29.0 K

Closure: Only 46 hours

Page 33: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ABC/PBES Beam Elements (modular beams with decks) + Pier Elements (precast pile caps) + Miscellaneous

Elements (precast approach slabs, precast parapets)

Page 34: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Existing Interchange

Belt Parkway Bridge over Ocean Parkway, New York City (Brooklyn) – 2004

Reconstructed Interchange

Page 35: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Replaced existing 2-span, 149-ft long, 78-ft wide bridge with 3-span, 221-ft long, 134-ft wide bridge …

… with no lane closures during peak traffic hours

Belt Parkway Bridge overOcean Parkway, New York City (Brooklyn) – 2004

Page 36: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Prefabricated:– Piles– T-Walls– Cap Beams– Superstructure– Parapets & Barriers– Approach Slabs

Belt Parkway Bridge over Ocean Parkway– 2004

51 superstructure segments in new 221-ft long x 134-ft wide bridge (49’-107’-65’)

Page 37: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Belt Parkway Bridge over Ocean ParkwayContract Requirements

• “A” + “B” Bidding Method to achieve reduced onsite construction timeline– “A” = bid items – “B” = “Critical Duration” x $85,000

Page 38: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Belt Parkway Bridge over Ocean ParkwayIncentives/Disincentives

• Incentive for completion before “Critical Duration”:– $85,000 per day– Cap of $2,000,000

• Disincentive for completion after “Critical Duration”:– $85,000 per day– No dollar limit

Page 39: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Belt Parkway Bridge over Ocean ParkwayConstruction Costs

• Engineer’s Estimate $ 60.0 M• Number of bidders 5• Low Bid $ 47.9 M• Awarded Bid * $ 55.5 M• Savings – 8 % = $ 4.5 M

* Best Value: only 285 “Critical Duration” days

Page 40: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Did these projects cost lessthan conventional construction?

Page 41: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

ProjectEngineer’s Estimate

Awarded Bid

Cost Savings$ %

WSDOT Lewis & Clark Bridge $ 28.8M $ 18.0M $ 10.8M 38TxDOT SH 66 Bridge

over Lake Ray Hubbard48.2M 40.9M 7.3M 15

NYCDOT Belt Parkway Bridge 60.0M 55.5M 4.5M 8NJDOT Rt. 1 Bridge 3.8M 3.5M 0.3M 8

CDOT Mitchell Gulch Bridge 0.394M 0.365M 0.029M 7Totals $ 141.2M $

118.3M$ 22.9M 16%

avg.

Page 42: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

So, what is needed to ensurecost savings or, at a minimum,

cost competitivenesson ABC/PBES projects?

Page 43: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

For Effective ABC Implementation

• Make ABC standard practice, not just project-specific use– Shows owner’s commitment to future use – a

program of work– Reduces costs with multiple use

• Example: Utah DOT transition to ABC as standard practice for projects as appropriate

Page 44: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

$0

$100,000

$200,000

$300,000

$400,000

$500,000

$600,000

$700,000

$800,000

$900,000

$1,000,000

I-215; 4500South

I-80; StateStreet to

1300 East

I-80; Mt.Delle toLambsCanyon

3300 Southover I-215

I-15;Widening,

500 North toI-215

PioneerCrossing

SP

MT

Co

st

Cost

Log. (Cost)

Cost per bridge span moved

Cost of implementing SPMT Bridge Moves

-19 Utah Bridges

Page 45: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

Module ConclusionYou should now be able to:• Identify examples of ABC/PBES replacement projects that

achieved onsite construction time and cost savings, and locate project contacts

• Describe combinations of PBES and contracting strategies that achieved accelerated onsite construction timelines at lower costs

• Explain why comparison of ABC costs and conventional construction costs may not be appropriate

• Explain why moving to ABC/PBES as a standard practice will achieve cost savings

Page 46: ABC/PBES COSTS by Mary Lou Ralls, P.E., Principal Ralls Newman, LLC (formerly Texas State Bridge Engineer)

QUESTIONS?

Mary Lou Ralls, [email protected]


Recommended