    HRD/July 26, 2013

    Mr. RAJENDRA SINGHPonta Road, Herbertpur,Dehradun (U.K.)

    Subject: Construction of Plat Form

    Dear Sir,

    With reference to your quotation dt. 18/07/2013, we are pleased to award you theconstruction of plat form for equipment at our Deharadun Plant as per the details givenbelow:

    SR.NO.

    DESCRIPTION Qty. Rate(Rs.)

    Amount(Rs.)

    1. Tin shed (precoated) withmaterial -12 X 50(Thickness 0.50mm )MS Round pipe for all sides andsquare pipe at top (to support shed)

    600Sq.Ft.

    110/= 66000/=

    2. Brick work with plaster42 X 3 X 2(with foundation of 1 Feet) 252Sq.ft 120/= 30240/=

    3. Linter (RCC)42 x 8.(Thickness3 )

    336 Sq.Ft.

    150/= 50400/=

    TOTAL 146640/=

    Payment terms :

    1. 25% Advance payment.

    2. 25% After completion of 75% of work as per work order.

    3. 40% after completion of full work as mentioned in the work order and afterproper inspection carried out by us.

    4. 5 % after six months from the date of completion of work

    5. 5 % after 12 months from the date of completion of work2 ..

  • 7/27/2019 Work Order Final 31 7 13

    2/10

    : 2 :

    TERMS & CONDITIONS :-

    1. Defect liability period One year from the date of completion.

    2. All your workers should be covered under insurance at your cost

    3. TDS/W.C.T/ESIC will be borne by you.

    4. Electricity & water will be provided by the company free of cost.

    5. All debris will be removed from the company at your cost.

    6. One year performance guarantee will be given for the project.

    7. Any Carelessness in the work carried out by you causing loss /

    damages to our materials the same will be adjusted against your bills.

    8. Safety measures are must while working with us, hence any worker

    while working must make use of the personal protective equipment

    without fail.

    9. You are required to insure all your employees under the W.C. Policy

    as it is your own responsibility to look after the accident etc., in thecase of occurrence of any eventualities in the premises of the

    Company. The Company will not be responsible for any damages

    and / or accident to your employees at the Company premises.

    10. While your workers are working, one of your safety Incharge should

    be present there.

    COMPLETION OF WORK : 31st August, 2013Penalty : Rs.1000/- per day if work not completed

    on or before 31st

    August. 2013. However if work isstopped due to rain that much time will be givenextra.

    ForHIND RECTIFIERS LIMITED

  • 7/27/2019 Work Order Final 31 7 13

    3/10

    HRD/

    July 26, 2013

    Mr. RAJENDRA SINGHPonta Road, Herbertpur,Dehradun (U.K.)

    Subject: Boundary WallDear Sir,

    With reference to your quotation dt. 17/07/2013, we are pleased to award you theConstruction of Boundary Wall at our Deharadun Plant as per the details given below:

    SR.NO.

    DESCRIPTION Qty. Rate(Rs.)

    Amount(Rs.)

    1. Brick Work410 X 4 = 1640Less- Frame 270

    1370Sq.Ft.

    100/= 137000/=

    2. Beam Thickness 9 410Sq.Ft.

    150/= 61500/=

    3. Pillar (Every 15 one pillar) 30 Nos. 1800/= 54000/=

    4. Frame Jali (3 X 1-1/2) x 60 nos. x 20kg. (Frame Jali will be informed later)

    1200Kg.

    60/= 72000/=

    5. Foundation (River side) 40 x 6 = 240

    x 2

    480

    Cubicft.

    90 43200/=

    6. Foundation70 x 2 = 140 x 1-1/2 =

    (Front Side)

    210CubicFt.

    90 18900/=

    7. Fencing Wire Fitting charges 340 Rft. 5000/=

    8. Putting stone, sand, & Bajri coveringthe same with cement at River side 120 x 6

    720 Rft. 80 57600/=

    TOTAL 449200/=

    1. Back side and river side work to be done immediately or first.2. Front side work to be started after prior permission from our side.3. Bricks lying with us at back side to be used for the back side work only and

    bricks lying with us at front side to be used for front side work only.4. No extra costs to be charged for Barbed wire fencing as well as for filling of pit

    wall near river side.

    2..

  • 7/27/2019 Work Order Final 31 7 13

    4/10

    Payment terms :

    1. 25% Advance payment.

    2. 25% after completion of 75% of work as per work order.

    3. 40% after completion of full work as mentioned in the work order and after properinspection carried out by us.

    4. 5 % after six months from the date of completion of work

    5. 5 % after 12 months from the date of completion of work

    TERMS & CONDITIONS :-

    1. Defect liability period One year from the date of completion.

    2. All your workers should be covered under insurance at your cost

    3. TDS/W.C.T/ESIC will be borne by you.

    4. Electricity & water will be provided by the company free of cost.

    5. All debris will be removed from the company at your cost.

    6. One year performance guarantee will be given for the project.

    7. Any Carelessness in the work carried out by you causing loss /

    damages to our materials the same will be adjusted against your bills.

    8. Safety measures are must while working with us, hence any worker

    while working must make use of the personal protective equipment

    without fail.

    9. You are required to insure all your employees under the W.C. Policy

    as it is your own responsibility to look after the accident etc., in the

    case of occurrence of any eventualities in the premises of the

    Company. The Company will not be responsible for any damages

    and / or accident to your employees at the Company premises.

  • 7/27/2019 Work Order Final 31 7 13

    5/10

    10. While your workers are working, one of your safety Incharge should

    be present there

    COMPLETION OF WORK :

    15th September, 2013Penalty : Rs.1000/- per day if work not completedon or before above date. However if work isstopped due to rain that much time will be givenextra.

    ForHIND RECTIFIERS LIMITED

  • 7/27/2019 Work Order Final 31 7 13

    6/10

    HRD/July 26, 2013

    Mr. RAJENDRA SINGHPonta Road, Herbertpur,Dehradun (U.K.)

    Subject: Drainage / Gutter

    Dear Sir,

    With reference to your quotation dt. 17/07/2013, we are pleased to award you toConstruct the Drainage / Gutter at our Deharadun Plant as per the details given below:

    SR.NO.

    DESCRIPTION Qty. Rate(Rs.)

    Amount(Rs.)

    1. Drain work Both side Brick Workwith plaster 325 x 1-1/2 x 2

    975Sq.ft

    120/= 117000/=

    2. Base for drain 975Sq.ft.

    30/= 29250/=

    TOTAL 146250/=

    Payment terms :

    1. 25% Advance payment.

    2. 25% After completion of 75% of work as per work order.

    3. 40% after completion of full work as mentioned in the work order and afterproper inspection carried out by us.

    4 5 % after six months from the date of completion of work

    5 5 % after 12 months from the date of completion of work

    TERMS & CONDITIONS :-

  • 7/27/2019 Work Order Final 31 7 13

    7/10

    1 Defect liability period 1 year from the date of completion.

    2 All your workers should be covered under insurance at your cost

    3 TDS/W.C.T/ESIC will be borne by you.

    4 Electricity & water will be provided by the company free of cost.

    5 All debris will be removed from the company at your cost.

    6 01 years performance guarantee will be given for the project.

    7 Any Carelessness in the work carried out by you causing loss / damages

    to our materials the same will be adjusted against your bills.

    8 Safety measures are must while working with us, hence any worker whileworking must make use of the personal protective equipment without fail.

    9 You are required to insure all your employees under the W.C. Policy as it

    is your own responsibility to look after the accident etc., in the case of

    occurrence of any eventualities in the premises of the Company. The

    Company will not be responsible for any damages and / or accident to

    your employees at the Company premises.

    10 While your workers are working, one of your safety Incharge should be

    present there.

    COMPLETION OF WORK :30th September, 2013Penalty : Rs.1000/- per day if work not completedon or before above date. However if work isstopped due to rain that much time will be givenextra.

    ForHIND RECTIFIERS LIMITED

  • 7/27/2019 Work Order Final 31 7 13

    8/10

    HRD/July 26, 2013

    M/s. MURTI FURNITURES6, New Patel Nagar,Uttarakhand.

    Subject: Carpentry work

    Dear Sir,

    With reference to your quotation dt. 17/07/2013, we are pleased to award you thecarpentry work at our Deharadun Plant as per the Drawing approved by us.

    SR.NO.

    DESCRIPTION Qty. Rate(Rs.)

    Amou(Rs.)

    1. Conference :-Table: Providing and making of (8.0 X 3.6) table with19mm board, 1mm lamination, slider channels, drawers and

    complete SS fittings.

    1 Unit 25300/= 2530

    2. Staff Section:-

    Working Table:- Providing and making of L-shape (5.0 X5.0) table with 19mm board, 1mm lamination, sliderchannels, drawers and complete SS fittings.

    Fancy Partition:- Providing and making of fancy partition withwooden frame of 1mm lamination paneling till 3ft from floor,soft board till 1 ft. from wooden frame and toughened glass till

    1ft from soft board (10.0 X 5.0)ft 2 Nos.

    File Cabinet:- Providing and making of

    (5.0 x 3.0 x 1.5)ft 1 No.

    (9.0 X 2.0 X 1.5)ft. 1 No.

    4Unit

    100Sqft.

    15Sqft.18Sqft.

    25300/=

    552/=

    862.50

    862.50

    10120

    55200

    12938

    15525

  • 7/27/2019 Work Order Final 31 7 13

    9/10

    Sofa:- Providing and making of sofa in upholstery (uptoRs.600 per m.)3-Seater - 1 No.

    3 PerSeat

    7475/= 37375

    3. Senior Staff Section:- Providing and making of :

    Table with 19mm board, 1mm lamination, slider channels,drawers and complete SS fittings. (5 x 5 )Sq.ft. 4 Nos.

    (Rate of table for senior staff is based on per sq.ft. basis. Ifarea is reduced amount will be adjusted accordingly)

    Fancy Partition:- Providing and making of fancy partition withwooden frame of 1mm lamination paneling till 3ft from floor,soft board till 1 ft. from wooden frame and toughened glass till1ft from soft board ( 21 x 4) Sq.Ft - 2 Nos.

    84Sqft.

    25300/=

    552/=

    10120

    46368

    TOTAL 39510

    VAT & Service tax : Extra as applicable.Final amount will be calculated on measurement of actual area

    Payment terms :

    1. 25% Advance payment of total work order.

    2. 25% After completion of 50% work as per total work order.

    3. 40% of material and labour within 10 days after completion of full work asmentioned in the work order and after proper inspection carried out by us.

    4. 10% of material within 10 Day and labour within 1 month from the date ofcompletion of work.

    TERMS & CONDITIONS :-

    1. Defect liability period One year from the date of completion.

    2. All your workers should be covered under insurance at your cost.

    3. ESIC will be borne by you.

  • 7/27/2019 Work Order Final 31 7 13

    10/10

    4. Electricity & water will be provided by the company free of cost.

    5. All debris will be removed from the company at your cost.

    6. One year performance guarantee will be given for the project.

    7. Any Carelessness in the work carried out by you causing loss / damages to our

    materials the same will be adjusted against your bills.

    8. Safety measures are must while working with us, hence any worker while

    working must make use of the personal protective equipment without fail.

    9. You are required to insure all your employees under the W.C. Policy as it is your

    own responsibility to look after the accident etc., in the case of occurrence of any

    eventualities in the premises of the Company. The Company will not be

    responsible for any damages and / or accident to your employees at the

    Company premises.

    10. While your workers are working, one of your safety Incharge should be present

    there.

    COMPLETION OF WORK :

    30 Days from the date of work orderPenalty : Rs.1000/- per day if work not completed

    on or before 31st

    August, 2013. However if work isstopped due to rain that much time will be givenextra.

    ForHIND RECTIFIERS LIMITED