Westmeath County Water Conservation Project
Stage 3 Watermains RehabilitationWorks
Athlone Town
February 2013
Main Rehabilitation Works - Athlone
2
Potentially Recoverable Real Losses
• Why? Aging water distribution network
o Older Cast Iron mains, and o Asbestos Cement mains end of their design life.
Athlone Town in 2009 water shortages and overnight shut offs necessary to maintain water reservoir levels in Reservoirs
• Short Term Response Response deployment of water services resources. standpipes were set up at locations throughout the Town
• Long Term Response WCC plans to deal with the replacement and rehabilitation of
critical watermains Feb 2012 Coosan Road area watermain replaced.
3
• What next?
Replacement of over 25km of watermain
Replacement of the most problematic sections of watermain in terms of maintenance and water loss.
Opportunity arises via funding secured under the European Regional Development Fund (ERDF). Timeline is critical
Investment in the future of the network
Main Rehabilitation Works - Athlone
• Planning WCC are conscious that works in the streets will present particular
challenges.
Awareness of the need to minimise impacts on traffic flows
Ensure that business and residents are not adversely affected more than is necessary by the works.
Every effort made to avoid unplanned interruptions to water supplies
Ensure impact on other services such as transportation and emergency services are minimised.
Site investigation works complete to allow detailed design of the project.
Main Rehabilitation Works - Athlone
Old Galway Road
Battery HeightsConnacht Street
Arcadia
Assumption Road
North Gate St
Church Street
Sean Costello St
Ballymahon Rd
Old Dublin Rd
Works Locations in Athlone Town
Blyry Rd
Garycastle Rd
Army Barrack
Civic Offices
©Ordnance Survey Ireland License No. EN 0016012
6
Affected Roads / Streets Schedule
Works Section Name Roads / Streets affected
Old Galway Road/Roscommon Road/ Baylough
Old Galway Road/Roscommon Road/ Accommodation Road, Iona Park and St Josephs Villas,
Battery Heights Battery Heights, The Batteries, Battery Road, St. Anne's Terrace,
Connacht Street, Pearse Street St. Ruth's Park, St. Asicus Villas, Magazine Road, Connacht Street, Pearse and Barrack Street, Main street, High Street, Bastion Street, Parnell square, Patrick Street, Lyster Street
Arcadia Arcadia/One Mile Road to Roundabout Ballymahon RoadAssumption Road Assumption Road, Coosan Point Road, Beechpark, Auburn
Drive/Villas.North Gate Street/Abbey Road WTW site/ Wansboro Park, Marine View ,Coosan Road, Abbey
Road and North Gate Street, Lucas Lane, St. Francis Terrace, Court Divinish ,Preachers Lane
Church Street Custume Place, Church Street , Dublin Gate Street, Sean Costelloe Street, Griffith Street, Friars lane, Loyds Lane, Strand Street, Wolfe tone Terrace
Sean Costelloe StreetSean Costelloe Street, Irishtown, Castlemaine Street, St. Mary’s Place, Mardyke Street, Gleeson Street, Grace Park Road, Ballymahon Road, Lower Road, Bower Road, Sarsfield Square.
Old Dublin Road Castlemaine street, Brideswell, Dublin Road, Killyon HillBallymahon Road Ballymahon Road to Blyry Road Junction , Blyry road to
Garycastle
7
• Works Programme
Anticipated construction work will commence in June 2013
– Estimated 9 Month programme
– planned completion mid February 2014
– Account taken of overlaps with other works e.g. new road at Garrycastle
– The Gathering and other events e.g. Tri – Athlone
Contractor will be supervised on site by Employers Representative’s Site Agent
Liaison Officer to interface with public during construction stage
Works will be communicated to general public via local papers, radio and Westmeath County Council website
Main Rehabilitation Works - Athlone
8
• Contract Requirements/Tender Phase Traffic diversions - one way systems will be
required Specific Road closures for specified durations to
limit impact where possibleo Mid tem or holiday period for schools, o Barrack Street / Pearse Street in Augusto Avoid Main routes around Christmas period for Traderso programming to avoid simultaneous works on critical
traffic routes and Motorway Junctions
Traffic Management
9
• Pre Construction Works Contractor provides a Traffic Management Plan to
WCC Area Office/Roads Department for approval prior to commencing the works
• Construction Phase Alternative access arrangements will be facilitated where
required through development of the construction phase Traffic Management Plan
Disruption to be minimised by:– effective planning– avoidance of peak times in critical areas– appropriate phasing of multiple work crews– use of night work – not generally envisaged in residential areas– use of appropriate warning signage
Traffic Management
10
Investment in the Network means
Investment in Athlone
Westmeath County Water Conservation Project
Stage 3 Watermains RehabilitationWorks
Athlone Town
Questions