West Park Hospital Phase III (Dietary Build-out/Cedar Mountain/Med Records/Connector/Education) Monthly Project Report July 2015

West Park Hospital

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: West Park Hospital

West Park Hospital Phase III (Dietary Build-out/Cedar

Mountain/Med

Records/Connector/Education)

Monthly Project Report July 2015

Page 2: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 01 – Project Update

Page 3: West Park Hospital

1

WEST PARK HOSPITAL PHASE III Weekly Progress Report 022

Period ending July 19, 2015

Weather

Average Daily High Temp 74 F

Min Low Temp 56 F

Average Wind Speed 9 mph

Man Power

Number or Workers on Site: 42

Subcontractors on Site

• Basin Mechanical/NorPac Sheet Metal, Cowan Construction, Yellowstone Electric, Delta United

Specialties, MKM Construction, Spray on Solutions and Sure Steel

Schedule

•••• Upcoming Meetings – local time

o Sub Coordination Meeting, 9am MST July 21 – Conference Office

o Safety Orientation Meeting, 7am MST Daily – Conference Office

Page 4: West Park Hospital

2

Work Progress Ground Floor Dietary Buildout

General:

• Layout and Framing – 95%

• In-wall Rough-in – 80%

• Overhead Rough-In – 70%

Concrete:

Electrical:

• Overhead rough In - ongoing

• In wall R.I. ongoing

HVAC:

• Overhead duct installation ongoing

Plumbing

• Overhead R.I. - ongoing

• In-wall R.I. – ongoing

Drywall

• Framing Area D ongoing – 90%

• Framing Area A – 95%

• Top-out in Area A and B

• Drywall ongoing – 40%

Work Progress First Floor Medical Records

General:

• Fab and deliver door frames/Doors per revisions

Electrical:

• In wall R.I. ongoing

• Overhead R.I. ongoing

HVAC:

• Overhead ductwork install ongoing

• VAV install ongoing

Plumbing

• Overhead R.I. ongoing

• Hydronic piping install ongoing

Drywall/Stud Framing

• Framing of walls complete

Page 5: West Park Hospital

3

Work Progress Connector

General:

• Exterior framing started

• Fireproofing steel complete

Sitework/Concrete

• Backfill around columns ongoing

• Begin form sitework Concrete

Electrical:

• .

HVAC:

• Procurement of duct ongoing

• Equipment deliveries ongoing

Plumbing

• Procurement of materials ongoing

Drywall/Stud Framing

• Layout of walls ongoing – 20%

• Fab truss on-site ongoing

• Exterior framing started

Steel

• Column and beam fireproofing complete

Work Progress Cedar Mountain Center

General:

• Received final CD’s per state revisions on 6/11

• Layout and framing ongoing complete

• Overhead Rough-in – 60%

• In-wall Rough ongoing – 85%

Electrical:

• Overhead rough in ongoing – 80%

• In wall rough in ongoing – 85%

HVAC:

• Overhead rough in ongoing – 35%

• Procurement of materials per revised drawings ongoing

Page 6: West Park Hospital

4

Plumbing

• Overhead rough in ongoing – 50%

• Begin in-wall rough-in – 70%

Drywall/Stud Framing

• Layout and framing per final CD’s

• Topout ongoing

• Patching existing walls second floor ongoing

Work Progress Education

General:

• Layout complete

• Duct Installation ongoing

Electrical:

• Overhead rough in ongoing

• In wall rough in ongoing

HVAC:

• Overhead rough in ongoing

Plumbing

• Overhead rough in ongoing

• In wall R.I. complete

Drywall/Stud Framing

• Layout and framing ongoing

• Top-out ongoing

Work Progress Parking Lot

Sitework:

• SWPPP ongoing

• Utility pole relocated June 6th – Secondary service ongoing

• Infiltration system backfill complete

• Underground utility install ongoing

Page 7: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 02 � Project Schedule

Page 8: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

Cedar Mountain Renovation 01.20.15Cedar Mountain Renovation 01.20.15 158 135 14.58% 06-Apr-15 A 30-Nov-15

Project Overview and MilestonesProject Overview and Milestones 158 135 14.58% 06-Apr-15 A 30-Nov-15

A1560 Asbestos Remediation 10 0 100% 23-Apr-15 A 22-May-15 A

A1580 Start Cedar Mountain 0 0 0% 26-May-15*

A1620 State Review 30 8 75% 06-Apr-15 A 03-Jun-15

A1000 Overall Construction Duration 111 130 0% 27-Apr-15 A 23-Nov-15

A1510 Notice to Proceed 0 0 0% 26-May-15

A1640 Reissue Drawings State Review 0 0 0% 10-Jun-15

A1600 OFE Install 5 5 0% 30-Oct-15 06-Nov-15

A1590 LCC Document Close-Out to Owner 1 1 0% 18-Nov-15 19-Nov-15

A1010 Substantial Completion 0 0 0% 20-Nov-15

A1540 State Health Insection 0 0 0% 23-Nov-15

A1530 Finish Cedar Mountain 0 0 0% 23-Nov-15

A1610 Owner Prep/Owner Move-In 5 5 0% 23-Nov-15 30-Nov-15

Interior FinishInterior Finish 156 135 13.48% 06-Apr-15 A 30-Nov-15

A1550 State Review 30 8 75% 06-Apr-15 A 03-Jun-15

A1020 Build Temporary Walls/ICRA Setup 2 0 100% 27-Apr-15 A 28-Apr-15 A

A1030 Make Safe - MEP 5 0 100% 27-Apr-15 A 01-May-15 A

A1040 Demolition 20 2 90% 13-Apr-15 A 27-May-15

A1050 Layout 2 2 25% 04-May-15 A 29-May-15

A1570 Reissue Drawings State Review 1 1 0% 10-Jun-15* 10-Jun-15

A1630 Fab and Deliver Duct 30 30 0% 10-Jun-15 22-Jul-15

A1660 Door Frame Fab and Deliver 15 15 0% 10-Jun-15 01-Jul-15

A1060 Frame/Top-out Priority Walls 5 5 0% 01-Jul-15 08-Jul-15

A1100 Frame/Top-Out All Walls 5 5 0% 08-Jul-15 15-Jul-15

A1110 In Wall R.I. MEP 20 20 0% 14-Jul-15 11-Aug-15

A1170 Overhead Fire Protection R.I. 3 3 0% 15-Jul-15 20-Jul-15

A1180 Set Roof Curbs 1 1 0% 15-Jul-15 16-Jul-15

0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30

J J A S O N D J F M A M J

Asbestos Remediation

Start Cedar Mountain

State Review

Overall Construction Duration

Notice to Proceed

Reissue Drawings State Review

OFE Install

LCC Document Close-Out to Owner

Substantial Completion

State Health Insection

Finish Cedar Mountain

Owner Prep/Owner Move-In

State Review

Build Temporary Walls/ICRA Setup

Make Safe - MEP

Demolition

Layout

Reissue Drawings State Review

Fab and Deliver Duct

Door Frame Fab and Deliver

Frame/Top-out Priority Walls

Frame/Top-Out All Walls

In Wall R.I. MEP

Overhead Fire Protection R.I.

Set Roof Curbs

Page 1 of 3

Early Bar

Critical Bar

Actual Bar

Level of Effort

Actual Level of Effort

Project Baseli...

Milestone

Run Date: 27-May-15

Data Date: 26-May-15

Project ID: 15HCG0120

Layton Construction Co., Inc.

27-May-15 Schedule

Page 9: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A1190 Patch Roof 2 2 0% 16-Jul-15 20-Jul-15

A1070 Overhead R.I. Mechanical 20 20 0% 22-Jul-15 19-Aug-15

A1080 Overhead R.I. Electrical 20 20 0% 29-Jul-15 26-Aug-15

A1090 Overhead R.I. Plumbing 20 20 0% 29-Jul-15 26-Aug-15

A1120 In-Wall/Framing Inspection 1 1 0% 11-Aug-15 12-Aug-15

A1130 Prep/Form/Pour Concrete Bathroom Curbs 2 2 0% 12-Aug-15 14-Aug-15

A1140 Insulate/Hang Drywall 5 5 0% 12-Aug-15 19-Aug-15

A1160 Tape/Finish Walls 5 5 0% 17-Aug-15 24-Aug-15

A1210 Frame Hard Ceilings/Soffits 5 5 0% 20-Aug-15 27-Aug-15

A1150 Equipment/FCU Install 3 3 0% 26-Aug-15 31-Aug-15

A1200 Above Ceiling Inspection 1 1 0% 31-Aug-15 01-Sep-15

A1220 Hang Hard Ceilings/Soffits 3 3 0% 01-Sep-15 04-Sep-15

A1230 Tape/Finish Hard Ceilings/Soffits 5 5 0% 04-Sep-15 11-Sep-15

A1240 Prime/1st Coat Walls and Ceilings/Soffits 5 5 0% 11-Sep-15 18-Sep-15

A1250 Ceramic Tile Bathrooms 15 15 0% 18-Sep-15 09-Oct-15

A1270 Ceiling Grid 3 3 0% 18-Sep-15 23-Sep-15

A1280 Sprinkler Drops 3 3 0% 22-Sep-15 25-Sep-15

A1290 Millwork 10 10 0% 23-Sep-15 07-Oct-15

A1310 MEP Trim-Out Ceilings 4 4 0% 23-Sep-15 29-Sep-15

A1320 Above Ceiling Punch 1 1 0% 29-Sep-15 30-Sep-15

A1430 Equimpent Startup 2 2 0% 29-Sep-15 01-Oct-15

A1330 Above Ceiling Inspection 1 1 0% 30-Sep-15 01-Oct-15

A1340 Drop Ceiling Tile 3 3 0% 01-Oct-15 06-Oct-15

A1440 Pre-Cx/PFC Equipment 5 5 0% 01-Oct-15 08-Oct-15

A1350 Resilient Flooring/Carpet/Base 15 15 0% 02-Oct-15 23-Oct-15

A1300 MEP Trim-Out 5 5 0% 07-Oct-15 14-Oct-15

A1470 Equipment ID/Panel Schedules 1 1 0% 08-Oct-15 09-Oct-15

A1260 MEP Trim-Out Bathrooms 3 3 0% 09-Oct-15 14-Oct-15

A1360 Final Paint 5 5 0% 23-Oct-15 30-Oct-15

A1370 Install Accessories/OFE 5 5 0% 30-Oct-15 06-Nov-15

A1650 Install Doors and Hardware 3 3 0% 02-Nov-15 04-Nov-15

A1460 TAB 4 4 0% 04-Nov-15 10-Nov-15

A1380 Construction Clean 2 2 0% 06-Nov-15 10-Nov-15

0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30

J J A S O N D J F M A M J

Patch Roof

Overhead R.I. Mechanical

Overhead R.I. Electrical

Overhead R.I. Plumbing

In-Wall/Framing Inspection

Prep/Form/Pour Concrete Bathroom Curbs

Insulate/Hang Drywall

Tape/Finish Walls

Frame Hard Ceilings/Soffits

Equipment/FCU Install

Above Ceiling Inspection

Hang Hard Ceilings/Soffits

Tape/Finish Hard Ceilings/Soffits

Prime/1st Coat Walls and Ceilings/Soffits

Ceramic Tile Bathrooms

Ceiling Grid

Sprinkler Drops

Millwork

MEP Trim-Out Ceilings

Above Ceiling Punch

Equimpent Startup

Above Ceiling Inspection

Drop Ceiling Tile

Pre-Cx/PFC Equipment

Resilient Flooring/Carpet/Base

MEP Trim-Out

Equipment ID/Panel Schedules

MEP Trim-Out Bathrooms

Final Paint

Install Accessories/OFE

Install Doors and Hardware

TAB

Construction Clean

Page 2 of 3

Page 10: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A1450 Commissioning 1 1 0% 10-Nov-15 11-Nov-15

A1390 LCC/AOE Punch 1 1 0% 10-Nov-15 11-Nov-15

A1480 Owner Training 2 2 0% 11-Nov-15 13-Nov-15

A1400 Final Clean 3 3 0% 11-Nov-15 16-Nov-15

A1410 Fire Marshall/Local Final Inspections 2 2 0% 16-Nov-15 18-Nov-15

A1490 LCC Document Close-Out to Owner 1 1 0% 18-Nov-15 19-Nov-15

A1520 Substatial Completion 1 1 0% 19-Nov-15 20-Nov-15

A1420 State Health Inspection 1 1 0% 20-Nov-15 23-Nov-15

A1500 Owner Prep/Owner Move-In 5 5 0% 23-Nov-15 30-Nov-15

0 0 1 2 2 0 1 2 2 0 1 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 3 0 1 2 2 0 1 1 2 0 0 1 2 2 0 1 2 2 0 1 1 2 0 0 1 2 30

J J A S O N D J F M A M J

Commissioning

LCC/AOE Punch

Owner Training

Final Clean

Fire Marshall/Local Final Inspections

LCC Document Close-Out to Owner

Substatial Completion

State Health Inspection

Owner Prep/Owner Move-In

Page 3 of 3

Page 11: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

WPH Connector and RenovationWPH Connector and Renovation 137 106 22.63% 31-Mar-15 A 20-Oct-15

Project OverviewProject Overview 137 106 22.63% 31-Mar-15 A 20-Oct-15

A1520 Notice to Proceed 0 0 100% 31-Mar-15 A

A1590 Start Connector and Renovation 0 0 100% 31-Mar-15 A

A1000 Overall Construction Duration 124 97 21.77% 31-Mar-15 A 07-Oct-15

A1010 Reissue Drawings State Review 0 0 0% 19-Jun-15*

A1490 OFE Install 3 3 0% 29-Sep-15 01-Oct-15

A1510 LCC Paperwork to Owner 1 1 0% 12-Oct-15 12-Oct-15

A1610 Substantial Completion 0 0 0% 12-Oct-15

A1620 State Health Inspection 0 0 0% 13-Oct-15

A1600 Finish Connector and Renovation 0 0 0% 13-Oct-15

A1500 Owner Prep/Move-In 5 5 0% 14-Oct-15 20-Oct-15

ConstructionConstruction 137 95 30.66% 31-Mar-15 A 20-Oct-15

A1060 Notice to Proceed 1 0 100% 31-Mar-15 A 13-Apr-15 A

A1070 Working Control for Layout 1 0 100% 08-Apr-15 A 09-Apr-15 A

A1080 Demo as needed for Control/Layout/Canopy5 0 100% 20-Apr-15 A 20-Apr-15 A

A1090 Field Verify Steel 1 0 100% 14-Apr-15 A 14-Apr-15 A

A1100 Excavate for Footings/Foundation 5 0 100% 13-Apr-15 A 14-Apr-15 A

A1110 Form/Prep/Rebar/Anchor Bolts 5 0 100% 15-Apr-15 A 08-May-15 A

A1120 City Inspection 1 0 100% 15-Apr-15 A 08-May-15 A

A1130 Pour Foundations 2 0 100% 15-Apr-15 A 08-May-15 A

A1140 Erect Steel 5 5 0% 10-Jun-15* 16-Jun-15

A1150 Install Decking/Detailing 5 5 0% 17-Jun-15 23-Jun-15

A1550 Reissue Drawings State Review 1 1 0% 19-Jun-15 19-Jun-15

A1160 Steel Inspection 1 1 0% 24-Jun-15 24-Jun-15

A1170 Form/Prep SOD 2 2 0% 25-Jun-15 26-Jun-15

A1180 City Inspection SOD 1 1 0% 29-Jun-15 29-Jun-15

A1190 Pour SOD 1 1 0% 30-Jun-15 30-Jun-15

A1200 Exterior Layout North and South Elevations 1 1 0% 01-Jul-15 01-Jul-15

A1450 Fireproofing 3 3 0% 01-Jul-15 03-Jul-15

A1210 Roofing System 10 10 0% 02-Jul-15 15-Jul-15

A1220 Exterior Sheathing and Dry In 5 5 0% 06-Jul-15 10-Jul-15

A1230 Interior MEP Overhead R.I. 5 5 0% 13-Jul-15 17-Jul-15

A1240 Exterior Finishes 20 20 0% 20-Jul-15 14-Aug-15

A1530 Install Window Systems 5 5 0% 20-Jul-15 24-Jul-15

A1250 Interior Framing 5 5 0% 17-Aug-15 21-Aug-15

A1260 Interior MEP In-Wall R.I. 5 5 0% 24-Aug-15 28-Aug-15

A1270 Site Work/Exterior Landscape 8 8 0% 31-Aug-15 09-Sep-15

A1280 Interior City Inspection 1 1 0% 31-Aug-15 31-Aug-15

A1290 Hang Drywall 3 3 0% 01-Sep-15 03-Sep-15

A1300 Tape/Float Walls 4 4 0% 04-Sep-15 09-Sep-15

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

Start Connector and Renovation

Overall Construction Duration

Reissue Drawings State Review

OFE Install

LCC Paperwork to Owner

Substantial Completion

State Health Inspection

Finish Connector and Renovation

Owner Prep/Move-In

Working Control for Layout

Demo as needed for Control/Layout/Canopy

Field Verify Steel

Excavate for Footings/Foundation

Form/Prep/Rebar/Anchor Bolts

City Inspection

Pour Foundations

Erect Steel

Install Decking/Detailing

Reissue Drawings State Review

Steel Inspection

Form/Prep SOD

City Inspection SOD

Pour SOD

Exterior Layout North and South Elevations

Fireproofing

Roofing System

Exterior Sheathing and Dry In

Interior MEP Overhead R.I.

Exterior Finishes

Install Window Systems

Interior Framing

Interior MEP In-Wall R.I.

Site Work/Exterior Landscape

Interior City Inspection

Hang Drywall

Tape/Float Walls

Page 1 of 2

Early Bar

Critical Bar

Actual Bar

Level of Effort

Actual Level of Effort

Project Baseline Bar

Milestone

Run Date: 02-Jun-15

Data Date: 26-May-15

Project ID: 15HCG0126

Layton Construction Co., Inc.

02-Jun-15 Schedule

Page 12: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A1310 Prime/1st Coat Paint 3 3 0% 10-Sep-15 14-Sep-15

A1320 MEP Trim-Out 3 3 0% 15-Sep-15 17-Sep-15

A1410 Ceiling Grid Install 2 2 0% 15-Sep-15 16-Sep-15

A1430 MEP Trim-Out Ceilings 2 2 0% 17-Sep-15 18-Sep-15

A1440 Above Ceiling Inspection 1 1 0% 21-Sep-15 21-Sep-15

A1420 Drop Ceiling Tile 2 2 0% 22-Sep-15 23-Sep-15

A1330 2nd/Final Coat Paint 3 3 0% 24-Sep-15 28-Sep-15

A1470 Install Flooring 5 5 0% 24-Sep-15 30-Sep-15

A1460 OFE Install 3 3 0% 29-Sep-15 01-Oct-15

A1540 Construction Clean 2 2 0% 01-Oct-15 02-Oct-15

A1340 TAB 0 0 0% 02-Oct-15

A1350 LCC/Owner/Design Punch 2 2 0% 05-Oct-15 06-Oct-15

A1360 Final Clean 2 2 0% 07-Oct-15 08-Oct-15

A1480 Substantial Completion 1 1 0% 07-Oct-15 07-Oct-15

A1370 City Inspection 1 1 0% 09-Oct-15 09-Oct-15

A1380 LCC Paperwork to Owner 1 1 0% 12-Oct-15 12-Oct-15

A1390 State Health Inspection 1 1 0% 13-Oct-15 13-Oct-15

A1400 Owner Prep/Move-In 5 5 0% 14-Oct-15 20-Oct-15

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

Prime/1st Coat Paint

MEP Trim-Out

Ceiling Grid Install

MEP Trim-Out Ceilings

Above Ceiling Inspection

Drop Ceiling Tile

2nd/Final Coat Paint

Install Flooring

OFE Install

Construction Clean

TAB

LCC/Owner/Design Punch

Final Clean

Substantial Completion

City Inspection

LCC Paperwork to Owner

State Health Inspection

Owner Prep/Move-In

Page 2 of 2

Page 13: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

West Park Hospital Build out and RenovationWest Park Hospital Build out and Renovation435 147 66.21% 17-Apr-14 A 16-Dec-15

Project OverviewProject Overview 435 147 66.21% 17-Apr-14 A 16-Dec-15

Phase 2; Cedar Mountain RenovationPhase 2; Cedar Mountain Renovation 124 124 0% 26-May-15 13-Nov-15

Phase 3; Dietary / Dinning RenovationPhase 3; Dietary / Dinning Renovation 176 125 28.98% 26-Jan-15 A 16-Nov-15

A4520 Start Dietary 0 0 100% 26-Jan-15 A

A4700 Education Release MEP Underslab 0 0 100% 27-Feb-15 A

A4710 Education GMP 0 0 100% 13-Apr-15 A

A4540 Overall Construction Duration 162 114 29.63% 26-Jan-15 A 03-Nov-15

A4720 Reissue Drawings State Review 0 0 0% 01-Jun-15*

A4670 OFE Install/Kitchen Equipment 15 15 0% 21-Sep-15 09-Oct-15

A4640 LCC Paperwork to Owner 5 5 0% 15-Oct-15 21-Oct-15*

A4630 Substantial Completion 0 0 0% 21-Oct-15*

A4530 Finish Dietary 0 0 0% 03-Nov-15

A4650 Owner/Prep Move-in 5 5 0% 04-Nov-15 10-Nov-15

A4660 State Health Inspection 0 0 0% 04-Nov-15

Area DArea D 141 90 36.3% 26-Jan-15 A 28-Sep-15

A3360 Excavation for new ductwork 5 0 100% 16-Mar-15 A 14-Apr-15 A

A3370 Demo Concrete wall and slabs for ductwork 3 0 100% 10-Mar-15 A 11-Mar-15 A

A3380 Sand bedding for new ductwork 3 0 100% 19-Mar-15 A 13-Apr-15 A

A3720 Build ICRA Walls 3 0 100% 26-Jan-15 A 29-Jan-15 A

A3730 Locate underground MEP 1 0 100% 26-Jan-15 A 30-Jan-15 A

A3740 Layout All new Underground MEP 2 0 100% 02-Feb-15 A 04-Feb-15 A

A3750 Demo above ceiling MEP in excavating area2 0 100% 10-Feb-15 A 13-Feb-15 A

A4390 Make Ready/Equipment/ICRA 5 0 100% 26-Jan-15 A 30-Jan-15 A

A4680 Education Release MEP Underslab 1 0 100% 27-Feb-15 A 27-Feb-15 A

A4690 Education GMP 1 0 100% 26-Mar-15 A 27-Mar-15 A

A3390 Underground ductwork 5 0 100% 19-Mar-15 A 17-Apr-15 A

A3400 Prep and pour flowable fill around ductwork 1 0 100% 24-Mar-15 A 22-Apr-15 A

A3410 underground plumbing 5 0 100% 31-Mar-15 A 06-Apr-15 A

A3420 Underground Electrical 5 0 100% 31-Mar-15 A 06-Apr-15 A

A3430 MEP underground inspection 1 0 100% 17-Apr-15 A 20-Apr-15 A

A3440 Backfill compaction 1 0 100% 20-Apr-15 A 21-Apr-15 A

A3450 Termite Treatment 0 0 100% 20-Apr-15 A 20-Apr-15 A

A3460 Vapor Barrier/SOG prep/Form work 2 0 100% 06-May-15 A 07-May-15 A

A3470 Pre Slab Inspection 1 0 100% 07-May-15 A 07-May-15 A

A3480 Pour Slab on Grade 1 0 100% 08-May-15 A 08-May-15 A

A3490 Wet Cure Slab 5 0 100% 09-May-15 A 14-May-15 A

A3500 Framing Layout 1 0 100% 13-May-15 A 13-May-15 A

A3510 Frame Priority Walls 1 0 100% 15-May-15 A 18-May-15 A

A3520 Overhead MEP/Sprinkler 10 10 0% 26-May-15 08-Jun-15

A3530 Frame all walls 1 0 100% 15-May-15 A 18-May-15 A

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

LCC Final Paperwork to Ownwe for StatePhase 1 Final CompletePhase 1 Substantial Completion Phase 2; Substantial CompletionPhase 3 Substantial CompletionFinal Completion of the ProjectPhase 3 Final Complete

Overall Construction Duration

Reissue Drawings State Review

OFE Install/Kitchen Equipment

LCC Paperwork to Owner

Substantial Completion

Finish Dietary

Owner/Prep Move-in

State Health Inspection

Excavation for new ductwork

Demo Concrete wall and slabs for ductwork

Sand bedding for new ductwork

Underground ductwork

Prep and pour flowable fill around ductwork

Underground Electrical

MEP underground inspection

Backfill compaction

Termite Treatment

Vapor Barrier/SOG prep/Form work

Pre Slab Inspection

Pour Slab on Grade

Wet Cure Slab

Framing Layout

Frame Priority Walls

Overhead MEP/Sprinkler

Frame all walls

Page 1 of 4

Early Bar

Critical Bar

Actual Bar

Level of Effort

Actual Level of Effort

Project Baseline Bar

Milestone

Run Date: 02-Jun-15

Data Date: 26-May-15

Project ID: 14213-1

Layton Construction Co., Inc.

02-Jun-15 Schedule

Page 14: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A3540 In wall rough in MEP 5 10 0% 18-May-15 A 08-Jun-15

A3550 In wall inspection LCC/City 1 1 0% 09-Jun-15 09-Jun-15

A3560 Insulate/Hang drywall 3 3 0% 10-Jun-15 12-Jun-15

A3570 Frame Hardlids and Soffits 3 3 0% 12-Jun-15 16-Jun-15

A3580 Tape/Finish walls 3 3 0% 17-Jun-15 19-Jun-15

A3590 Above Ceiling Inspection 1 1 0% 19-Jun-15 22-Jun-15

A3600 Tape/Finish soffits/hard lids 3 3 0% 22-Jun-15 25-Jun-15

A3610 Prime/Paint 1st Coat walls and ceilings 3 3 0% 25-Jun-15 30-Jun-15

A3620 Ceramic Tile in Bathrooms 8 8 0% 30-Jun-15 13-Jul-15

A3630 MEP trim out bathrooms 3 3 0% 13-Jul-15 16-Jul-15

A3640 Ceiling Grid 3 3 0% 16-Jul-15 21-Jul-15

A3650 Sprinkler Drop 1 1 0% 20-Jul-15 21-Jul-15

A3660 Above ceiling punch 1 1 0% 21-Jul-15 22-Jul-15

A3670 Millwork 1 1 0% 22-Jul-15 23-Jul-15

A3680 Drop Ceiling Tile 2 2 0% 23-Jul-15 27-Jul-15

A3690 MEP Trim out ceilings 4 4 0% 27-Jul-15 31-Jul-15

A3700 Final Coat Paint 2 2 0% 31-Jul-15 04-Aug-15

A3710 LCC/AOE Punch 2 2 0% 04-Aug-15 06-Aug-15

A4610 VCT Flooring 2 2 0% 24-Sep-15 28-Sep-15

Area AArea A 129 98 24.12% 14-Apr-15 A 08-Oct-15

A3760 Excavation for new ductwork 5 0 100% 15-Apr-15 A 08-May-15 A

A3770 Demo Concrete wall and slabs for ductwork 1 1 0% 26-May-15 26-May-15

A3780 Sand bedding for new ductwork 19 0 100% 14-Apr-15 A 08-May-15 A

A3790 Underground ductwork 5 0 100% 15-Apr-15 A 18-May-15 A

A3800 Prep and pour flowable fill around ductwork 1 0 100% 13-May-15 A 14-May-15 A

A3810 underground plumbing 5 1 80% 13-May-15 A 26-May-15

A3820 Underground Electrical 2 2 0% 26-May-15 27-May-15

A3830 MEP underground inspection 1 1 0% 28-May-15 28-May-15

A3840 Backfill compaction 1 0 100% 26-May-15 A 27-May-15 A

A3850 Termite Treatment 0 0 100% 14-May-15 A 14-May-15 A

A3860 Vapor Barrier/SOG prep/Form work 3 3 0% 29-May-15 02-Jun-15

A4730 Reissue Drawings State Review 1 1 0% 01-Jun-15* 01-Jun-15

A4740 Fab and Deliver FSD/FD 20 20 0% 02-Jun-15 29-Jun-15

A3870 Pre Slab Inspection 1 1 0% 03-Jun-15 03-Jun-15

A3880 Pour Slab on Grade 1 1 0% 04-Jun-15 04-Jun-15

A3890 Wet Cure Slab 5 5 0% 05-Jun-15 09-Jun-15

A3900 Framing Layout 1 1 0% 08-Jun-15 09-Jun-15

A3910 Frame Priority Walls 2 2 0% 09-Jun-15 11-Jun-15

A4810 Install Coiling Door Steel Support 3 3 0% 09-Jun-15 12-Jun-15

A3920 Overhead MEP/Sprinkler 10 10 0% 30-Jun-15 14-Jul-15

A3930 Frame all walls 3 3 0% 14-Jul-15 16-Jul-15

A4820 Install Coiling Doors 3 3 0% 17-Jul-15 21-Jul-15

A3940 In wall rough in MEP 10 10 0% 21-Jul-15 03-Aug-15

A3950 In wall inspection LCC/City 2 2 0% 31-Jul-15 04-Aug-15

A3960 Insulate/Hang drywall 10 10 0% 04-Aug-15 18-Aug-15

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

In wall rough in MEP

In wall inspection LCC/City

Insulate/Hang drywall

Frame Hardlids and Soffits

Tape/Finish walls

Above Ceiling Inspection

Tape/Finish soffits/hard lids

Prime/Paint 1st Coat walls and ceilings

Ceramic Tile in Bathrooms

MEP trim out bathrooms

Ceiling Grid

Sprinkler Drop

Above ceiling punch

Millwork

Drop Ceiling Tile

MEP Trim out ceilings

Final Coat Paint

LCC/AOE Punch

VCT Flooring

Excavation for new ductwork

Demo Concrete wall and slabs for ductwork

Sand bedding for new ductwork

Underground ductwork

Prep and pour flowable fill around ductwork

underground plumbing

Underground Electrical

MEP underground inspection

Backfill compaction

Termite Treatment

Vapor Barrier/SOG prep/Form work

Reissue Drawings State Review

Fab and Deliver FSD/FD

Pre Slab Inspection

Pour Slab on Grade

Wet Cure Slab

Framing Layout

Frame Priority Walls

Install Coiling Door Steel Support

Overhead MEP/Sprinkler

Frame all walls

Install Coiling Doors

In wall rough in MEP

In wall inspection LCC/City

Insulate/Hang drywall

Page 2 of 4

Page 15: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A3970 Frame Hardlids and Soffits 5 5 0% 14-Aug-15 21-Aug-15

A3980 Tape/Finish walls 5 5 0% 21-Aug-15 28-Aug-15

A3990 Above Ceiling Inspection 1 1 0% 28-Aug-15 31-Aug-15

A4000 Tape/Finish soffits/hard lids 3 3 0% 31-Aug-15 03-Sep-15

A4010 Prime/Paint 1st Coat walls and ceilings 4 4 0% 04-Sep-15 11-Sep-15

A4040 Ceiling Grid 5 5 0% 11-Sep-15 18-Sep-15

A4050 Sprinkler Drop 3 3 0% 17-Sep-15 22-Sep-15

A4070 Millwork 5 5 0% 17-Sep-15 24-Sep-15

A4060 Above ceiling punch 2 2 0% 22-Sep-15 24-Sep-15

A4080 Drop Ceiling Tile 3 3 0% 24-Sep-15 29-Sep-15

A4090 MEP Trim out ceilings 5 5 0% 24-Sep-15 01-Oct-15

A4100 Final Coat Paint 5 5 0% 25-Sep-15 02-Oct-15

A4020 VCT Flooring 8 8 0% 28-Sep-15 08-Oct-15

A4110 LCC/AOE Punch 3 3 0% 02-Oct-15 07-Oct-15

Area BArea B 138 105 23.91% 13-Apr-15 A 21-Oct-15

A4120 Excavation for new ductwork 5 0 100% 13-Apr-15 A 08-May-15 A

A4130 Demo Concrete wall and slabs for ductwork 1 0 100% 11-May-15 A 11-May-15 A

A4140 Sand bedding for new ductwork 3 0 100% 11-May-15 A 13-May-15 A

A4150 Underground ductwork 5 0 100% 06-May-15 A 14-May-15 A

A4160 Prep and pour flowable fill around ductwork 1 0 100% 11-May-15 A 11-May-15 A

A4170 Underground plumbing 5 0 100% 29-Apr-15 A 20-May-15 A

A4180 Underground Electrical 2 0 100% 13-May-15 A 14-May-15 A

A4190 MEP underground inspection 1 0 100% 13-May-15 A 13-May-15 A

A4200 Backfill compaction 1 0 100% 13-May-15 A 13-May-15 A

A4210 Termite Treatment 0 0 100% 13-May-15 A 13-May-15 A

A4220 Vapor Barrier/SOG prep 3 3 0% 28-May-15 01-Jun-15

A4750 Reissue Drawings State Review 1 1 0% 01-Jun-15* 01-Jun-15

A4230 Pre Slab Inspection 1 1 0% 02-Jun-15 02-Jun-15

A4760 Fab and Deliver FSD/FD 20 20 0% 02-Jun-15 29-Jun-15

A4240 Pour Slab on Grade 1 1 0% 03-Jun-15 03-Jun-15

A4250 Wet Cure Slab 7 7 0% 04-Jun-15 10-Jun-15

A4770 Demo Roof for Doghouse 2 2 0% 08-Jun-15 09-Jun-15

A4780 Erect steel supports at doghouse 2 2 0% 10-Jun-15 11-Jun-15

A4260 Framing Layout 1 1 0% 10-Jun-15 11-Jun-15

A4270 Frame Priority Walls 2 2 0% 11-Jun-15 15-Jun-15

A4790 Frame/Hang/Exterior Finish Doghouse 10 10 0% 12-Jun-15 25-Jun-15

A4800 Install MEP/ Louvers at Doghouse 5 5 0% 12-Jun-15 18-Jun-15

A4280 Overhead MEP/Sprinkler 10 10 0% 30-Jun-15 14-Jul-15

A4290 Frame all walls 3 3 0% 10-Jul-15 14-Jul-15

A4300 In wall rough in MEP 10 10 0% 23-Jul-15 05-Aug-15

A4310 In wall inspection LCC/City 1 1 0% 06-Aug-15 06-Aug-15

A4320 Insulate/Hang drywall 5 5 0% 07-Aug-15 13-Aug-15

A4330 Frame Hardlids and Soffits 2 2 0% 14-Aug-15 17-Aug-15

A4340 Tape/Finish walls 3 3 0% 18-Aug-15 20-Aug-15

A4350 Above Ceiling Inspection 1 1 0% 20-Aug-15 20-Aug-15

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

Frame Hardlids and Soffits

Tape/Finish walls

Above Ceiling Inspection

Tape/Finish soffits/hard lids

Prime/Paint 1st Coat walls and ceilings

Ceiling Grid

Sprinkler Drop

Millwork

Above ceiling punch

Drop Ceiling Tile

MEP Trim out ceilings

Final Coat Paint

VCT Flooring

LCC/AOE Punch

Excavation for new ductwork

Demo Concrete wall and slabs for ductwork

Sand bedding for new ductwork

Underground ductwork

Prep and pour flowable fill around ductwork

Underground plumbing

Underground Electrical

MEP underground inspection

Backfill compaction

Termite Treatment

Vapor Barrier/SOG prep

Reissue Drawings State Review

Pre Slab Inspection

Fab and Deliver FSD/FD

Pour Slab on Grade

Wet Cure Slab

Demo Roof for Doghouse

Erect steel supports at doghouse

Framing Layout

Frame Priority Walls

Frame/Hang/Exterior Finish Doghouse

Install MEP/ Louvers at Doghouse

Overhead MEP/Sprinkler

Frame all walls

In wall rough in MEP

In wall inspection LCC/City

Insulate/Hang drywall

Frame Hardlids and Soffits

Tape/Finish walls

Above Ceiling Inspection

Page 3 of 4

Page 16: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A4360 Tape/Finish soffits/hard lids 3 3 0% 21-Aug-15 25-Aug-15

A4370 Prime/Paint 1st Coat walls and ceilings 5 5 0% 26-Aug-15 01-Sep-15

A4380 Ceramic Tile in Bathrooms 3 3 0% 02-Sep-15 04-Sep-15

A4480 Stonehard Flooring Kitchen 12 12 0% 02-Sep-15 18-Sep-15

A4500 MEP trim out Bathrooms 1 1 0% 02-Sep-15 02-Sep-15

A4400 Ceiling Grid 5 5 0% 03-Sep-15 10-Sep-15

A4510 Toilet Accessories / Div. 10 Specialties/ Doors and Hardware20 20 0% 03-Sep-15 01-Oct-15

A4410 Sprinkler Drop 5 5 0% 11-Sep-15 17-Sep-15

A4420 Above ceiling punch 2 2 0% 18-Sep-15 21-Sep-15

A4490 OFE Install/Kitchen Equipment 10 10 0% 21-Sep-15 02-Oct-15

A4430 Millwork 3 3 0% 22-Sep-15 24-Sep-15

A4440 Drop Ceiling Tile 3 3 0% 25-Sep-15 29-Sep-15

A4450 MEP Trim out ceilings 3 3 0% 30-Sep-15 02-Oct-15

A4620 VCT Flooring 6 6 0% 08-Oct-15 16-Oct-15

A4460 Final Coat Paint 5 5 0% 12-Oct-15 16-Oct-15

A4470 LCC/AOE Punch 3 3 0% 19-Oct-15 21-Oct-15*

CommissioningCommissioning 37 37 0% 25-Sep-15 16-Nov-15

C7640 O & M Info 10 10 0% 25-Sep-15 08-Oct-15

C7550 Point to Point Checks 2 2 0% 05-Oct-15 06-Oct-15

C7560 Pre-Commissioning, Checks / Start Up / Test 1 1 0% 07-Oct-15 07-Oct-15

C7680 Final Commissioning, Control System 1 1 0% 08-Oct-15 08-Oct-15

C7570 Startup Documentation 5 5 0% 12-Oct-15 16-Oct-15

C7580 Air Balance 2 2 0% 16-Oct-15 19-Oct-15

C7590 Water Balance 1 1 0% 16-Oct-15 16-Oct-15

C7600 Equipment Identification 2 2 0% 16-Oct-15 19-Oct-15

C7630 Owner Training 2 2 0% 16-Oct-15 19-Oct-15

C7610 Performance / Endurance Testing 4 4 0% 19-Oct-15 22-Oct-15

C7650 Final Commissioning, Electrical System 1 1 0% 20-Oct-15 20-Oct-15

C7660 Final Commissioning, Heating / Cooling and Fan System1 1 0% 20-Oct-15 20-Oct-15

C7620 Consultant/Owner Verification 2 2 0% 22-Oct-15 23-Oct-15

C7670 Final Commissioning, Fireprotection Equipment1 1 0% 26-Oct-15 26-Oct-15

C7700 Attic Stock, Keys & Certification to Owner 3 3 0% 26-Oct-15 28-Oct-15

C7690 Demonstrations 2 2 0% 27-Oct-15 28-Oct-15

C7710 Issues Test & Balance Report / Flame Spread Lab Report3 3 0% 27-Oct-15 29-Oct-15

Close OutClose Out 30 30 0% 06-Oct-15 16-Nov-15

C7760Produce As-Built Drawing 10 10 0% 06-Oct-15 19-Oct-15

C7740Fire Marshall Inspection 1 1 0% 02-Nov-15 02-Nov-15

C7770Final Clean 10 10 0% 03-Nov-15 16-Nov-15

C7800LCC Document Close-Out Submitted to Owner1 1 0% 03-Nov-15 03-Nov-15

C7750State Health Inspector / Inspection 0 0 0% 03-Nov-15

C7730State Certification 1 1 0% 16-Nov-15 16-Nov-15

25 01 08 15 22 29 06 13 20 27 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 07 14 21 28 04 11 18 25 02 09 16 2330

June 2015 July 2015 August 2015 S October 2015 N December 2015 January 2016 February 2016 March 2016 April 2016 May 2016June 2016

Tape/Finish soffits/hard lids

Prime/Paint 1st Coat walls and ceilings

Ceramic Tile in Bathrooms

Stonehard Flooring Kitchen

MEP trim out Bathrooms

Ceiling Grid

Toilet Accessories / Div. 10 Specialties/ Doors and Hardware

Sprinkler Drop

Above ceiling punch

OFE Install/Kitchen Equipment

Millwork

Drop Ceiling Tile

MEP Trim out ceilings

VCT Flooring

Final Coat Paint

LCC/AOE Punch

O & M Info

Point to Point Checks

Pre-Commissioning, Checks / Start Up / Test

Final Commissioning, Control System

Startup Documentation

Air Balance

Water Balance

Equipment Identification

Owner Training

Performance / Endurance Testing

Final Commissioning, Electrical System

Final Commissioning, Heating / Cooling and Fan System

Consultant/Owner Verification

Final Commissioning, Fireprotection Equipment

Attic Stock, Keys & Certification to Owner

Demonstrations

Issues Test & Balance Report / Flame Spread Lab Report

Produce As-Built Drawing

Fire Marshall Inspection

Final Clean

LCC Document Close-Out Submitted to Owner

State Health Inspector / Inspection

State Certification

Page 4 of 4

Page 17: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

Medical RecordsMedical Records 132 59 55.3% 16-Mar-15 A 15-Sep-15

Project Overview and MilestonesProject Overview and Milestones 131 58 55.73% 04-May-15 A 14-Sep-15

A1000 Start Medical Records 0 0 100% 04-May-15 A

A1020 Notice to Proceed 0 0 100% 04-May-15 A

A1010 Overall Construction Duration 94 53 43.62% 04-May-15 A 07-Sep-15

A1040 OFE Install 5 5 0% 25-Aug-15 31-Aug-15

A1030 LCC Document Close-Out to Owner 1 1 0% 07-Sep-15 07-Sep-15

A1050 Substantial Completion 0 0 0% 07-Sep-15

A1060 State Health Inspection 0 0 0% 08-Sep-15

A1080 OwnerPrep/Owner Move-In 5 5 0% 08-Sep-15 14-Sep-15

A1070 Finish Medical Records 0 0 0% 08-Sep-15

Interior FinishInterior Finish 132 59 55.3% 16-Mar-15 A 15-Sep-15

A1090 ICRA Setup 2 0 100% 16-Mar-15 A 04-May-15 A

A1100 Make Safe - MEP 5 0 100% 18-Mar-15 A 24-Mar-15 A

A1110 Demolition 15 0 100% 25-Mar-15 A 14-Apr-15 A

A1120 Layout 3 0 100% 15-Apr-15 A 17-Apr-15 A

A1130 Frame/Top Out Priority Walls 3 0 100% 20-Apr-15 A 29-May-15 A

A1150 Frame/Top Out All Walls 5 0 100% 23-Apr-15 A 08-May-15 A

A1140 Overhead R.I. MEP 25 3 90% 23-Apr-15 A 29-Jun-15

A1160 In-Wall R.I. MEP 10 1 90% 11-May-15 A 25-Jun-15

A1170 Overhead Fire Protection R.I. 5 5 0% 25-Jun-15 01-Jul-15

A1180 In-Wall Framing Inspection 1 1 0% 29-Jun-15 29-Jun-15

A1190 Insulate/Hang Drywall 8 8 0% 30-Jun-15 09-Jul-15

A1200 Tape/Finish Walls 5 5 0% 10-Jul-15 16-Jul-15

A1230 Prime/First Coat Walls 3 3 0% 17-Jul-15 21-Jul-15

A1240 Ceiling Grid 3 3 0% 22-Jul-15 24-Jul-15

A1260 MEP Trim-Out Walls 5 5 0% 22-Jul-15 28-Jul-15

A1250 MEP Trim-Out Ceilngs 5 5 0% 27-Jul-15 31-Jul-15

A1270 Sprinkler Head Drops 2 2 0% 27-Jul-15 28-Jul-15

A1290 Millwork 5 5 0% 27-Jul-15 31-Jul-15

A1300 Above Ceiling Punch 1 1 0% 03-Aug-15 03-Aug-15

A1310 Equipment Startup 2 2 0% 03-Aug-15 04-Aug-15

A1220 Above Ceiling Inspection 1 1 0% 04-Aug-15 04-Aug-15

A1280 Drop Ceiling Tile 3 3 0% 05-Aug-15 07-Aug-15

A1340 Pre Cx/PFC Equipment 5 5 0% 05-Aug-15 11-Aug-15

A1320 VCT-Base 8 8 0% 10-Aug-15 19-Aug-15

A1350 TAB 3 3 0% 19-Aug-15 21-Aug-15

A1330 Final Paint 3 3 0% 20-Aug-15 24-Aug-15

A1360 Commissioning 3 3 0% 24-Aug-15 26-Aug-15

A1370 Install Accessories/OFE 3 3 0% 25-Aug-15 27-Aug-15

A1380 Owner Training 2 2 0% 27-Aug-15 28-Aug-15

22 29 06 13 20 27 03 10 17 24 31 07 14 21 28

July 2015 August 2015 September 2015 October 2015

Overall Construction Duration

OFE Install

LCC Document Close-Out to Owner

Substantial Completion

State Health Inspection

OwnerPrep/Owner Move-In

Finish Medical Records

Overhead R.I. MEP

In-Wall R.I. MEP

Overhead Fire Protection R.I.

In-Wall Framing Inspection

Insulate/Hang Drywall

Tape/Finish Walls

Prime/First Coat Walls

Ceiling Grid

MEP Trim-Out Walls

MEP Trim-Out Ceilngs

Sprinkler Head Drops

Millwork

Above Ceiling Punch

Equipment Startup

Above Ceiling Inspection

Drop Ceiling Tile

Pre Cx/PFC Equipment

VCT-Base

TAB

Final Paint

Commissioning

Install Accessories/OFE

Owner Training

Page 1 of 2

Early Bar

Critical Bar

Actual Bar

Level of Effort

Actual Level of Effort

Project Baseline Bar

Milestone

Run Date: 15-Jul-15

Data Date: 25-Jun-15

Project ID: 14213.02102015

Layton Construction Co., Inc.

15-Jul-15 Schedule

Page 18: West Park Hospital

Activity ID Activity Name Original

Duration

Remaining

Duration

Duration

%

Complete

Start Finish

A1390 Construction Clean 1 1 0% 28-Aug-15 28-Aug-15

A1400 LCC/AOE Punch 2 2 0% 31-Aug-15 01-Sep-15

A1410 Final Clean 2 2 0% 02-Sep-15 03-Sep-15

A1420 Fire Marshall/Local Final Inspections 1 1 0% 04-Sep-15 04-Sep-15

A1430 LCC Document Close-Out to Owner 1 1 0% 07-Sep-15 07-Sep-15

A1440 Substantial Completion 1 1 0% 07-Sep-15 07-Sep-15

A1450 State Health Inspection 1 1 0% 08-Sep-15 08-Sep-15

A1460 Owner Prep/Owner Move-In 5 5 0% 09-Sep-15 15-Sep-15

22 29 06 13 20 27 03 10 17 24 31 07 14 21 28

July 2015 August 2015 September 2015 October 2015

Construction Clean

LCC/AOE Punch

Final Clean

Fire Marshall/Local Final Inspections

LCC Document Close-Out to Owner

Substantial Completion

State Health Inspection

Owner Prep/Owner Move-In

Page 2 of 2

Page 19: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 03 – Change Order Log

ghill
Text Box
See attached CO Log
Page 20: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 04 – Submittal Log

Page 21: West Park Hospital

Layton Construction Co., Inc.

Project 14213 - West Park Hospital Ph 3 - CodySUBMITTAL LOG

107/29/2015

07:22 AMTime:Date:Page: of 1

03

05

07

09

21

PL030353-01

C051200-04

E051200-01

C073113-01

C096519-01

CM096800-02

C211000-03

Submittal Id

Miscellaneous Cast in Place Concrete

Connector - Revised Erection DrawingsEducation Erection and Shop Drawings

Connector Asphalt Shingles

Connector Resilient Tile Flooring

Cedar Mountain - Flooring Finishes Shop Drawings ASI 03

Connector - New Dry Valve Location

Title

Out For Approval

Out For ApprovalOut For Approval

Out For Approval

Out For ApprovalOut For Approval

Out For Approval

Status From Sub From Architect

1

1

1

1

1

1

1

LastRev.

06/29/2015

06/22/2015

06/09/2015

07/08/2015

07/27/2015

From Sub

06/29/2015

06/08/2015

06/09/2015

06/22/2015

06/09/2015

07/08/2015

07/27/2015

To Architect From Architect To Sub

Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.

ResponsibilityRequired Forwarded

Project: 14213

Operator:Run Time:Run Date:

Report Code:

07/29/201507:22 AMGBALDWIN

Report ParametersEND OF REPORT

Package:

Responsibility Partner:

Status: OTFRAPP

Spec Section:

Spec Section:

Spec Section:

Spec Section:

Spec Section:

From Specification Section: To Specification Section:

Break By: Spec. Section (S)

Responsibility Partner Type:Received From Partner:Received From Partner Type:Sent To Partner:Sent To Partner Type:Returned By Partner:Returned By Partner Type:Forwarded To Partner:Forwarded To Partner Type:

Sort By: Submittal Sort Order

ReturnedSentReceived

TLCPM3041

Page 22: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 05 – RFI Log

Page 23: West Park Hospital

14213 - West Park Hospital Ph 3 - Cody

REQUEST FOR INFORMATION LOG

Layton Construction Co., Inc. 07/29/201507:21 AM

Page: of1

14213

RFINumber Cost Subject From Company To Company

Date Created

DateRequired

DateAnswered Status Answered By

Date:Time:Job:

1

RFI-0127

RFI-0134

RFI-0140

Education - Skyfold Door Existing Beam Clash

Dietary - Wall Rating/Duct Clarification

Cedar Mountain - Hydronic System Clarifications

Layton Construction Co., Inc.

Layton Construction Co., Inc.

Layton Construction Co., Inc.

Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.

Johnson, Johnson, Crabtree Architects P.C.

06/25/2015

07/06/2015

07/28/2015

07/02/2015

07/13/2015

08/04/2015

Open

Open

Open

Project:Sent To:

14213

Operator:Run Time:Run Date:

Report Code:

07/29/201507:21 AMGBALDWINPM3011

Report Parameters

END OF REPORT

Restrict Value of: From Date:To Date:

Status Class:

Create Date

Status:

Basin Mechanical, Inc. WILL POINDEXTER

Co-Author:

Co-Author:

Co-Author:

Potentially

Potentially

Potentially

Co-Author RFI #:

Co-Author RFI #:

Co-Author RFI #:

Page 24: West Park Hospital

West Park Hospital Phase III (2nd Floor patient build�out)

Section 06 – Progress Photos

Page 25: West Park Hospital

Building Connector

Parking Lot

Page 26: West Park Hospital

5

Progress Photos

Dietary Area A Dry Wall

Connector Slab on Deck

Page 27: West Park Hospital

6

Connector Exterior Framing

Connector Fireproofing

Page 28: West Park Hospital

7

Cedar Mountain Top-out and Fireproofing

Dietary Area B Dry Wall