37
Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations Veterinary Medical Center Building 371 1352 Boyd Avenue St. Paul, MN 55108 Veterinary Science Building 374 1971 Commonwealth Avenue St. Paul, MN 55108 U of M Project # 02-374-09-1691 July 10, 2009 Predesign Document

Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

  • Upload
    others

  • View
    5

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Veterinary Medical CenterVeterinary Science Building

Bottle Washer Installation andMinor Room Renovations

Veterinary Medical Center Building 3711352 Boyd Avenue

St. Paul, MN 55108

Veterinary Science Building 3741971 Commonwealth Avenue

St. Paul, MN 55108

U of M Project # 02-374-09-1691

July 10, 2009

Predesign Document

Page 2: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

U of M Department of Research Animal ResourcesVeterinary Science Cage Washer and HVAC Upgrades Table of Contents

HGA Commission No. 0265-115-00 July 10, 2009

Table of Contents

1.0 Executive Summary 1

2.0 Project Summary 2.1 Architectural (see drawings) 3

2.2 Mechanical 4

2.3 Electrical 9 3.0 Code Analysis 20 4.0 Cost Analysis 4.1 Total Project #1 Rm 345D Cost 21 Project #1 Construction Cost 4.2 Total Project #2 Rm A357 Cost 23 Project #2 Construction Cost 4.3 Total Project #3 Rm A361 Cost 25 Project #3 Construction Cost 4.4 Total Project #4 Rm C211 Cost 27 Project #4 Construction Cost 4.5 Total Project #5 Rm D201 Cost 29 Project #5 Construction Cost

5.0 Architectural Drawings

Page 3: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

U of M Department of Research Animal ResourcesVeterinary Science Cage Washer and HVAC Upgrades Executive Summary

HGA Commission No. 0265-115-00 July 10, 2009

EXECUTIVE SUMMARY

The Veterinary Science Bottle Washer and HVAC Upgrade project consists of fi ve interior renovation projects, one located in the Veterinary Science Building 374 and four located in the Veterinary Medicine South Building 371. The scope of work includes renovating rooms for animal caging and installation of an existing bottle washer.

Project #1Installation of Bottle Washer, Room 345D, Veterinary Science Building 374

There is currently not a dedicated cage washer for the cages located in the Veterinary Science Area 3 vivarium. The Veterinary Science Area 1 washer does not have the capacity to wash cages from both areas, due to the existing quantity of cages, plus the increase in cages from selected animal programs. The existing Steris bottle washer (also used for cages) in Room 345D was relocated to the St. Paul campus from the Academic Health Center’s Research Building Management Services, located at 717 Delaware Street, several years ago. It has not been connected for use since it’s arrival at the St. Paul Campus.

The washer is an electric heated unit requiring 480V, 3-phase, 50-amp power. As Building 374 does not have this amount of power in this area, a transformer is needed in the main electrical room to step up feeder voltage to 480V. Adequate plumbing utilities are available, including adequate supply and drain. An exhaust fan is needed for excess condensate evacuation that vents directly to the exterior of the building.

In the event that the existing washer unit does not function properly upon connection, a second option is being considered that requires the purchase of a new Steris steam-heated washer unit. This unit will fi t within the room in the same location as the existing washer. The power and ventilation requirements are the same as for the existing washer. Plant steam currently serving Building 374 would be utilized, with the supply and return connections running from the washer unit to an existing fl ash tank located within Room 345D. The Energy Management standards for the University of Minnesota for operating this equipment will be met. Note: purchase of the washer is not included in this Project.

Project #2 & #3Renovation of Rooms A357 and A361, Veterinary Medicine South Building 371

Renovation of these two rooms is required as the current confi guration of cages limits the number of animals that can be housed in the room. There is also a potential health and safety hazard created by the cages in their existing locations.

Section 1.0 Page 1

Page 4: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

U of M Department of Research Animal ResourcesVeterinary Science Cage Washer and HVAC Upgrades Executive Summary

HGA Commission No. 0265-115-00 July 10, 2009

Renovations include the removal of concrete curbs and installation of new fl oor drains formed in existing trenches along the side walls of each room. The fl oor will be refi nished with an epoxy paint applied over a cementitious underlayment, walls will be patched to match existing fi nishes and a new scrubbable acoustical ceiling tile with new lights and mechanical diffusers will be provided to replace the existing ceiling of the same materials. Electrical work consists of lighting, devices and branch circuit wiring.

All areas disturbed on the fl oor below these two rooms due to the installation of plumbing connections will be patched to match existing conditions.

Project #4 and #5Renovation of Rooms C211 and D201, Veterinary Medicine South Building 371

Renovation of these two rooms is needed to house animals that are being relocated from the Veterinary Science South Building on Level 2. Due to the variety of animals being relocated, the existing rooms need to be subdivided.

Renovations include the removal of concrete curbs and the installation of new concrete block partitions dividing Room C211 into two rooms and Room D201 into four rooms. New prefabricated fl oor drains will be installed in parts of the existing fl oor slab that can be penetrated without compromising the structural integrity of the existing concrete pan and joist system. The fl oor slab removed for the new trenches will be replaced below the trenches with a formed deck and lightweight concrete in quantities that ensure a one-hour-rated fl oor slab. The fl oor will be fi nished with an epoxy paint applied over a cementitious underlayment, walls will be patched to match existing fi nishes and a new moisture-resistant gypsum board ceiling tile with new lights and mechanical diffusers will be provided.

Additionally, new stainless steel sinks and hose bibs will be installed in the new rooms, connecting to existing supply and vent piping. HVAC systems will be modifi ed and/or expanded to serve the new rooms; separate room temperature controls are included.

Power work includes removing existing circuits to the existing air handling unit and providing circuits to two new air handling units for Room C211. Additional work consists of lighting, devices and branch circuit wiring.

Additional Project ProposalInstallation of DDC Controls for Veterinary Science 1st Floor Fan Units 001, 002 and 012 and Veterinary Science 3rd Floor Fan Unit 010

This Project will not be included in the scope of work as additional research is required to determine desired outcomes.

Section 1.0 Page 2

Page 5: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

U of M Department of Research Animal ResourcesVeterinary Science Cage Washer and HVAC Upgrades Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Architectural

Architectural Systems

Refer to Section 5.0 Architectural Drawings for summary of architectural related work.

Section 2.1 Page 3

Page 6: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

MECHANICAL SYSTEMS

Mechanical Scope - Project #1

Accommodate Bottle Wash unit in Room 345D. Refer to Drawing A200

Option 1: Use existing Electric Heated unit (currently in place, not connected):Utilities: Connect CW, HW, CA (CW & HW available in room)6” welded SST exhaust from unit exhaust fan (top of unit) to outside (roof) with goose neck (insulate duct inside building with 1” fi berglass insulation with PVC jacket). Include roof curb.Floor Drain: Use existing drain directly below proposed unit location.

C. Option 2:New Steam Heated Unit (confi rm who provides):Utilities: Connect CW, HW, CA (CW & HW available in room) 6” welded SST exhaust from unit exhaust fan (top of unit) to outside (assume roof location) with goose neck (insulate duct inside building with 1” fi berglass insulation with PVC jacket).Floor Drain: Use existing drain directly below proposed unit location.Steam: Use plant steam, 30-80 PSIG required, use existing 50 PSIG service and fl ask tank in room. Extend 1-1/4”” HPS and ¾” HPR to unit connect. Connect HPR from unit to existing fl ash tank in room.

D. Include all related piping, valves, traps, insulation, etc. in accordance with U of M Design Standards.

E. Install equipment in accordance with manufacturers written instructions.

F. Demolition shall include removal of all related supports, controls and capping of ducts and pip-ing.

G. All work shall be done in accordance with all applicable local, state, and federal codes and the latest version of the University of Minnesota Standards and Procedures for Construction.

A.

B.1.2.

3.

1.2.

3.4.

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Mechanical

Section 2.2 Page 4HGA Commission No. 0265-115-00 July 10, 2009

Page 7: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

Below is a memorandum from the University of Minnesota’s Energy Management Department outlining requirements for Project #1.

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Mechanical

Section 2.2 Page 5HGA Commission No. 0265-115-00 July 10, 2009

Page 8: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Mechanical

Section 2.2 Page 6

MECHANICAL SYSTEMS

Mechanical Scope - Projects #2 and #3

A. Floor / trench drain modifi cations only (no other plumbing or HVAC scope). Refer to Drawing A201.

B. Rooms A357 and 361: Remove Concrete pads / curbs and related trench drains along back wall (by General) and install fl ush trench drains along sides of room behind planned cages (no other scope items):

1. Install 6 new 4” fl oor drains w/ integral drain fl ange in new trench drains to be formed in concrete fl oor along walls. Demo existing drain piping and install new drain piping in ceiling space on fl oor below.

2. Existing fl oor drains in middle of rooms to remain.

C. Include all related piping, valves, insulation, etc. in accordance with U of M Design Stan-dards. Install equipment in accordance with manufacturers written instructions.

D. Demolition shall include removal of all related supports, controls and capping of ducts and piping.

E. Install equipment in accordance with manufacturers written instructions.

F. Maybe signifi cant constructability issues due to limited access on fl oor below.

G. HVAC system performance (ventilation rates, temperature and humidity control, etc.) will be limited to existing system capabilities.

H. All work shall be done in accordance with all applicable local, state, and federal codes and the latest version of the University of Minnesota Standards and Procedures for Construc-tion.

U of M Department of Research Animal ResourcesProject #2 & #3 Building 371Room A357 & A361 Renovation

Page 9: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Mechanical

Section 2.2 Page 7

MECHANICAL SYSTEMS

Mechanical Scope - Projects #4 and #5

A. Room C211: Remove Concrete pads / curbs (by general) install new trench drains along sides of room behind planned cages and subdivide room into 2 rooms with dedicated HVAC (SA & EA) & temperature control for each room, new hose station / racks and sinks. Refer to Drawing A202

1. Install 8 new pre-fabricated trench drains w/ cover. Demo existing drains and piping and install new drain piping in ceiling space of fl oor below.

2. Demo existing sink and hose stations / racks and install 2 new SST sinks and hose stations / racks. Connect to existing CW, HW, san and vent piping. Include tempera-ture balanced water control valves for each hose station.

3. Modify / expand HVAC system to serve each room with new separate supply air w/ dedicated fan coil or CV hot water reheat terminal unit and supply duct and diffusers. Include separate room temperature sensor to provide separate room temperature control. Provide new exhaust for each room with room replaceable 30% throwaway fi lter bank with 3 full sets of fi lters for each room.

B. Room D201: Remove Concrete pads / curbs (by general) install new trench drains along sides of room behind planned cages and subdivide room into 4 rooms with dedicated HVAC (SA & EA) & temperature control for each room, new hose station / racks and sinks. Refer to Drawing A203

1. Install 10 new pre-fabricated trench drains w/ cover. Demo existing drains and piping and install new drain piping in ceiling space of fl oor below.

2. Demo existing sink and hose stations / racks and install 2 new SST sinks and hose stations / racks. Connect to existing CW, HW, san and vent piping. Include tempera-ture balanced water control valves for each hose station.

3. Modify / expand HVAC system to serve each room with new separate supply air w/ dedicated fan coil or CV hot water reheat terminal unit and supply duct and diffusers. Include separate room temperature sensor to provide separate room temperature control. Provide new exhaust for each room with room replaceable 30% throwaway fi lter bank with 3 full sets of fi lters for each room.

C. Include all related piping, valves, insulation, ductwork, controls etc. in accordance with U of M Design Standards.

D. Demolition shall include removal of all related supports, controls and capping of ducts and piping.

E. Install equipment in accordance with manufacturers written instructions.

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Page 10: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Section 2.2 Page 8

F. Maybe signifi cant constructability issues due to limited access on fl oor below.

G. HVAC system performance (ventilation rates, temperature and humidity control, etc.) will be limited to existing system capabilities.

H. All work shall be done in accordance with all applicable local, state, and federal codes and the latest version of the University of Minnesota Standards and Procedures for Construc-tion.

Mechanical

Page 11: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Section 2.3 Page 9

ELECTRICAL SYSTEMS

Electrical Scope - Project #1

A. All electrical work associated with Room 345D unless listed below.

B. Items currently not included in the scope of work 1. Telephone System: Telephone hardware and electronics, cabling, faceplates, terminal

blocks, termination and testing. 2. Data System: Data network electronics such as concentrators, switches, servers,

uninterruptible power supplies, and other electronic equipment, as well as cabling, faceplates, patch panels, network equipment racks, terminations and testing is not included.

3. Cable TV (CATV) System: VCR’s, video signal processors, other electronics, as well as cabling, outlets, faceplates, are not included.

Service and Distribution Scope

A. Project consists of providing power to connect an existing Steris Basil 3700 Cage Washer in Room 345D.

1. The existing building service is 120/208V. 2. The Steris unit is 480V 3 phase, 50 amps. 3. There is an existing feeder from the service distribution board to the area of the

fl oor below the project (Room 257) that can be utilized to power the Steris unit. A transformer will be provided in the main electric room to step up feeder voltage to 480V. The existing feeder will be extended from Room 257 (above ceiling) to the Steris equipment location, and reconnected through the transformer in the electric room. Provide feeder from existing service board to transformer utilizing existing cir-cuit breaker. Provide a local disconnect at the equipment location. Also provide 120V power to associated exhaust fan for steam evacuation.

B. The following voltages are typical 1. Motors ½ HP or greater: 208V 3 phase. 2. Lighting: 120V. 3. Receptacles and motors 1/3 HP or less: 120V.

C. General convenience duplex receptacle locations and quantities 1. Corridors: Receptacles every 40 feet throughout for housekeeping purposes. 2. Storage, utility spaces: One receptacle at entrance door, 48” AFF 3. Mechanical spaces: Receptacles spread throughout for maintenance purposes 4. Outdoor: One receptacle at each entrance/exit from the building, with additional pe-

rimeter outlets to reduce the spacing to 100’-0” maximum. 5. Roof equipment: One receptacle within 50’ of any rooftop mechanical equipment.

Electrical

Page 12: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Electrical

Section 2.3 Page 10

D. Other power requirements 1. Equipment Connection: see above.

E. Motor Controls 1. Stand-alone Motor Starters: Provide a magnetic starter for all motors without integral

controls. Provide a combination starter when starters are mounted within sight of the motor.

Basic Materials and Methods

A. General: Shop drawings, Operation and Maintenance Manuals, and Operating instructions for the Owner are required for this project.All materials shall be new, excepted as noted above, UL Listed and Approved for the purpose, and installed per code.Work shall be installed per the NEC (NFPA 70) and applicable state and local codes and shall meet the requirements of nationally recognized standards. Secure and pay for all permits, licenses, utility and inspection fees, and coordinate all work with local inspection authorities.All systems shall be completely functional and wiring systems shall test free of defects using megger, continuity, ground, voltage, current, and phase rotation tests. Balance system phase currents to within 5% of each other. Provide all cutting and patching necessary for installation of electrical work and re-store fi nished surfaces disturbed by this Contractor. Do not cut or drill structural members. Provide general cleanup of waste and rubbish in the work area, and clean all removed and reinstalled equipment and luminaires. Clean all equipment that has become dirty during construction.

B. Equipment Support: Provide support of all electrical work through the use of hanger rods, clamps, structural framing, fastening devices, and backboards. Provide vibration isolation in all supporting hardware for vibrating electrical equipment installed by this Contractor. Pro-vide 4” high concrete pads for fl oor mounted equipment.

C. Identifi cation: Provide engraved nameplates, wire and cable markers, embossed tape, and device plate cover engraving on electrical distribution and control equipment and the loads they serve, main power and special system cabinets, motor control centers, motor starters and variable frequency drives, and disconnects.

D. Temporary Electric Services: Provide complete, adequately sized, and metered temporary electric power and lighting services for all trades. The General Contractor will pay energy charges. Provide service equipment, feeders, panel boards, panel board receptacles, and lighting as required for the trades to perform quality work in a safe environment. Energize hoists, cranes, elevators, fi eld offi ces, and other large signifi cant loads. Work shall include ground fault protection where required and comply with OSHA and the NEC. Remove facili-ties prior to occupancy.

1.

2.

3.

4.

5.

6.

Page 13: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Electrical

Section 2.3 Page 11

E. Raceway Systems Conduits: Rigid steel, IMC, EMT, Flexible steel and Liquid tight, and PVC conduits will be used with approved fi ttings. Provide complete raceway systems including outlet boxes, pull boxes, and fi ttings. Conceal conduits in fi nished spaces. Size conduits, boxes, and bends per the NEC. Provide expansion fi ttings, conduit seals, drain tees, conduit hubs, fi re/smoke barriers where required. Metal conduits shall have continu-ous grounding integrity.

a. EMT will be used for interior feeders and branch circuits. b. Flexible steel or Liquid-tight will be used for connection to motors and trans-

formers

F. Wire And Cable: Branch circuit conductors shall be THWN/THHN solid copper through #12 and stranded copper #8 and larger. Minimum wire size is #12. Conduit fi ll shall conform to NEC table 3. All conductors shall be in raceways with color coded insulation and each volt-age system shall be separately identifi ed. A green ground conductor will be installed in each feeder and branch circuit conduit.

Provide a separate neutral conductor for all 120/208-volt branch circuits.

G. Boxes and CabinetsPull and Junction Boxes: Indoor boxes shall be NEMA 1, constructed of a single piece code gauge steel, with folded and welded corners, complete with fl at removable screw down cover. Outdoor boxes utilizing rigid metal conduit shall be cast iron with cast iron gasketed cover held down with stainless steel screws. Outdoor boxes utiliz-ing PVC conduit shall be plastic with screw down gasketed cover. Size all boxes per NEC article 370. Provide boxes to comply with code and to provide ease of conductor installation. Outlet Boxes and Fittings: Interior outlet boxes shall be galvanized steel, non gang-able, with knockouts and covers or extension rings as required. Exterior surface outlet boxes shall be cast iron alloy with threaded hubs and screw down gasketed WP covers.

H. Devices And Cover Plates Receptacles shall be heavy-duty specifi cation grade, duplex or single outlet, voltage, and NEMA confi guration as required. Provide GFI receptacles as required. GFI re-ceptacles shall have test and reset buttons and indicator lights. Interior device plate covers shall be:

a. Unfi nished areas (storage, mechanical, etc.): Galvanized steel b. Finished, public spaces: Stainless steel c. Exterior device plates shall be galvanized steel WP with hinged lid.

I. Grounding And Bonding Equipment Grounding:

a. Motor circuits shall have a ground conductor pulled with the phase conduc-tors.

b. Scrape light fi xture fi nish to assure a good ground.

1.

1.

1.

2.

1.

2.

1.

Page 14: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Electrical

Section 2.3 Page 12

2. Provide a green grounding conductor in all branch circuit and feeder conduits sized per NEC. Provide grounding conductors in all conduit systems, fl exible conduit lengths, and surface raceways.

3. Provide grounding of all equipment comprising a permanent bonding together of all metallic, non current carrying parts of the electrical system like raceways, boxes, pan-els, cabinets, equipment enclosures, housings, motor frames, ducts, and luminaires.

Electrical Distribution Equipment

A. Transformers: Transformers shall be dry-type with kVA ratings as shown on the drawings. Primary shall be 480 volt, 3 phase, 3 wire, delta and secondary shall be 120/208 volt, 3 phase, 4 wire wye. Transformer shall include four primary voltage adjustment taps, class H insulation for 150 degree C rise above 40 degrees C ambient, and a ventilated enclosure. Transformers shall be rated for non-linear loads and shall have k-ratings as shown on the plans. Provide a 45 kVA transformer.

B. Panelboards: Panelboard enclosures shall be made of code gauge steel with fi nished cabinet front with concealed trim clamps, concealed door hinges, and lockable trim door with fl ush locks all keyed alike. 120/208 volt circuit breakers shall be bolt on, minimum 10,000 AIC rat-ing, 277/480 volt circuit breakers shall be bolt-on, minimum 18,000 AIC rating. Panel board bus ampacity shall be as indicated elsewhere in this narrative. Provide removable typewrit-ten circuit breaker identifi cation inside door.

C. Circuit Breaker Disconnects: Provide molded case disconnect switches, 600 volt, 3-pole in the elevator machine room. Provide one disconnect switch per elevator. Provide circuit breaker with shunt trip. Circuit breaker AIC rating shall coordinate with the circuit.

D. Motor ControlsMagnetic / Combination Starters: NEMA 1 enclosure with pilot light, HOA switch, con-trol transformer with matching closing coil, 1 NO & 1 NC auxiliary contact and thermal overload protection sized to the motor. Fusible switches shall be quick make, quick break with interlock to door. Starters shall be full voltage across the line sized as necessary.

1.

Page 15: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 13

ELECTRICAL SYSTEMS

Electrical Scope - Projects #2 and #3

A. All electrical work associated with Rooms A357 and A361 unless listed below.

B. Items currently not included in the scope of workTelephone System: Telephone hardware and electronics, cabling, faceplates, termi-nal blocks, termination and testing. Data System: Data network electronics such as concentrators, switches, servers, uninterruptible power supplies, and other electronic equipment, as well as cabling, faceplates, patch panels, network equipment racks, terminations and testing is not included. Cable TV (CATV) System: VCR’s, video signal processors, other electronics, as well as cabling, outlets, faceplates, are not included.

Service and Distribution Scope

A. No power distribution work is required for this project. Electrical work consists of lighting, devices, and branch circuit wiring. No fi re alarm work is included in scope.

B. The following voltages are typical Lighting: 120VReceptacles and motors 1/3 HP or less: 120V.

C. General convenience duplex receptacle locations and quantitiesCorridors: Receptacles every 40 feet throughout for housekeeping purposes.Storage, utility spaces: One receptacle at entrance door, 48” AFFMechanical spaces: Receptacles spread throughout for maintenance purposesOutdoor: One receptacle at each entrance/exit from the building, with additional pe-rimeter outlets to reduce the spacing to 100’-0” maximum.

Lighting Scope

A. Interior Lighting: Lighting systems appropriate for the task and design of the space will be selected. Lighting levels will meet or exceed IES recommended lighting levels.

B. Lighting installations will be designed to meet local energy code requirements. Design will utilize energy effi cient T8 fl uorescent lamps and electronic ballasts.

C. Indoor Lighting Specifi csInterior spaces are described below, with maintained illumination levels and luminaire types.

a. Other spaces – animal holding rooms will utilize vaportite 1 x 4 recessed lu-minaires, sealed and gasketed. Lighting shall be timeclock controlled (time-clocks are existing) with override switches.

1.

2.

3.

1.2.3.

1.2.3.4.

1.

U of M Department of Research Animal ResourcesProject #2 & #3 Building 371Room A357 & A361 Renovation

Page 16: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 14

Basic Materials and Methods

A. General: Shop drawings, Operation and Maintenance Manuals, and Operating instructions for the Owner are required for this project.All materials shall be new, except as noted above, UL Listed and Approved for the purpose, and installed per code.Work shall be installed per the NEC (NFPA 70) and applicable state and local codes and shall meet the requirements of nationally recognized standards. Secure and pay for all permits, licenses, utility and inspection fees, and coordinate all work with local inspection authorities.All systems shall be completely functional and wiring systems shall test free of defects using megger, continuity, ground, voltage, current, and phase rotation tests. Balance system phase currents to within 5% of each other. Provide all cutting and patching necessary for installation of electrical work and re-store fi nished surfaces disturbed by this Contractor. Do not cut or drill structural members. Provide general cleanup of waste and rubbish in the work area, and clean all removed and reinstalled equipment and luminaires. Clean all equipment that has become dirty during construction.

B. Equipment Support: Provide support of all electrical work through the use of hanger rods, clamps, structural framing, fastening devices, and backboards. Provide vibration isolation in all supporting hardware for vibrating electrical equipment installed by this Contractor.

C. Raceway Systems Conduits: Rigid steel, IMC, EMT, Flexible steel and Liquid tight, and PVC conduits will be used with approved fi ttings. Provide complete raceway systems including outlet boxes, pull boxes, and fi ttings. Conceal conduits in fi nished spaces. Group conduits on racks leaving 25% conduit space and suspend from the structure. Size conduits, boxes, and bends per the NEC. Provide expansion fi ttings, conduit seals, drain tees, conduit hubs, fi re/smoke barriers where required. Metal conduits shall have continu-ous grounding integrity.

a. EMT will be used for interior feeders and branch circuits. b. Flexible steel or Liquid-tight will be used for connection to motors and trans-

formers

D. Wire And Cable: Branch circuit conductors shall be THWN/THHN solid copper through #12 and stranded copper #8 and larger. Minimum wire size is #12. Conduit fi ll shall conform to NEC table 3. All conductors shall be in raceways with color coded insulation and each volt-age system shall be separately identifi ed. A green ground conductor will be installed in each feeder and branch circuit conduit.

Provide a separate neutral conductor for all 120/208-volt branch circuits.

1.

2.

3.

4.

5.

6.

1.

1.

U of M Department of Research Animal ResourcesProject #2 & #3 Building 371Room A357 & A361 Renovation

Page 17: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 15

E. Boxes And CabinetsPull & Junction Boxes: Indoor boxes shall be NEMA 1, constructed of a single piece code gauge steel, with folded and welded corners, complete with fl at removable screw down cover. Exposed boxes shall be NEMA 3R. Size all boxes per NEC article 370. Provide boxes to comply with code and to provide ease of conductor installation. Outlet Boxes and Fittings: Surface outlet boxes shall be cast iron alloy with threaded hubs and screw down gasketed WP covers.

F. Devices And Cover Plates Switches shall be heavy-duty specifi cation grade, 20 amp, 120/277 volt, quiet toggle, momentary contact, pilot type or illuminated toggle. Provide single pole, double pole, 3 way, 4 way, or SPDT as required similar to Hubbell 1221 series. Receptacles shall be heavy-duty specifi cation grade, duplex or single outlet, voltage, and NEMA confi guration as required. Provide GFI receptacles as required. GFI re-ceptacles shall have test and reset buttons and indicator lights. Interior device plate covers shall be:

a. Interior device plates shall be stainless steel WP with hinged lid.

G. Grounding And Bonding Equipment Grounding:

a. Motor circuits shall have a ground conductor pulled with the phase conduc-tors.

a. Scrape light fi xture fi nish to assure a good ground. 2. Provide a green grounding conductor in all branch circuit and feeder conduits sized per

NEC. Provide grounding conductors in all conduit systems, fl exible conduit lengths, and surface raceways.

3. Provide grounding of all equipment comprising a permanent bonding together of all metallic, non current carrying parts of the electrical system like raceways, boxes, pan-els, cabinets, equipment enclosures, housings, motor frames, ducts, and luminaires.

Lighting Equipment

A. Luminaires: Luminaires will be provided complete with lamps, ballasts, and all necessary accessories and mounting hardware. Luminaires will be compatible with ceiling or wall sys-tems.

Lensed troffers: Flush aluminum doors, 0.156” min A12 prismatic acrylic lens. B. Ballasts

Fluorescent: Rapid-start electronic, low harmonic (10% THD or less at 120V, 15% THD or less at 277V)

1.

2.

1.

2.

3.

1.

1.

1.

U of M Department of Research Animal ResourcesProject #2 & #3 Building 371Room A357 & A361 Renovation

Page 18: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 16

ELECTRICAL SYSTEMS

Electrical Scope - Project #4 and #5

A. All electrical work associated with Rooms C211 and D201, unless listed below.

B. Items currently not included in the scope of workTelephone System: Telephone hardware and electronics, cabling, faceplates, termi-nal blocks, termination and testing. Data System: Data network electronics such as concentrators, switches, servers, uninterruptible power supplies, and other electronic equipment, as well as cabling, faceplates, patch panels, network equipment racks, terminations and testing is not included. Cable TV (CATV) System: VCR’s, video signal processors, other electronics, as well as cabling, outlets, faceplates, are not included.

Service and Distribution Scope

A. Power work includes removing circuit to existing AHU and provide two circuits to two new AHU’s for room C211. Additional work consists of lighting, devices, and branch circuit wiring. No fi re alarm work is included in scope.

B. The following voltages are typical Lighting: 120VReceptacles and motors 1/3 HP or less: 120V.

C. General convenience duplex receptacle locations and quantitiesCorridors: Receptacles every 40 feet throughout for housekeeping purposes.Storage, utility spaces: One receptacle at entrance door, 48” AFFMechanical spaces: Receptacles spread throughout for maintenance purposesOutdoor: One receptacle at each entrance/exit from the building, with additional pe-rimeter outlets to reduce the spacing to 100’-0” maximum.

Lighting Scope

A. Interior Lighting: Lighting systems appropriate for the task and design of the space will be selected. Lighting levels will meet or exceed IES recommended lighting levels.

B. Lighting installations will be designed to meet local energy code requirements. Design will utilize energy effi cient T8 fl uorescent lamps and electronic ballasts.

1.

2.

3.

1.2.

1.2.3.4.

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Page 19: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 17

C. Indoor Lighting Specifi csInterior spaces are described below, with maintained illumination levels and luminaire types.

a. Other spaces – animal holding rooms will utilize vaportite 1 x 4 surface lumi-naires, sealed and gasketed. Lighting shall be timeclock controlled (two time-clocks are existing) with override switches. Provide additional astronomical timeclocks for new rooms.

Basic Materials and Methods

A. General: Shop drawings, Operation and Maintenance Manuals, and Operating instructions for the Owner are required for this project.All materials shall be new, except as noted above, UL Listed and Approved for the purpose, and installed per code.Work shall be installed per the NEC (NFPA 70) and applicable state and local codes and shall meet the requirements of nationally recognized standards. Secure and pay for all permits, licenses, utility and inspection fees, and coordinate all work with local inspection authorities.All systems shall be completely functional and wiring systems shall test free of defects using megger, continuity, ground, voltage, current, and phase rotation tests. Balance system phase currents to within 5% of each other. Provide all cutting and patching necessary for installation of electrical work and re-store fi nished surfaces disturbed by this Contractor. Do not cut or drill structural members. Provide general cleanup of waste and rubbish in the work area, and clean all removed and reinstalled equipment and luminaires. Clean all equipment that has become dirty during construction.

B. Equipment Support: Provide support of all electrical work through the use of hanger rods, clamps, structural framing, fastening devices, and backboards. Provide vibration isolation in all supporting hardware for vibrating electrical equipment installed by this Contractor.

C. Raceway Systems Conduits: Rigid steel, IMC, EMT, Flexible steel and Liquid tight, and PVC conduits will be used with approved fi ttings. Provide complete raceway systems including outlet boxes, pull boxes, and fi ttings. Conceal conduits in fi nished spaces. Group conduits on racks leaving 25% conduit space and suspend from the structure. Size conduits, boxes, and bends per the NEC. Provide expansion fi ttings, conduit seals, drain tees, conduit hubs, fi re/smoke barriers where required. Metal conduits shall have continu-ous grounding integrity.

a. EMT will be used for interior feeders and branch circuits. b. Flexible steel or Liquid-tight will be used for connection to motors and trans-

formers

1.

1.

2.

3.

4.

5.

6.

1.

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Page 20: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 18

D. Wire And Cable: Branch circuit conductors shall be THWN/THHN solid copper through #12 and stranded copper #8 and larger. Minimum wire size is #12. Conduit fi ll shall conform to NEC table 3. All conductors shall be in raceways with color coded insulation and each volt-age system shall be separately identifi ed. A green ground conductor will be installed in each feeder and branch circuit conduit.

Provide a separate neutral conductor for all 120/208-volt branch circuits.

E. Boxes And CabinetsPull & Junction Boxes: Indoor boxes shall be NEMA 1, constructed of a single piece code gauge steel, with folded and welded corners, complete with fl at removable screw down cover. Exposed boxes shall be NEMA 3R. Size all boxes per NEC article 370. Provide boxes to comply with code and to provide ease of conductor installation. Outlet Boxes and Fittings: Surface outlet boxes shall be cast iron alloy with threaded hubs and screw down gasketed WP covers.

F. Devices And Cover Plates Switches shall be heavy-duty specifi cation grade, 20 amp, 120/277 volt, quiet toggle, momentary contact, pilot type or illuminated toggle. Provide single pole, double pole, 3 way, 4 way, or SPDT as required similar to Hubbell 1221 series. Receptacles shall be heavy-duty specifi cation grade, duplex or single outlet, voltage, and NEMA confi guration as required. Provide GFI receptacles as required. GFI re-ceptacles shall have test and reset buttons and indicator lights. Interior device plate covers shall be:

a. Interior device plates shall be stainless steel WP with hinged lid.

G. Grounding And Bonding Equipment Grounding:

a. Motor circuits shall have a ground conductor pulled with the phase conduc-tors.

b. Scrape light fi xture fi nish to assure a good ground. 2. Provide a green grounding conductor in all branch circuit and feeder conduits sized per

NEC. Provide grounding conductors in all conduit systems, fl exible conduit lengths, and surface raceways.

3. Provide grounding of all equipment comprising a permanent bonding together of all metallic, non current carrying parts of the electrical system like raceways, boxes, pan-els, cabinets, equipment enclosures, housings, motor frames, ducts, and luminaires.

1.

1.

2.

1.

2.

3.

1.

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Page 21: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Project Summary

HGA Commission No. 0265-115-00 July 10, 2009

Electrical

Section 2.3 Page 19

U of M Department of Research Animal ResourcesProject #4 & #5 Building 371Room C211 & D201 Renovation

Lighting Equipment

A. Luminaires: Luminaires will be provided complete with lamps, ballasts, and all necessary accessories and mounting hardware. Luminaires will be compatible with ceiling or wall sys-tems.

Lensed troffers: Flush aluminum doors, 0.156” min A12 prismatic acrylic lens,

B. BallastsFluorescent: Rapid-start electronic, low harmonic (10% THD or less at 120V, 15% THD or less at 277V)

1.

1.

Page 22: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Code Anaylsis

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesVeterinary Science Cage Washer and HVAC Upgrades

A. Summary

A brief review was conducted with Clayton Talbot, University of Minnesota Plans Examiner to orient the Building Code Division with the scope of work for all the projects. The functions of all the reno-vated rooms will remain the same; the work does not impact current exit paths. All new doors and their associated hardware will be installed to meet accessibility code requirements. All mechanical and electrical work will be performed in compliance with all currently applicable codes as noted be-low. There are no hazardous chemicals used in the renovated rooms.

B. Applicable Codes: - Building Code: 2007 Minnesota State Building Code (2006 IBC with amendments) - Mechanical Code: 2009 Minnesota State Mechanical Code - Plumbing Code: International Plumbing Code and IBC Chapter 29 - 2003 Minnesota State Plumbing Code - Electrical Code: 2008 National Electrical Code - Fire Code: 2006 International Fire Code (Minnesota State Fire Code, Chapter 7510) - Life Safety Code: 2006 International Fire Code (Minnesota State Building Code, Chapter 7510) - 2007 Accessibility Code: ADAAG (Minnesota State Building Code, Chapter 1341) and EEOC Ac-

cessibility Guidelines - 2009 Energy Code: Minnesota State Building Code, Chapters 7670-7678 - Environmental Protection Agency Standards - Minnesota Department of Labor – OSHA Regulations

C. Occupancy and Construction Type: - Building 371: B / H-3 (Classroom, Lab, Offi ce, Lounge, Other) Construction Type: II-A - Building 374: B / A-3 (Auditorium, Classroom, Lab, Offi ce. Lounge, Other) Construction Type: III-A D. University Fire Protection Master Plans

The University is in the process of providing the infrastructure piping for automatic sprinkler systems for Buildings 416 and 427. The University’s plan is to provide this infrastructure for Buildings 371, 385A and 374, dependent upon funding. Per a review of the proposed fi re protection drawings for Buildings 374 and 371, the rooms being renovated in this Predesign document do not fall within the scope of future work for these buildings. Hence, no sprinkler work is being provided.

Section 3.0 Page 20

Page 23: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Cost

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Section 4.1 Page 21

Page 24: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

U of M Department of Research Animal ResourcesProject #1 Building 374Room 345D Bottle Washer

Construction Estimate

The following construction estimate was prepared by Cy-Con, Inc., General Contractors.

Section 4.0 Page 22

Page 25: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Cost

Section 4.2 Page 23

U of M Department of Research Animal ResourcesProject #2 Building 371Room A357 Renovation

Page 26: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Estimate

The following construction estimate was prepared by Cy-Con, Inc., General Contractors.

U of M Department of Research Animal ResourcesProject #2 Building 371Room A357 Renovation

#2

Section 4.2 Page 24

Page 27: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Cost

Section 4.3 Page 25

U of M Department of Research Animal ResourcesProject #3 Building 371Room A361 Renovation

Page 28: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Estimate

The following construction estimate was prepared by Cy-Con, Inc., General Contractors.

Section 4.3 Page 26

U of M Department of Research Animal ResourcesProject #3 Building 371Room A361 Renovation

Page 29: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Cost

Section 4.4 Page 27

U of M Department of Research Animal ResourcesProject #4 Building 371Room C211 Renovation

Page 30: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Estimate

The following construction estimate was prepared by Cy-Con, Inc., General Contractors.

Section 4.4 Page 28

U of M Department of Research Animal ResourcesProject #4 Building 371Room C211 Renovation

Page 31: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Cost

Section 4.5 Page 29

U of M Department of Research Animal ResourcesProject #5 Building 371Room D201 Renovation

Page 32: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations

Cost Analysis

HGA Commission No. 0265-115-00 July 10, 2009

Construction Estimate

The following construction estimate was prepared by Cy-Con, Inc., General Contractors.

Section 4.5 Page 30

U of M Department of Research Animal ResourcesProject #5 Building 371Room D201 Renovation

#5

Page 33: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations
Page 34: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations
Page 35: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations
Page 36: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations
Page 37: Veterinary Medical Center Veterinary Science Building · 2017-01-10 · Veterinary Medical Center Veterinary Science Building Bottle Washer Installation and Minor Room Renovations