Vermilion Energy Inc. The Wandoo Story- Marine and Subsea Life Extension Abigail Anderson – Operations Engineer

Vermilion Energy Inc. - SUT · Vermilion Energy Inc. The Wandoo Story- Marine and Subsea Life ... ♦Software- Orcaflex, MOSES, FEMAP . 27 CALM Buoy Modelling . 28 Extending the IMR

Embed Size (px)

Citation preview

1

Vermilion Energy Inc.

The Wandoo Story-

Marine and Subsea Life

Extension

Abigail Anderson – Operations Engineer

2

Vermilion Energy

♦ VOGA is an Canadian based Oil and Gas Company focused on mature oil and gas fields.

♦ Operations in Canada, France, Netherlands, Ireland and Australia.

♦ In Australia we are 100% owner of the Wandoo field located 75km offshore Karratha.

♦ We acquired the Wandoo field from Ampolex in 2007.

♦ Wandoo currently produces around 8,000bopd.

3

Presentation Overview

♦ Introduction to Wandoo

♦ The Life Extension Story – Subsea and Marine

♦ Replacement Studies

♦ LE Feasibility Review

♦ Operator Drivers

♦ Schedule

♦ Basis of Design

♦ Inspections & Data Gathering

♦ Analysis

♦ IMR Plans

♦ Operator Experience

♦ Summary

4

The Wandoo Facilities

5

The Wandoo Story : WNA

Wandoo A

WNA installed in 1993 with

design life of 15 years.

Recertification was performed

for the structure in 2008 and

again in 2013.

WNA is an unmanned

monopod with 5 well heads.

6

The Wandoo Story: Construction

Wandoo B

The Wandoo Concrete

Gravity Structure (CGS)

was built by the Wandoo

Alliance in Bunbury, WA.

The CGS was towed to

the Wandoo Field, 75km

offshore Karratha, and

installed in 1996.

Design Life: 20 Years

7

The Wandoo Story: Flooding and Towing

8

The Wandoo Story: Install

9

The Wandoo Story: Flowlines

10

The Wandoo Story: Installation

First production: March 1997

11

The Life Extension Story

12

Replacement Studies

♦ Wandoo A & B Studies completed in 2013 –

– Wandoo Assets Scoping Study

– SEA Flowline Replacement Study

– Export Offloading Configuration Screen Study

♦ Results from Flowline Replacement Study showed

that the cost of replacement (~$80M) was

uneconomical.

♦ Report recommended that a life extension feasibility

study was completed.

13

Initial Feasibility Review for LE

14

Operator Drivers

Vermilion Oil & Gas Australia (VOGA) intend to operate the Wandoo Oil Facilities for an extended period to end of field life, recent field development planning indicates that the platform is required for a further 20-years.

15

Life Extension Schedule

16

Life Extension Scopes

7 key systems were identified for life extension:

SSS1: WNB Superstructure SSS2: WNB Substructure SSS3: Subsea Systems (Flowlines) SSS4: Marine Systems (Export Systems) SSS5: Safety Systems SSS6: Wells SSS7: Process Systems

17

Life Extension Process- SOV

18

Basis of Design

♦ Establish the basis of original design

♦ Define the basis for life extension

♦ Analysis methodology

♦ Agreement on correct design codes, latest vs original

♦ Input requirements

♦ Software requirements

19

Inspections and Data Gathering

♦ ROV Campaigns

♦ Diving campaign

♦ Sonar

♦ Atmospheric survey - rope

♦ Internal inspections - CSE

♦ Intelligent Pigging

20

ROV

Video

21

ROV – Platform Launch

22

Sonar : Flowlines

23

Sonar

Video

24

Subsea Life Extension

♦ Code and Standard Selection

♦ Flowline Reassessment Report

– On-bottom stability numerical analysis

– In-place tie-in assessment

– Flowline original design factor check

♦ Riser Analysis Report

– In-place Strength, Fatigue & Seismic numerical analysis

♦ PLEM Analysis Report

– Gap analysis

– In-place Strength, Fatigue, Foundation Capacity & Seismic numerical analysis

♦ Modelling – Orcaflex

25

Riser System Modelling

26

CALM Buoy Life Extension

♦ Codes and Standard Review

♦ Current condition review – inspection report review

♦ Mooring Analysis

♦ Mooring Line Assessment

♦ Structural Analysis

♦ Buoy Flooding Analysis

♦ Submarine Hose Assembly Analysis

♦ Anchor Assessment

♦ Software- Orcaflex,

MOSES, FEMAP

27

CALM Buoy Modelling

28

Extending the IMR Plans

29

Operator Experience

♦ Lessons Learnt-

– Early involvement of the Independent Verifying Body is

essential to ensure aligned life extension process

– Contractor selections is critical

– As-built historical documents can be difficult to locate

– Sheer amount of documentation required

– Dedicated personnel to project controls required

– Track ever changing schedules!

30

Summary

♦ Vermilion is on it’s way to achieving life extension of the

Wandoo assets

♦ Life extension doesn’t happen overnight – schedules,

resources and budgets need to be considered prior to

undertaking

31

Life Extension Team

Thanks to the Vermilion Life Extension Team

And some of the Life Extension Contractors:

32

Questions?