Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
VDOT T.R.I.P. PILOT
18 MONTH SUMMARY August 5, 2019
1
Document Revision History
Revision Date Changed By Description/Change Made
0 8/2/2019 Scott Kapton Initial release of report
1 8/2/2019 Tom Clark Edited content and recommended inclusion of
additional material
2 8/15/2019 Scott Kapton Final edits and changes accepted
3 8/20/2019 Dan Glass Format modification
2
Table of Contents Introduction .................................................................................................................................................. 3
1) Program Development .......................................................................................................................... 3
2) Outreach ............................................................................................................................................... 5
3) Application Process ............................................................................................................................... 6
4) Training ................................................................................................................................................. 7
5) Program Deployment ............................................................................................................................ 9
6) Program Management ........................................................................................................................ 10
7) Record Keeping ................................................................................................................................... 12
8) Lessons learned ................................................................................................................................... 12
9) Performance measures ....................................................................................................................... 14
3
Introduction TRIP is a recovery incentive program that
pays heavy-duty towing and recovery
companies a monetary bonus for quickly
clearing crashes involving commercial
vehicles. The specific objective of TRIP is to
reduce the impact of major commercial
vehicle incidents while achieving the
aggressive lane clearance goal of 90
minutes or less.
The goal for TRIP is to standardize the towing response and facilitate safe and quick
clearance of commercial vehicle crashes by improving towing procedures and on scene
cooperation and coordination among first responders. The TRIP program potentially
reduces the number of secondary crashes by reducing lane clearance times and
restoring normal traffic flow.
The most important aspect of a successful TRIP program is ensuring companies maintain
the minimum established level of equipment, training and certified staff who are engaged
in the program. This required a team of Parsons’ staff in partnership with VDOT staff and
various stakeholders to be engaged in developing, monitoring progress, coordinating
meetings, participating in after action reviews and updating policies and procedures as
needed. This document will serve to summarize the activity that occurred during program
development and the first 18 months of TRIP program deployment and operation.
1) Program Development The first step towards implementation was early program development. The process
included multiple meetings between Parsons and VDOT staff to discuss, identify and
determine the pathway to defining what the eventual TRIP program would look like.
Additionally, meetings with the Virginia State Police (VSP) were held to secure their feedback
and support for implementation of TRIP. The Richmond Regional TIM Committee and the
Virginia Association of Towing and Recovery Operators (VATRO) were also early stakeholders
and were solicited for their feedback.
Parsons staff also spent the first few months prior to implementation collecting and
reviewing commercial motor vehicle (CMV) crash data statistics for the entire Richmond/
Petersburg interstate system and used that historical data to provide a predictive model of
how many TRIP crashes may occur in the future. Initially, a seven-year historical review was
conducted, but ultimately a three-year crash average was established, after it was noted
that the CMV crash rate had risen noticeably in the last three years. This baseline was used
to predict the number of TRIP activations for the Pilot Program. Comparisons with other
Figure 1
4
similar towing programs were also an important element of the early program development,
as they provided many lessons already learned.
In order to ensure an objective and measurable foundation, the following areas were
examined and developed:
a) TRIP activation criteria - this was essential as it identified what a qualifying crash
would look like and provided the direction and the basis for all stakeholder training
and program communications moving forward. It also established a baseline for
predicting and budgeting for incentive payments. The original intent was to activate
TRIP for only those CMV crashes that were actively blocking lanes.
b) Specifications, Qualifications & Training - One of the challenges of the existing heavy
wrecker rotational towing process is that there was no consistent method to account
for wrecker specifications, identify qualified operators or evaluate performance. TRIP
sought to change that dynamic.
• Wrecker specifications - These were based on industry-wide towing standards
and matched up with the proposed task at hand. The goal of a standardized
response from the towing community was set, and all specifications were
based on the ability to relocate a casualty CMV weighing up to 80,000 pounds
from the roadway and facilitating safe, quick clearance. Minimum
specifications were established and implemented.
• Qualifications - Each company was required to meet minimum requirements
for a variety of items such as:
(a) Wrecker Specifications
(b) Support vehicle and specific list of additional tools and equipment
(c) Training requirements for all TRIP operators and supervisors
(d) Agreements with others to provide additional resources as defined by the
program
(e) Agree to participate in and complete continuing education/ training over
the life of the program
• Training - Training modules were developed to specifically target all
stakeholder groups and were predicated on the roles and responsibilities for
each group. VDOT staff, VSP and Safety Service Patrol personnel were
identified as primary stakeholders and received specific training on TRIP
program language, intent, activation procedures and timekeeping duties.
Local Police and Fire personnel were defined as secondary TRIP stakeholders
and were supplied with awareness training that was designed to provide an
overview and intent of TRIP and help educate those responders that would be
on scene, but not a primary TRIP participant. Outreach to those groups has
continued throughout the first 18 months of the Pilot Program.
5
c) Identification of potential TRIP participants - With the assistance of VDOT and VSP,
the existing rotational towing lists were examined and vetted for potentially qualified
TRIP companies. In addition, regional searches were conducted to identify those
towing companies not currently on a rotation list to ensure full inclusion during the
outreach and application process. Approximately 20 companies were identified in
the Richmond Region and the initial outreach effort focused on the identified group.
Figure 2
2) Outreach A critical element of program development was the outreach effort to towers and other
stakeholders. It cannot be understated how important this element was to the program
development process and continued to be a key element during implementation and for
early program success. TRIP significantly changed the approach to clearing CMV crashes
and that change was felt by all responding stakeholders. Educating, explaining, illustrating
benefits, and days of hand holding over many months was necessary to ensure that the
impacted groups were educated enough to foster the necessary buy in for the program.
Parsons and VDOT staff teamed up as the face of the program and sent out a consistent and
clear message about TRIP every step of the way.
Initial outreach efforts were met with significant pushback from a majority of towing
companies, although a few companies understood the benefit and became quick partners
early on. Parsons and VDOT staff had to establish credibility with the towing community and
that proved to be a challenging exercise. The team was faced with a group of professional
tow company owners who initially took the position that they would wait us out, and not sign
up for anything, thus killing the program before it started. Their position was made very
clear during the kickoff meeting in May of 2017, when the group made their position about
TRIP known, and it was not a positive message. Over time and with consistent effort and
messaging during the development phase, the Parsons and VDOT staffs were able to
establish credibility with the group as it became apparent that the specifications,
6
qualifications and expectations were based on real world experience and lessons learned
elsewhere.
The Virginia Association of Towing and Recovery Operators (VATRO) became one of the
conduits used to communicate with the towing community on a broad basis regarding the
TRIP effort, and VATRO leadership proved invaluable to the process. Over the course of the
outreach effort and during the first few months of TRIP program deployment, all TRIP
participants became members of VATRO. Face to face meetings with the VATRO group as
well as one on one meetings with towing company owners was necessary and critical to
establishing TRIP credibility.
At the same time, the outreach and education for VSP, VDOT staff (including TAMS, IMC, and
TOC Operations staff) along with Safety Service Patrol operators focused on educating all on
the concepts of TRIP.
Additionally, the Regional TIM and Executive TIM Committees in Richmond were used to
educate the greater TIM community and bring all impacted stakeholders into the TRIP
conversation. This step proved critical as it established awareness and support for the
program from the larger TIM community.
The overall outreach effort was predicated on identifying and successfully illustrating the
problem that we were trying to solve. Some CMV crashes over the past few years had
resulted in extensive, hours-long periods of lane blockage or complete interstate closures,
thus exposing responders to greater danger. Once the entire stakeholder group understood
the goals, and started to buy in to this unique approach to clearing CMV crashes, the effort
to implement was underway.
3) Application Process The application process began during the outreach effort in the summer of 2017 and
included the fully completed program document. By this time, outreach efforts had been
ongoing for months and individual towing company owners were beginning to buy into the
TRIP philosophy. Parsons staff used the application process to continue the outreach effort
and the team worked one on one with individual towing companies to be as inclusive as
possible and provide every interested towing company the same opportunity to apply for
TRIP service.
VDOT required that all TRIP application criteria be met at the time of submission, and this
included all employee training. Since this was a brand-new program, and the development
phase was on an extremely tight schedule, some considerations for securing equipment
were given and a grace period beyond the application due date was implemented to give
companies more time to comply. These exceptions were specifically called out in the
program language, and further allowed for companies to meet the program goals.
7
The applications were designed to solicit as much objective information as possible so side
by side comparisons could be made when evaluating each one. Some of the criteria for
approval included the following:
a) Meeting wrecker and equipment specifications
b) Listing the required list of tools
c) Meeting training requirements for all employees submitted
d) Proximity to the interstate
e) Successful site and wrecker inspections
All applying companies were required to meet the minimum level of qualifications to be
considered for TRIP duty. Parsons accepted and reviewed fifteen applications. Parsons
staff worked with each submitting company to ensure completeness and accuracy of their
application. One application was rejected and considered non-responsive (incomplete).
Three applications were rejected for not fully meeting the minimum requirements. Eleven
companies were ultimately approved for participation in TRIP. Parsons and VDOT staff met
with each company that did not qualify to discuss in detail the exact reasons why their
application was not approved.
Once the eleven companies received conditional approval (pending final site inspections)
Parsons staff, with input from VDOT, began the process of designating each of the recovery
response zones. The recovery zone designation was predicated on several factors:
f) Proximity to the interstate or limited access on ramp
g) Ability to achieve the 45- 60-minute response requirement
h) Crash data history/areas of concern
i) Free flow response from a single direction
j) Areas of recurring congestion
k) Ability to meet the operational needs of VDOT
Once these recovery zones had been designated and final inspections had been conducted
and approved, Parsons and VDOT met with each of the approved towing companies to
discuss the details and thoughts behind each of the recovery zones. Feedback was solicited
from each and TRIP assignments were made.
Each of the designated recovery zones was captured in a document that was distributed to
all stakeholders but primarily to the VDOT Richmond TOC staff. This document serves as the
primary tool for dispatching the appropriate TRIP company to a crash.
Training The training for those connected with the TRIP Pilot program included all stakeholders and
required a variety of approaches and classes to effectively train multiple large groups from
various disciplines. Most of this training was performed directly by both Parsons and VDOT
staff to ensure consistency of message leading up to program deployment.
8
l) Towing community- Parsons and VDOT identified specific areas of training that would
be critical to the success of the program and to be concluded at the time of
application. This required a significant commitment from the towing community.
Parsons partnered with WreckMaster, a nationwide tow industry training company, to
provide two levels of wrecker training for all towing company employees. VDOT
provided a 50% cost participation for the WreckMaster training to help facilitate and
encourage participation. This process resulted in the entire TRIP wrecker community
receiving formal wrecker training. Before TRIP, less than a dozen wrecker operators
in the region had received formal wrecker training. Once TRIP deployed, every
responding wrecker operator and supervisor from every participating tow company
had received formal wrecker training. Additionally, TRIP required the towing
community to receive NIMS ICS training, Basic Work Zone, Haz-Mat awareness, and
SHRP2 TIM training. This package of training was designed to elevate the TRIP
wrecker operators to a much higher and consistent level of ability. This high level of
training has translated into efficiency of operations, quicker lane clearance and much
better communication and interaction with Incident Command staff.
m) VDOT IMC, TAMS, SSP and VSP personnel- As primary TRIP activating Stakeholders,
these groups all participated in direct TRIP program and activation training. These
training classes were designed to be very detail oriented and each class participant
was educated on the details of the TRIP program and the processes for success.
This training was conducted jointly with Parsons and VDOT staff to ensure
consistency of message. They focused in part on the following duties:
i) Identify and verify TRIP qualifying event
ii) Participate in the time stamping process
• Arrival
• NTP
• Work stoppage
• Lane clearance
• Tactical decision making
n) VSP Dispatch and VDOT TOC Staff- Since this was a significant change to the
traditional rotational towing procedure historically handled by VSP Dispatchers, it was
necessary to perform joint training now that the VDOT TOC staff would be dispatching
TRIP. Both entities received similar training as the activating stakeholder group, but
also received specific training for their individual and joint responsibilities. It was
important to develop a TRIP procedure that simply layered into the already existing
procedures, and not disrupt either operation.
i) Within the first few months, the VDOT TOC had shown the ability to correctly
identify TRIP criteria and had been engaging the process with a high level of
accuracy, especially when camera coverage was sufficient to give a clear view of
9
a crash. This resulted in a decision to allow the TOC Supervisors, under certain
specific circumstances, to activate TRIP independent of a first responder. This
change in procedure has allowed for TRIP activations in a little as three minutes
for several TRIP incidents.
o) Secondary Stakeholders- This group consists primarily of local/county law
enforcement and fire personnel. It became apparent early in the program that these
responders would have exposure to TRIP but not be primary activators or have a
direct role on scene as TRIP is concerned. Due to lessons learned in the first few
months, an awareness training program for TRIP was developed as a twenty minute,
narrated in-service module. This training focused more on the overall TRIP message
and what a responder could expect at a TRIP crash scene. To date, it has been
distributed to all local police and fire departments for their use.
p) TIM Committee/ Conferences- The Parsons staff used the regional TIM committee
and various regional presentation opportunities to educate the greater responder
community about TRIP. This effort is ongoing and will continue for the life of the
program.
Parsons has also developed and released a five-minute, high level training video for
continued outreach and education about TRIP. This video can be used by any stakeholder
group for this purpose and is now incorporated into the original TRIP training syllabus.
It was required that all towing companies complete their training at the time of their
application in August of
2017. The stakeholder
training for TRIP operations
however, took place in the
late fall of 2017. This
approach, albeit on a tight
schedule, was pushed back
deliberately to ensure that
on day one of TRIP
implementation on
December 15, 2017 all
training would be fresh in
everyone’s mind.
Program Deployment VDOT set the deployment date for TRIP program implementation for December 15, 2017.
The final group of approved towing companies came to eleven providers assigned to just
over 200 miles of Interstate in the Richmond Region. The eleven companies are:
Figure 3
10
• Anytime Towing
• Dennis Towing
• Robinson Towing
• Glen Allen Towing
• Bob Alley Towing
• Eagle Towing
• Central City Towing
• Coastal Towing
• Capital Garage
• WS Campbell Towing
• Bishops Towing
A pre-deployment kickoff meeting was scheduled for early December and was designed to
bring all leadership TRIP stakeholders together to review and prepare for deployment of the
program. This meeting focused on the tight coordination and clear understanding required
to launch TRIP seamlessly. Attendance included:
• VDOT IMC
• VDOT TOC
• VSP
• VDOT SSP
• VDOT TAMS
• TRIP towing community
Figure 4
Program Management Once the TRIP program deployed, the process of ongoing management began. During the
first few months of TRIP, all stakeholders were learning a new process and it was important
for the Parsons and VDOT team to account for and address any “growing pains” issues as
11
they arose. In turn, these issues were evaluated, solved and shared with the overall
stakeholder group as they occurred.
Within the first few months of the Pilot Program a determination was made to expand the
TRIP activation criteria to include those CMV crashes whose response by towing and other
first responders would result in lane blockage. This expansion of TRIP activation has yielded
benefits as all CMV lane impacting crashes now qualify for TRIP activation, even if the CMV
has left the roadway. A key element to the program management effort is the monthly TRIP
After Incident Review Meetings. These meetings were made mandatory for all TRIP towing
companies and an open invitation was extend to all other stakeholders. In this meeting each
month, the previous month’s crashes are reviewed, discussed and evaluated for incentive
approvals or denials. This open forum has proven to be highly effective at bringing in
lessons learned from each crash scene provided by the towing community, incident
commanders and VDOT IMC and TAMS staff. Participants in this meeting are walked
through the high-level details of each crash and anyone who had a role on scene is
encouraged to share their details and lessons learned. Over the first 18 months, we have
been successful in building a cohesive coalition of TRIP stakeholders who are actively
engaged in the TRIP effort and eagerly share their experiences with each other. The result
has been a steady improvement in the performance of the program over the first 18 months.
In order to prepare for each monthly meeting, the Parsons staff works behind the scenes
every day to ensure that all elements of the TRIP program are being met by all of the
stakeholder groups. As a result, Parsons staff have daily, weekly and monthly interactions
depending on the topic, but are also available as needed for any TRIP program participant.
This 24/7 focus and open line of communication across all disciplines is a key factor in the
success of the program.
Over the course of each month, Parsons staff process and/or participate in the following:
i) Synopsis reports- these are provided by all TRIP activating stakeholders, TRIP
companies and the VDOT TOC. This redundant reporting tool ensures that all
details and all timestamps are captured accurately for each TRIP event
ii) Invoicing- Supplied by each TRIP towing company and processed for incentive
payments
iii) Photos- received from various sources and become part of the official record for
each TRIP call and used in the monthly review meeting
iv) PPT development - A new power point is generated each month to highlight each
TRIP event and drive the monthly meeting. Excerpts are used for TRIP relevant
presentations elsewhere.
v) Emails - Occur daily and have become the primary means of communication for
Program Management amongst the TRIP group
vi) Phone calls - Occur daily and at all hours depending on circumstance
vii) Ongoing outreach - Continues as awareness of the program grows and new
stakeholders come on board.
12
viii) Periodic program reviews - An ongoing process in the first 18 months, this is a
collaborative effort and has recently led to program language changes as we
prepare for the second two-year cycle for TRIP
Record Keeping Once the application process began, Parsons began designing the record keeping system
that would track and document the entire program. This development continued through
the entire first year of the pilot program as the process was refined based on real world
activity and lessons learned along the way. Ultimately, each TRIP company is assigned a
cradle to grave file that captures all current activity, cycles out employees and equipment no
longer in use, and tracks towing employee training and certifications to ensure program
compliance.
A TRIP reporting process was created for all primary TRIP stakeholders, and each use this
reporting tool to document each TRIP incident and log all timestamps. The TRIP towing
community also uses this system to self-report and all documentation is compared to the
Richmond TOC reporting. The TOC serves as the formal record keeper for TRIP and this
redundant reporting method has proven to be nearly 100% accurate. During the first 18
months of the TRIP Pilot program, only one reporting discrepancy was noted.
Furthermore, Parsons developed an invoicing mechanism to process incentive payments for
successful TRIP performance. This process did take some time to refine as there was no
clear path for VDOT to pay the incentives directly. As a result, Parsons processes all invoices
through VDOT and pays the incentives directly to the towing companies.
Lessons learned Beginning with the early stages of outreach and through the first 18 months, there were
many lessons learned that allowed the Parsons and VDOT staff to identify challenges and
solve the issues that materialized. Several examples are listed below to illustrate:
a) Consistency of message - early on during the outreach phase of TRIP, it became
apparent that the initial reaction to TRIP was not always positive. As we spread the
word and met with stakeholders, there was a significant number of questions flowing
back through both Parsons and VDOT staff members. Often, the towing community
would “shop” for the answer they were looking for and would attempt to circumvent
previous answers and direction. The Parsons/ VDOT team anticipated this dynamic
and took measures to ensure that the TRIP message was consistent regardless of
who the messenger was. As a result, these types of issues became short lived and
have not been an issue since program deployment.
b) Stakeholder identification/involvement - Early during the process of identifying
potential TRIP activating stakeholders, the Parsons team had meetings with
13
representatives from the Virginia State Police. Those meetings centered around VSP
involvement and addressed other law enforcement entities that may handle CMV
crashes on the interstate. At that time, VSP indicated that no other law enforcement
agency was a primary responder or investigator at CMV crashes. Shortly after
program implementation, a County law enforcement officer found himself as the
Incident Commander at a rollover CMV crash that qualified for TRIP activation.
Because he was not familiar with TRIP, no activation was made, and the crash was
handled by the normal rotational towing procedure. It will be important for any future
TRIP implementations in the Commonwealth to ensure that a complete list of
stakeholders is developed as early as possible.
c) TRIP activation education - In addition to the example above, during the first 12
months of TRIP, several potential TRIP activations were not activated. In the first
year, program managers identified at least 14 crashes, that in hindsight, may or
should have been activated for TRIP but were not. This was attributed to the
“growing pains” element referenced earlier as many first responders either did not
identify the crash as TRIP qualifying or were concerned about making a bad decision.
As a result of a few months of this growing trend, the Parsons and VDOT team met
directly with VSP Division 1 leadership staff and presented a consolidated TRIP
message designed to educate and encourage the use of the TRIP standardized
response tool. Furthermore, an online training module was developed and distributed
for those agencies not normally assigned as primary TRIP stakeholders but may have
occasional exposure. This training was distributed regionwide and will be used for
any future TRIP implementations.
d) Tactical Decision Making - Prior to July 2017, Virginia statutes did not contain a “hold
harmless” law for the towing community. Because of this lack of statutory support,
the towing community practiced “damage free towing” and the idea of quick lane
clearance strategies was not the normal path to clearing CMV crashes. HB 2022 was
passed in July 2017 and coincided perfectly with the WreckMaster training that was
required for the program. TRIP is a quick clearance program first, and a towing and
recovery program second. This statutory change coupled with the philosophy of TRIP
changed the mindset within the entire stakeholder group, but most notably with the
towing community. During outreach and continuing through the life of the program,
the message continues to be about tactical decision making. Can we move it?
Relocate to a safer area? Or, do we have to work the crash where it is? These are
the tactical decisions that must be presented by the towing professional to the
incident commander at each TRIP crash. This was new to the entire stakeholder
group and this type of decision-making approach remains a constant topic as the
TRIP group learns and evolves.
e) TOC TRIP Activation - During the first few months of the TRIP Pilot Program, it became
apparent that the VDOT TOC Supervisory Staff were doing an incredible job during
TRIP activations. They became very adept at disseminating crash information from
the field and imparting good Q&A in their effort to assist with the TRIP process. On a
number of occasions, staff opined about a particular crash qualifying for TRIP, only to
be told that TRIP was not going to be activated. This generated much discussion,
14
and it was recommended and approved for the TOC staff to activate TRIP under very
specific circumstances. To date, this change has paid huge dividends as the TOC
Supervisors have activated TRIP in as little as 2 or 3 minutes from the time of the
crash, thus expediting the towing response. It is recommended that TOC Supervisor
activation authority be part of the Concept of Operations consideration for any future
expansion of TRIP in the Commonwealth.
f) Towing Community Credibility – The TRIP program is also about relationships
between all responding stakeholders. Prior to TRIP, some towing companies did not
enjoy a healthy and respectful relationship with other responding entities. Lack of
training, communication and lack of awareness of the ICS process were identified as
the most likely causes. The level of TRIP training, a change in professional behavior
on scene, and monthly interactions in the formal review meetings have paved the
way for the building of good relationships. In the first 18 months, representatives
from all the stakeholder groups, including senior levels of Division 1 VSP have
complimented the TRIP program and the TRIP towing partners for their high level of
professional performance at the scene of CMV crashes, and their acknowledgement
on the value of TRIP.
g) Monthly After Incident Review meeting- The recurring monthly review meetings have
proven to be an excellent tool in evaluating each TRIP crash to determine program
performance. It has also served to bring the greater towing community and
responding stakeholders together to share experiences and provide lessons learned.
This sharing of experiences is invaluable and has brought the entire TIM stakeholder
community together.
Performance measures After the conclusion of the first twelve months of TRIP, and in partnership with Virginia
Transportation Research Council staff, the Parsons and VDOT team participated in a
detailed performance data review of TRIP. This review compared TRIP to historical crash
data to illustrate the benefits of TRIP as compared to historical rotational towing practices.
The details contained within that report are available for further review and will not be
duplicated here.
In addition to the data collection, comparison and reporting that the Research Council staff
engaged in, the Parsons and VDOT team kept every detail of each TRIP crash. This summary
will serve to provide a brief overview of the data collection specific to the TRIP program.
a) TRIP Activations- December 15, 2017 through June 30, 2019
i) 130 TRIP activations
ii) 94 qualified for incentive bonus payment
iii) 30 did not meet TRIP performance goals and did not qualify for incentive bonus
payment’
iv) 6 TRIP calls were cancelled and received a $600 mobilization incentive
15
In the first 18 and a half months of TRIP, the towing companies achieved an incentive bonus
by meeting performance goals 75% of the time. During a review of just the last six months it
has been noted that the percentage has risen to just over 83% of TRIP crashes resulting in
an incentive bonus being paid. This is an internal trend that the Parsons team has been
tracking and is indicative of the level of performance steadily rising as stakeholders become
more accustomed to the program, and as the TRIP towing community refines their skill set.
The Research Council report highlights the entire life of each crash, and within those details
lies activities by others that have nothing to do with the TRIP effort and performance but still
impact overall clearance times.
Another factor that the Parsons team has monitored in the first 18 months was individual,
overall performance of each of the towing companies participating in TRIP. Their individual
success rate for achieving incentive payments are as follows:
• Anytime Towing 94% success rating
• Bishops Towing 71% success rating
• Bob Alley Towing 80% success rating
• Central City Towing 60% success rating
• Capital Garage 78% success rating
• Coastal Towing 38% success rating
• Dennis Towing 73% success rating
• Eagle Towing 80% success rating
• Glen Allen Towing 80% success rating
• Robinson Towing 81% success rating
• WS Campbell Towing 88% success rating
Overall success rating 75%
As illustrated above, all but one TRIP provider is performing at a very high level and most of
the reasons a TRIP company did not meet program goals was primarily for lane clearance
issues due to the circumstance of the crash. There were several late arrivals and failure to
wear the required safety vest, but those numbers are low when compared to the overall
number of TRIP activations.
Performance reviews are part of the ongoing evaluation of the TRIP program and as we
collect enough data and number of TRIP crashes, we will be performing formal reviews of
each company’s performance and will work with each one to identify:
• Base reason for missed incentive
• Details of the crash scene
• Time of day
• Weather conditions
• Cooperation with Incident Command
• Activities outside of their control
• Comparisons to similar crash circumstances
16
Any company that falls below 70% has been monitored, and a full performance review will
be triggered should improvements not materialize.