alue stream mapping (VSM)can be an extremely powerfultool, combining material pro-

cessing steps with information flow aswell as other important related data.VSM is arguably one of the most pow-erful lean tools for an organizationwanting to plan, implement andimprove on its lean journey. This toolallows users to create a solid imple-mentation plan that will make themost of their available resources.

For a lean journey, think of VSM asthe launch pad to begin identifyingand improving a process family. VSMis about sparking change—declutter-ing the process of the nonessentialactivities that don’t add value butwaste time and resources.

VSM, as it is known today, stemsfrom Toyota Motor Co.’s material andinformation flow diagrams.1, 2 In itsmost basic form, VSM shows the

process steps from order entry todelivery.

The value stream in VSM is thepoint at which value is actually addedto the product or service by changing

the market form or function to meetthe customer’s needs. For example,value adding activities can be thingslike: machining, assembly, welding,drilling, folding, painting and so on. Ifyou are not adding value, you areprobably adding muda, (the Japaneseword for waste).

Pictorial representations of VSM are

easy ways to learn a language thatanyone in your organization canunderstand—a key element whencommunicating with process maps.Building a VSM offers detail that goesbeyond the amount of informationyou can relay with any standard flow-chart.

Value Stream Scope

Understanding the scope of thevalue stream under examination is animportant place to start the VSM task.Think of the scope as the door to doorprocess for a facility level map. Adepartmental or interdepartmentalpractice is considered a process levelmap. When multiple plants, cus-tomers or suppliers are included, anextended level map is created.

Consider an extended level map asthe view of the values stream at 60,000feet, the facility level map at 30,000

64 I JUNE 2006 I www.asq.org

Value Stream Mapping—an Introductionby Tony Manos

V

LEAN LESSONS

A tool that combines material processingsteps, information flow.

Process Family Matrix ExampleFIGURE 1

1. Q

uotin

g2.

Ord

er e

ntry

3. C

redi

t rev

iew

4. P

urch

asin

g5.

Ord

er re

view

6.

Too

l pre

para

tion

7. S

ched

ulin

g8.

Rec

eivi

ng9.

Per

fora

ting

10. L

evel

ing

11. S

hear

ing

12. C

ut to

leng

th13

. Slit

ting

14. R

adiu

s ro

lling

15. P

unch

ing

16. E

mbo

sing

17. P

ress

bre

ak18

. Sta

mpi

ng19

. Out

side

ser

vice

20. P

acka

ging

21. S

hipp

ing

Proc

ess

fam

ily

Name150 80,000 lb/mo X X X X X X X X X X X 1 Coil to coilORM005 80,000 lb/mo X X X X X X X X X X X 1 Coil to coil020 AI GLD 5,000 pcs/mo X X X X X X X X X X X X X 2 Ornamental020 AI Stuco 1,000 pcs/mo X X X X X X X X X X X X X 2 Ornamental73518 400 pcs/mo X X X X X X X X X X X X X X X 3 Fab flatBallast 300,000 lb/mo X X X X X X 4 BallastNordham 100 pcs/yr X X X X X X X 5 Pass through611402401 250 pcs/mo X X X X X X X X X X X X X X X 6 Fab formVT4880 50 pcs/mo X X X X X X X X X X X X X X X 6 Fab formEAW435? 150 pcs/mo X X X X X X X X X X X X X X X X 6 Fab formYNG Filter 25 pcs/mo X X X X X X X X X X X X X X X 6 Fab formGehl 001 150 pcs/mo X X X X X X X X X X X X X X X 6 Fab form509566 700 pcs/mo X X X X X X X X X X X X 7 Coil to sheet to size601 250 pcs/mo X X X X X X X X X X X X X 7 Coil to sheet to size020 AI MF 8,000 pcs/mo X X X X X X X X X X X X 8 Coil to blankNailor 500 pcs/mo X X X X X X X X X X X X X 8 Coil to blank202262 20,000 pcs/mo X X X X X X X X X X X X XStock Plate 250,000 lb/mo X X X X X X X X X X X X 9 Stock plate

Page 2: Value Stream Mapping—an Introduction

feet and the process level map at10,000 feet.

It is best to start at diagramming afacility level map before attempting todraw a process level map or extendedlevel map so you do not optimize onearea and suboptimize another. Thiscolumn will focus on the facility levelmap.

Ready a Team for the Event

The best—and probably easiest—way to create a VSM is to form a crossfunctional team that includes supervi-sory or managerial level membersfrom throughout the organization.

Representatives from departmentslike sales, customer service, schedul-ing, purchasing, operations, inventorycontrol, maintenance, quality andinformation technology can be valu-able contributors to this part of theVSM journey. Even customers or sup-pliers—both internal or external—addunique perspectives.

Be aware of the actual size of this

team and how it can affect decisionmaking and action. A good team sizeis usually between seven and 10members. This size makes it easier formembers to conduct interviews and“walk the flow,” that is, actually visit-ing each of the work areas affected bythe process evaluation and includedin the VSM to see firsthand howthings work or don’t work.

Predictably, the larger the team, themore difficult it may be to manage. Ifthe team has fewer than seven mem-bers, there may not be enough voicesto provide well-rounded input.

Finally, never create a map with ateam of one. You will not get enoughvaluable input or cross functional dia-logue or the results may be biased forone area, person or department.

Kaizen Kick-Off

Once the team is formed, a threeday kaizen (Japanese for “change forthe better”) event, as seen in Table 1,is usually enough time to create thecurrent state and future state maps,along with the draft plan (more detailon these deliverables is highlightedlater). More time may be needed to

QUALITY PROGRESS I JUNE 2006 I 65

Common VSM IconsFIGURE 2

VA

NVA

Value added time

Nonvalue added time

Inventory or queue time

Cycle or process time

Office

Warehouse

Customers/suppliers

Person

Go see

Information flow

Material flow

Kanban?route

HardcopyElectronic

Movement

Push

Truck -deliveries/shipments

Kanbans?arrivingin groups

Withdrawal (move) Kanban

Production (make)Kanban

Supplier (batching) Kanban

Queue/waitingQ

= Number of people/shift

Office/support data box P/T = Processing time Diff = Difficulty (1-5) C/O = Changeover A&C = Accurate & Complete Prior = Prioritize Rel. = Reliability Qty = Quantity per ____

Office

Software

Department/work center

Withdrawal

Supermarket

OXOX

- FIFO -Maximum

(First-in, first-out)

Heijunka(Level loading)

InventoryI

= Number of people/shift

Manufacturing/shop C/T = Cycle time M/T = Machine time C/O = Changeover FPY = First pass yield Rel. = Reliability Qty = Quantity per ____

Kaizen?burst/improvement

Expd = Expediting costs

Supplier/Outside processing Dist = Distance Qty = Quantity FPY = First pass yield OTD = On-time delivery Serv = Service level

Loop

Typical Three-Day VSM Kaizen Event AgendaTABLE 1

Day 1 Day 2 Day 3• Introduce VSM.• Determine process

families.• Walk the flow and

gather information.

• Draw the current statemap.

• Perform lean conceptstraining.

• Create the future statemap.

• Develop the draft plan.

Page 3: Value Stream Mapping—an Introduction

complete the detailed draft plan anddetermine the resources required toimplement the lean ideas. It is impor-tant to designate an individual withprevious experience in VSM to facili-tate this kaizen event.

At the kaizen event, the team mustcomplete four important steps toprogress through VSM:

• Determine the process family.• Draw the current state map.• Determine and draw the future

state map.• Draft a plan to arrive at the future

state.

Process Family

A process family, also known as aproduct family, is a group of productsor services that go through the sameor similar processing steps. To deter-mine your process family, create amatrix similar to the example shownin Figure 1 (p. 64).

• Along the top row, write all theprocess steps your organizationperforms from a 30,000-foot pointof view.

• In the first column, write down

the parts (for example, compo-nents, stock keeping units, fin-ished good items or services) yourorganization makes or provides.

• Place an X in the correspondingbox if the part goes through theprocessing step.

Many cross functional teams skipthis step in the process. A team maydecide this step seems unnecessary.The team may mistakenly believe ithas already identified the valuestreams, or it may consider this steptoo difficult or complicated to per-form.

I must emphasize this point again:Do not skip this step. Building aprocess family matrix can save youmuch time in the future and helpavert headaches down the line. Takingthis step will help everyone under-stand the value streams and wherethey are in the process.

For example, one company claimedit had a very simple process and theteam elected not to perform this step.There were many process steps theteam didn’t consider and steps not inthe main flow, so these parts were not

included in the original matrix. Aftercloser examination, the team thatthought its company had only oneprocess family actually had nine fami-lies.

After completing this vital step,examine the matrix and look for partsthat go through similar or the exactsame processing steps. Search foritems or parts that share about 80% ofthe steps. Look for items or parts thatwould make sense if they were createdalongside each other in a manufactur-ing cell. In other words, consider itemsor parts that share many of the samesteps and procedures that can be creat-ed together—by the same workersusing similar or related steps—moreefficiently in a manufacturing cell.

At this point, the team must selectthe particular process family it willconcentrate on for the current statemap.

Every organization may have a dif-ferent reason for selecting one processfamily over another when decidingwhich map to draw first or whichorder it should map out its valuestreams. Here are some criteria the

66 I JUNE 2006 I www.asq.org

LEAN LESSONS

VSM Current State Map ExampleFIGURE 3

Page 4: Value Stream Mapping—an Introduction

VSM team may use to decide whichprocess family to draw:

• Biggest bang for the buck.• Largest reduction in lead time or

inventory.• Biggest impact to the customer.• Highest probability for success.• Most visible to stakeholders.• New product line.• Volume or quantity.

Plotting the Current State

The current state map should illus-trate how your organization’s process-es perform in today’s work envi-ronment. To create a current state map,collect the data and information bywalking the flow and interviewing thepeople who perform the task. Thereare two main reasons why walking theflow is more beneficial to creating themap than staying seated at your deskin front of the computer:

• The team will have the opportuni-ty to see the entire process andlook for waste.

• Value-adders—the people whoactually perform the work (opera-tors, assemblers, technicians,

etc.)—can answer questions andclarify any misconceptions or pre-conceived notions on how tasksare performed.

From walking the flow, the teamcan collect on a worksheet severaltypes of information, such as:

• Cycle time or processing time.• Changeover time.• Reliability of equipment.• First pass yield.• Quantities.• Number of operators and shifts.• Hardcopy information.• Electronic information.• Inventory levels.• Queue or waiting times.There’s a rule of thumb to help the

team: If the information is in the ball-park then it can be used to get started.For example, if an operator says hermachine breaks down about fourhours every week, the team can markdown 90% for reliability (of equip-ment). If it’s discovered later the actu-al reliability was 91%, that differencewouldn’t have that much of animpact. Ninety percent was badenough for the team to know some

changes were necessary. You do nothave to wait for perfect data (analysisparalysis), but wrong or disinforma-tion needs to be clarified. If you are indoubt about any of the data, then con-sider measuring it to verify.

Pencil And Paper

With the information gathered fromwalking the flow and the ensuingteam discussions, it’s now time tosharpen the pencil and put the lead topaper. Any VSM can be drawn usingsimple symbols or icons, some ofwhich are shown in Figure 2 (p. 65).

Once the information has been col-lected, I recommend drawing the mapon 11 by 17 paper (landscape) usingpencil and—probably a large eraser.Key areas on the map are:

• The upper right corner for cus-tomer information.

• The upper left corner for supplierinformation.

• The top half of the paper for infor-mation flow.

• The bottom half for material (orproduct) flow.

• The gutters on top and bottom to

QUALITY PROGRESS I JUNE 2006 I 67

VSM Future State Map ExampleFIGURE 4

Page 5: Value Stream Mapping—an Introduction

calculate value added and nonval-ue added time.

Calculate the cycle time vs. theinventory time (in days) for the mater-ial and information flow. Every VSMwill look slightly different dependingon the exact process, the author whodrew the map and how it was drawn.See Figure 3 (p. 66) for an example ofa VSM current state map used for ametal fabricating company.

If this is one of your first VSMkaizens, have the experienced facilita-tor draw the map on a large dry-eraseboard and the team members draweach of their own maps on paper. Ifyour team members are more experi-enced, they may gather the data firstand then draw the map. If they areexperts they may just draw the map asthey gather the data. The current statemap is usually completed by the sec-ond day, but it needs to be refined alittle the next morning. Remember,

when drawing your maps, your eraseris your best friend.

Future State Map

Once the current state map is com-plete, the team can set its sights on cre-ating the future state map. Make surethe team members have some basictraining on lean principles to develop arealistic future state map (see Figure 4,p. 67). Different authors will suggestquestions to guide you to a futurestate. Be careful to use the questionsappropriate to your type of business.Here is a short list of questions withcommon elements that may fit mosttypes of business:

• What is the takt time? Takt is theGerman word for the baton a con-ductor uses to control his orches-tra’s speed, beat and timing. Takttime refers to how frequently apart or component must be pro-duced to meet your customers’

demand. The formula is the timeavailable (per shift) divided by thedemand (per shift). For example:

22,000 seconds (time available) ÷ 200 pieces (demand) = 110 seconds/piece.

• Are there bottlenecks or con-straints? From the data collectionduring the kaizen, look at the cycletimes or processing times. If any ofthese are greater than your takttime, you have a candidate for abottleneck or constraint. This maybe causing overproduction wasteor work in process (WIP) in someareas or extra processing time,such as overtime, to meet demand.

• Where can inventory (or queuetime) be reduced or supermarketsused? Look at raw material, WIP,buffer stock, safety stock and fin-ished goods inventories to see

68 I JUNE 2006 I www.asq.org

LEAN LESSONS

Project: Value Stream Mapping

10%

30%60%

PercentagecompleteStatus Goals and objectives Location/facility: Promedica - North Campus Lab

Process family: Chem Line AutomaticValue stream manager: Eileen Allott

Date reviewed:NOTE: Update value stream map

N = Not started 2 20%Reduce lead-time by 50%Reduce inventory by 50%

Improve teamwork

I = In-progress 4 40%C = Closed 4 40%

Total: 10

ID

Stat

us

Loop

Effo

rt

Impa

ct

Prio

rity

Description Start date End date Leader Team Comments

1 C 1 L H 1 5S kaizen in assembly area XX/XX/XX XX/XX/XX Tom Improved safety

2 I 1 L L 3 QCO on press #31 XX/XX/XX XX/XX/XX Joanne Waiting for parts

3 C 1 L M 2 Poka-yoke the assemblyprocess XX/XX/XX XX/XX/XX Bob No errors

4 C 2 L H 1 Create standardize work inassembly XX/XX/XX XX/XX/XX George Reduce cycle time

by three minutes

5 C 2 M L 3 Redux=ce batch size by 50% XX/XX/XX XX/XX/XX Ralph Improved flow, nolate deliveries

6 I 3 M M 2 Eliminate paperwork in orderentry XX/XX/XX XX/XX/XX Jennifer Need help from IT

7 I 3 M H 2 Improve FPY on part family#502 XX/XX/XX XX/XX/XX Homer SSBB leading

project

8 I 3 H L 3 Perform TPM event toimprove reliability of WC #12 XX/XX/XX XX/XX/XX Bart In progress this

week

9 N 4 H M 3 Create assembly cell XX/XX/XX XX/XX/XX Marge Not started

10 N 5 H H 2 Set up kanban/supermarketpull system XX/XX/XX XX/XX/XX John Not started

Example of a VSM PlanFIGURE 5

Page 6: Value Stream Mapping—an Introduction

whether these can be reduced. Doesit make sense to put in a supermar-ket replenishment system? A supermarket is a controlled

inventory system—the down-stream process removes itemsfrom the shelf and the processowners upstream replenish thatamount to the supermarket.The key is to find ways to reduce

inventory in a logical manner.Also look for opportunities forpaperwork to flow and not sitaround, like in batching.

• Where can you improve flow? Is itpossible to put materials into a cellor eliminate materials from stop-ping and waiting? If flow improve-ment isn’t possible, could a first in,first out lane be establishedbetween processes?

• What other improvements arerequired? For instance, does thereliability of equipment need to beimproved? Are the first pass yieldor quality levels acceptable? Dowe need to perform training in 5S(workplace organization)? Do weneed to create a new layout for anarea?

On the map, place a kaizen burst (seeFigure 2, p. 65) around any items tosignal improvement is needed. Itemsmay include low equipment reliabilityor first pass yield, long changeovertimes, large batches, any waste such asoverproduction, motion, transporta-tion, waiting, defects or adjustments,and over or extra processing.

If you are not sure whether thereneeds to be an improvement duringthis timeframe, put a kaizen burstaround it anyway. You can determineif it will be a priority when you puttogether your plan.

From the answers to these and otherquestions related to the process, youwill be able to draw a future statemap that reflects how you want youroperations to be based in six or 12months, as shown in the example inFigure 4 (p. 67).

Estimate the amount of inventoryand queue times based on improve-ments that are achievable. Recalculatethe value added vs. nonvalue addedtime on the sawtooth line.

Draft Plan

Creating (and executing) the draft

plan is the most important part ofVSM. Creating the maps can be anenlightening experience. But if you donot execute the plan, you have justcreated more muda.

During a typical VSM event, it ispossible to create the draft plan basedon the information from the futurestate map. The plan will need furtherrefinement—especially in determin-ing resources required, such as time,people and budgets. A good plan, asshown in the example in Figure 5, willinclude the description of the project,name of the project leader, possibleteam members, a schedule (or Ganttchart) of events and deliverables, anestimate of costs and the impact, goalsor benefits.

VSM can be an effective tool tobuild improvements and efficienciesfor any organization. For completingthis part of the lean journey, the pay-offs can be immense for any organiza-tion. VSM requires a dedicated teamready to ask difficult questions andthink beyond the current state—and ateam not afraid to admit error and usethat eraser a few times along the way.

REFERENCES

1. Mike Rother, John Shook and Jim Womack,Learning to See, Mellon’s Books, 1999.

2. Jeffrey Liker, The Toyota Way, McGraw-Hill,2004.

BIBLIOGRAPHY

Keyte, Beau, and Drew Locher, TheComplete Lean Enterprise: Value StreamMapping for Administrative and OfficeProcesses, Productivity Press, 2004.

ANTHONY MANOS is a catalyst withProfero, Inc., a lean consulting, training andimplementation firm. He is a senior member ofASQ, an instructor for ASQ’s course on LeanEnterprise and Kaizen and is the current chairof the Lean Enterprise Forum. Tony has anMBA from the University of Illinois-Chicago.

QUALITY PROGRESS I JUNE 2006 I 69

commentPlease

If you would like to comment on

this article, please post your remarks

on the Quality Progress Discussion

Board at www.asq.org, or e-mail

them to [email protected].

backbasics

QP Goes

Do you have a quality tool

or concept to share? Many

of our readers say they need

inexpensive, concise infor-

mation on the fundamental

concepts and basic tools of

quality to share with co-

workers who don’t have

backgrounds in quality.

Quality Progress is seeking

submissions to its “Back

to Basics” column, published

every other month. The

columns are limited to one

printed page or 800 words.

Submissions are reviewed

by members of the QP

Editorial Review Board.

Send questions or submis-

sions to [email protected].

to