74

Trimscaac Rev4 Signed

Embed Size (px)

Citation preview

  • 8/12/2019 Trimscaac Rev4 Signed

    1/74

  • 8/12/2019 Trimscaac Rev4 Signed

    2/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 2 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Content

    PageInstruction ............................................................................................................................................ 3Introduction .......................................................................................................................................... 4Scope ................................................................................................................................................... 4Normative references .......................................................................................................................... 5Definitions and abbreviations .............................................................................................................. 7

    1.1 Definitions......................................................................................................................... 71.2 Abbreviations ................................................................................................................... 8

    Environmental ...................................................................................................................................... 91.3 General ............................................................................................................................. 9

    Line survey .......................................................................................................................................... 91.4 Plans and profiles ............................................................................................................. 9

    1.5 Setting-out of route ........................................................................................................... 91.6 Survey beacons at bend points ........................................................................................ 91.7 Survey by the Contractor................................................................................................. 91.8 Pegging by the Contractor............................................................................................. 10

    Foundations ....................................................................................................................................... 111.9 Design and Geotechnical ............................................................................................... 111.10 Foundation systems ....................................................................................................... 161.11 Guy anchors ................................................................................................................... 201.12 Concrete and grouts ....................................................................................................... 221.13 Construction ................................................................................................................... 241.14 Concrete foundations ..................................................................................................... 261.15 Anchor block (deadman), Pile and Rock Anchor testing ............................................... 33

    Towers ............................................................................................................................................... 39

    1.16 Tower Design ................................................................................................................. 391.17 Tower Manufacturing ..................................................................................................... 391.18 Guy ropes and guy attachments .................................................................................... 451.19 Tower erection ............................................................................................................... 461.20 Tower Dressing .............................................................................................................. 48

    Stringing ............................................................................................................................................. 481.21 Material supply ............................................................................................................... 481.22 Installation of phase and earth conductors .................................................................... 491.23 Stringing of OPGW ......................................................................................................... 57

    Insulators: Handling, Storage, Transport and Installation Practice ................................................... 571.24 Receiving........................................................................................................................ 571.25 Storage ........................................................................................................................... 571.26 Loading and off-loading .................................................................................................. 58

    1.27 Transport to site ............................................................................................................. 581.28 Insulator Handling .......................................................................................................... 581.29 Installation ...................................................................................................................... 581.30 Post Installation .............................................................................................................. 591.31 Visual Inspection of Insulators ....................................................................................... 59

    Marking, labeling and packaging ....................................................................................................... 60Spares................................................................................................................................................ 60Annex B - Details of bolt tolerances. ................................................................................................. 61Annexure C: Details of safety step bolt. ............................................................................................ 62Annex D: Guideline for the compilation of tower erectionsafe work procedures / method statements....................................................................................... 63

  • 8/12/2019 Trimscaac Rev4 Signed

    3/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 3 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Instruction

    This Technical Instruction supersedes TRMSCAAC1 Rev 3 and is to be used with immediate effect.

    The next step will be the creation of an Eskom Standard, via the Eskom SCOT process.

    Applicability

    This Technical Instruction pertains to all personnel designing and/or constructing Transmission powerlinesfor Eskom.

  • 8/12/2019 Trimscaac Rev4 Signed

    4/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 4 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Development team

    RIAZ VAJETH TECHNICAL AND STRATEGIC GUIDANCE

    DAN DUKHAN DEVELOPMENT TEAM LEADER

    GEOFFREY SMALL SHEQ MANAGER

    BERTIE JACOBS TECHNICAL AND STRATEGIC GUIDANCE

    VIVENDHRA NAIDOO TECHNICAL AND STRATEGIC GUIDANCE

    NEELS HENDERSON LINE HARDWARE SPECIALIST

    BHARAT HARIDASS TECHNICAL AND STRATEGIC GUIDANCE

    WILLEM COMBRINCK FOUNDATION SPECIALIST

    SIYABONGA DUBAZANA FOUNDATION ENGINEER

    PIERRE MARAIS TAP CIVIL , STRUCTURAL ANDGEOTECHNICAL CONSULTANT

    CHRIS SEMMELINK TAP CIVIL CONSULTANT

    Introduction

    This document provides extensive requirements for the design and detailed construction environment andincludes, but is not limited to safety parameters. This document must be read in conjunction with all

    applicable normative references as listed in section 2.

    Keywords

    Powerlines, servitudes, insulators, hardware, conductor, corona, geotechnical, anticlimbs, tower erection

  • 8/12/2019 Trimscaac Rev4 Signed

    5/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 5 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Scope

    This specification details the requirements for the design, detailing, fabrication, testing, supply, delivery anderection of powerline towers, poles and foundations, together with the erection of all conductors andassociated line hardware and fittings.

    Normative references

    The following documents are to be read in conjunction with this specification. In cases of conflict, theprovisions of this specification shall take precedence. Unless otherwise stated, the latest revision, editionand amendments shall apply.

    International document(s):

    ASCE Manual No. 52 Guide for design of steel transmission towers

    BS 183:1972 Specification for general purpose galvanised steel wire strand.

    BS 443:1982 Specification for testing zinc coatings on steel wire and for qualityrequirements.

    BS 970 Specification for wrought steels for mechanical and allied engineeringpurposes.

    BS EN 287-1:2004 Approval testing of welders for fusion welding. Part 1: Essential variables,range of approval examination and testing, acceptance requirements, re-tests, period of validity. Annexes on steel groups, welders test certificate,procedure specification and job knowledge.

    BS EN 288-3:1992 Specification and approval of welding procedures for metallic materials.

    Part 3: Welding procedure tests for the arc welding of steels.

    South African National document(s):

    OHSACT Occupational Health and Safety Act , Act 85 of 1993 and regulations

    ECCS Recommendations for angles in lattice transmission towers, No. 39.

    SANS 282 Bending dimensions of bars for concrete reinforcement.

    DIN EN ISO 898-1:1999 Mechanical properties of fasteners made of carbon steel and alloy steel.Part 1: Bolts, screws and studs

    SANS 471:1971 Portland cement (ordinary, rapid-hardening and sulphate-resisting).

    SANS 626:1971 Portland blast furnace cement.

    SANS 675:1997 Zinc-coated fencing wire.

    SANS 121:2011/

    ISO 1461

    Hot dip galvanised coatings on fabricated iron and steel articles-specifications

    and test methods

    SANS 831:1971 Portland cement 15 (ordinary and rapid hardening).

  • 8/12/2019 Trimscaac Rev4 Signed

    6/74

  • 8/12/2019 Trimscaac Rev4 Signed

    7/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 7 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Definitions and abbreviations

    1.1 Definitions

    Employer: The party for whom the worksare to be executed and in this specification means Eskomand where applicable, includes Eskoms successor in title but not, except with the writtencontent of the Contractor, any assignee of Eskom.

    Contractor: The party appointed by the Employerto Provide the Works.

    DesignEngineer:

    The person appointed by the Employer from time to time to act in the capacity andnotified, by name and in writing by the Employer to the Contractor, as required in TheNEC Engineering and Construction Contract. He/She shall be ECSA accredited.

    EskomSiteRepresentative:

    The person appointed by the Employer from time to time to act in the capacity andnotified, by name and in writing by the Employer to the Contractor, as required in TheNEC Engineering and Construction Contract.

    ProjectManager

    The appointed person responsible for co-ordinating all aspects of a project. Allcommunication must be channelled via the Project Manager.

    Batch:A specified quantity of samples, components or members.

    TransverseFace:

    See diagram below:

  • 8/12/2019 Trimscaac Rev4 Signed

    8/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 8 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.2 Abbreviations

    EIA: Environmental Impact Assessment

    EMP: Environmental Management Plan

    OHSACT Occupational Health and Safety Act , Act 85 of 1993 including regulations

    SHEQ: Safety, Health, Environmental and Quality

  • 8/12/2019 Trimscaac Rev4 Signed

    9/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 9 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Environmental

    1.3 General

    This section refers to Eskoms SHEQ policy. The SHEQ policy takes precedence. The environmentalmanagement during the construction activities is to ensure that the EIA recommendations, thestatutory EIA Environmental Authorisation Conditions, the EMP, the landowners Special Conditionsand all relevant environmental legislation are implemented, by monitoring the site works and regularreporting.

    All activities relevant to the establishment of Transmission line construction and designimplementation should be undertaken in accordance with the Eskom SHEQ Policy.

    Line survey

    1.4 Plans and profiles

    The route of the line will be surveyed by the Employer, who will provide all necessary route plansand templated profile drawings, on which, tower types and the position thereof will be indicated.

    Position of aircraft warning spheres, bird guards and bird flights diverters will be indicated on theconstruction profiles.

    1.5 Setting-out of routeThe line route will be set-out by the Employerprior to the commencement of construction. Bendpositions are to be demarcated with iron pegs, set in concrete and clearly labelled as per approvedprofile. The diameter of the iron pegs must not be less than 16 mm with 20 mm diameter preferredin rural areas. To ensure visibility of bend positions a cairn of stones must be placed around thepeg and white washed. The route must further be demarcated by online reference stakes at least1,2 m high and at approximately 2 km intervals and should in most cases be inter-visible.

    1.6 Survey beacons at bend points

    At bend positions, the original iron pegs indicating the centre line of the transmission line route are

    on no account to be disturbed or removed, as these are required for servitude registrationpurposes. The Contractoris to, during foundation installation, concrete the bend pegs in position.

    1.7 Survey by the Contractor

    a) The pegging of tower positions, and where necessary, the establishing of self-supporting towerleg extensions and guy anchor positions for guy towers, shall be carried out by professional landsurveyors or registered surveyors.

    b) The Contractor, on completion of each 20km or suitable section of the line, is to supply recordsof all distances measured for each individual tower position. These should agree with the profiles,and any discrepancy reported immediately to the Design Engineer.

  • 8/12/2019 Trimscaac Rev4 Signed

    10/74

  • 8/12/2019 Trimscaac Rev4 Signed

    11/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 11 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    Foundations

    1.9 Design andGeotechnical

    1.9.1 Foundation design loads

    All foundations shall be designed to the ultimate load as per the relevant line/project specification.

    1.9.2 Soil and rock classification

    a) Hard Rock: hard to very hard solid or moderately fractured continuous rock, and includinghard to very hard rock of any other description which meets the strength requirements ofclause 6.1.3

    b) Soft Rock: weathered or decomposed very soft to soft continuous rock, and including rockof any other description which does not satisfy the requirements for classification underclause 6.1.3.

    c) Type 1 soils: competent soil with equal or better consistency (strength or toughness) thanone would encounter in stiff cohesive soils or dense cohesionless soils above the watertable. This soil shall have a broad balanced texture (constituent particle sizes) with highaverage combinations of undrained shear strength and internal angle of friction, withminimum values of 80kN/m and 30respectively. Th e minimum dry specific weight shall notbe less than 1800 kg/m.

    d) Type 2 soils: a less competent soil than type "1", with equal or less consistency than onewould encounter in firm to stiff cohesive soils, or dry poorly graded medium dense to densecohesionless soils above the water table. This soil has a dominating texture of clay or sandand silt and with minimum undrained shear strength of 40kN/m. The minimum dry specificweight shall not be less than 1600kg/m.

    e) Type 3 soils: dry loose cohesionless soil or very soft to soft cohesive soil. If pebbles andboulders are encountered it must be disposed of as per clause 6.4.2.h, then use importedbackfill as specified in clause 6.4.2.i.

    f) Type 4 soils: submerged cohesionless and cohesive soils. This includes all soils belowthe permanent water table, including soils below a re-occurring perched water table, or

    permeable soils in low-lying areas subjected to confirm seasonal flooding.

  • 8/12/2019 Trimscaac Rev4 Signed

    12/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 12 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.9.3 Geotechnical design parameters

    a) For rock

    Parameters Soft rock Hard rock

    Maximum toe bearingpressure at foundationdepth

    800 kPa. 2 000 kPa.

    Rock Frustum angle 37 45

    Interface friction-concrete to rock

    140 kN/m 350 kN/m

    SANS 10161descriptions

    (R1-R2) Indentations of 1-3mm

    shows in the specimen with firmblows of the geological pick point.Can be just be scraped with a knife.

    (R3-R4)Handheld specimen can

    be broken with hammer end.Cannot be scraped or peeled witha knife.

    b) Soil types 1 and 2

    Parameters Type 1 Type 2

    Maximum soilbearing pressure

    300 kPa 150 kPa

    Maximum toe bearing

    pressure

    375 kPa 200 kPa

    Frustum angle forsuspension towers

    30 20

    Frustum angle forstrain towers

    25 15

    Undrained shearstrength (Interfacefriction concrete tosoil)

    80 kN/m 40 kN/m

    Density of backfill 1800kg/m3 1600kg/m3

    Density of reinforcedconcrete

    2400 kg/m3 2400 kg/m3

  • 8/12/2019 Trimscaac Rev4 Signed

    13/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 13 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    SANS 10161descriptions

    COHESIVE SOIL (S4-S5)Slight indentation produced bypushing Geologist pick point into

    the soil. Cannot be moulded byfingers.Hand pick required for excavation.COHESIONLESS SOlLVery high resistance to penetrationof sharp end of geological pick.Requires many blows of hand pickfor excavation.

    COHESIVE SOlL (S3)Sharp end of Geologist pick can bepushed in up to 10mm. Can just be

    penetrated with an ordinary spade.

    COHESIONLESS SOILConsiderable resistance topenetration by sharp end ofgeological pick. Considerableresistance to shovelling.

    c) Soil types 3 and 4

    Parameters Type 3 Type 4Maximum soilbearingpressure

    100 kPa 50 kPa

    Maximum toebearingpressure

    125 kPa 65 kPa

    Frustum anglefor suspensiontowers

    0 0

    Frustum angle

    for strain towers

    0 0

    Density ofbackfill

    1400kg/m3 1000kg/m3

    Density ofreinforcedconcrete

    2400 kg/m3 1400 kg/m3

    SANS 10161descriptions

    COHESIVE SOlL (S2-S1)Sharp end of Geologist pick can bepushed in 30 to 40 mm. Moulded byfingers with some pressureNo resistance to shovelling.

    COHESIONLESS SOlLSmall resistance to penetration bysharp end of geological pick.

    Type 4 is a condition i.e. waterloggedor submerged foundations conditions.This includes all soils below thepermanent water table, including soilsbelow a reoccurring perched watertable, or permeable soils in low-lyingareas subjected to confirmedseasonal flooding.

    NOTE: For maximum soil bearing pressure and maximum toe bearing pressure, use the tabledpressure or 80% of the ultimate tested bearing pressure determined from appropriate tests.

  • 8/12/2019 Trimscaac Rev4 Signed

    14/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 14 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.9.4 Soil /rock - foundation nomination

    a) The Contractor shall be responsible for the soil/rock investigation and shall delegate this work toan experienced registered professional duly authorised to do so on behalf of the Contractorand,who shall accept the responsibility for all the foundation test pit investigations and the foundationtype nominations for the corresponding soil profiles.The signed foundation type nomination list andsoil profile log sheets shall be submitted to theDesign Engineerfor acceptance. All soil profilingshall be done in the presence of the Eskom site representative.

    b) Unless otherwise indicated in the Works Information, the minimum soil investigation requirementshall be the excavation of a test pit next to each foundation position, to allow for the in-situinspection of the soil, recording thereof on a soil profile log sheet and the soil type assessment.Soil profiling standards shall be in accordance with SANS 10161. The test pits shall be excavatedoutside the zone of influence of the appropriate foundation, and shall be taken down to a depthequal to the lesser of the depth of the foundation system to be constructed or 3m. In addition,appropriate soils tests as described in clause 6.1.5 shall be carried out where further clarification isrequired for the correct identification of a soil category. The soil/ rock foundation type nominationsbased on the aforementioned procedures shall take place well in advance of actual foundationinstallation, so as not to disrupt construction activities, and to allow for the possibility of having toconduct laboratory tests on suspect soils and/or rocks.

    c) Due to the fact that combinations of two or more of the soil or rock classifications as described inclause 6.1.2 and 6.1.3 could occur at any one foundation position, including rock boulders in a soilmatrix, the soil or rock nomination in terms of one of the six classifications in clause 6.1.2 shallthen be conservatively based on the load transfer capability in terms of clause 6.1.3 of the soiland/or rock encountered over the depth of influence of the approved foundation system. Forexample, a combination of a type 1 soil and soft rock over the depth of influence of an approvedtype 1 soil foundation design shall be nominated as a type 1 soil condition and the approvedtype1 soil foundation system installed. By following this procedure, the soil or rock nomination ateach foundation position shall be one of the six classifications as described in clause 6.1.1 andthis shall in turn define which system design is to be installed.

    d) The test pit shall be suitably backfilled immediately after the relevant inspections and tests havebeen completed.

    e) Should the foundation conditions at the actual foundation location be found to differ from thoseidentified at the corresponding test pit, the Contractor shall immediately inform the Eskom SiteRepresentative and a revised assessment made. The acceptance by the Eskom SiteRepresentative of the soil type foundation nomination shall not relieve the Contractor of thisresponsibility.

    f) Where site conditions, such as difficult access or environmentally sensitive areas, water courses,slopes with erodible dispersive soils etc., an additional more detail investigation of the area shallbe done by the Contractor and acceptance of the proposed procedures to be obtained from LineEngineering.

    1.9.5 Soil and rock tests

    a) In addition to the minimum soil/rock investigation requirements, tests shall be carried out by theContractor, if so required by the Design Engineer to confirm a soil or rock type classificationand shall be conducted in accordance with accepted, good geotechnical engineering practices,and shall include but not be limited to the following:

    i) Standard penetration tests or Dutch Cone penetrometer tests.

    ii) Visual classification of soilsiii) Determination of present and probable water table level.

  • 8/12/2019 Trimscaac Rev4 Signed

    15/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 15 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    iv) Laboratory and/or site tests to determine soil friction angles and cohesion values.v) Laboratory tests to determine stress-strain modules of soils and rock.vi) Laboratory and/or site tests to determine soil unit weights.vii) Laboratory and/or on site tests to determine the soil texture i.e. whether the soil is

    predominately clay, silt, sand or gravel.viii)Continuous rock cores with recovery values and drilling times.

    The standard penetration tests and recovery of soil samples shall be obtained in each soil strataencountered or at 1.5m intervals whichever is less. Rock cores shall extend a minimum of 3.5minto sound rock.

    b) The soil/rock investigation shall be conducted to recognised standards to ensure that allencountered soil and/or rock strata are identified and delineated by area along the line route. Itshall be the Contractor's responsibility to perform adequate soil/rock investigations to thesatisfaction of the Eskom Site Representativeto determine the soil/rock suitability at each site.

    1.9.6 Drilled foundations, geotechnical design parameters

    Soil /rock design parameters for final design and construction of drilled foundations shall be determinedby pile tests, foundation tests or comprehensive soil /rock investigations as described in clause 6.1.5.The Contractoris fully responsible for the final foundation designs. As a guide only, "average"parameters are set out below.

    a) In type 1 or type 2 soils, a skin friction with a maximum of 80 kPa in a type 1 soil, and amaximum of 40 kPa in a type 2 soil, may be used. The skin friction values that are used shallnot exceed 80% of the ultimate friction determined from appropriate soil tests in accordance withclause 6.1.5.

    b) In soft rock, when non-shrink grout or concrete is utilised, a maximum skin friction of 135kPa maybe used in all piles or anchors. A 37frustum sha ll be used to check anchor group pull outresistance. The skin friction value shall not exceed 80% of the ultimate friction determined fromappropriate rock tests in accordance with clause 6.1.5.

    c) In hard rock, when non-shrink grout or concrete is utilised, a maximum skin friction of 350kPamay be used in anchors with a maximum diameter of 150mm. A 45frustum shall be used tocheck anchor group pull out resistance. The skin friction value shall not exceed 80% of theultimate friction determined from appropriate rock tests in accordance with clause 6.1.5.

    d) The depth of any pile(s) in a pile group in soils shall be so calculated to resist the uplift force onthe pile or pile group. For a type 1 soil, a 30 frustum for suspension towers, and a 25frustumfor angle strain towers may be assumed. Similarly for a type 2 soil, a 20frustum for suspension

    towers, and a 15frustum for angle strain towers m ay be assumed. Assumed material densitiesto be as per clause 6.1.2.

    e) No horizontal shear resistance on the piles or pile cap shall be assumed for re-compactedexcavated soil. The lateral resistance of undisturbed soil shall be ignored in the top 300mm fromground line, and taken as the lesser of 100kPa or 80% of the permissible bearing determinedfrom appropriate tests from 300mm below ground level to the bottom of the pile cap. If the pilecap is not capable of restraining the entire horizontal base shear, the piles and pile cap shall bedesigned to resist the shears and moments introduced from the pile cap to the individual piles. Asoil bearing pressure of 200kPa in type 1 or 100kPa in type 2 soil shall be allowed under thepile cap. End bearing components for compressive loads shall not be considered in soilreplacement type piles with a diameter less than 750mm.

  • 8/12/2019 Trimscaac Rev4 Signed

    16/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 16 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.10 Foundation systems

    1.10.1 General

    a) Before foundation excavation commences the Contractorshall submit to the Design Engineer,drawings and relevant design calculations of all the proposed foundations intended for use.Acceptance by theDesign Engineerdoes not relieve the Contractor of his responsibility for theadequacy of the design, dimensions and details. The Contractorshall be fully responsible for hisdesigns and their satisfactory performance in service. A registered Civil Engineer or CivilEngineering Technologist, duly authorised to do so on behalf of the Contractor, shall acceptresponsibility for all foundation designs and drawings submitted to the Design Engineer, andshall sign all drawings accordingly. If the Employer provides foundation designs and/ordrawings, a registered Civil Engineer or Civil Engineering Technologist, acting on behalf of theContractor, shall check and assume responsibility for such designs and/or drawings. Allfoundation design loads are to be shown on the relevant foundation drawing.

    b) No foundation shall be constructed without the Design Engineer acceptance. All drawingrevisions shall be submitted to the Design Engineer before being issued for constructionpurposes.

    c) Only with the specific permission of theDesign Engineer,may more than one design per soil orrock type of any foundation system for a tower type be utilised.

    d) A ground slope of up to and including 12 degrees to the horizontal in any direction shall beassumed at all foundation positions for design purposes.

    1.10.2 Pad and pier foundations for self-supporting towers

    a) The foundations shall be designed to withstand, with less than 20 mm of differential settlement ordisplacement, the maximum foundation reactions resulting from the withstand loadings stated inthe Works Information, with the dead weight of the tower included at unity factor of safety.

    b) The foundations shall be designed for the maximum combinations of compression, uplift andhorizontal shear forces. In addition, a 650 mm maximum projection of the pier and stub aboveground level shall be incorporated in the design. The stub only is to be encased in concrete; thetower steel above the diagonal members is not to be encased.

    c) All concrete subjected to tension, where the permissible tensile stress is exceeded, shall beadequately reinforced with deformed reinforcing steel bars. The design shall be in accordancewith the requirements of SANS 10100. The maximum permissible tensile stress in the concreteshall be 1.75 MPa. Piers shall be reinforced for their full length with the reinforcing properlyanchored in the pad. The minimum number of longitudinal bars provided in a pier shall be four 12mm diameter bars with a minimum yield stress of 450 MPa. The links shall be 8mm diametermild steel bars at a maximum spacing equal to the smallest lateral dimension of the section, less100 mm.

    d) Pads designed with a full 45core may be utilised. All faces of such a core where the permissibletensile stress in the concrete is exceeded are to be adequately reinforced to prevent thedevelopment of tension cracks.

    e) The foundation shall be designed to resist the vertical compression load at the bottom of thefoundation. The foundation shall be checked to ensure that "punch-through" of the stubs shall notoccur. The maximum soil bearing pressure allowed due to the vertical compressive load, plus themass of the foundation, less the mass of the soil displaced by the foundation, shall not exceed thevalues specified in clause 6.1.3 for the soil type involved.

  • 8/12/2019 Trimscaac Rev4 Signed

    17/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 17 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    f) In addition to the vertical compression and tension loadings, the foundations shall be designed forthe overturning moment and resultant soil toe pressure due to the remaining horizontal baseshears applied at the top of the foundation, including the maximum foundation projection. Themaximum soil toe pressure shall not exceed the value specified in clause 6.1.3 for the soil typeinvolved.

    g) The foundation shall be designed to resist the vertical uplift load, by means of the mass of thefoundation plus the nett mass of the soil frustum acting from the bottom of the foundation base.Bracing shears may be neglected in the case of suspension towers, but shall be considered in thepier design in the case of strain towers.

    h) The structural steelwork shall be firmly keyed into the concrete by means of adhesion betweensteel and concrete and bolted-on cleats. The load shall be transferred by means of bolted-oncleats. The cleats shall be so positioned on the structural steel member, so as to limit punchingshear in the concrete due to both tension and compression load cases. When calculating thenumber and size of cleats required the maximum contact pressure between cleat and concreteshall not exceed 10MPa. The number of cleat bolts required shall be calculated in accordancewith SANS 10162. Galvanising of stubs and cleats shall be in accordance with SANS 121:2011/ ISO 1461.

    i) The least lateral dimensiond of a pier shall not be less than the greater of 400mm or L/5, where'L' is the lesser of the vertical height measured from top of pad level to the top of the concretepier, or the vertical height measured from founding level to the top of the concrete pier when apad is not utilised. For circular pier sections,d represents the diameter and for square orrectangular sectionsd represents the length of the shortest side.

    1.10.3 Pad and plinth foundations for guyed tower centre supports

    a) The foundations shall be designed to withstand, with less than 20 mm of settlement, themaximum foundation reactions resulting from the loadings stated in the specification, with theultimate load.

    b) The minimum depth of the mast support foundation/s shall be 750 mm in type 1 and type 2 soil,and 1000 mm in type 3 and type 4 soil. The soil at the bottom of the foundation shall resist allstresses resulting from the vertical compressive loads and toe pressures due to horizontal shears.The mass of the foundation less the mass of the soil displaced by the foundation shall be includedin the vertical load applied. The maximum soil toe pressure shall not exceed the values specifiedin clause 6.1.3.

    c) The foundations shall be designed for the maximum combinations of compression and horizontalshear forces. In addition, a 1100mm projection of the plinth above ground level in the case ofcross rope suspension type towers, and a 650mm projection in the case of guyed V type towers,shall be incorporated in the design to allow for leg extension increments.

    d) All concrete subjected to a tension where the permissible tensile stress is exceeded, shall beadequately reinforced with steel reinforcing bars in compliance with SANS 920. The design shallbe in accordance with the requirements of SANS 10100.

    e) Anchoring of the tower bases of guyed V towers shall be by means of anchor bolts. Themaximum shear on anchor bolts shall be 0,6 times the ultimate tensile strength of the bolt. If theanchor bolts shall resist compression loads from the base plate, the compression load shall be

    resisted by mechanical anchorage, and not by adhesion between steel and concrete, unlessdeformed bars are utilised for anchor bolts.

  • 8/12/2019 Trimscaac Rev4 Signed

    18/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 18 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.10.4 Drilled foundations

    The Contractor shall have equipment for, and personnel knowledgeable and experienced in, theevaluation and construction of this type of foundation.

    a) Generali) The Contractor shall allow for the testing of two separate piles/anchors in each of the soil or

    rock types for which they have been designed. Pile/anchor tests as described in clause 6.1.6if so required by theProject Design Engineer,are to be successfully tested to theProjectDesign Engineerssatisfaction prior to construction of cast-in-situ pile/anchor foundations.

    ii) All design clauses in 6.1.3relating to drilled concrete foundations shall apply.iii) Piles shall be designed to limit ground line vertical deflection, at maximum loadings, to less

    than 12mm.iv) The minimum centre to centre spacing of any two piles in a group of piles shall be four pile

    diameters of the pile with the larger diameter, unless otherwise accepted by the DesignEngineer.

    v) The structural steelwork shall be firmly keyed into the concrete by means of bolted-on cleats. Theadhesion between steel and concrete shall not be relied upon to transmit the load to thefoundation. The cleats shall be so positioned on the structural steel member, so as to limitpunching shear in the concrete due to both tension and compression load cases. Whencalculating the number and size of cleats required the maximum contact pressure between cleatand concrete shall not exceed 10 MPa. The number of cleat bolts required shall be calculated inaccordance with SANS 10162-1:2005.

    b) Single cast-in-situ piles

    Foundations utilising one cast-in-situ concrete pile will be considered by the Design Engineer ifthe following criteria are met:

    i) If a pile cap is not utilised, the pile shall have a minimum diameter of 350 mm in order that thestructural steel attachment of the tower can be accommodated without conflict with thereinforcing steel. The option of raking with the correct set to reduce shear may be consideredshould a pile cap be utilised, the minimum pile diameter shall be 300 mm.

    ii) The pile shall be constructed vertically, and shall be designed for the maximum combinationsof uplift and compression loadings, and the total horizontal base shears associated with thevertical loadings. Total horizontal shear applied at the top of the foundation, including the 650mm maximum projection above ground level, is to be included. Lateral load design bendingmoments shall be calculated taking into account possible plastic soil deformation. Raked pileswill be accepted upon submission of all method statements and review of calculations anddrawings by the Design Engineer for acceptance.

    iii) The pile shall be designed to ensure that it acts as a rigid pile. Horizontal deflection at the topof the projected pile under ultimate loading shall be limited to 5mm.

    iv) Single in line guy anchor piles shall only be designed for type 1 soil and with an additional loadfactor of 1.2 and meet all the requirements of clauses 6.2.5 a) and 6.1.3 .

    v) The lateral pressure on the leading face of the cap in the rock, as well as the friction on thetwo side faces in the rock shall be 135 kPa for soft rock and 300 kPa for hard rock or 80% ofthe permissible value determined from appropriate tests.

    vi) Piles shall be tested as to clauses 6.6

    c) Multiple cast-in-situ piles

    Foundations utilising multiple cast-in-situ piles of a minimum diameter of 300mm, will be consideredby theDesign Engineerif the following criteria are met:

    i) A minimum of two vertical piles per leg are used, connected to the structural steelwork bymeans of a reinforced concrete pile cap. Raked piles will be accepted in accordance with

  • 8/12/2019 Trimscaac Rev4 Signed

    19/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 19 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    6.2.5 a) x) upon submission of all method statements and review of calculations anddrawings by Design Engineerfor acceptance.

    ii) The piles and pile cap shall be designed for the maximum combinations of uplift andcompression loadings, and the total horizontal base shears associated with the verticalloadings, including leg shear. Lateral load design bending moments shall be calculatedtaking into account possible plastic soil deformation.

    iii) The piles shall be reinforced for their entire lengths in order to resist the applied axial andbending forces and sufficient reinforcing hoops shall be provided to support the verticalreinforcing. The reinforcement shall extend into the pile cap sufficiently, and shall besuitably anchored to ensure full utilisation of reinforcement from pile cap to pile. The pilecap shall be reinforced to withstand the shear and bending forces applied by the structuralsteelwork.

    iv) The minimum pile centre to centre spacing shall be three times the pile diameters.Allowance shall be made for the smaller group effect when two or more piles, with a centreto centre spacing of less than three pile diameters, are used in a group.

    d) Rock anchors

    Foundations utilising grouted rock anchors will be considered by theDesign Engineerif thefollowing criteria are met:

    i) A minimum of four vertical rock anchors shall be used and connected to the structuralsteelwork by means of a reinforced concrete pile/anchor cap. Inclined rock anchors shall notbe used without theDesign Engineersprior acceptance.

    ii) The rock anchors shall be designed to resist the full axial forces imparted by the maximumcombinations of uplift and compression loadings, and additional axial loads due to the totalhorizontal base shear. The design shall incorporate a 650mm maximum projection of the

    foundation above ground level. The rock anchors shall not carry any horizontal shear load.iii) The pile/anchor cap shall be designed to resist the total horizontal base shear. No horizontalshear resistance shall be assumed for re-compacted excavated soil. The base of the pilecap shall be extended to a minimum of 150mm below the top of sound rock over its full areairrespective of horizontal shear resistance requirements.

    iv) The rock anchors shall be reinforced for their entire length in order to resist the applied axialforces and the reinforcing extends into the pile cap sufficiently and is suitably anchored toensure full utilisation of reinforcement from pile/anchor cap to anchor. The cap shall bereinforced to withstand the shear and bending forces applied by the structural steelwork.The rock anchor reinforcing steel shall be debonded, by a method accepted by the DesignEngineerfor a length of 100mm above and 300mm below the pile cap base.

    v) Rock anchors shall only be installed in hard rock, or sound competent soft rock. Proposals toutilise rock anchors in materials such as shale etc. shall be specifically accepted by the

    Design Engineerafter a pile/anchor test, as described in clause 6.6.1, has been conducted.An additional test to verify that the pile cap will resist the entire horizontal base shear mayalso be required if so specified by the Design Engineer. The lateral pressure on the leadingface of the cap in the rock, as well as the friction on the two side faces in the rock shall be135 kPa for soft rock and 300 kPa for hard rock or 80% of the permissible value determinedfrom appropriate tests.

    vi) The use of grout mixes, including proprietary mixes, shall be accepted by the DesignEngineer prior to the use of such. Documented evidence of use in other similarapplications, which have been accepted by a recognised authority, shall be submitted asproof of suitability. In-situ rock anchor testing shall be carried out as specified in clause6.6.1.

    vii) Rock anchors with diameter smaller than 85mm shall only be installed in sound competentrock where the holes have uniform diameters, straight sides and special grouts are used

    (epoxy or similar with 50 MPa minimum strength) as approved by the Design Engineer. In-situ rock anchor testing shall be carried out as specified in clause 6.6.1.

  • 8/12/2019 Trimscaac Rev4 Signed

    20/74

  • 8/12/2019 Trimscaac Rev4 Signed

    21/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 21 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    i) The link plate shall be firmly keyed into the concrete by means of bolted-on cleats. The cleatsbearing pressure on the concrete shall not exceed 10MPa. When calculating the number and size ofcleats required, the number of cleat bolts required shall be calculated in accordance with the boltgrade ultimate strength.

    1.11.2 Single inclined drilled / pile anchors

    a) The inclined anchor shall be design the with an additional geotechnical safety factor of 1.2.

    For single in linedrilled / pile anchors, the following top minimum depths at least shall be ignoredfor anchorage purposes:

    i) for rock/soil anchors less or equal to 250mm in diameter ignore the top 500mm of thesoil/rock profile

    ii) for soil anchors greater or equal to 250mm in diameter ignore the top 1000mm of the soilprofile

    iii) for rock anchors greater or equal to 250mm in diameter ignore the top 500mm of the rockprofile

    b) The anchors bars (in the holes) shall be galvanized and have a minimum diameter of 25mm dia.

    c) The distance between the highest point of the foundation and the ground surface shall be a minimumof 250mm and a maximum of 600mm.

    d) The concrete grout shall be pumped by means of a tremie pipe into the hole from the bottom upwards toensure the filling of all the hollows, irregularities (fissures) of the sides and obtain a 100% compaction. Thetremie pipe shall extend down the full length of the anchor.

    e) Proof load testing (full scale) is to be done on a minimum of 2% of all anchors which will be randomlyselected or where required by the client.

    1.11.3 Foundations for concrete or steel poles

    a) General

    i) The Contractorshall be responsible for the design of all foundations for pole structures.ii) The foundations shall be designed to withstand the maximum combinations of induced factored

    moment, compression and torsion. The dead weight of the pole shall be included at unity factor ofsafety.

    iii) All foundation designs are to be accepted by the Design Engineerprior to the utilisation of any suchdesign for pole installation purposes.

    b) Testing

    i) Prior to the construction of any pole foundations, the Contractorshall, if instructed by the DesignEngineerinstall in each general soil type encountered and at any additional locations, test poles forthe purpose of carrying out full scale load tests to determine the moment carrying capacity in eachsoil type.

    ii) The test pole and foundation shall not be part of a final foundation.iii) The Contractorshall prepare the test procedure, and supply all equipment and personnel to perform

    the tests. The tests shall be conducted in the presence of the Eskom Site Representative.iv) The pole foundation shall be capable of withstanding the full design moment for 5 minutes with a

    displacement at ground level of less than 5mm.v) The test shall be continued to failure of either the pole or the foundation i.e. either a creep rate

    greater than or equal to 2mm per minute of the pole measured at ground level, or a pole tip

  • 8/12/2019 Trimscaac Rev4 Signed

    22/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 22 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    deflection greater than or equal to 10with respec t to the original point of intersection of the pole withthe ground.

    vi) Upon completion of the test, the pole shall be either removed or broken down to at least 600mmbelow ground level and properly disposed of.

    1.11.4 Special foundation designs

    If the geotechnical investigation reveals any other severe or extreme conditions applicable to theconstruction of the foundations, special foundation designs may be required. This is applicable forthe construction of power lines over undermined areas, on severe slopes or foundations subjected towater scour. These foundation designs shall be subject to the approval of the Design Engineer.

    1.12 Concrete and grouts

    1.12.1 General

    a) Concrete mix designs shall be proportioned to obtain a minimum required strength of 25 MPa at 28days, and a target strength of 35MPa, with a maximum cement water ratio of 1.8 as per SANS10100-2 Table A.8 Class 1. No more than one individual 28 day concrete test cube result from the 4cube batch shall fall below 90% of the 25 MPa specified strength. For moderate to severe conditionsthe mix design shall comply with SANS10100-2 where the minimum cement content shall be 340kg/m

    3CEM II or CEM I cement with extenders.

    b) Grout mix designs for rock anchors shall be proportioned to attain a minimum strength of 35 MPa at28 days with any expansive additives included. The use of epoxy grouts is to be used only with theDesign Engineersapproval.

    c) Water shall be of a potable quality, clean and free from all earthy, vegetable or organic matter, acids

    or alkaline substances in solution or suspension.

    1.12.2 Cement types

    a) Concrete shall be batched utilising common cement types manufactured in accordance with SANSENV 197-1

    b) The minimum cement class used in concrete will be class 32.5c) CEM I - Class 52.5 and accelerating admixtures shall not normally be utilised for concrete batching.

    Their use will only be considered by the Design Engineer in unusual circumstances, in order toexpedite tower erection to facilitate conductor stringing. The Contractorshall make test cubes andarrange for their testing, to confirm the concrete strength, and obtain acceptance from the EskomSite Representativebefore proceeding with other activities.

    d) Site blending will be acceptable provided the following criteria are met:i) Proportion of Portland cement and Extenders are within industry norms (i.e. maximum 50%

    replacement for slag and maximum 25% replacement for Fly Ash).ii) The cementaitious materials shall be weighted into the mix with an accuracy of 2% or better. In

    special cases the Design Engineermay require that the replacement value indicated in i)abovebe increased.

    e) The cement utilised for grout mixes shall be of a non-shrink type. Any shrinkage-compensatingadmixture shall only be used with the Design Engineersacceptance.

    f) Cement extenders used shall comply with the following SANS specifications:i) Ground granulated blast furnace slag (slag) SANS 1491-1

    ii) Fly Ash (FA) SANS 1491-2

    iii) Condense silica fume SANS 1491-3

  • 8/12/2019 Trimscaac Rev4 Signed

    23/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 23 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.12.3 Aggregates

    a) Fine and coarse aggregate shall be obtained from sources accepted by the Design Engineerandshall be assessed in accordance with SANS 1083.

    b) Fine aggregate shall be natural sand or other accepted inert material with similar characteristics,composed of clean, hard, strong, durable, uncoated particles. Fine aggregates shall be free fromdeleterious amounts of soft, flaky or porous particles, loam, soft shale, clay lumps or organicmaterial.

    c) Fine aggregates shall be selected from local sources to provide a reasonably uniform grading of thevarious size fractions. Fine aggregates having a large deficiency or excess of any size fraction, shallbe avoided to the extent practicable.

    d) Coarse aggregate shall consist of crushed stone, gravel or other accepted inert material of similarcharacteristics having hard, strong, durable, uncoated pieces free from deleterious substances.

    e) Coarse aggregates up to 26,5mm nominal size may be single-sized stone. Coarse aggregates up to40mm nominal size shall be blended consisting of two parts by volume of single-sized 40mm stoneto one part by volume of single-sized 20mm stone. The content of fine material (less than 4,75mm)in coarse aggregate shall be less than 10% by mass.

    f) The bulk void content of fine or coarse aggregate shall not exceed 48%. Aggregate shall not containany materials that are reactive with any alkali in the aggregate itself or in the cement, the mixingwater or in water in contact with the finished concrete or grout in amounts sufficient to causeexcessive localised or general expansion of the concrete or grout.

    g) Notwithstanding the limits on chlorides as per SANS 1083 (BS 882), the acid soluble chloride asNaCl level in aggregate as a percentage by mass shall not exceed the limits given in the followingtable:

    CONCRETE TYPE COARSEAGGREGATE

    FINE

    AGGREGATE

    Reinforced with OPC(Ordinary portland cement)

    0.05% 0.10%

    Reinforced with SRPC(Sulphate resisting portland cement)

    0.02% 0.05%

    NOTE: These limits shall be subject to the overall limit for the concrete as mixed.

    h) The maximum nominal aggregate size for concrete batching shall be as follows:

    unreinforced concrete: 37,5mm

    reinforced concrete excluding piles: 26,5mm

    piles: 19mm

    grout: 10mm

  • 8/12/2019 Trimscaac Rev4 Signed

    24/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 24 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.12.4 Workability

    a) Concrete mix designs and batching shall be conducted in a manner to achieve adequate workability,to ensure that the concrete will be dense, without voids of honeycomb.

    b) The design mix workability of the concrete, as determined by the Slump Test, shall meet thefollowing requirements by application:

    i) unreinforced concrete: 25mm 75mm

    ii) reinforced concrete for conventional foundations and pile caps: 50 mm 100mm

    iii) reinforced concrete for cast in-situ piles: 100mm 150mm

    iv) reinforced concrete for cast in-situ inclined piles/anchors: 150mm 200mm

    c) The consistency of grout mixtures shall be proportioned so that the mixture is pourable. The fineaggregate to cement ratio shall not exceed 3:1 irrespective of workability.

    d) Any admixtures to the concrete proposed by the Contractorshall be subject to the DesignEngineersacceptance.

    1.12.5 Reinforcing steel

    a) All main reinforcing steel shall conform to SANS 920 Type C, Class 2, Grade II hot rolled deformedbars with a minimum yield stress of 450MPa. The minimum bar size utilised shall be 10mm.

    b) All secondary reinforcing for stirrups, hoops and spirals, shall as a minimum conform to SANS 920Type "A" hot rolled bars of plain cross-section of mild steel with a minimum yield stress of 250 MPa.

    c) At the Contractor's option or as required by design, Type B or Type C reinforcing steel may beutilised. The minimum bar sizes utilised shall be at least 0,25 times the largest main reinforcing bar,or 0,01 times the average of the cross-sectional dimensions of the concrete with a minimumdiameter of 6mm allowed.

    1.13 Construction

    1.13.1 Excavation

    a) At each tower or pole position, the Contractor shall excavate, construct the appropriate foundation

    and backfill the excavation as required. Excavation in this instance shall be the removal of soil/rockby any accepted means for the purpose of constructing a particular foundation system, includingconventional pad and pier type foundations, spread footings, piles, anchors, etc.

    b) No excavation work, other than for soil investigation, shall be commenced on a section of line untilthe following conditions have been met:

    i) The Contractor has submitted a schedule of tower leg ground levels and proposed legextension lengths to the Design Engineer.

    ii) The Contractorhas submitted the proposed foundation and soil type schedules to the DesignEngineer.

    iii) If drilled cast-in-situ piles or rock anchors are proposed, soil samples and pile/anchor tests havebeen conducted, if so instructed by the Design Engineer.

    c) Excavations shall be made to the full dimensions required, and shall be finished to the prescribedlines and levels. The bottom or sides of excavations upon or against which concrete is to be poured

  • 8/12/2019 Trimscaac Rev4 Signed

    25/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 25 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    shall be undisturbed. If, at any point in excavation, the natural material is disturbed or loosened orover excavated, it shall be backfilled with 10 MPa concrete, including the application of a blindinglayer at the base of foundations where these eventualities are likely to occur during the constructionprocess. Soil backfilling will not be accepted.

    d) In soil which is incapable of withstanding the design loads which will be imposed upon it by a padand pier type of foundation, the Contractor shall propose a method of increasing the effectivebearing area of the foundation. This may entail the installation of a foundation with a larger pad, orother suitable solutions proposed by the Contractor. Any such proposal shall be submitted to theDesign Engineerfor acceptance prior to excavation.

    e) When the material at foundation depth is found to be partly rock or incompressible material, andpartly a soil or material that is compressible, all compressible material shall be removed for anadditional depth of 200mm and backfilled with 10MPa concrete reimbursable as per to the bill ofrates.

    f) The excavations shall be protected so as to maintain a clean subgrade until the foundation is placed.Any water, sand, mud, silt or other objectionable material which may accumulate in the excavationincluding the bottom of pile or anchor holes, shall be removed prior to concrete placement.

    g) Excavations for cast-in-situ concrete, including pile caps cast against earth, shall be concreted withinseventy-two hours after beginning the excavations. In addition to this general requirement, pileand/or anchor holes that are not adequately protected against the elements to the satisfaction of theEskom Site Representative, shall be cast on the same day that drilling/excavation has taken place.Excavations that remain unconcreted longer than seventy-two hours may, at the option of theEskom Site Representative, be required to be enlarged by 150mm in all dimensions.

    h) The excavations shall be kept covered or barricaded in a manner accepted by the Eskom ProjectManagerandSite Representativeto prevent injury to people or livestock. Plastic danger tape shallbe added to barricade for visual purposes. Failure to maintain proper protection of excavations mayresult in the suspension of excavation work until proper protection has been restored.

    i) The Contractor is to notify the Eskom Site Representativeupon completion of the excavation forthe foundations. No concrete is to be placed until the excavation; shuttering and reinforcing steelhave been inspected and accepted in writing by the Eskom Site Representative.

    1.13.2 Backfilling

    a) After completion of foundation construction, the Contractor shall backfill each excavation withsuitable material. The Eskom Site Representative shall accept the materials used for backfill, theamounts used and the manner of depositing and compaction of the materials.

    b) The material to be utilised for compacted backfill shall be deposited in horizontal layers, having athickness of not more than 300mm before being compacted. In backfilling, the pad of the foundationshall be covered, first with a 200mm layer of well-graded material containing no pieces larger than20mm, before any coarse material is deposited.

    c) The backfill material to be compacted shall contain no stones more than 150mm in diameter, and befree from organic material such as trees, brush, scraps, etc.

    d) The distribution of material shall be such that the compacted material will be homogenous to securethe best practicable degree of compaction, impermeability and stability.

    e) Prior to and during compaction operations, the backfill material shall have the optimum moisturecontent required for the purpose of compaction, impermeability and stability.

  • 8/12/2019 Trimscaac Rev4 Signed

    26/74

  • 8/12/2019 Trimscaac Rev4 Signed

    27/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 27 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.14.3 Tolerances for concrete construction

    The intent of this paragraph is to establish tolerances that are consistent with construction practice,and the effect that permissible deviations will have upon the structural action or operational function ofthe structure. Where tolerances are not stated for any individual structure or feature, permissibledeviations will be interpreted in conformity with the provisions of this paragraph. The Contractor shallbe responsible for setting out and maintaining concrete excavations, shuttering and structuralsteelwork within the tolerance limits so as to ensure completed work within the specified tolerances.Concrete work, that exceeds the tolerance limits specified shall be remedied, or removed andreplaced.

    a) Variation in structure location

    Transverse to centre-line: less than 50mm

    Longitudinal displacement: less than 300mm

    b) Variation in relative vertical elevation of structural steelwork (one leg to another) less than 5mm

    c) Variation in horizontal distance between structural steelwork from that computed

    Adjacent legs: less than 5mm

    Diagonal legs: less than 7mm

    d) Rotation - maximum deviation of transverse axis of structure from bisector of interior line angle

    less than 0 12

    e) Elevation - variation of tower base from centre-line peg

    minus 150mm

    plus 1 000mm

    f) Height of concrete foundations above ground level

    min. 250mm (10mm)

    max. as per design

    g) Variation in relative placement of foundation components from those indicated on drawings, includingpiles, shuttering, and structural steelwork

    less than 50mm

    h) Tolerances for placing reinforcing steel

    Variation of protective cover: 5mm Variation from indicated spacing: 25mm

    i) Tolerances for guy anchors

    Guy anchors shall be installed such that the attachment point of the anchor is within 250mm of thecorrect calculated position. The attachment point shall be a minimum of 350mm and a maximum of750mm above the ground level.

    Guy anchors designed for use with anchor rods extending below ground level shall have the anchorrod installed in line with the guy wire slope, within 1:20 (2.8 ) or such lesser tolerance as required bydesign.

    j) Tolerances for pole foundations

    Pole foundations shall be constructed such that the pole, and the associated foundation works arewithin 50mm of the correct calculated position.

  • 8/12/2019 Trimscaac Rev4 Signed

    28/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 28 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    1.14.4 Workmanship

    Concrete shall be proportioned, mixed, placed and finished in such a manner as to be free of honeycomb,segregation and other defects of workmanship.

    1.14.5 Formwork

    a) Forms shall be of wood, metal or other suitable material.b) The formwork shall be mortar-tight and shall be designed, constructed, braced and maintained such

    that the finished concrete will be true to the line and elevation, and will conform to the requireddimensions and contours. It shall be designed to withstand the pressure of concrete, the effect ofvibration as the concrete is being placed and all loads incidental to the construction operationswithout distortion or displacement.

    c) Where the bottom of the formwork is inaccessible, provision shall be made for cleaning out

    extraneous material immediately before placing the concrete.

    d) All exposed corners of the concrete shall be chamfered approximately 20 mm. A suitable nosing toolmay be used for horizontal chamfers only if approved by the Eskom Site Representative. Allformwork dimensions shall be checked, and if necessary, corrected before any concrete is placed.

    e) All forms shall be treated with a formwork-release agent accepted by the Eskom SiteRepresentativebefore concrete is placed. Any release agent, which will adhere to, discolour or bedeleterious to the concrete, shall not be used.

    1.14.6 Proportioning of concrete

    a) The concrete mix shall consist of ordinary Portland cement, fine aggregate, coarse aggregate andwater proportioned in accordance with the mix design accepted by Design Engineer. Adjustmentsin these proportions may be directed at any time when found necessary as a result of field tests ofthe concrete. No change in proportioning shall be made unless instructed by the Eskom SiteRepresentative. As an alternative to the use of ordinary Portland cement, the Design Engineermay consider the use of other approved types of cement or blends thereof.

    b) No change in the source, character or gradation of materials shall be made without notice to theEskom Site Representative and without a revised proportioning mix design being prepared andaccepted by the Design Engineerprior to use of these materials.

    c) During the concrete operations, the concrete mixture shall be tested for each batch by theContractor to determine the slump of the fresh concrete in accordance with SANS Method 862.

    Records of slump tests shall be supplied to the Eskom Site Representative.

    d) Test cubes shall be prepared, in accordance with SANS Method 863 at the initiation of concreteplacement of each mix design and every day that concrete is batched thereafter. Test cubes shallonly be made out of a concrete batch at the point of discharge. The Contractor shall install suitableon-site laboratory facilities for the storage and crushing of test cubes. The crushing equipment shallbe appropriately calibrated and accompanied by up-to date certification available for inspection at alltimes. The Eskom Site Representative shall witness all cube tests.

    i) Each set of test cubes shall consist of four cubes minimum plus a 5thcube as directed by the

    Eskom Site Representative where an accelerated 24hour curing test is needed.The 5

    thcube to be tested as per the 24hour curing test, for every first batch of a new supplier

    and randomly thereafter as advised by the Eskom Site Representative (procedure as perline project appendix).

  • 8/12/2019 Trimscaac Rev4 Signed

    29/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 29 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    ii) Additional test cubes shall be prepared where the concrete strengths are in question andcrushed as directed by the Eskom Site Representative.

    e) All cement shall be batched by mass. Cement shall be weighed to within 2% accuracy.

    f) Aggregates may be batched by mass or by volume, provided that volumetric batching equipment iscalibrated at the start of concrete operations by weighing a typical discharge. The quantities ofaggregate batched shall be volume batched within 3% accuracy. Adjustments of fine aggregatevolumes due to "bulking" shall be accounted for in batching.

    g) The amount of moisture in the aggregates shall be determined daily by a method accepted by theEskom Site Representative, and the water requirements as per the mix design altered accordingly.

    h) Water quantities, including aggregate moisture allowances, shall be determined within 2% accuracy.The use of water meters for dispensing water shall be subject to the Eskom Site Representativesacceptance.

    1.14.7 Mixing of concrete

    a) Concrete shall be mixed sufficiently to ensure that the various sizes of aggregate are uniformlydistributed throughout the mass, and each particle of aggregate is adequately coated with cementpaste of uniform consistency. Concrete delivered to site that lacks homogeneity should be mixed fora longer time or discarded, as directed by the Eskom Site Representative.

    b) For mixers of one cubic metre or less, the mixing time shall not be less than ninety seconds after allingredients have been charged in the mixer. For mixers of larger capacities, minimum-mixing timesshall be increased by fifteen seconds for each additional half cubic metre of mixer capacity, orfraction thereof.

    c) Concrete delivered to the job site shall be mixed en-route. Mixing shall be rigorously controlled foragitating time, mixing time and overall time upon arrival at the foundation site. Concrete dischargeshall be completed within one and one-half hours after introduction of the water to the cement andaggregate.

    d) In exceptional cases only, theContractormay at his own risk add water to a concrete mix at thepoint of delivery. The maximum amount of water that may be added at site is three litres per cubicmetre of concrete. At no time shall the cement / water ratio of 1.7 be creased.

    e) Non-shrink grout shall be mixed in a suitable mechanical grout mixer/pump accepted by the EskomSite Representative.

    1.14.8 Placement of reinforcing steel

    a) Eskom Site Representative, the Contractor shall install all the reinforcing steel required forfoundations. Reinforcing steel shall be fabricated and bent in strict accordance with the drawingsand SANS 82.

    b) Reinforcing steel, before being positioned, shall be thoroughly cleaned of mill scale and any coatingsthat will destroy or reduce bond.

    c) Reinforcing steel shall be accurately positioned and secured against displacement during placingand vibrating of concrete. Reinforcing bars shall be tied at all intersections with no less than No.18gauge annealed wire. Reinforcing bars shall be overlapped forty-five diameters at all splices, unlessshown otherwise on the drawings. Reinforcing steel shall be provided and placed as detailed on the

  • 8/12/2019 Trimscaac Rev4 Signed

    30/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 30 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    drawings. Unless otherwise shown on the drawings, the minimum cover to the main reinforcing barsin a slab, pile cap, chimney, pile or anchor, shall be 50mm and 75mm for the bottom of the slab.Use of suitable accepted spacers or supports shall be made, to ensure that the minimum concretecover to the reinforcement is maintained during the placement of concrete. Where cover blocks areused to support the lower layers of reinforcing, these shall be at least 75mm thick to make allowancefor the uneven ground surface on which the reinforcing cage rests.

    1.14.9 Placement of embedded items

    a) The Contractor shall install all required embedded items shown on the drawings, prior to placing ofconcrete. Structural steelwork or holding down bolts shall be accurately positioned and securelyheld in place during the placement of concrete. The minimum cover to all embedded items, butexcluding angle stubs, shall be 150mm. The minimum cover to angle stubs and cleats shall be75mm unless otherwise shown on the drawings.

    b) Angle stubs may be supported on the bottom of excavations by either precast concrete slabs set atthe correct level by placing suitable grout or concrete underneath it, or on a previously placedblinding layer installed up to the correct level. The precast slab shall be square in plan with a sidedimension of 300mm, and a depth of 75 mm, and shall be constructed using reinforced concrete witha minimum characteristic strength of 25 MPa. The placing of loose rubble, stones, bricks, etc. underthe precast slab will not be acceptable.

    c) Structural steelwork or anchor bolts shall be embedded such that the top of the concrete of thefoundation correctly coincides with the designed level.

    d) Earthing requirements are to be as per the latest revision of specification TST41-321 Earthing ofTransmission Line Towers.

    1.14.10 Placement of concrete

    a) No concrete for foundations shall be placed until each foundation has been inspected and acceptedby the Eskom Site Representative. The foundation at the time of this inspection shall be ready forconcrete placement including reinforcing steel, embedded items and any necessary formwork.

    b) All surfaces of the foundation upon or against which concrete is to be placed shall be free from mudand/or loose or disturbed material. A blinding layer of 10MPa between 50mm to 100mm is to beinstalled on all bottom surfaces where warranted.

    c) The surfaces of dry absorptive materials, against which concrete is to be placed, shall be moistenedprior to the placing of concrete to prevent excessive moisture being withdrawn from the freshconcrete.

    d) At least two suitable concrete poker vibrators shall be ready for operation at the site prior toplacement of concrete.

    e) Freshly mixed concrete shall be handled, transported and deposited in such a manner as to preventsegregation or loss of material. When discharging by chute, the slope of the chute shall be uniformthroughout its length and shall not be flatter than 1 in 3 or steeper than 1 in 2. Baffles shall beprovided at the end of the chute to ensure a vertical discharge into the foundation. The maximum

    discharge height shall be three metres, and for heights in excess of this, a tremie pipe shall be used.

  • 8/12/2019 Trimscaac Rev4 Signed

    31/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 31 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    f) Placement of concrete shall not commence when the air temperature is below 2C and rising, orbelow 5C and dropping.

    g) The temperature of the concrete mixture immediately before placement shall not exceed 32C.Concrete exceeding this temperature shall be discarded. During hot weather concreting operations,the Contractorshall take the temperature of each batch of concrete.

    h) No concrete shall be placed which has taken its initial set, regardless of whether the specified oneand one-half hour period has elapsed or not. If a retarder, accepted by the Design Engineer, hasbeen used, the one and one-half hour period may be exceeded provided the concrete has not takenits initial set. The Contractorshall dispose of waste concrete in a place acceptable to the EskomSite Representative.

    i) Concrete shall be placed under water, with a suitable watertight tremie, accepted by the Eskom SiteRepresentative, of sufficient length to reach the bottom of the excavation. The tremie shall be freeof water when filled with concrete to the bottom of the excavation. The tremie shall be kept full ofconcrete during the entire concrete placing operation. The discharge end of the tremie shall not belifted out of the freshly placed mass of concrete until placement has been completed.

    j) Concrete shall be thoroughly settled and compacted into a dense homogeneous mass throughoutthe whole depth of each layer being consolidated, using internal vibrators. Excessive vibration,causing segregation, is to be avoided. Concrete vibrators shall not be used to move concrete.

    k) The concrete in cast-in-situ piles shall be vibrated from the bottom upwards.

    l) Unless authorised by the Eskom Site Representative, the Contractor shall not place concrete,unless the Eskom Site Representative is present during the entire placement operation.

    m) When alternative foundations consisting of multiple cast-in-situ piles and pile caps are utilised, theContractor shall at approximately one tower in twenty, open up on two sides of the completedfoundation of one leg, the pile cap and top 500mm of the piles, if so instructed by the Eskom SiteRepresentative. If the foundation is rejected for any reason, the Contractorshall open up as manyadditional foundations as determined by the Eskom Site Representative, as is necessary to fullyassess the problem. Foundations accepted are to be backfilled using 10 MPa concrete up to a levelat least 150 mm above the base of the pile cap.

    n) Concrete in all drilled foundations utilising piles with a diameter greater than 150mm, shall beinspected immediately prior to concrete placement using a suitable high powered torch andmeasuring tape. The inspection is required to determine:

    i) That no soil has fallen into the drilled hole such that either the design length or the designdiameter of the pile has been affected, and

    ii)That no material from the hole sides has become dislodged and has fallen against reinforcing.No concrete will be allowed to fall directly against the hole sides during placement. A pokervibrator shall be placed in the bottom of the pile hole prior to any concrete placement andgradually lifted with the concrete pour. With inclined piles the concrete is to be placed bymeans of a tremie pipe which extends down the full length of the pile. The tremie pipe,together with the poker vibrator can then be gradually lifted with the pour.

    1.14.11 Construction joints

    a) In general, foundations shall be constructed monolithically. Construction joints are to be avoided asfar as possible. If construction joints cannot be avoided and are accepted by the Eskom SiteRepresentative, the Contractor may be permitted to make a construction joint if the followingcriteria are met:

  • 8/12/2019 Trimscaac Rev4 Signed

    32/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 32 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    i) The concrete is reinforced and the reinforcing steel will develop full bond strength both sides ofthe construction joint. No construction joints will be allowed in unreinforced concrete.

    ii) In single cast-in-situ piles, the construction joint is located one third the depth of the excavation,300mm and at least 150mm below the bottom of the structural steelwork or anchor bolts.

    iii) In multiple cast-in-situ piles, the construction joint is to be 75mm, and in rock anchors 100mm,above either the base of the pile cap excavation or the top of blinding level. If the piles areconstructed after the excavation for the pile cap has taken place, suitable ring shutters of thesame diameter of the piles shall be used to construct the above mentioned pile/anchorprojections.

    b) No construction joints will be allowed in piles, pile caps, deadman anchors and pad slabs of pad andpier foundations.

    c) At all construction joints, the surfaces of the previously placed and hardened concrete shall bethoroughly cleaned of all foreign matter, and primed with a 15mm thick layer of a wet mix of cementand sand in equal proportions, in the presence of the Eskom Site Representative before newconcrete is placed. The grout coating shall be brushed over the concrete surface to ensure thoroughcoverage, particularly between the reinforcing bars. The new concrete shall be placed before thegrout coating has taken its initial set.

    1.14.12 Concrete surface finish

    a) The top surface of the foundation shall be at least a wood float finish, and shall be contoured to shedwater.

    b) All concrete placed against shuttering shall be free from irregularities, fins, rock pockets or otherimperfections. Any rock pockets, porous or defective concrete shall be removed to the extentinstructed by the Eskom Site Representative and repaired by filling these voids with concrete,cement mortar or dry packed concrete, as instructed by the Eskom Site Representative.

    c) All exposed concrete sections shall be shuttered to a minimum of 250mm below ground level.

    1.14.13 Concrete curing

    a) The Contractor shall provide means of maintaining concrete in a moist condition (for curing) for atleast seven days after the placement of concrete.

    b) At the Contractor's option, concrete may be cured either by retaining shuttering in place andapplying a liquid curing compound which forms a moisture retaining membrane on unshutteredconcrete surface, or by removing shuttering and applying a curing compound as described to allexposed concrete surfaces. Curing compounds utilised shall be of a type accepted by the DesignEngineer. Notwithstanding these requirements, formwork shall not be removed until at least 36hours after the final placement of the concrete against such formwork. The Contractorshall removeformwork in such a way that shock forces and damage to the concrete are avoided.

    1.14.14 Concrete cracks repair

    For crack widths:

    a) Less than 0.4mm repair using Xypex or similar material approved by the Design Engineer.

  • 8/12/2019 Trimscaac Rev4 Signed

    33/74

    Document Classification: Controlled Disclosure/Confidential

    THE DESIGN AND CONSTRUCTION OF OVERHEADPOWERLINES

    UniqueIdentifier:

    240-47172520

    Revision: 4

    Page: 33 of 74

    ESKOM COPYRIGHT PROTECTED

    When downloaded from the WEB, this document is uncontrolled and the responsibility rests with the userto ensure it is in line with the authorised version on the WEB.

    b) Between 0.4mm and 2mm and less than 30mm depth, repair using Xypex or similar