55
TMP Development Module 7

TMP Development

  • Upload
    pier

  • View
    70

  • Download
    0

Embed Size (px)

DESCRIPTION

TMP Development. Module 7. What is a TMP?. Set of coordinated transportation management strategies applied to manage work zone impacts of the project Scaleable – projects with larger anticipated impacts may require more strategies Required in all FA projects – - PowerPoint PPT Presentation

Citation preview

Page 1: TMP Development

TMP Development

Module 7

Page 2: TMP Development

What is a TMP?

Set of coordinated transportation management strategies applied to manage work zone impacts of the project

Scaleable – projects with larger anticipated impacts may require more strategies

Required in all FA projects – TMP=TCP in some projects TMP=TCP+TO+PI components in others

Page 3: TMP Development

TMP Development Process

Page 4: TMP Development

TMP Development, Implementation, and Assessment

11 Step Process1. Compile Project Material2. Determine TMP Needs3. Identify Stakeholders4. Develop TMP5. Update/Revise TMP6. Finalize Construction Phasing/Staging and

TMP

Page 5: TMP Development

TMP Development, Implementation, and Assessment

11 Step Process (continued)7. Re-evaluate/Revise TMP8. Implement TMP9. TMP Monitoring10. Update/Revise TMP Based on

Monitoring11. Post-Project TMP Evaluation

Page 6: TMP Development

TMP Team Approach

Better coordination throughout the process from development to implementation

Involve all involved offices internallyTMP CoordinatorPlanningDesignTraffic engineeringConstructionOperations (maintenance)?

Page 7: TMP Development

Step 1 - Compile Project MaterialStaff responsible for each stage of the project (planning, preliminary engineering, design, construction) begins by compiling available project materials such as:

Project definition Construction phasing/staging alternates Preliminary work zone management strategies. Preliminary cost estimates for strategy implementation Information from other projects in the corridor to evaluate

the combined or cumulative impact of the projects.

Page 8: TMP Development

Step 2 - Determine TMP Needs

Necessary Components of TMP Impact assessment Duration of project Possible Strategies

Determine if it is a significant project:

Based upon the agency's policy and procedures, project's anticipated work zone impacts.

Page 9: TMP Development

Step 2a - Basic TMP

Basic TMPs – Applied on construction or maintenance projects

with minimal anticipated impacts Projects typically only involve the development of a

TCP – layout of devices, phases, etc.

Page 10: TMP Development

Step 2b - Intermediate TMP

Intermediate TMPs – Used for construction or maintenance projects

that are anticipated to have more than minimal disruption, but have not been identified as significant projects.

Include more detailed work zone impacts analysis and management strategy information than Basic TMPs, including some element of PI and/or TO strategies as well as TCP.

Page 11: TMP Development

Step 2c - Major TMP - Significant ProjectsMajor TMPs are intended for significant projects.

Major impacts to road users, residents and businesses TMPs for significant projects shall consist of a TCP, and

also address PI and TO components. In addition to the TMP components required by the Rule,

TMPs may also contain cost estimates, coordination strategies between stakeholders, secondary mitigation strategy(s), analysis of potential impacts on detour routes, and analysis of the potential effects of the management strategies.

Page 12: TMP Development

Step 3 – Identify Stakeholders

Internal and external that can provide valuable input to the agency on what strategies to include in the TMP to help manage the work zone impacts of a project.

Page 13: TMP Development

Step 4 – Develop TMPThe level of detail of the TMP during early planning is largely dependent upon the type of planning activity, the expected impacts of the project, and the availability of data.

At a minimum, early planning should entail a qualitative exercise to list the potential impacts of a project, along with a list of potential management strategies, and the expected costs of those management strategies.

Page 14: TMP Development

Step 5 – Update/Revise TMP

The TMP is updated or revised as the project progresses through its various

developmental stages as more project-specific information becomes

available.

Page 15: TMP Development

Step 6 – Finalize Construction Phasing/Staging and TMP

PS&Es shall include either all the applicable elements of a TMP, or the provisions for a contractor to develop a TMP.

TMP development should begin prior to project letting, even for design-build projects.

Some elements could be accomplished early in process – alternate route work or beginning of PI plan

Some may not be in PS&E – agency in house

Page 16: TMP Development

Step 7 – Re-evaluate/Revise TMP

If alternative construction phasing/staging plans or other management strategies have been suggested, technical specialists from the contractor or agency need to review the TMP to see if changes are needed.

Page 17: TMP Development

Step 8 – Implement TMP

The TMP is implemented.

In some cases, components of the TMP may need to be implemented prior to construction (e.g., public relations campaign, improvements to detour routes, etc.).

Page 18: TMP Development

Step 9 – TMP Monitoring Monitor operational

performance of work zone during the construction phase

Are predicted impacts realistic?

Are the strategies in the TMP effective in managing the impacts?

Do any adjustments to TMP need to be initiated?

Page 19: TMP Development

Step 10 – Update/Revise TMP Based on Monitoring

If performance requirements are not met, the agency and/or contractor should revisit the TMP and consider alternate management strategies and/or phasing/staging approach(es) that meet the approval of the agency.

Page 20: TMP Development

Step 11 – Post-Project TMP Evaluation

TMP performance assessment can aid in addressing the following concerns:

Which management strategies have proven to be either more or less effective in improving the safety and mobility of work zones?

Are there combinations of strategies that seem to work well? Should TMP policies, processes, procedures, standards, and/or

costs be adjusted based on what has been observed or measured?

Are the best decisions in planning, designing, implementing, monitoring, and assessing work zones being made?

Performance assessment may involve two tracks: 1) the overall TMP process 2) actual field performance of the work zone and TMP.

Page 21: TMP Development

TMP PROCESS –CA Example

Conceptual Planning and Design

Request TMP Data Sheet

What Kind of TMP is

required?

Establish TMP Team (Ops, Design, Traffic, Const, CHP)

START

MAJOR

Prepare Data

Sheet

Arrange forFunding ofTMP Strategies

Detailed Plans & Specs (inc.TMP)

Modify Strategies as

Needed Start early TMP elements

Begin Construction

Implement TMP

Minor

Maintenance and Permits activities

Blanket

** Modify TMP Strategies as Needed / Monitor traffic initially / Provide Lessons Learned

Page 22: TMP Development

Ohio DOT’s TMP Development Process Start

Project

MOTAAMOT Policy Exception Requests

Stage 1Design

ConstructProject

Page 23: TMP Development

Developing the TMP (Putting the components together) Traffic Control Plan

Layout of traffic control devices to guide road users through or around work zone.

Determined after analysis of strategies Contain any restrictions on work hours Include Work Zone Speed Limits – State policy?

Page 24: TMP Development

TYPICAL TRAFFIC CONTROL PLANS CONTENTS: LANES WIDTHS WORK AREA &

DIMENSIONS CONSTRUCTION

SEQUENCE SCHEDULE, STAGES &

ACTIVITIES /STAGE ADJACENT HAZARDS

TEMPORARY DRAINAGE TYPE OF AREA (CBD,

RURAL, URBAN) GEOMETRICS LOCAL ORDINANCES SPECIAL PROVISIONS PAY ITEMS

Page 25: TMP Development

TYPICAL TRAFFIC CONTROL PLANS CONTENTS:

LOCATION/TYPES OF TC DEVICES

SIGNS, BARRIERS, PAVEMENT MARKINGS, ARROW BOARDS, CMS, ETC…

EMERGENCY ACCESS PEDS./BYCLIST ACCESS EQUIPMENT, WORKERS

ACCESS CROSSOVERS/EMERGENCY

OPENINGS

EXISTING REGULATORY SPEED LIMIT/OTHER SIGNS

TRAFFIC CONTROL NOTES LIGHTING/GLARE SCREEN GEOMETRICS LOCAL BUSINESS/RESIDENT

ACCESS DETOURS, IF APPLICALIBE

Page 26: TMP Development

PEDESTRIAN/BICYCLISTS Situations That Warrant Special

Considerations: Sidewalks Traverse Work Zone Designated School Route Significant Pedestrian/Bicyclist Activity ADA compliance Existing Generators (Parks, Schools,

Shops)

Page 27: TMP Development

Additional TMP Components for Significant Project

Transportation Operations Plan Improvements to alternate

route Traffic Signal retiming Intersection geometric

improvements Utilize existing

infrastructure – detectors, cameras, TMC

Page 28: TMP Development

Traffic Operations Plan

Incident management plan for work zone Pre-stationed tow operators during peak hours

Motorist Assist Patrols Utilize existing with added units Contract during project

Demand reduction strategies Carpools Increase transit ridership

ITS real time traffic information systems

Page 29: TMP Development

Other Considerations

Existing state policies Work zone speed limits

Reduced at all times? Reduced when workers present and exposed? Use of Law Enforcement?

Use of Positive Protection – PCB or other 23 CFR 630 Subpart K

Page 30: TMP Development

MUTCD Sec 6C.01

“Reduced speed limits should be used only in the specific portion of the TTC zone where conditions or restrictive features are present…A TTC plan should be designed so that vehicles can reasonably safely travel through the TTC zone with a speed limit reduction of no more than 10 mph.”

Page 31: TMP Development

Increase in Fatal Plus Injury Accident RatesFrom Before to During Construction

98.6

4.1

147.9

112.5

0

20

40

60

80

100

120

140

160

0 10 15 20 25 30

Speed Limit Reduction (mph)

Per

cent

age

Incr

ease

(%)

Rural - traveled way & detours

Page 32: TMP Development

Increase in Speed Variance fromUpstream to Work Zone

61.2

34.1

86.7 82.692.6

80.6

0102030405060708090

100

0 10 15 20 25 30Speed Limit Reduction (mph)

Per

cent

age

Incr

ease

(%)

Page 33: TMP Development

Minimizing Variance

Safest traffic operations result when speed variance is minimized

Only police enforcement is effective in reducing speeds without increasing speed variance

Page 34: TMP Development

Stationary Police Vehicle on Approach

Page 35: TMP Development

Enforcement

Enforcement Impact on Vehicle Speeds Enforcement Policies Problems Work Zone Training for Police Policies on Work Zone Speed Limits

Page 36: TMP Development

Observed Problems

Difficult to ticket speeders in work zonesOfficers have little guidance on when or

where to deployLack of ticketingOfficers are stationed in unsafe

positions

Page 37: TMP Development

Observed Problems (cont.)

State laws affect enforcement optionsTTC plans are not designed for

enforcementOfficers are in short supply

Page 38: TMP Development

Do not allow this…

Page 39: TMP Development

Reduction in Mean Speeds BetweenUpstream and Work Locations

7

4

10

8

0

2

4

6

8

10

12

0 10

Police PresentNo Police

Speed Limit Reduction (mph)

Red

uctio

n in

Mea

n S

peed

(mph

)

Page 40: TMP Development

Comparison of Speed Variance Between Upstream and Work Locations

11

17

1

21

0

5

10

15

20

25

0 10

Police PresentNo Police

Speed Limit Reduction (mph)

Incr

ease

in S

peed

Var

ianc

e (m

ph)

Page 41: TMP Development

Incident Management Plan Ensure access to all areas for emergency

vehiclesHospitals nearby?Trauma centers?

Plan to provide access within work site Identify alternate routesPre-sign for use during incidents?

Pre-station tow operators during peak hours

Page 42: TMP Development

Business Access Temporary entrances

SigningPavement

Advance notification of phase changes Keep owners informed

Work SchedulesChristmas shopping seasonWeekends

Page 43: TMP Development

Residential Access

Keep residents informed as project begins and progresses Maintain access if

possible Neighborhood

association meetings, newletters, mailings, etc.

Page 44: TMP Development

Additional TMP Components Public Information

Strategies to inform public of work zone conditions

Website Real time traffic information system Community outreach – residents and businesses Twitter TV – Radio – commuters

Occasionally contracted out to PR firm for major campaign

Page 45: TMP Development

Billboards on Project Project logo Progress

Page 46: TMP Development

NHI 380072A16-46

THE STEVENSON RECONSTRUCTION

Brochures for MediaKits and Public

Distribute early – may influence alternate route choice

Page 47: TMP Development

Example ChecklistFHWA Guide

Page 48: TMP Development

Example ChecklistFHWA Guide

Page 49: TMP Development

Example ChecklistDDOT

Page 50: TMP Development

Example ChecklistDDOT Guide

Page 51: TMP Development

Example ChecklistDDOT Guide

Page 52: TMP Development

Example ChecklistDDOT Guide

Page 53: TMP Development

TMP Overview 53

Summary Estimate and budget for TMP development and

implementation early in project development (update as appropriate throughout project)

Consider and address WZ impacts from a broad transportation management perspective (rather than solely a traffic control perspective)

Coordinate with key parties to jointly identify WZ impacts issues to account for and management strategies to address them

Strive to use strategies that keep lanes open, especially during peak traffic times

Page 54: TMP Development

TMP Overview 54

Summary (cont.) Consider using extended closures or full closures versus

numerous night closures Consider strategies that facilitate decision-making by the

public to avoid the WZ (e.g., public awareness, advance signage in locations prior to key motorist decision points)

Training is important for all personnel involved in TMPs Management support is needed for effective TMP efforts

Page 55: TMP Development

Questions ?