1
The Signalling Programme
Status May 2015
06.05.2015 Presented by Morten Søndergaard
Date of meeting
keeper of the minutes
2
Agenda
– Walk through of status of the different Signalling Programme
projects
3
Danish signalling needs to be renewed now
3
• 3.000+ trains/day
• 60% of all signalling will exceed absolute
final service-life within 15 years
• DK-ATC life expires in 2020
• It takes 10-12 years to renew all signalling
assets
• More systems have risk of serious
breakdowns even today
• 50% of today's train delays are due to
signalling failures
• In 2006 a total of 39.000 trains were
delayed
4
A total renewal of the signalling system minimises total cost and provides better performance
A total renewal is the best solution:
• Cheapest and fastest implementation • Provides higher punctuality and capacity • Most benefits for the passengers • Benefits are achieved faster
2006: Strategic political decision of a total renewal strategy 2007-08: Detailed plans & budget for a total renewal programme Jan 2009: Final political decision for a fully financed total renewal
programme was decided by the Danish Parliament Feb 2009-12: Signalling Programme procurement phase 2012 - Contract signed
4
5
S-Banen
– Operating on the first S-Bane line (Jærgersborg - Hillerød) is scheduled to start
in Autumn 2015. The installations and tests are completed
– The Roll Out Phase is ongoing
– The first stage in the Roll Out phase is named RO2 including commisioning of the
line Klampenborg to Hellerup and Jægersborg to Hellerup
– Infrastructure works are ongoing
– 61 trains have been fitted
– Drivers and controllers have been trained
– Operational System Rules are finished
– Operational Test has been conducted
Status
6
S-Banen
Driver’s Cab
7
S-Banen
ICI equipment. Yellow machine solution
8
S-Banen
Technical Object Building – VIP visit
9
Fjernbane West
– Fjernbane West has now started the Implementation stage of
EDL which will run until November 2015
– Fitment of EDL: Langå - Frederikshavn
– Mostly Civil Works installations
– 132 km ploved cable, a lot of cable laying at stations
– 570 Fundation for markerboards
– 13 km new Cable Ducts
– Design: Passed final design milestone with a few outstandings
Status
10
Fjernbane West
Existing Cable ducts
11
Fjernbane East and West
New Cable ducts
12
Fjernbane East
– Signalling Layout of EDL is completed and approved
– The Technical Object Building at Herfølge has been installed
– The infrastructure – mostly Civil Works - installations are
ongoing
– Design activities: Detailed design almost finished
Status
13
Passenger Trains
Qty
Lint 41 – DMU 84
Y - DMU 5
DM - (Desiro) DMU 8
On-board fitment: Passengers Trains
13
Passenger Trains Qty
ET (Øresund train) - EMU/dual voltage
111
ER (IR4) – EMU 44
MF (IC3) – DMU 96
MG (IC4) – DMU 83
MP (IC2) – DMU 23
MQ (Desiro-2) – DMU
20
MR – DMU 42
BR605 (ICE TD) – DMU
13
ABS (batch 1) - Steering cars
7
ABS (batch 2) - Steering cars
11
RT (IC2) - DMU 13
14 Different First of Class Total : 560 Passenger Trains
14
Locomotives Qty
V100, Alstom diesel locomotive
9
G 1206 Vossloh diesel locomotive
2
Freight Locos
14
Locomotives Qty
ME - diesel locomotives
25
EA - electric locomotives
3
EG - electric locomotives
13
BR 185 - electric locomotives
23
MY/MX - diesel locomotives
28
MZ - diesel locomotives
10
MK - Shunting locomotive
1
T43 H - diesel locomotive
1
M32, diesel locomotive
1
T66, T66K, diesel locomotive
2
12 Different First of Class Total : 118 Locomotives
15
Yellow Machines Qty
P&T, MTW 100 Service vehicle 1
Saalasti RTV 158 Vacuum Excavator
1
RACO, Saurer TMIII Service vehicle
4
Jølemo, 10t Service vehicle 33
KØF Traction Unit, Frichs 5
KØF III Traction Unit, Gminder 1
P&T, PBR-4000D Ballast regulator
1
P&T, SSP110 Ballast regulator 3
P&T, USP 2010-2K Ballast regulator
1
P&T, OBW 10 Service vehicle, 20t
15
Robel, type 54.22, Service vehicle
1
Yellow Machines (maintenance)
15
Yellow Machines Qty
P&T, MTW 10 Service vehicle 8
P&T, Combi 08-275 Tamping machine
5
P&T, DGS 42N and 62N Track stabilizer
3
P&T, 08-475 4S Tamping machine, switches
2
P&T, 08-32U Tamping machine 3
P&T, 09-3X Tamping machine 1
P&T, 08-275 ZW Tamping machine
1
P&T, 09-16/4S Tamping machine, switches
1
P&T, HOBW-120-4A Service vehicle
2
P&T, OBW 100 Service vehicle 2
P&T, OBW 10.054 Service vehicle, 27/28t
15
Total : 109 Yellow Machines
16 16
ERTMS Onboard Project Status (General)
- Final generic solution to be delivered to BDK this summer 2015
(EVC software 6.3.0)
- Generic solution includes TSI Baseline 3 functionalities (SRS 3.3.0
+ some MR1 CRs) + BDK functionalities (e.g. Online Key
Management System, ETCS over GPRS)
- This will be the version to start the training and Supervised
Commercial Operation on Early Deployment lines
- Decision to upgrade to TSI 3.5.0 not taken yet (depends on the
maturity of the Specifications)
17 17
ERTMS Onboard Project Status (Design & Test)
ERTMS functions already tested in the lab (TSI 3.3.0), NoBo
certificate available
Integration with Danish STM baseline 3 done (only minor non-
regression tests to be conducted with final EVC software this
summer)
Integration with Swedish STM in progress. Need to do formal
integration tests with final version of EVC.
Joint Test Lab activities (test with trackside projects) in progress
18 18
ERTMS Onboard Project Status (Installation)
- Fitment of two Danish Test Trains in progress (one is completed)
- Next steps: dynamic tests
- APIS for starting tests in mixed traffic September 2015
- Installation design for all passenger trains almost completed
(except for trains not surveyed: Øresund trains and double
deckers)
- No installation design for freight trains except for MY and MX locos
as these were surveyed for other passenger train operators
19
GSM-R On-board Infrastructure and voice
– GSM-R infrastructure finished. Upgrade to GPRS under negotiation
– S-Bane trains are fully fitted with GSM- R voice radios
– Fitment of other trains is progressing according to plan
– Arriva fitment is closed and all MR litras from DSB (except 2 Alstom test
trains) have been fitted with GSM-R (51 trains)
– Next big milestone is the serial fitment of the DSB IC3 trains
Status
20
FTN
Passive Network EDL
– Deployment of tubes and fiber on the line Roskilde – Køge has been
performed
– The work on the stations is progressing and the first fiber blowing
and station connectivity will be finalised soon
Active Network EDL
– Low-level fully redundant (routers, power, locations of fibers) network
design connecting all EDL FTN sites and EDL East and West has been
completed
– Active equipment installation starts in June
Status
21
Operational Rules
– S-Banen: Traffic rules have been approved for training,
approval for operation is still pending
– DSB's own set of rules drawn up and approved for training
– Final approval is pending approval of the technical system
– Fjernbanen: Traffic rules have been prepared
– Final approval is pending approval of the technical system
Status
22
Training
S-Banen: Staff has been trained for EDL
Refresher training is ongoing
Training Pilot for PICOPs, East has been
conducted
Training Pilot for On-board training has
been finalised (drivers and maintainers)
Training Pilot for infrastructure East and West is
ongoing
Adjusted Training Specifications have been
Forwarded to G-ISA
Adjusted Training Specifications will be approved
by NSA during summer and Fall 2015
Status
23
TRIS
– The new Traffic Information System has almost finished
development
– Implementation concept is to use TRIS with data from existing
signaling and later data from the new Signaling System
– Shortly after this summer we start testing the on first stations
– We expect to test at the line in April 2016 , and have
implemented the whole system out by the end of 2016.
– In the period 2016-2021 the system will handle both the non-
migrated lines and migrated lines.
Traffic Information System
24
Traffic Control Centers (TCC)
Trafiktårnet Øst
At TCC East masonry is nearly finished Internal walls are established and installation of chanels, pipes and ducts are close to being finished The first employees from Banedanmark and Vejdirektoratet will be moving in October 2015
25
Traffic Control Centers (TCC)
Trafiktårnet Vest
At TCC West masonry is close to being finished Internal walls are being established and installation of channels, pipes and ducts are approximately 75% finished
26
Traffic Control Centers
Visualisation
27
Simple solution overview of signaling programme and scope of Joint Test Lab (JTL) tests
TMS
Point Machine
Axle Counter
LX/ PWS/SC
IXL RBC
Balise
SIL2
TMS
Point Machine
Axle Counter
LX/ PWS/SC
RBC IXL
Balise
SIL2
On-line Scheduler
Key Management
Server
Long Time Planner
Decision Support System
Hand Held Terminal
Hand Held Terminal
TRIS
Enterprise Service
Bus
External
GSM-R
Integration between different suppliers
28
29
Joint Test Lab
Server Room
30
Joint Test Lab
”Control Room”
31
ERTMS baselines
• The ERTMS specifications are being managed by the European Railway
Agency.
• Currently there are 2 specification baselines:
• Baseline 2 (SRS 2.3.0d) has been used on high speed lines in ES, IT
and BE/NL and a few conventional lines in CH, NL, LX.
• Baseline 3 (currently SRS 3.4.0, next release planned end of 2015)
being used as basis for the national deployments in UK, DK, NL, SE,
NO, DE, CH, BE and likely also the remaining countries.
• Trains with Baseline 3 are backwards compatible with B2 infrastructure,
but B2 trains cannot run on B3 infrastructure. (Essentially B2 trains can
only run on the B2 lines they were built for)
31
Management of the European specifications
32
ERTMS baseline 3
Baseline 3 challenges
• Bigger nodes/stations
• Radio capacity/ETCS over GPRS/EDGE,
• Cold movement Detection-SoM,
• Braking Curves
• Online key management
• Backwards compatibility to 2.3.0d trackside (first Swedish lines)
• Finishing test specifications baseline 3 (certification of Onboard)
• SP will be maturing part of the ERTMS specifications
BDK will be maturing baseline 3
33
The Signalling Programme ERTMS baseline
– Contracted on SRS 3.3.0
– Design being made according to 3.4.0 + ETCS over GPRS and
O-KMS
– Final target is the 2015 release (R2/3.5.0) as it is
introducing ETCS over GPRS and O-KMS
– Backwards compatibility will be demonstrated both with lab
interconnection (already being done) and on the actual
Swedish B2 lines
34
National borders for the DK implementation
ERTMS Corridor B ~ RFC3
35
Time schedules
Phases Fjernbane and S-bane
2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Fjernbane
2021
Procurement
Design
Test
Roll-out
S-bane
2018
Procurement
Design
Test
Roll-out