Upload
elvin-dawson
View
223
Download
1
Tags:
Embed Size (px)
Th
e S
cottis
h P
arlia
men
t
Starts on next page
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Sep
tem
ber
2000
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Holyrood Report, Fraser Chapter 8 page 97
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Scottish Parliament Project Organisation Structure 2000
Multi Headed Client, Fraser Report Chapter 12 page 194
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Other Parliamentary buildings
http://www.scottish.parliament.uk/business/research/briefings-03/sb03-52.pdf
TOOL STANDARD USEAGE USEAGE ON SCOTTISH PARLIAMENT BUILDING
Launch Meeting Understand and agree scope and responsibilities
Project Manager was not in position at the first meeting
Action Plan/Work Breakdown Schedule
Identify activities, durations, milestones, personnel
This was in place, but not updated, hence useless
Activity Orientated Budget
Allow cost estimates based on historic data gathered on similar projects.
Not adopted.
Risk Management (budgetary)
Identify sources of risk, analyse them and agree a response
Risks were identified and analysed but no action taken.
Project Evaluation and Review Techniques
Calculate activity slack/float times and rank in order – pessimistic, most likely, optimistic
This does not appear to have been carried out and certainly not adhered to.
Gantt Chart Sequencing of operations Bovis utilised their own methods, which were criticised by team members as being difficult to understand.
Goldratt’s Critical Chain
To focus on common project issues of unrealistic due dates, too many changes, lack of resources and data, unrealistic budget.
Trade offs should have been made between design – cost or design – time, but this did not occur.
Plan – Monitor – Control Cycle
Specific measurement of performance cost and time to allow these items to be controlled. Data should have been collected and regular reports instigated.
These reports were compiled, but the findings “filtered out” by the civil service to give an unrealistic performance report.
(adapted from Meredith et al, 2004 and Fraser, 2004)
STANDARD PROJECT MANAGEMENT TECHNIQUES Th
e S
cottis
h P
arlia
men
t
Earned Value Analysis Measurement of % budget spent against completion – not a good indicator of completion.
Not adopted in this case
Project Control Should regulate results by altering activities accordingly by correcting errors, considering impact on creativity and innovation.
Ineffective as the architect ignored the project manager’s instructions and requests.
Go/No Go System Agreed standard must be met before permission is given to continue with another item of work
Not adopted – instead post-control seems to have been in place.
Change Control Requested changes should be reviewed, impact on other areas evaluated, communicated and agreed prior to action.
Not followed – architect and client simply agreed changes without informing project manager or other team members
Project Evaluation Appraise progress vs goals and objectives to improve performance
Conducted but ignored.
Project Termination Decide whether to continue with an under-performing project based on “sunk costs” or to terminate and cut losses.
Considered but never seriously evaluated.
Final Report Measure project’s performance, admin, organisation structure, project management techniques.
Not yet prepared.
(adapted from Meredith et al, 2004 and Fraser, 2004)
TOOL STANDARD USEAGE USEAGE ON SCOTTISH PARLIAMENT BUILDINGTh
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/business/research/pdf_res_notes/rn01-64.pdf
Mr Davidson drew a number of conclusions in his report including the following;
“…it must be noted that in costing terms the Spencely Report indicated a realistic price range expectation of £195 Million to £230Million. This was at a stage when some of the designdifficulties were not fully designed through. The conclusion from this is that the motion put to and passed by the Scottish Parliament, known as the “Jackson Motion”, which was for afixed cash sum at current prices of £195 Million, was somewhat optimistic and, in light of the complexity of the tender and control process inherited from the previous Scottish OfficeAdministration, naïve for such a complicated and indeed unique design.”
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/business/committees/historic/audit/reports-00/aur00-06-03.htm#ana01
• 28 SEPTEMBER 2000.• At the Audit Committee meeting on
Tuesday, 26 September, Muir Russell agreed to provide notes on a number of issues that were touched on during the evidence taking session on the Auditor General for Scotland's Report on the new Scottish Parliament Building.
• I thought it would be helpful to put in writing the areas on which the Committee is expecting to receive clarification. These are:
• Details of the person specification and recruitment method adopted for the replacement project manager
Th
e S
cottis
h P
arlia
men
t
RESPONSE
• Appointment of Project Manager• As Dr Gibbons and I told the Committee, we were able to
minimise the gap following the resignation of the former project manager because the project team was clear about the type of person and experience needed for project manager in the circumstances of this project and a suitably experienced person was available to transfer to this role. He was at that time project manager on the interim Parliament project (the Mound), performing successfully in that role, so he was a known quantity.
• His appointment to that post followed a decision to establish separate project management for the interim Parliament project, to ensure its successful delivery and to enable the Holyrood project team to concentrate on the main project itself. He was appointed after discussion with a number of project management companies on how best to secure the capability to move the interim Parliament project forward quickly, and was seconded from Project Management International Plc, of which he was and remains an employee, with reimbursement made to the company
Th
e S
cottis
h P
arlia
men
t
http://www.parliament.uk/commons/lib/research/notes/snpc-03357.pdf
• Lord Fraser highlighted in the Holyrood Inquiry that:
• …the £40 million figure could never have been a realistic estimate for anything other than most basic of new Parliament buildings. However, what can be stated clearly is that at the time £40 million was included in the White Paper, there was no clear understanding whether that was a total cost including professional fees or only a construction cost. It was certainly not explained to the Scottish public what the figure
Th
e S
cottis
h P
arlia
men
t
• The Auditor General Report of 2004 made the following conclusions:
• Spillage• The main cause of the 20 months delay to the project since
September 2000 was the• production of detailed design variations and the late supply of
information during the• construction process.• Cost Increases• The main reasons for construction cost increases after 2000
were design development• and delay in the construction process. The design development
was entirely related to• realising the detail of the building and aspects such as the
quality of finish and the• palette of materials that were used, in accordance with the
client’s requirements.• Project management and control• Although it is likely that a high quality building is being
delivered, the time and cost• objectives have not been met. The same quality could have
been achieved for less if• the whole design and construction process had been better
executed.
Th
e S
cottis
h P
arlia
men
t
Summary of the Holyrood Inquiry’s Conclusions andRecommendations
• The Holyrood Inquiry was published in September 2004 by Lord Fraser.
• One of the principal conclusions found in the Holyrood Inquiry was that “whenever there was a conflict between quality and cost, quality was preferred”.
• Lord Fraser further concluded that since Donald Dewar was determined in building a new parliament for Scotland as soon as possible, the timetable dictated the high risk and “fast track” procurement route.
• In regards to the procurement method adopted, there was an inadequate level of evaluation or understanding of the construction management route; subsequently ministers were not informed of all the risks involved.
Th
e S
cottis
h P
arlia
men
t
The Origins of the £40 million Figure
The evidence before the Inquiry is reasonably clear that this figure originally came from Mr Wyllie. On 10 June 1997 he minuted Mrs Doig with his costing of the option of onstructinga new building on a greenfield site. Assuming a building with an area of 15,000m² gross (11,250m² net – a net to gross ratio 25%) including 1,000m² for the Chamber, 3,000m² for Committees and Ministers and 11,000m² for the remainder, he put forward figures “in the order of £35-40 million”.His minute made it clear that the figures included professional fees, fit out, furniture and VAT although the position in this respect contrasts with his written recognition in which he said that his figures had “excluded site works, fit out, professional fees and VAT”. In a further minute of the same date to Dr Gibbons he elaborated on that range of figures asfollows:
Holyrood Report, Fraser, Chapter 3 Page 23
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-11.htm#1
Was a ‘Pause’ Recommended?• Within the Spencely Report there is no specific
recommendation for a two month pause in the Project to enable a costed design to be achieved. However, in evidence Mr Spencely explained that the eight week pause was implicit within paragraph 5.4 of his Report:
• ‘It is clearly imperative that the Brief is frozen now and that the Design Team proceeds immediately to produce a Scheme Design including a cost plan to a Brief and a budget approved by the client, so that approval may be given to proceed with the Project by 8 June 2000.’
• There has been some uncertainty amongst witnesses as to whether SPCB members were aware that Mr Spencely was recommending a pause. During a discussion of the Report’s findings at the SPCB meeting on 28 March, Dr Gibbons advised that: "Detailed design and construction would continue to run in parallel and there was no reason for a pause until 8 June." There is also reference to Mr Spencely recommending one option as: "the cessation of all project activity for a period of three months" in the SPCB’s report to Parliament,
Th
e S
cottis
h P
arlia
men
t
• In relation to the functions of his suggested "Progressing Group" Mr Spencely’s evidence was as follows:
• "I expected the Progressing Group to operate as the Client — receiving reports and recommendations "upwards" from the Project Sponsor and acting on the latter — to accept, modify or reject; and receiving and sifting requests for variations to the Brief "downwards" from MSPs and Parliamentary staff; all in the light of the Budget and the Programme; and to control Budget expenditure and Programme by making the appropriate management decisions".
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-10.htm#3
• In his oral evidence Dr Gibbons, when asked about viability at handover, said:
• "From what we know now, it clearly was not."• I am bound to conclude that:• 1. The Brief was not up to date, and did not reflect the
changes made since November 1998. • 2. The Brief did not anticipate the requirements of the
Parliament with the inevitable result that adherence to it would have produced an unsuitable building.
• 3. The budgeted construction cost of £62 million was flawed in that:
• a. there was inadequate accounting for risk, and the stated budget bore no relationship to a cost plan;b. there had been a failure to fully appreciate the complexity of the design; andc. account had not been taken of considerations of blast and security.
• In short, the Project was not in a viable and healthy condition when it was handed over to the SPCB on 1 June 1999.
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/vli/holyrood/inquiry/sp205-14.htm#12
Impact on Overall Cost and Programme
• 13.77 There is no doubt that by having to focus on specific recurring themes in relation to Queensberry House, the HPG and the Project Team found it difficult to make progress and that these issues were discussed at the highest level by the First Minister and Presiding Officer to try and find a resolution. Crucially, however, it is to be noted this did not cause any delay to the overall programme, as Queensberry House was never on the critical path. At the same time the costs of Queensberry House have been significantly greater than anticipated at the outset.
Th
e S
cottis
h P
arlia
men
t
• http://www.scottish.parliament.uk/business/committees/audit/reports-04/grice-auditrep.htm
Adequacy of Cost Plan • AGS’s comments in paragraphs 4.3 – 4.7 of the
report reflect a misunderstanding of the purpose of the Cost Plan at Stage D. Such a plan is needed to translate the Stage D design into individual works packages and to estimate the value of the works under each package. This provides a basis for project management and the consultants to compare the values of tenders based on the Stage D design. The adequacy of the Cost Plan for this purpose is reflected in the fact that, on average and after allowing for inflation, tenders on which contracts were based were within 5% of the Cost Plan Estimate. In view of the uncertainties identified in Exhibit 9, this could be regarded as a reasonably satisfactory result.
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
Th
e S
cottis
h P
arlia
men
t
http://www.scottish.parliament.uk/business/committees/historic/finance/or-02/fi02-2502.htm
• Alasdair Morgan: I find it difficult to understand why the target date has not only slipped three to four months since last you gave evidence on 8 October, but has become less certain rather than more certain.
• Sarah Davidson: The current target date of best completion at the end of August, which means that everything will have happened to the best possible outcome, has the same status as the previous date of the end of April.
• Alasdair Morgan: Do you have a worst possible outcome date?• Sarah Davidson: No.• Alasdair Morgan: What kind of Gantt chart is used? Some kind of
worst-case scenario must have been considered.• Robert Brown: The object of the exercise is to finish the thing as
quickly as possible—that is clearly what we are after and the progress group is keeping on top of the contractors to try to ensure that that happens. However, as we have already explained, the business of the glazing and blast proofing could have had a dramatic effect on the progress of the contract. Had last Friday's blast test failed, we would be coming to the committee today to report a serious situation; there are no two ways about that. Happily, the blast test was passed. Although we have to take account of the fact that the test had to happen in the first place, that is part of the risk review that is taking place at the moment. The major concerns that we would have had if the blast test had failed have not materialised. We are therefore able to come to the committee with good news on that particular point because passing the test removes what was probably the single biggest risk that remained on the contract.