Upload
mahola
View
42
Download
1
Tags:
Embed Size (px)
DESCRIPTION
The Material Requirements Planning Process. What is MRP?. MRP answers the following questions: What materials are required? How many of the materials are required? When are the materials required?. A Few Key Terms. PIR – Planned Independent Requirements - PowerPoint PPT Presentation
Citation preview
The Material Requirements
Planning Process
Slide 2
What is MRP? MRP answers the following questions:
What materials are required? How many of the materials are required? When are the materials required?
Slide 3
A Few Key Terms PIR – Planned Independent
Requirements Forecasts based on actual and forecasted
sales CIR – Customer Independent
Requirements Forecasts based on actual customer sales
Usually derived from sales orders Dependent Requirement – A dependent
item (such as assembly or raw material) Independent Requirement – Not
dependent on another material
Slide 4
MRP AND Production
Slide 5
MRP Process Flowchart
Slide 6
MRP Problems (1) Too much inventory
Materials in stock that we cannot sell Raw materials that we no longer need in
the manufacturing process Materials that have lost significant value Expired materials
Slide 7
MRP Problems (2) Too little inventory
Out of stock conditions Backorder conditions
Slide 8
Cisco Case Purchased extra parts Did not accurately estimate demand Did not forecast demand drop-off Cisco wrote off $2.5 billion in inventory
in 2001
Slide 9
MRP Data Dependencies Materials (Material masters) Vendors (for acquisition) Production (for estimates) Warehouse (to get raw materials and
store finished goods)
Slide 10
Production Planning Process (Overview)
DemandManagement
Forecasting
Sales & OperationsPlanning
SIS CO/PA
MPS
MRP
ManufacturingExecution
OrderSettlement
ProcurementProcess
Strategic Planning
Detailed Planning
Slide 11
What Causes an MRP Sales and operations planning estimates
materials (finished goods) requirements Sales quotation / orders
Demand management calculates the required raw materials to produce the finished goods
Final production proposals are generated which trigger production
Slide 12
MRP Master Data Bill of material is used to determine raw
materials Product routings are used to estimate
production time Material Master have various views that
control the MRP process
Slide 13
MRP (SAP) Remember that we have four MRP views
of a material Discussed in the next screens
MRP is defined at the plant level as expected We can subdivide into MRP areas
MRP is relevant to both discrete, repetitive, and process manufacturing
Slide 14
MRP vs MPS Master Production Scheduling
One level of a material’s BOM is used to calculate material requirements
It’s a high level analysis Material Requirements Planning
Run after MPS to determine detailed requirements
It’s time phased (recommendations to reschedule open orders)
Considers dependent requirements Assemblies (semi-finished goods)
Slide 15
MRP (Types of Planning) Consumption-based relies on historical
consumption data Reorder point planning
See figures 8.3 and 8.4 Forecast-based planning uses historical
data and forecasted estimates Time-phased planning is used when
materials arrive on specific days of the week
Slide 16
MRP Reorder Point Planning
Slide 17
Reorder Point Planning (Details) When material is withdrawn, the reorder
level is checked Net requirements are then calculated
Available stock + firmed receipts (purchase orders, production orders)
If a shortage exists, calculate the procurement quantity according to material master lot sizing procedure
Procurement is then scheduled
Slide 18
MRP (Types of Planning – Illustration)
Slide 19
Material Master (MRP Tabs) MRP1 – Overall strategy MRP2 – Scheduling MRP3 – Material availability MRP4 – BOM Selection
Slide 20
MRP 1 (MRP Procedure) MRP type
Forecast-based planning, time-phase planning, etc.
Reorder Point is only used only with reorder point planning
Planning time fence - Number of days before procurement that planning (automated procurement) is frozen Only applies to MRPs with “firming types”
Slide 21
MRP 1 (Lot Size Data) Lot size – The procedure used to
determine the lot size (quantity produced) Static lot-sizing
Fixed lot size (predetermined value) Lot-for-lot (exact quantity required)
Period lot-sizing (combine requirements for multiple time periods)
Optimum lot-sizing (takes into account economic order quantity and economic production quantity)
Slide 22
MRP 1 (Lot Size Data) Minimum and Maximum Lot size
contains the min and max amounts that can be made during a production run
Ordering costs are used in optimum lot sizing procedures
Rounding profiles used to round the lot size to a “deliverable quantity)
Slide 23
MRP 1 (Illustration)
Slide 24
MRP 2 (Procurement) Procurement type
In-house production External
In-house production time This comes from production It can be derived from product routing
Slide 25
MRP 2 (Scheduling) In-house production time
Only used when we are producing goods “in-house”
This comes from production Planned delivery time is only used when
material is procured externally GR (Goods receipt) processing time
Slide 26
MRP 2 (Net Requirements) Safety stock
Desired Minimum
Safety time ind. is used to enable safety stock calculations
Slide 27
MRP 2
Slide 28
MRP 3 (Forecast Requirements) Period Indicator
Time period for which planning takes place (M=Monthly, W=Weekly, etc…)
Fiscal Variant Use to describe how the fiscal year is
calculated (for financial accounting)
Slide 29
MRP 3 (Planning) Strategy group
Make to stock Make to order
Sales order based consumption Assemble to order
Similar to make to order Assemble finished goods from
prefabricated assemblies There are others
Slide 30
MRP 3 (Planning) Consumption mode
Backward or forward Back. consumption per contains the
number of workdays used for backward consumption
Forw. Consumption per contains the workdays for future consumption
Slide 31
MRP 3 (Planning) Availability check
Strategy to determine whether a material will be available on a specific date
Supply side Existing inventory, purchase requisitions,
production orders, purchase orders Demand side
Material reservations, safety stock, production orders
Slide 32
MRP 3 (Planning
Slide 33
MRP 4 (BOM) BOM Selection Method
Determines which bill of material to use based on
Production version Date Order quantity
Requirement Group Combine or display requirements
individually
Slide 34
MRP 4 Define repetitive manufacturing
characteristics Storage Location MRP is used to plan for
a specific storage location
Slide 35
MRP 4
Slide 36
Forecasting (Introduction) Caveat – Forecasts are always wrong
But some are more wrong than others Accurate forecasts essential to
manufacturing Our goal is to match supply and
demand This is challenging for innovative products,
fashions
Slide 37
Forecasting Models Trend Seasonal Trend and seasonal Constant
Slide 38
Strategy Groups On MRP 3, it defines the high-level
strategy used to plan production The following are make-to-stock (10) make to stock is the simplest
Based on PIRs (30) production by lot size (40) Planning with final assembly
Utilizes consumption (discussed in a moment)
Slide 39
Strategy Groups Make-to-order production strategies
(20) make-to-order (used for a particular sales order)
(50) Planning without final assembly (we are really building “assemblies”)
(60) Planning with planning material Use with variant parts such as the same
products in different container with different labels
Slide 40
The Process of Consumption Customer Independent
Requirements consume materials produced through Planned Independent Requirements
CIRs are filled through existing stock Planned Independent Requirements are
created in anticipation of customer orders
See table 8.1 on page 280
Slide 41
Consumption (Types) Backward
CIRs consume PIRs dated prior to the CIR Forward
CIRs consume PIRs dated after the CIR Combination
Slide 42
Consumption (Illustration)
Lot Size
Replenishment Lead Time
Safety Stock
Reorder Point
Slide 43
Product Groups Instead of planning for a single product,
we plan for a group of related products or “product family”
It’s possible to hierarchically group products using a process called aggregation Product groups can be nested
Materials can belong to different product groups so as to support different planning scenarios
Slide 44
Product Group (SAP) Transaction MC84, MC85, MC86 to
maintain product groups
Slide 45
GBI Product Groups
Slide 46
Product Groups (Other) Product groups can be assigned a
proportion Low-level plans can be aggregated into
high-level plans High-level plans can be disaggregated
into low-level plans
Slide 47
Global Bike Product Groups
Slide 48
Sales and Operations Planning (SOP) Purposes
Create sales forecasts Define inventory requirements It’s a high-level plan (rough-cut plan)
Operations plans are developed from SOP These are the formal plans to produce
Required only for make-to-stock production
We perform aggregation and disaggregation here
Slide 49
Top-Level Product Group
Slide 50
Second Level Product Group
Slide 51
SOP Planning (SAP)
Slide 52
SOP Planning Used to generate production plans
based on various assumptions (sales forecasts)
Types Standard planning uses predefined
planning models Flexible planning allows users to configure
their own sophisticated production plans
Slide 53
SAP Planning Table It’s a tabular form containing sales,
production, and stock-level estimates Sales data derived from forecast
Slide 54
Sales Planning Table (Illustration)
Slide 55
Sales Planning (Fields) Sales contains the sales plan (number
of units we plan to sell) Production contains the production
plan (calculated by the system) Target stock contains the desired
inventory levels Day’s supply contains a calculated
value Inventory / sales per workday
Slide 56
Sales Plan (Creating) From profitability analysis in
management accounting From historical sales From adjusted historical sales Manually From another product group sales plan
Slide 57
Disaggregation One the high-level product group plan is
complete we disaggregate to the raw material level
Slide 58
MRP – The final step MRP plans for all elements in the BOM