95
THE IMPORTANCE OF PRELIMINARIES ITEMS NORHISHAM B. ABDUL GHANI UNIVERSITI TEKNOLOGI MALAYSIA

The Importancy of Preliminaries

Embed Size (px)

Citation preview

Page 1: The Importancy of Preliminaries

THE IMPORTANCE OF PRELIMINARIES ITEMS

NORHISHAM B. ABDUL GHANI

UNIVERSITI TEKNOLOGI MALAYSIA

Page 2: The Importancy of Preliminaries
Page 3: The Importancy of Preliminaries

" I hereby declare that I have read this project report and in

my opinion this report is adequate in term of scope and quality

In fulfillment of the requirement for the award of the degree of

Master of Science (Construction Management)'o

I Signature :

Name of Supervisor ;

Date :

Assoc. Prof. Aziruddin Ressang

12th .December 2006

Page 4: The Importancy of Preliminaries

THE IMPORTANCE OF PRELIMINARIES ITEM

NORHISHAM BIN ABDUL GHANI

A Project Report in partial fulfillment of the Requirements for the award of the degree of

Master of Science (Construction Management)

Faculty of Civil Engineering

University of Technology, Malaysia

DEC 2006

Page 5: The Importancy of Preliminaries
Page 6: The Importancy of Preliminaries

Specially dedicated to my beloved family my farther and mother Abdul Ghani Abdul

Rajab and Komariah Hussain, my sisters Norhasmimi and Norhafikan for your support

and everlasting love and care…

Page 7: The Importancy of Preliminaries

II

ACKNOWLEDGEMENT

In preparing this master project report, it was never an individual effort. I was in

contact with many people especially contractors and academicians. They have involved

in contributing towards my understanding and thoughts directly or indirectly. In

particular I wish to express my greatest sincere appreciation to my supervisor Asso. Prof

Azirudin Ressang with all the guidance and advices given from the supervisor this

master project was able to complete on time. His dedication and continuous assistance

have led the author to strive for better achievement in this master project.

I am also wish to express my gratitude to my family and friends for their support

and assistance at various occasion. Last but not least. I also wish to all those who have

contribute in any way in making this master project a possible one.

Page 8: The Importancy of Preliminaries

III

ABSTRACT

The items found in the preliminaries section of a bill of quantities are usually the

most difficult to price and would produce the greatest variation in prices with each

contractor having his own idea of pricing preliminaries. Not all preliminary items need

to be priced, some are remain unpriced. The aim of the study to understand the

preliminaries item and identify mandatory items in selected project that should be priced

by contractors. The findings will give benefits to contractor as strategies to price

preliminaries accordingly and accurately. The study conducted with reference to the

selected group of contractor who has vast experiences in tender pricing. The

methodology adopted for the study includes interviews with contractor and industry

wide questionnaire survey among the contractors that involved in JKR projects. The data

collected were analysed using content analysis method and using appropriate statistical

method such as frequency analysis and relative index method. The study has determined

what the items are considered as mandatory items that should be price by contractor and

the strategies in pricing preliminaries as a guide. Apart from that the study also

established factors that influence in pricing preliminaries as well as can help contractor

pricing preliminary accurately.

Page 9: The Importancy of Preliminaries

IV

ABSTRAK

Item kerja-kerja awalan yang dijumpai di dalam senarai kuantiti adalah selalunya

yang paling sukar untuk dihargakan dan menghasilkan perbezaan yang ketara di dalam

harga dengan setiap kontraktor mempunyai idie dan cara tersendiri dalam menghargakan

kerja-kerja awalan. Tidak semua kerja-kerja awalan perlu dihargakan, sesetengah adalah

kekal tidak berharga. Matlamat kajian adalah untuk memahami item bagi kerja-kerja

awalan dan mengenal pasti item mandatori di dalam projek terpilih yang sepatutnya

dihargakan oleh kontraktor. Hasil kajian akan memberi faedah kepada kontraktor

sebagai strategi untuk menghargakan kerja-kerja awalan dengan sebetulnya dan tepat.

Kajian telah dijalankan dengan rujukan kepada kumpulan kontraktor terpilih yang

mempunyai pengalaman yang luas dalam menghargakan tender. Kaedah yang dipilih

bagi kajian ini termasuklah temubual bersama kontraktor dan soal selidik industri di

antara kontraktor yang terlibat dengan projek JKR. Data terkumpul di analisa dengan

menggunakan kaedah kandungan analisis dan kaedah statistik yang sesuai seperti kaedah

analisis frekuensi dan indeks relatif. Kajian telah menentukan apakah item-item yang

dikira sebagai item mandatori yang sepatutnya dihargakan oleh kontraktor dan strategi

untuk dijadikan sebagai panduan. Selain dari itu, kajian juga telah mengetahui faktor

yang mempengaruhi dalam menghargakan kerja-kerja awalan dan seterusnya dapat

membantu kontraktor untuk menghargakan kerja-kerja awalan dengan tepat.

Page 10: The Importancy of Preliminaries

V

TABLE OF CONTENTS

CHAPTER TITLE PAGE

TITLE PAGE II

DECLARATION III

DEDICATION IV

ACKNOWLEDGEMENT V

ABSTRACT VI

ABSTRAK VII

TABLE OF CONTENTS VIII

LIST OF TABLES IX

LIST OF FIGURES X

LIST OF APPENDIXES XI

1 INTRODUCTION

1.1 Background 1

1.2 Problem Statement 2

1.3 Objectives 4

1.4 Scope of Study 4

1.5 Brief Research Methodology 5

2 THE PRELIMINARIES ITEMS

2.1 Introduction 7

2.2 Definition of Project Overhead as Preliminaries 8

2.3 The Category of Preliminaries item 9

Page 11: The Importancy of Preliminaries

VI

2.4 The preliminaries Section in standard Method of

Measurement (SMM) 11

2.5 The Preliminaries Section in P.W.D Format 16

2.6 Summary 19

3 MANDATORY ITEMS IN PRELIMINARIES

3.1 Introduction 21

3.2 Items Normally priced by Contractor 21

3.3 The Mandatory Items 24

3.3.1 Insurance 25

3.3.2 Workmens’ Compensation 25

3.3.3 Performance Bond 25

3.3.4 Setting Out 26

3.3.5 Construction Industry Development Board

(Payment for levy) 27

3.3.6 As-built Drawings 28

3.3.7 Work Programme 28

3.3.8 Hoarding and Fencing 29

3.3.9 Client/Employer’s Requirement 29

3.3.9.1 Vehicle for the S.O 30

3.3.9.2 Equipment and Facilities 31

3.4 Conclusion 32

4 METHODOLOGY

4.1 Introduction 33

4.2 Determination of the Research Objectives 33

4.3 Literature Review 34

4.4 Data Collections 34

4.4.1 Development of the questionnaire in the survey 35

4.5 Interview with the experts 35

4.5.1 Objective of the interview 36

Page 12: The Importancy of Preliminaries

VII

4.5.2 Methodology of interview 36

4.5.2.1 The structure Interview Questionnaire 37

4.5.2.2 Face to face interview 37

4.6 Industry Questionnaire of the industry Survey 38

4.6.1 Methodology of the industry Survey 38

4.6.2 Questionnaire for the industry Survey 38

4.7 Data Analysis 39

4.7.1 Content Analysis 40

4.7.2 Frequency Analysis 40

4.7.3 Average Index Analysis 40

4.7.4 Relative Index Analysis 42

5 FACTORS INFLUENCING PRICING DECISIONS

5.1 Introduction 44

5.2 Factor Influencing Pricing Decisions 44

5.2.1 Understanding Contract Particular 45

5.2.2 Site Condition 45

5.2.3 Location of the site 46

5.2.4 Difficult contract and restriction site 46

5.2.5 Magnitude of Contract 47

5.2.6 Plant and Equipment 47

5.2.7 Any Obligation or restriction imposed by Employer 48

5.2.8 Commitment number of project 48

5.2.9 Availability at Resources by the Contractor 48

5.3 Data analysis and Result 49

5.3.1 Background of the Respondents 49

5.3.2 The Industry Questionnaire Survey 51

5.3.3 Factor that influence the pricing of Preliminaries

By Contractor 52

5.3.4 Other Factor that influence the pricing of

Preliminaries by Contractor 53

Page 13: The Importancy of Preliminaries

VIII

5.3.5 General Comment from the respondents 53

6 DISCUSSION

6.1 Introduction 55

6.2 Factor influence The Pricing of Problem Items 56

6.3 Other Factor that Influence The Pricing of 59

Preliminaries items by the Contractors.

6.4 The Summary of Overall Findings of Study 60

7 STRATEGIES IN PRICING PRELIMINARIES

7.1 Introduction 62

7.2 Strategy in Pricing Preliminaries 62

7.2.1 Establishing pricing objectives 63

7.2.2 Examining each of prelim items 65

7.2.3 Considering Factors Influencing pricing decisions 66

7.2.4 Attention to methods of price determination 67

7.2.5 Tactical consideration in setting prices 68

7.3 Conclusion 69

8 CONCLUSION AND RECOMMENDATION

8.1 Introduction 70

8.2 Conclusion 70

8.3 Recommendation for further study 72

Page 14: The Importancy of Preliminaries

IX

LIST OF TABLES

TABLE NO. TITLE PAGE

4.1 The level of agreement and evaluation for average

Index analysis 41

5.1 Distribution of the respondents based on disciplines 50

5.2 Distribution of panel respondent based on experience 51

5.3 Number of respondent to the Questionnaire 52

5.4 Frequency analysis or factors in pricing preliminaries 53

6.1 Factor influencing price in preliminaries according to

ranking of importance 56

Page 15: The Importancy of Preliminaries

X

LIST OF FIGURES

FIGURE NO. TITLE PAGE

1.1 Research methodology sequence. 6

4.1 Five ordinal measures of agreement of Likert’s scale. 35

5.1 Distribution of expert respondent based on professional

by percentage. 50

5.2 Distribution of panel respondent based on experience

by percentage. 51

6.2 Percentage allow for lump sum(preliminaries item)

By respondents. 58

6.3 Percentage of experience of respondents in construction

Industry. 59

Page 16: The Importancy of Preliminaries

XI

LIST OF APPENDIXES

APPENDIX TITLE PAGE

A Survey Questionnaire 76

Page 17: The Importancy of Preliminaries

1

CHAPTER 1

INTRODUCTION

1.1 Background

The preliminaries section in bill quantities is one of the most important sections

that require being priced preliminaries, describing and consisting of informations of

project, requirements related to project, services and facility that need to be prepared,

contract conditions and so forth. Items in this section are divided into two parts, one is

descriptive item where intended to give contractor overall picture of project that no need

to priced. The other part is where contractor need to prepare and provide where it needs

to be priced. Doing estimating for preliminary items is really complicated and always

changed for every project.

Page 18: The Importancy of Preliminaries

2

There is no specific and standard way of doing the estimate for preliminaries.

However previous project can be used as guidance for the estimating in the future.

Although the approximate cost for each item can be obtained, by using previously priced

similar jobs as yardstick still remains at best (John Milne, 1990). Nowadays, there are

many contractors company in the country looking for projects. They are competing each

other by putting in low price in order to get the projects. The best way is by cost cutting

in the preliminary items. Yet, they have to follow all restrictions and requirements by the

client’s and priced what client’s wanted for that particular project. Failure in fulfilling

and pricing such items will raise problem later especially during construction. The

contractor has to bare their own cost and definitely will incurred lose to contractor. This

is because whatever items listed inside the preliminary is deemed to be priced by the

contractor.

1.2 Problem Statement

The items found in the preliminaries section of a bill of quantities are usually the

most difficult and arbitrary of all to price. If all the tenderers’ priced bills for any project

could be examined, this preliminaries section would produce the greatest variation in

prices with each estimator having his own idea as to the scale and extent of the costs

involved. There is problem encountered by client during preparing tender evaluation

especially on cost comparison for preliminaries each of tenderer. If there are 20

tenderers, there will be 20 different set of price. Some of them not even priced the

preliminaries and just sufficiently allowing certain percentage out of construction cost to

the preliminaries. Overhead cost can be divided into general overhead and job overhead

costs. General overhead costs include all overhead costs that cannot be charged to any

particular job. Job overhead costs include all overhead costs include all overhead and job

but cannot be charged to labour, materials, or equipment(H.E. Pulver, 1989).

Page 19: The Importancy of Preliminaries

3

Preliminaries are all about cost overhead that has to be borne by the contractor to start

the work and during the construction period. The first thing they have to do when

deciding to go for tender is to understand what the items that need to be priced are. What

are the extra restrictions, limitations and extra requirements that client’s imposed for that

particular project. Pricing of the preliminaries section will usually be one of the last

operations before adjudication of the tender price, and will require that decisions relating

to working methods, major plant, gang strengths, subcontractors, temporary work (Mudd

D.R., 1993).When there is not enough time, the contractor tend to look back at a

previously priced set of preliminaries similar project and then extract the price for use in

the current project for tender(John Amile, 1986). If contractor overlooked such item, it

could lose him a great deal of money and they have to bare all the cost. It is believed that

an under-assessment of Preliminaries as far as cost is concerned is one of the reasons

why many builders and contractors do not receive a proper return of profit – that is to

say, by under-pricing their Preliminaries the loss sustained thereby is deducted from

profit (R.D Wood, 1990). This because all preliminaries items listed in the tender

deemed to be priced by the contractor accordance with the Principle of the Standard

Method of Measurement of Building Works.

Since each set of preliminaries is different in pricing, therefore is a necessary to

understand each of preliminary items. A tremendous amount of thought and care is

needed when pricing preliminaries. A constant check of the site costs and an

appreciation of all problems which arise on the site need to be understood by an

Estimator (R.D. Wood, 1990). To understand which items that mandatory to be priced

by the contractor based on findings of research so as to avoid any discrepancies and

problems arise during construction as well as reduced loses to the contractors due to

overlooked the preliminaries items and reasons why many of them do not receive a

proper return of profit.

Page 20: The Importancy of Preliminaries

4

1.3 Aims and Objectives

The aim of the study is to understand the preliminaries item and identify mandatory

items in selected projects that should be priced by contractors. The findings will give

benefits to contractor as strategies to price preliminaries accordingly and accurately. The

aim of this research can be achieved with the following objectives.

1) To identify the mandatory items in the preliminary

2) To identify the factor that influence in pricing preliminaries

3) To propose a strategies for contractor to price preliminaries.

1.4 Scope of the Study

The scope of study will focused on the government projects with the medium to bigger

project capacity within range of RM 1 million and above carried out by JKR using PWD

203A form of contract. The study specifically carried limited in the area of Selangor and

Kuala Lumpur. The data collection about preliminary estimate will be gathered from

literature review a survey will be carried out among contractor specifically class A and

B contractor just to know their understanding agreed on the results that have been

produced.

Page 21: The Importancy of Preliminaries

5

1.5 Brief Research Methodology

The methodology used in conducting this research is through literature search,

data collection, structured interviews with the professionals who are involved in their

estimating and contract works and questionnaire survey among the contractors in the

Selangor and Kuala Lumpur.

Data collection will be gathered from the project as stated in the scope of study.

From the results, the questionnaire survey will be conducted among the contractors

within the category of the study to asses their opinions of the findings towards the

objectives of the study. Besides the questionnaire survey some interviews has also been

conducted with the professionals as the expert panel, project manager, engineer and

quantity surveyor to assess their opinions toward the findings each preliminaries items

based on data that have gathered. The interviews are divided into face to face question

and answer session and answering the structured questionnaire.

The qualitative data generated from the questionnaire has been analyzed using

statistical method and finally inferences were made to support the study findings. The

overall sequence of research process undertaken is shown in figure 1.1

Page 22: The Importancy of Preliminaries

6

Figure 1.1 Research Methodology Sequence

Determining the Research Objective and Scope

Literature Review

Data Collection

Data Analysis

Discussion

Conclusion and Recommendation

Interview with the Experts panel (Face to Face & Structured

Questionnaire)

Questionnaire Survey with the Contractors

Page 23: The Importancy of Preliminaries

7

CHAPTER 2

THE PRELIMINARY ITEMS

2.1 Introduction

Preliminary is one of the important parts in the Bill of Quantities. The items

generally set out to describe the requirements of the peculiar to the job in question, the

nature of the site, description of the works and names of the parties involved conditions

of the contract. According to John A Milne (1990) this part (preliminaries) of the bill is

the most difficult to price. It is normal practice by some of the contractors in Malaysia,

which they still resort to allowing a lump sum for all preliminaries items based on the a

percentage of the tender value. The calculation of the preliminary cost is one of the

hardest and complicated where there is no specific method to measure and always differ

between one project to another. Many factors influencing preliminary costing such as

main work value, the size of the project, location, complicated of the work and duration

of the project. Normally estimate for preliminaries estimated between 5% to 10% from

main work value. This is based on example of the percentage preliminaries work that

had been taken from PWD projects within period of January to June 1990.

Page 24: The Importancy of Preliminaries

8

Basically the contractors will be using of their previous priced similar jobs as a

yardstick and this remains the best method to obtain the approximate cost for

preliminary. But still the preliminary section will give the greatest variation in prices

especially during tender evaluation

According to John A. Milne (1990) although space is provided for extra items to

be written in when required. It is also likely that all of the items would be needed for

every contract, in which case those would obviously remain unpriced. The schedule

would be priced in accordance with the requirements stated in the preliminaries and a

total lump sum figure obtained which is then transferred to the tender summary.

2.2 Definition of Project Overheads as Preliminaries

According to J.I.W Bently, (1986), Project overhead is defined in the Code of

Estimating (CEP) as the cost of administering a project and providing general plant, site

staff, facilities and site based services. The project overheads are often called

‘preliminaries’. The preliminaries or project overhead cannot be priced in detail until the

construction programme, method statements and layout diagram have been prepared;

most of the items based and some, like temporary roads and hoardings, have to be

measured.

As an aid to a methodical assessment and pricing for the preliminaries or

overhead, and to act as check list, the estimator will usually use a ‘Pro-forma’(type form

of checklist) which is filled in according to circumstances. In the example there are

Page 25: The Importancy of Preliminaries

9

nineteen sections, and no matter what size of job being tendered for, all of the items

need to be checked to see if a cost will be incurred.

According to Ronald McCaffer (1986) the calculation of the sum of money

required to cover site overheads or on-costs is based upon detailed checklists containing

references to all items of materials, plant and services necessary of operate a

construction project. Allowance has to be made for the following site on-costs;

a) Supervision

b) Clerical staffs

c) Site offices and compound facilities

d) Services

e) Site transports

f) Sundries

g) General plant and major plant items.

2.3 The Category of Preliminaries item

The preliminary section of the tender documentation fulfils a number of

functions from the estimator’s point of view. At an overall level the preliminaries

section provides a high-level overview of the project, including a description of the

project and the site and details of the conditions of the contract to be used, but the

preliminaries will also include a considerable amount in the detailed information about

specified issue (Mudd D.R, 1989). Therefore, information covered in the preliminaries

section can be determined and categorized as following;

Page 26: The Importancy of Preliminaries

10

a) Descriptive items

Not all of items in the preliminaries bill will need pricing since many of them are

purely descriptive and intended to give the contractor an overall picture of the

work. The Example of each items under descriptive items are as follow:

1 The Preliminary particulars – names of the parties, description of the

site, description of the works, and submission of tenders.

2 Definitions and qualifications – definitions, quantities, cost analysis

information, pricing of preliminaries, rates in bills of quantities.

b) Condition of contract

The form of contract is always clearly stated together with a brief

schedule of the clause headings which are to apply, including those clauses

which are to be amended or deleted for this particular job and the details which

are to be inserted in the appendix to the conditions. With regard to the conditions

of the contract, most clauses will have no effect on cost at this stage and so will

not be priced.

c) Other obligations and restrictions imposed by the employer

In addition to the obligations imposed by the conditions of the contract,

there may be further obligations or restrictions imposed by the employer and it is

likely that such items will involve the contractor in further expenses such as the

Page 27: The Importancy of Preliminaries

11

provision of guarantee bond, provision of temporary accommodation and etc.

Items which appear under this heading will normally need pricing by the

estimator and for his convenience are usually grouped together.

2.4 The Preliminaries Section in Standard Method of Measurement(SMM)

Preliminaries are defined in the Standard Method of Measurement 2 (SMM2)

clearly explained, are divided into several path of heading. There are consisting of

preliminaries particular, contract, works, goods and materials by other and general

facilities and obligation. The details each of the headings as the following:

a) Preliminaries particular

Under preliminaries particular project, all parties and consultants which is

description the name, nature and location of the project shall be stated in the

preliminaries. A general description of the works shall be given. The names and

addresses of the Employer and consultants to be named in the contract as well as

other consultants shall be given. Description of site-information to indicate the

boundaries of the site, the means of access and the position of the works shall be

given. Attention shall be drawn to any drainage, water, gas and other mains or

power services known to exist on or over the site. Attention shall be drawn to

any adjacent or abutting buildings either. Information to facilitate visiting the site

shall be given. The last one in particular is drawings and other document. All

shall be given of the drawings from which the bills of quantities have been

Page 28: The Importancy of Preliminaries

12

prepared. Addresses where drawings and other documents may be inspected by

appointment or otherwise shall be given too.

b) Contract

Form, type and conditions of the contract – Where the conditions of the

contract are standard and published for general use, particulars of the edition to

be used and a schedule of the clause headings shall be given. Where the standard

conditions provide for alternative or optional clauses, the clauses which are to

apply shall be stated. Amendments to standard conditions shall be given in full.

When the conditions of the contract are not standard and published for general

use, the conditions shall be set out in full in the bills of the quantities. In either

case where the conditions provide for alternative or optional clauses, the clauses

which are to apply shall be stated. Where there is an appendix to the conditions

of the contract requiring inserting to be he damage to the work. For Employer’s

liability should be given where the cost of insuring any liability of the Employer

is required to be included in the contract sum, such cost shall be given as a

provisional sum. Under the contract should be described about obligation and

restrictions imposed by the Employer such as access to possession or use of the

site, limitations of working space, limitation of working hours and the use or

disposal of any material found on site.

Page 29: The Importancy of Preliminaries

13

c) Works, goods and materials by others

i) Works by nominated sub-contractor

Works which are required to be carried out by a nominated sub-

contractor shall be given as a prime cost sum. The name of the firm to be

nominated shall be given together with a description of the sub-contract

work. An item shall be given in each case for general attendance which

shall be deemed to include the use of the Contractor’s temporary roads,

pavings and paths, standing scaffolding, standing power operated hoisting

plant, the provision of temporary lighting and water supplies, clearing

away rubbish, provision of space for the sub-contractor’s own offices and

for the storage of his plant and materials and the use of messrooms,

sanitary accommodation and welfare facilities, which shall all be without

charge to the sub-contractor.

ii) Goods and materials from nominated suppliers

Goods and materials which are required to be obtained from a

nominated supplier shall be given as a prime cost sum. The name of the

supplier shall be given if known. Fixing goods and materials shall be

given in accordance with the appropriate clauses in this document.

Unloading, storing, hoisting the goods and materials and returning

packing materials to the nominated supplier carriage paid and obtaining

credits therefore shall be deemed to be included with the items for fixing.

Particulars shall be given where the Contractor is required to pay the

Page 30: The Importancy of Preliminaries

14

costs of conveying goods and materials to the site and/or of any special

packing or similar requirements.

iii) Works by government or statutory authorities

Works which are to be carried put by a government or statutory

shall each be given separately as a provisional or prime cost sum. Works

which are to be carried out by the government or statutory authority in

accordance with statutory obligations shall be described, stipulating the

scope and timing of the work and its effect on the Contractor’s

operations.

iv) Works or goods and materials by the Employer

A description shall be given of goods and materials provided by or on

behalf of the Employer including fixing goods and materials.

d) General Facilities and Obligation

For convenience in pricing, items for the following if applicable shall be

given. Maintaining temporary works, adapting, clearing away and making good

including any notices and fees to government or statutory authorities related to

the following items shall be deemed to be included with the items. Thus, there

may be items in the preliminaries section of the bill of quantities that might

Page 31: The Importancy of Preliminaries

15

influence the pricing generally, such as the names if the consultants, or the

particular need to execute a section of the work by a specific time. In every case

the preliminaries section of the bills of quantities should be closely scrutinized to

ascertain which items need pricing and which items have a general facilities and

obligations are:

a) Plant, tools and vehicles;

b) Scaffolding;

c) Site administration and security;

d) Transport for workpeople;

e) Protecting the works from inclement weather.

f) Water for the works

g) Lighting and power for the works

h) Temporary roads, hard standings, crossings and similar items.

i) Temporary accommodation for the use of the Contractor.

j) Etc.

However, according to J.I.W Bently (1990), from his opinion preliminaries are

defined in the Standard Method of Measurement (SMM), is largely come under the

heading of General facilities and obligation rather then other heading as describe above.

Although this section producing the major part of the cost of preliminaries, it is still has

to consider and other heading or items as mentioned earlier where we can get the overall

project cost for preliminaries item accurately.

2.5 The Preliminaries Section in PWD format

Page 32: The Importancy of Preliminaries

16

Based on practice in PWD projects that using PWD form of contract (PWD

203A), there are standard format of listing the preliminaries item for certain project

inside the Bill of Quantities. But there is still has a flexibility and space for the client to

add any additional items inside the preliminary which consider and might be necessary

to suit for that particular project. This is supported by John A. Milne (1990) although

space is provided for extra items to be written in when required. It is also likely that all

of the items would be needed for every contract, in which case those would obviously

remain unpriced. The schedule would be priced in accordance with the requirements

stated in the preliminaries and a total lump sum figure obtained which is then transferred

to the tender summary.

Basically the preliminaries item under PWD projects are divided into several

importance sections following by the sequence as below:-

1) General Information

2) Condition of contract

3) Contract administration

4) General Facilities and Obligation

5) Contingency Sum

After listing all the items according to main part of the preliminaries, then we will

determine and identified which items should be priced and should not be priced.

a) General Information

Items in this section give general information as an overall picture of the

project to contractor such as the names of the client and his professional adviser,

Page 33: The Importancy of Preliminaries

17

a description works and the site and the condition of the contract applicable to

the contract. These entire items are not to be priced.

b) Condition of Contract

Items in this section are describing about type of contract that to be used

and conditions of contract to be followed by contractor based on clauses that

included in the form of contract. In this section there are items that give

information which are not to be price and some other are required to price.

Among the main items are as following:-

i) Scope of works

ii) Contract drawing

iii) Setting out and survey

iv) Site cost management – Site agent etc

v) Variation work, Provisional and Prime Cost Sum

vi) Insurance-Public Liability, Fire, Contractors All Risk etc.

vii) Workmen’s Compensation

viii) Performance Bond – Bank Guarantee etc.

ix) Nominated Sub Contractors

x) Defect Liability Period

xi) Liquidated Ascertained Damages

xii) Etc

c) Contract Administration

Page 34: The Importancy of Preliminaries

18

Items in this section are additional to the condition of the contract for the

purpose to smooth the contract matters that to be executed by the contractor.

Among the items involved in this section as below:

i) Progress work and chart for every month

ii) Progress report

iii) Progress Photograph

iv) Site meeting

v) Licenses and permit

vi) Instruction of works

vii) Progress Payment

viii) Maintenance of the site

ix) Other expenses

d) General Facilities and Obligations

Items under this section describing about general facilities that to be

provided by contractor before and during the construction is on progress. All

these items are mostly need to be priced. The items involved are as below:

i) Plant and equipment

ii) Safety, health and welfare of the workmen

iii) Providing scaffolding

iv) Temporary water storage

v) Temporary electricity

vi) Providing temporary access road to the site

vii) Temporary building

a) Site office

b) Canteen

c) Store, etc

Page 35: The Importancy of Preliminaries

19

viii) Telephone

ix) Temporary hoarding

x) Temporary drainage system

e) Contingency Sum

This section is a sum allowed or allocated for total expenses from

contingency works that might be done by contractor but does not state

specifically in the contract.

2.6 Summary

This chapter has discussed the literature review regarding the preliminaries items

and identifying what are exactly content of the items inside the preliminaries. At the

same time to know what are the items generally used especially based on PWD form of

contract compared to what is definitions of preliminaries inside the SMM2. All the fact

is mostly reefing to PWD form of contract and Standard method of measurement in

identifying the preliminaries item with that’s will influence contractor how to price the

preliminaries item.

The discussion in this chapter is to identify what are the main important items

generally in the preliminary based on SMM and specifically what has been practicing

using PWD form of contract.

Page 36: The Importancy of Preliminaries

20

CHAPTER 3

MANDATORY ITEMS IN PRELIMINARIES

3.1 Introduction

This chapter will discuss about findings on the literature review in the previous

chapter. The discussions will summarize accordingly based on the objectives of the

studies with regard to the literature review and the respondents in the industry. This

chapter will highlight all the mandatory items in the preliminaries that should to be

priced and considered by contractor when pricing preliminaries.

3.2 Items Normally Priced by Contractor

There are many items in each part of the preliminary works where some have to

be priced and some are not. It can readily be seen that, although the preliminaries section

Page 37: The Importancy of Preliminaries

21

typically contains a very large amount of written information; only some of the items are

actually priceable (Solomon, 1993). However, all the items under that are not price are

still influencing indirectly to overall cost estimate of the preliminary that has to done.

One of the major changes in new standard of measurement is the fact that certain facts

will be taken for granted or “deemed to be included in term” and will not therefore

appear in the Bills of quantities (R.D. Wood, 1990). This means all the preliminaries

items are deemed to priced and prepared by the contractor. Following are the items that

normally will be priced by the contractors for many projects:

1) Site Supervision – Site Agent etc

2) Temporary offices, storage sheds, man store

3) Small plant

4) Haulage and Unloading Plant

5) Cranes, Passenger lifts(tall building)

6) Concreting plant and hoist

7) Scaffolding

8) Safety Measures

9) Code of welfare conditions

10) Telephone

11) Temporary roads

12) Temporary compounds

13) Temporary fencing, hoardings, screens, gantries and walkaway

14) Setting out

15) Attendance on clerk of works

16) Watching and lighting

17) Temporary Power and Site Lighting

18) Pumping and baling

19) Traveling time fares

20) Additional overtime

21) Notices and fees to local Authorities and Public Undertakings

22) Transportation to site

Page 38: The Importancy of Preliminaries

22

23) Maintenance of the public and private roads

24) Weather protection and precautions

25) Protection and casing of finished work

26) Completion i) Defect liability

ii) Drying out

iii) Tidying site and clearing rubbish

iv) Cleaning out Buildings

v) Clearing windows and floors

27 Testing materials

28 Temporary water on site

29 Insurances

All discussed and listed above, there are only a few items that categorized as

mandatory items that should be priced by contractor. Mandatory items can be considered

of any obligation or restriction that may be imposed on the contractor by the employer in

respect of any matter not covered by any clause in the conditions of contract shall be

given as an item stating the relevant particular (SMM, RCIS, 1968). Besides that a client

requirement also is part of the mandatory items that contractor should fulfilled. All

preliminary items however have an indirect bearing on the pricing even they are not

specifically priced (R.D. Wood, 1989)

3.3 The mandatory items

Basically there are five sections according to the subsequence of preliminaries

item in the tender documents based on JKR format. The discussion of the mandatory

items will be in each of this part as the following:

Page 39: The Importancy of Preliminaries

23

a) Site Condition and Ground Condition

b) Contract Document

c) Contractual Obligation Procedures

d) Plant, Site Facilities, Social And Site Safety

e) P.C and Provisional Sum, Sub contractor and supplier.

Based on the findings, the followings are the basic mandatory items that therefore have

to be considered by contractor for pricing on every contract:-

3.3.1 Insurance

The various kinds of insurance in which a contractor is interested are many.

Some of the kinds of insurance are required by law, other kinds are required by the

owner, and some other kinds are desirable for the protection of the contractor. Some of

the general kinds are described briefly in the article on Insurance.(H.E. Pulver, 1990).

The Contractor shall effect and maintain an insurance of Works for the whole of the

Contract Sum plus professional fees. Notwithstanding the conditions of Contract Clauses

33 and 36 of the JKR 203A (Rev 10/83) clearly stated that the Contractor shall effect

and maintain a Contractor’s All Risk (CAR) insurance policy to cover for public

Liability and Fire Insurance of the Works under the name of government and contractor.

Even in JCT Form of Contract (1998) in clause 22(A), when used for new buildings,

states that the builder shall insure the building against fire risk, etc(W.Howard, 1994).

All the above statement has defined that insurance is essentially important as a one of

the mandatory items that contractor should not miss to price.

Page 40: The Importancy of Preliminaries

24

3.3.2 Workmen’s compensation

Clause 34 under JKR 203A (Rev 10/83), Workmen’s compensation insurance

shall not be less than 20% of Contract Sum less Preliminaries, PC and Provisional Sum

which must be approved by the S.O. but without prejudice to the Contractor’s legal

liability. The contractor has to insured certain amount of money not less than 20% of

contract sum for workmen’s compensation without prejudice and clearly that this items

can be included in a mandatory items.

3.3.3 Performance bond

It is usual on many contracts for client to require a guarantee bond or other

surety. A contractor normally pays a single insurance premium for this and it can be a

very expensive item depending on the financial status and experience of the contractor

(W. Howard, 1994). The purpose of such a bond is to guarantee the faithful fulfillment

of the contract by the contractor. Contract bonds are of two kinds, construction and

material supply. These bonds are two kinds, construction and material supply. These

bonds are sometimes called surety or guarantee bonds(H.E. Pulver, 1990). The

Contractor shall, as a condition precedent to the commencement of nay work under this

Contract, deposit with Government a Security Deposit in the form of approved Banker’s

Guarantee only to five(5) per cent of the contract Sum, for the due observance and

performance of this contract. The performance bond shall be held or shall remain valid

and effective for such period as provided in the approved Banker’s Guarantee. If the

contractor fails to execute the Contract, the government or the S.O. on its behalf may

utilize and make payment out of or deduction from the said performance Bond or any

part thereof in accordance with the terms of this Contract. Performance bond the

contractor has to pay 5% of original contract sum. The payment in term of bank

guarantee or deducted (10%) of each interim payment until the total amount deducted is

Page 41: The Importancy of Preliminaries

25

equivalent to 5%of original contract sum. This performance bond is actually part of a

condition precedent to the commencement of the work. For employees social act the

contractor has to submit the code number of the worker to the Superintending officer

and pay contribution for the worker. This ensures that should the contractor be unable to

fulfill his contractual obligations, the guarantor will either pay damage to the employer

up to full value of the bond or arrange or another contractor to finish off the outstanding

work, again, up to the value of the bond.(J.IW Bently, 1990). If contractor is failed to

pay, it will breach of the contract based on clause 35.

3.3.4 Setting out

The Contractor’s shall employ a Licensed Surveyor for the setting out of base

lines for the works. The setting out shall be carried out before the works commences.

The Surveyor to carry out before the works commences. The surveyor to carry out on

the setting out of the piling points before piling works commence. The setting out of the

points is to be established according to the proposed grid lines as indicated on the

Architectural and Structural drawings. Submit five (5) copies of such setting out survey

drawings duly endorsed by the Registered Land Surveyor for the S.O. approval. Upon

completion of the piling works, a survey exercise have to be carry out for the

driven/installed pile points and is to be verified and endorsed by the Registered Land

Surveyor. Submit five (5) copies of the said as-built survey drawings of the piles

driven/installed for the S.O. approval. No claims for extra payment as a result of any

discrepancy will be entertained later. Setting out works is considered compulsory work

that contract need to do and prepare such as undertake boundary and engineering survey

of the site and install bench marks and marking. Contractor also has to allow certain

amount of money to engage licensed land surveyor to carry out the work. This made this

item is the most important item and part of mandatory items.

Page 42: The Importancy of Preliminaries

26

3.3.5 Construction Industry Development Board (Payment for levy)

The contractor shall comply to part VIII of the Lembaga Pembangunan Industri

Pembinaan Malaysia Act 1994 and the Construction Industry (Levy Collection)

Regulations 1996, and shall submit a notification on Form CIDB L1/96 to Lembaga not

late than 14 days after the issuance of the Letter of Acceptance/ Letter of Award/ or any

document that constitutes acceptance of a contract of works, or not less than 14 days

before commencement of the Works, whichever date is earlier. The contractor shall

display a copy of his registration with CIDB together with a copy of the work site and

shall make it available arising out of his neglect of this Clause. The Contractor shall

indemnify the Employer against all loses that may arise due to the failure on the part of

the Contractor shall indemnify the Employer against all loses that may arise due to the

failure on the part of the Contractor to comply with this requirement.

3.3.6 As-built Drawings

From the findings, as built Drawing is among the most important items in this

part and considered as mandatory items that contractor has to provide during

construction. The contractor shall prepare and submit as built drawings of Architecture’s

and Civil and Structure’s Works. The Contractor shall supply the original together with

five (5) sets of all record drawings, two sets of diskettes and one set of reduced size

drawings. All as-built drawing must be endorsed by P.E and to be submitted to the S.O

within two (2) months from the date of handing Over. If the contractor fails to supply all

as built drawing requested by the S.O, the S.O will employ others to do the drawings and

charged the expenses incurred to the contractor. This make contractor felt need to price

for this items

Page 43: The Importancy of Preliminaries

27

3.3.7 Work Programme

According to JKR 203A (Rev 10/83), Within 14 days after the receipt of the

Letter of Acceptance of the Tender, the Contractor shall submit to the S.O ten (10)

copies for his approval a programme showing the order or procedure and method in

which the Contractor propose to carry out the Works and shall whenever required by the

S.O or the S.O.’s representative furnish for his information particulars in writing the

Contractor arrangements for carrying out of the Works and the Constructional plants and

temporary works, if any, which the Contractor intends to supply use or construct as the

case may be. The programme shall be on a Critical Path Method (CPM) by using latest

version software of Microsoft Project 2000 or Primavera Project Planning (P3e) or

equivalent and shall show the programme data’s for the Commencement and completion

of the various elements in the works. Like as built drawing, work programme falls under

compulsory items that contractor has to provide and shall submit proposal programme

within 10 days of acception of the contract to the S.O. after approval of the programme

then eventually become approval proggramme.

3.3.8 Hording and fencing

The contractor shall supply, erect and maintain hoarding or banner to isolate the

works in the works in the site from other areas. All works shall be carried out in

accordance to the Architectual Drawings and to the Satisfaction of the S.O and local

Authorities. It if often necessary to erect wire compounds around sites in isolated

locations or just around the area where materials are stored (W.Howard, 1994).

Page 44: The Importancy of Preliminaries

28

3.3.9 Client/Employer’s Requirement

The section will include specific Employer’s requirement relating to any

provision stated on the invitation to tender or form of tender, provision by the architect

and consultant, supervision and administration of the work, requirements for

safeguarding the site (Mudd. D.R, 1980). The requirement also may include

requirements for health, safety, prevention of nuisance, security, control of pollution,

and protection of existing trees, services etc. For the certain projects, the employer will

ask for the specific item with specific brand for the used of the project. The items

normally required by the clients are below:-

3.3.9.1 Vehicle for the S.O.

Some of the provision imposed by the employer asked the contractor to

provide within two(2) weeks of the date of possession of the site until the expiry

of the Defects Liability period or the issue of the certificate of the completion of

the making good defects, whichever is the later the following item :-

1) one No. new four wheel drive engine vehicle of not less

than 2500c.c

2) New four wheel drive of 1300 c.c Kembara

3) 1 No. 2000 c.c of Honda CRV

4) 4 Nos. new motorcycle of 110 c.c capacity to the brand

approved by the S.O

Page 45: The Importancy of Preliminaries

29

As soon as practicable after purchasing the vehicle, the Contractor shall

produce the registration card and insurance policy together with receipts for

premium paid for the same to the S.O.

The vehicles shall be reverted to the Contractor after the certification of

completion of making good defects is issued by the S.O.

3.3.9.2 Equipment and Facilities.

The Contractor has to provide the following equipment and facilities for

the use of the Superintending Officer (S.O) and/or his staff. All equipment

provided shall benew delivered, tested and installed within a month of the

issuance of the Letter of Acceptance. The place of delivery and installation shall

be as directed by the S.O. The equipment provided shall be maintained by the

Contractor or his appointed agent throughout the contract period. Maintenance

shall be including all necessary monthly servicing to according to manufacturer’s

specification and supply of accessories and consumables. The contractor fails to

provide or maintain any equipment specified below the Government shall have

right to procure the equipments from other sources or maintain it and all expense

arising shall be borne by the Contractor and appropriate adjustment shall be

made to the Contract Sum. On completion of the contract after the Certification

of Practical Completion has been issued, the computers including the software

applications, printers digital camera, Photostat machine shall become the

property of the employer.

Page 46: The Importancy of Preliminaries

30

a) Computers

1) Notebook Computer with Intel Pentium 4

2) Computer with Intel Pentium 4 Processor

b) Printer

1) ‘Xerox’ or other equal and approved Phaser laser Printer

c) Software

d) Digital camera

e) Photostat machine

f) LCD projector

3.4 Conclusion

As discussed above are the mandatory items that should be priced by contractor

when pricing preliminaries. The intention is plainly to provide contractors with the

opportunity to show more accurately in their priced preliminaries. Other purpose of

identifying mandatory is to provide a space for contractor to price not just allow a lump

sum percentage for preliminaries. This is obviously for the use the quantity surveyor and

the contractor to ease the preparing of interim valuation payment.

Page 47: The Importancy of Preliminaries

31

CHAPTER 4

METHODOLOGY

4.1 Introduction

This chapter describes the methods used in carrying out the study. A thorough

planning and scheduling had been organized on the study in proper sequence to ensure a

smooth running of the study program from literature review, interview, questionnaire

survey data collection, data analysis, the discussion of the results and finally the

suggestion and conclusion.

4.2 Determination of the research Objectives.

Preliminaries study has been carried out to determine the research objectives and

scope of the dissertation. In the process some information about preliminaries has been

Page 48: The Importancy of Preliminaries

32

gathered. Some interviews have been carried out to the respondent from expert of the

contract, senior QS in Quantity Surveyor Consultant and Contractor Company. After the

preliminary review, some specific facts about preliminary have been identified and

gathered as discussed in previous chapter.

4.3 Literature Review

Literature review has been carried out to establish some knowledge and to collect

information pertaining to the study area. The literature review has been obtained from

several sources such as published books, textbooks, information from internet, articles in

journals and papers of some published guidance from practice in the industry and

previous construction records. The purpose of literature review is to gather important

information related to the topic of preliminary.

4.4 Data Collections

Data collections have been done in two stages i.e. through interviews with the

experts’ panel and questionnaire survey with the contractors in the industry. The

interviews are divided into sessions which include face to face interview for session one

requesting the respondents to answer the structured questionnaires in the later.

Page 49: The Importancy of Preliminaries

33

4.4.1 Development of the questionnaire in the survey

The structured questionnaire in the interview with the experts panel and the

questionnaires used in the questionnaire survey in the industry are developed mainly

based on the Likert’s scale on five ordinal measures of agreement from 1 to 5 toward

each statement as in figure 1

Ordinal scale of 1 to 5 in ascending order

Least Agree Very Strongly Agree

1 2 3 4 5

Increasing order of agreement

Figure 4.1 : Five ordinal measures of agreement of Likert’s scale

4.5 Interview with the experts

The interview of the experts comprises of the professionals who have been

involved in the costing in tendering and contracting in the industry will be carried out to

review their opinions about method of pricing the preliminaries. The interview also

requested to identify the factors and the importance of the preliminaries to the

contractors. These interviews are conducted at random selection face to face questions

and answers session and respondents were also requested to answer the structured

questionnaire.

Page 50: The Importancy of Preliminaries

34

4.5.1 Objective of the interview

The objectives if the interviews are to strengthen the research findings based on

the main objectives as specified earlier. These objectives are:

ii) To identify mandatory item that should be priced by contractor.

iii) To identify the factors that influence in pricing the preliminaries

items

iv) To propose strategies to price preliminaries

4.5.2 Methodology of the interview

The interviews were conducted in two stages with professionals in the

government agencies and the Senior Quantity Surveyor from private firm who has

contract background in their works and practices. The first stage is face to face

questionnaires and answers sessions and the second stage is requesting the expert to

answer the structured questionnaires.

Page 51: The Importancy of Preliminaries

35

4.5.2.1 Face to Face interview

A total number of 15 professionals of various engineering disciplines including

quantity surveyors and 2 lecturers have been approached for face to face interviews.

Their views were obtained to evaluate the understanding and the current scenario over

method been used by the contractor nowadays. The experts also been asked about the

opinion in establishing a standard guideline in pricing the preliminaries.

4.5.2.2 The Structure Interview Questionnaire

In addition to face to face interviews the same panels has been given a set of

structured questionnaire requesting them to respond based on their experts’ opinion and

experience in how to price preliminaries and their understanding of preliminaries costing

in the industry. Their actual practice and views has been then translated in the results for

further discussion and studies.

The structured questionnaire comprises of 3 sections as below:

Section A : To obtain information about respondents’ background;

Section B: To obtain general information about the organization;

Section C: To identify their understanding of how preliminaries are estimated

and their opinion on what is the current practice of estimating the

Page 52: The Importancy of Preliminaries

36

preliminaries in our local construction industry and what are the

factor that influence pricing preliminaries.

4.6 Industry Questionnaires Survey

The questionnaire survey in the industry was carried out to pool the opinion of

the contractors towards the understanding of the contract document. The result of the

survey then compared with numbers contract document in similar projects to match the

similarity of thought for the discussion and conclusion in this study.

4.6.1 Methodology of the Industry Survey

The questionnaire survey has been carried out among the group of contractors

chose at random to gather the information based on their practice and experience in the

industry. A total of 100 sets of questionnaire have been distributed through mail and

some other means to contracting companies in Selangor and Kuala Lumpur. Most of the

company had the experience in implementing the government projects in their respective

states. Respond to the questionnaire were then analyzed based on the category of

questionnaire to obtain the results for further discussion and conclusion.

Page 53: The Importancy of Preliminaries

37

4.6.2 Questionnaire for the industry Survey

The questionnaires are structures into four sections:

Section A : To identify the general information about the respondent;

Section B : To identify the background of the Organization/Company

Section C : To identify factor influence the pricing of the preliminaries

Items

The sample of questionnaire used for the survey in this project is shown in

Appendix II.

4.7 Data Analysis

Data analysis is carried out for the qualitative data obtained from the

questionnaire survey. Qualitative data collected through the questionnaire were first

segregated and separated to answer different study objectives. The data will be

categorized under different variables to represent the result of the research objectives.

Different statistical methods such as content analysis. Frequency analysis, average index

analysis. The discussions are mainly to evaluate the results obtained from the survey to

compare any similarity with the expert’s opinions in conjunctions with the objectives of

the study. The summary of the study are then presented with the recommendation along

with the conclusion for further studies in this area.

Page 54: The Importancy of Preliminaries

38

4.7.1 Content Analysis

Content analysis is used to analyze the number of response that the respondent’s

gives in proposing to different variables based on the same questionnaires. The proposed

variables are tabulated and analyzed based on the opinions given by the respondents.

4.7.2 Frequency Analysis

The frequency analysis is used to represent result of data analysis of the number

of response that the respondent gives to different variables in the questionnaire. The

result has been tabulated in the form of frequency number and percentage according to

total respondents. For graphic result presentation, pie chart has been used as the

summary.

4.7.3 Average Index Analysis

In Average index analysis, the results are further summarized to obtain the level

of importance in evaluating the factors which involve in the understanding of contract

document. The respondents have been requested to gauge and evaluate the proposed

factors element in every section of the questionnaire in structured interview

questionnaire and the industry survey questionnaire and the industry survey

questionnaire based on five-point scale starting with 1 for least agreed to 5 for very

Page 55: The Importancy of Preliminaries

39

strongly agreed. The average index analysis for each variable is calculated by using the

formula below:

Average index (A.I) = ∑ 1X1 + 2X2 + 3X3 + 4X4 + 5X5 ∑X1 + X2 + X3 + X4 + X5

Where,

X1 = Number of respondents for least Important

X2 = Number of respondent for fairly important

X3 = Number of respondent for important

X4 = Number of respondent for strongly important

X5 = Number of respondent for Very Strongly important

The overall level of agreement by the respondents to the factors which influence

the understanding of contract document by the contractors are summarized based on the

categories as specified earlier and show in the table 3.1.

Table 4.1 : The level of agreement and evaluation for average index analysis

Average Index Level of Agreement of Evaluation

0.0 < Average Index < 1.50

1.50 < Average Index < 2.50

2.50 < Average Index < 3.50

3.50 < Average Index < 4.50

4.50 < Average Index < 5.0

Least Important

Fairly Important

Important

Strongly Important

Very Strongly Important

Page 56: The Importancy of Preliminaries

40

4.7.4 Relative Index Analysis

Relative indices are a technique used to compute the strength of indices of

agreement for each question to enable subsequent comparison between each factor to

support the level of important of the subject.

The result will be summarized to obtain ranking according to the level of

importance in evaluating the understanding toward contract documents. The respondents

has been requested to evaluate the factors that contribute to improving the level of

understanding toward contract document and they has been also requested to give their

views based on their experience toward factors that inhibit the understanding of contract

document based on their experience toward factors that inhibit the understanding of

contract document based on five point scale starting with 1 for least important, 2 for

fairly important, 3 important, 4 strongly important and 5 for very strongly important.

The relative index analysis for each variable is calculated by using

the formula as follows:

Relative Index (R.I) = ∑1x1 + 2x2 +3x3 + 4x4 + 5x5

5∑x1 + x2 + x3 + x4 + x5

Where,

x1 = Number of respondents for least important;

x2 = Number of respondents for fairly important;

x3 = Number of respondents for least important;

x4 = Number of respondents for strongly important;

x5 = Number of respondents for very strongly important;

Page 57: The Importancy of Preliminaries

41

The computation of RI using formula yield the value of RI ranging from 0.2 to 1,

where 0.2 represent the minimum strength and 1 the maximum strength. The RI

computed is referred to make comparison between each factor generated from the

survey.

Page 58: The Importancy of Preliminaries

42

CHAPTER 5

FACTORS INFLUENCING PRICING DECISIONS

5.1 Introduction

In this chapter, the analysis of data has been on two categorized of respondents.

The first category is the views of the expert panels which comprises of the professional

of different disciplines and the second category is the contractors who are involved in

the construction industry.

The questionnaire has been first analyzed and summarized based on their good

knowledge and experience to answer questions in respective industry questionnaire

survey. The results were then tabulated and analyzed for further discussion and

conclusion. Analysis on the contractors’ views in the industry has also been conducted

based on the questionnaire and open ended questions. The results were then analyzed for

further discussion.

Page 59: The Importancy of Preliminaries

43

5.2 Factors Influencing Pricing Decisions

The factors have been suggested based on the expert experience in their

undertaking pertaining to the subject matter. These entail gathering information about

the various factors that should be taken into consideration when pricing preliminaries.

Prelims can be higher in certain circumstances for instance if sites require special

measures. The followings are the factors that have to be considered when pricing

preliminaries by contractor:-

5.2.1 Understanding contract particular

The estimator should be conversant with the standard forms of contract and

should note cover any amendments. Items which should be particularly noted by the

estimator are Cost Variation Clause, Limit and period of retention, discounts on

nominated suppliers and sub-contractors, insurances and special additional clauses.

5.2.2 Site condition

The estimator should visit the site and determine if an existing supply is available

and if it is sufficient and can be used for building operations (W.Atton, 1978). Before

commencing the pricing the estimator must visit the Architect’s office and study the

Drawings, specification and contract documents. Also the site must be inspected and any

Page 60: The Importancy of Preliminaries

44

special problems must be considered and appraised. Access, storage if materials,

positioning of mechanical plant and multiple loading on the site would all be important

matters to review. In good tendering practice drawings are always sent to the

tenderer.(R.D Wood, 1990)

5.2.3 Location of the site

If the contract being tendered for is in an existing factory which is enclosed by a

boundary fence or in an area where damage or stealing is unlikely the estimator will

usually include a nominal amount to cover losses or damage. If, however, damage or

stealing on a larger scale is expected a watchman would be employed for the whole of

the time when the contract was not working.

5.2.4 Difficult contract and restricted site

Many small contracts by the nature of the work involved, such as dangerous

underpinning, deep foundations in bad ground and similar items, or contracts where

working conditions and access are particularly bad, require foreman of great experience

and of above average organizing ability(W.Atton, 1978). All the above items must be

taken into account as they will influence the pricing of preliminaries and also the

number of general foremen and assistant general foremen required for the particular

contract.

Page 61: The Importancy of Preliminaries

45

5.2.5 Magnitude of contract

When pricing preliminaries the estimator must bear in mind the magnitude and

type of contract. A simple, small and straightforward contract can be, perhaps,

supervised by a modestly paid general foreman. On another contract of the same price

bracket the complications and problems of the work may involve a highly paid site

agent. The financial scope of contracts must also be considered and a range of examples

will be given later to cover these points.

5.2.6 Plant and equipment

The estimator has to decide the type of plant to be used on the contract being

tendered for and the length of the time the plant will be required on the site. Sometimes

using very rare plant equipment also will influence contractor in pricing preliminaries. it

is a practice for the majority of plant costs to be shown in the preliminaries section. This

is because most of the plant and equipment probably be shared by at least several trades

and it is difficult to apportion the cost between different items and section(W.Atton,

1978).

Page 62: The Importancy of Preliminaries

46

5.2.7 Any Obligation or restriction imposed by Employer

In respect of any matter not covered by any clause in the conditions of contract,

any obligation or restriction imposed by employer normally be given as an item stating

the relevant particulars in preliminaries item. The requirements basically about details

relating to tendering in addition to those on the invitation to tender, e.g. subletting,

provision and content of documents, management of the works, quality control, security,

safety, working restrictions, facilities to be provided for the client’s benefit and building

maintenance.

5.2.8 Commitment number of project

Commitment number of project is when contractor did not have enough time to

price thoroughly and some are tent to price it lump sum according to their past

experience and same project.

5.2.9 Availability at Resources by the Contractor

Availability of resources much influence to contractor when pricing the

preliminaries. It is noted that some of the factor are repeatedly mention by the contractor

in the survey for instant the availability of the plant and equipment by the contractor.

This will be advantage to the contractor that have their own plant and equipment and

Page 63: The Importancy of Preliminaries

47

giving very great different of prices when pricing plant and equipment items. The

contractor will price low on this item compared to the contractors that have hire plant

and machineries and it showed that plant and equipment give a major factor to the

pricing of the preliminaries.

5.3 Data Analysis and Result

In this chapter, a detail analysis of the qualitative data has been analyzed by

using appropriate statistical approach as mentioned in the previous chapter. The analysis

of data has been on two categorized of respondents. The first category is the views of the

expert panels which comprises of the professional of different disciplines and the second

category is the contractors who are involved in the construction industry.

The questionnaire has been first analyzed and summarized based on their good

knowledge and experience to answer questions in respective industry questionnaire

survey. The results were then tabulated and analyzed for further discussion and

conclusion. Analysis on the contractors’ views in the industry has also been conducted

based on the questionnaire and open ended questions. The results were then tabulated

and analyzed for further discussion.

Page 64: The Importancy of Preliminaries

48

5.3.1 Background of the Respondents

Respondents of the interview comprises of 6 Professional of different discipline

background. i.e. 1 project directors, 9 quantity surveyor involved in contractor’s

company, 2 project managers and 3 engineers who were involved in tendering stage and

construction industry as shown in Table 5.1 and pie graph figure 4.1

Table 5.1 : Distribution of the respondents based on displines

Respondents Distribution Response Response %

Project Directors 20 1 5%

project Planner 20 1 5%

Quntity Surveyor 20 10 50%

Project Managers 20 3 15%

Engineer 20 5 25%

Supervisor 20 0 0%

Project Managers

15% Quntity Surveyor50%

project Planner5%

Project Directors

5%Supervisor

0%Engineer25%

Project Directors

project Planner

Quntity Surveyor

Project Managers

Engineer

Supervisor

Figure 5.1 Distribution of expert respondent based on profession by percentage

Page 65: The Importancy of Preliminaries

49

The working experiences of the respondents are between 2 up to more than 20 years. In

the Table 4.2 shows that most of the respondents have experienced in construction

industry within 6 to 10 years carried of 67% of the total percentage of respondents.

Table 5.2 : Distribution of panel Respondent based on experience

Experience of Respondent No. of Respondents Total %

2 - 5 Years 2 10%

6 - 10 Years 10 50%

11 - 15 Years 6 30%

16 - 20 Years 2 10%

> 20 Years 0 0%

Total 20 100%

No. of Respondents

10%

50%30%

10% 0% 2 - 5 Years6 - 10 Years11 - 15 Years16 - 20 Years> 20 Years

Figure 5.2 Distribution of panel respondent based on experience by percentage

Page 66: The Importancy of Preliminaries

50

5.3.2 The Industry Questionnaire survey

The Respondent has been randomly selected among the contractors from the

State of Kuala Lumpur. 50 sets of questionnaire wee distributed and 61 were returned

with complete answer. Thus 30% responded and 70% sets were not returned which

comprises of 6% as shown in the table 4.3.

Table 5.3 : Number of respondent responded to the Questionnaire

No. Respondents Frequency Percentage (%)

1 Replied with complete

questionnaires

20 40%

2 No reply 40 60%

3 Replied with incomplete

questionnaire

0 0%

60 100%

5.3.3 Factor Influence the pricing of the preliminaries items

Table 4.10 shows the analysis computed by average indices and relative indices.

From the analysis, all factors suggested scores are between 4.60 and 3.45. All

respondents strongly agree and very strongly agree to the proposed questionnaires. From

relative indices computation, the ranking of the factors are between 0.92 and 0.69. All

the nine factors can be summarized in order of importance based on the relative index

scores as shown in the table.

Page 67: The Importancy of Preliminaries

51

1. Availability of resources by the contractor

2. Plant and equipment to be used

3. Any obligation or restriction imposed by employer

4. Site Condition

5. Commitment number of projects

6. Location of the Site

7. Magnitude of contract. Eg. Small, simple contract

8. Lacking of understanding contract particular and Preliminary items by Contractor

9. Contract difficulties and site restriction

Frequency analysis

1 2 3 4 5 No. Questions

Freq % Freq % Freq % Freq % Freq %

Avg Index

Rel. Index Rank

1 Lack of understanding of each preliminary by Contractor

0 0% 3 15% 8 40% 4 20% 5 25% 3.55 0.71 8

2 Site Condition 0 0% 0 0% 6 30% 6 30% 8 40% 4.10 0.82 4

3 Location of site 0 0% 1 5% 3 15% 10 50% 6 30% 4.05 0.81 6

4 Contract difficulties and site restriction,

0 0% 3 15% 8 40% 6 30% 3 15% 3.45 0.69 9

5 Magnitude of Contract. 0 0% 2 10% 5 25% 6 30% 7 35% 3.90 0.78 7

6 Plant and equipment to be used

0 0% 1 5% 2 10% 2 10% 15 75% 4.55 0.91 2

7 Any obligation or restriction imposed by employer

0 0% 1 5% 2 10% 5 25% 12 60% 4.40 0.88 3

8 Commitment number of projects

0 0% 2 10% 3 15% 7 35% 8 40% 4.05 0.81 5

9 Availability of resources by the Contractor.

0 0% 0 0% 2 10% 5 25% 13 65% 4.60 0.92 1

Table 5.4 : Frequency analysis on factors influence in pricing Preliminaries

Page 68: The Importancy of Preliminaries

52

5.3.4 Other factor that influence the pricing of preliminaries by contractor.

The respondents are given open ended question to seek their additional opinion

of the other factor that contributes to the pricing of the preliminaries item. The factors

are as follows;

i. Depends on site condition and type of a project- infra or building works

ii. Uncertainty of material price

iii. Availability of resources by the contractor

iv. Using Plant and equipment (rare contribute to higher price)

v. Client Financial Background

vi. Site Condition and Resource as plant for equipment

vii. Extra requirement by clients that need to be priced

viii. Location, Local Authority requirement.

ix. Availability of equipment by the contractor

5.3.5 General comment from the respondents

The Analysis has shown that respondents have commented that still need to be

done about pricing preliminaries so that contractor do not miss anything while pricing

the preliminaries and chances winning the tender bidding is larger. The comments and

thoughts are as below:

i. Contractor to have their own standardize checklist in order to avoid missing items during tender stage.

ii. Provide the clause in the condition of contract

Page 69: The Importancy of Preliminaries

53

iii. Must be justified the items included in the preliminaries item more details and accurate cover the whole duration of the project plus tentative extension of the completion of the project

iv. Simplified the preliminaries description, use the simple word & put the

required item only.

Page 70: The Importancy of Preliminaries

54

CHAPTER 6

DISCUSSION

6.1 Introduction

This chapter will discuss about findings obtained based on the data analysis in the

previous chapter. The discussions will summarize accordingly based on the objectives of

the studies with regard to the literature review and the respondents in the industry. The

chapter will highlight all the important factors contributed by this study and comparison

will be made for their congruent opinions to be drawn in the conclusions. This chapter

will end with the factor that contributes when pricing the preliminaries items.

Page 71: The Importancy of Preliminaries

55

6.2 Factor Influence The Pricing Of The Preliminaries Items

Frequency analysis

1 2 3 4 5 No. Questions

Freq % Freq % Freq % Freq % Freq %

Avege Index

Rel Index Rank

1 Availability of resources by the Contractor.

0 0% 0 0% 2 10% 5 25% 13 65% 4.60 0.92 1

2 Plant and equipment to be used

0 0% 1 5% 2 10% 2 10% 15 75% 4.55 0.91 2

3 Any obligation or restriction imposed by employer

0 0% 1 5% 2 10% 5 25% 12 60% 4.40 0.88 3

4 Site Condition 0 0% 0 0% 6 30% 6 30% 8 40% 4.10 0.82 4

5 Commitment number of projects

0 0% 2 10% 3 15% 7 35% 8 40% 4.05 0.81 5

6 Location of site 0 0% 1 5% 3 15% 10 50% 6 30% 4.05 0.81 6

7 Magnitude of Contract. 0 0% 2 10% 5 25% 6 30% 7 35% 3.90 0.78 7

8 Lack of understanding of each preliminary by Contractor

0 0% 3 15% 8 40% 4 20% 5 25% 3.55 0.71 8

9 Contract difficulties and site restriction,

0 0% 3 15% 8 40% 6 30% 3 15% 3.45 0.69 9

Table 6.1 Factor influencing price in preliminaries according to ranking of

importance

Based on the analysis on the questionnaire in the industrial survey, the factors

that influence the preliminaries items are summarized and captured under the items of

factors that influence in pricing preliminaries as in table 6.1.

1. Availability of resources by the contractor

2. Plant and equipment to be used

3. Any obligation or restriction imposed by employer

4. Site Condition

Page 72: The Importancy of Preliminaries

56

5. Commitment number of projects

6. Location of the Site

7. Magnitude of contract. Eg. Small, simple contract

8. Lacking of understanding contract particular and Preliminary items by Contractor

9. Contract difficulties and site restriction

The analysis is aim to pool the respondent’s view with regard to personal factor

that influence the pricing of the preliminaries items. Based on the result, the respondent

strongly agreed that availability at resources by the contractor with (R.I) 0.92 is much

influence to contractor when pricing the preliminaries. This is followed by commitment

number of project 0.91 (R.I). These two factors are very strongly agreed by respondent

by scoring above 0.88 (R.I). The rest of factors are score under 0.7 (R.I) most of them

are interrelated to each other. This show that all the factors are reliable and relevant to be

considered in contributing influencing the pricing of preliminaries.

Availability of resources by the contractor and the type plant and equipment used

can consider in contributing influencing in pricing preliminaries. From the data obtained

all respondents have been strongly agreed that these factors are very relevant in order to

consider in pricing tender. The study has also found that inadequate resources by

contractor that caused contractor to put higher rates and price in preliminaries. This will

make the chances of winning bidding tender are bigger.

Factor such as other special obligations and restriction imposed by employer or

client and the condition of the site also the contributing factors that influence the way

contractor pricing preliminaries. Therefore a contractor has to understand and read

carefully all client requirements and obligations for that particular project in order to

have a chance in getting a competitive and acceptable price by client

Page 73: The Importancy of Preliminaries

57

From the study even though much have been said about factors that influencing

preliminaries, the respondents also agreed that the contractor difficulties and site

restriction also closely related to lack of understanding of preliminaries items.

Contractors felt that need to understand each of preliminaries items and get to know the

nature of the site whether involved dangerous underpinning or any deep foundation with

bad ground condition. This factor can be much affected to the overall cost of

preliminaries.

Commitment number of project is when contractor did not have enough time to

price thoroughly and some are tent to price it lump sum according to their past

experience and same project. To this reinforced this statement, one questioned being

asked to respondent how much approximate estimate percentage allowed by them for

one preliminaries items regardless type of the project. the range has been provided as pie

chart below shows that 55% agreed to choose 5% - 6% approximate percentage for

preliminaries and followed by 25% choosing 6% – 7% and 15% is choosing above 8% .

The majority of the respondent will go for range 5% to 6% if the want to price lump sum

for preliminaries items.

No. of Respondents

55%25%

15% 5% 5 - 6 %6 - 7 %8 - 9 %More Than 10 %

Figure 6.2: Percentage allow for lump sum (Preliminaries Item) by respondents

Page 74: The Importancy of Preliminaries

58

Other factor such as lack of understanding of each preliminaries items, lack of

experience is agreed by all respondent and not really contribute or matter to factor of

pricing preliminaries. This is proved by percentage of respondent about 92% of them

have experience in construction industry more than 6 years. They absolutely understand

and familiar with preliminaries items.

No. of Respondents

10%

50%30%

10% 0% 2 - 5 Years6 - 10 Years11 - 15 Years16 - 20 Years> 20 Years

Figure 6.3: Percentage of experiences of respondents in construction industry

6.3 Other Factor That Influence The Pricing Of Preliminaries Items By The

Contractors.

Based on the content analysis on the open questions to respondent there are 5

factors as thought by the correspondent to influence the pricing of preliminaries. The

factors have been suggested based on the expert experience in their undertaking

pertaining to the subject matter. It is noted that some of the factor are repeatedly mention

by the respondent although there are been asked earlier in the survey for instant the

availability of the plant and equipment by the contractor. This shows that plant and

equipment give a major factor to the pricing of the preliminaries. Other factor that

Page 75: The Importancy of Preliminaries

59

contractor has to take into consideration and been proposed by correspondent is factor

the time during construction tender stage when time is short. This factor will contribute

to the higher price of the preliminaries. Some of the respondent has said by using very

rare plant and equipment in the market will contribute to the factor to get competitive

price for preliminaries. The personal factor discussed above is also closely related to

factor in the survey.

The respondent also have been giving their comments about how to ensure that

preliminaries item is fully priced by the contractor for better competitive cost. They been

suggesting that the preliminaries is need to simplified the preliminaries description

which long and hard to understand by the contractor and also using simple word and just

to put the required items to be priced in. the other suggesting that the contractor should

have their own standard guidelines in pricing the preliminaries when pricing the

preliminaries items. One respondent also suggest that the price must be justified and

detail and cover the whole duration of project and plus the tentative extension of time of

the completion of the project in order to get a better competitive cost for preliminaries.

6.4 The Summary of overall Findings of study

Based on the discussion in the previous sections by observing the results

obtained from the interviews and questionnaire survey in the industry the overall

findings of the study can be summarized as in the following paragraphs.

After scrutinizing the facts from the literature review and the opinions from the

selected expert and survey, it is found that Contractors in the construction industry have

to understand and identify which factor that can be used and considered in giving the

Page 76: The Importancy of Preliminaries

60

best price to offer in pricing preliminaries. This can be shown in the results of the survey

as previously discussed where all the respondents agreed that availability of resources

and types of plants and equipments to be used were much influenced in pricing

preliminaries. Respondents had suggested that preliminaries items in bills of quantities

need to simplified the description and should have their own standard guidelines in

pricing the preliminaries when they were asked to comment on how to ensure the

preliminaries item is fully prices by contractors.

Page 77: The Importancy of Preliminaries

61

CHAPTER 7

STRATEGIES IN PRICING PRELIMINARIES

7.1 Introduction

This chapter will discuss about findings obtained based on the data analysis in

the previous chapter. The discussions will discuss accordingly based on the objectives of

the studies with regard to the literature review and the respondents in the industry. The

chapter will highlight strategies of pricing preliminaries item based on the factors

identified from the previous chapter

7.2 Strategy in pricing preliminaries

Contract pricing is not a simple matter. The construction industry is extremely

fragmented and highly competitive. Contractors have to bid competitively for most of

Page 78: The Importancy of Preliminaries

62

their work and at the same time deal with risks and uncertainties connected with tender

submission. The high level of price competition and low capital intensity which

characterizes the industry, often combine to cause depressed profit margins. A great deal

of current information is needed together with forecasts of demand, cost, competition,

etc., to enable prices to be set and adjusted to desired profit levels. Tellis (1986), for

instance, defines a pricing strategy as a reasoned choice from a set of alternatives prices

(or price schedule) that could aim at profit maximization within a planning period in

response to a given scenario. In relation to maximizing profit and winning the tender

bidding and need to consider the pricing decision approach that involves as the

following:

i) Establishing pricing objectives

ii) Examining each of preliminaries items

iii) Considering factors influencing pricing decisions

iv) Attention to methods of price determination

v) Tactical considerations in setting prices

7.2.1 Establishing pricing objectives

It is notes how a contractor's overall objectives determine its pricing objectives

which, in turn, establish the parameters of pricing policies. Davis (1978) reported that

price should be chosen in order to achieve a company's objective. Within this field

numerous pricing objectives have been identified. Three major types of setting pricing

objectives to be:

Page 79: The Importancy of Preliminaries

63

i) Cost-oriented objectives

- to pursue a target return on investment

- to recoup costs over a particular time period

ii) Competition-oriented objectives

- to discourage competition

iii) Demand-oriented objectives

- to meet the expectations of clients and the industry.

Govindarajan (1983), on the other hand, claimed that Contractors' pricing

objectives are related to expected profit levels, and usually concerned with either profit

maximization or profit satisfying. Abratt and Leyland's (1985) empirical study found a

correlation between the pricing objectives of contractor and their pricing strategies and

they also realised that most of the contractors with a target return on investment operated

a cost based pricing strategy. It may be expected that a contractor's pricing objectives

will have different weighted effects on its bid price decisions. Therefore contractors

need to establish objectives and their aim for every particular project before decide to

enter tender bidding and relate to the factors as discussed previously when considering

the pricing.

Page 80: The Importancy of Preliminaries

64

7.2.2 Examining each of preliminaries items

Examination each of preliminaries items is one of the strategies that contractor

has to take into consideration. Identification of the mandatory items is needed in order

to know what the priorities in pricing preliminaries are. In previous chapter has

discussed on findings what are the mandatory items that should be priced by

contractors. The items listed are as follows:

i) Insurance,

ii) Workmen’s compensation,

iii) Performance Bond,

iv) Setting out,

v) CIDB, payment for levy

vi) As Built Drawing,

vii) Work Programme,

viii) Hoarding and Fencing, and

ix) Client/Employer’s Requirement.

These are the items that imposed in any obligation or restriction by client. If

contractor fail to fulfill or price, it will cause them lose of profit and problem may

occur during construction due to under pricing. The contractor must completely

understand and identify what other items that should be priced because not all the items

are priceable.

Page 81: The Importancy of Preliminaries

65

It is important to for contractor to break down the price because some of them

are most reluctant to do so. It is absolutely necessary. The percentage of the total tender

price allocated to preliminaries in tender bills will vary widely from job to job

depending upon tendering and pricing strategies adopted, Mudd. D.R(1980). By

knowing which items that should be priced according to fixed and time-related charges,

it will provide contractors with the opportunity to show more accurately in their priced

bills. This is also used for the preparation of interim valuation payment. It may also aid

contractor substantiating claims for additional payments as a result of variations and for

reimbursement of loss and expense following the granting of extension of time.

7.2.3 Considering factors influencing pricing decisions

These entail gathering information about the various factors that should be taken

into consideration when making a bid price decision. Nine factors have being identified

in previous chapter such as availability of resources by the contractor, plant and

equipment to be used, any obligation or restriction imposed by employer, site condition,

commitment number of projects, location of site, magnitude of contract, lack of

understanding of each preliminaries items and lastly contract difficulties and site

restriction. All these factors are following the sequence of the importance. Contractors

have to consider each factors as mentioned above before pricing prelim because it is

help and much influence in the cost of preliminaries and overall total cost.

All respondents have agreed that availability of resource by the contractor is the

most influenced in pricing preliminaries. Contractor should identify what are the sources

that they have and go to the site to see the actual condition of the site. This can provide

Page 82: The Importancy of Preliminaries

66

ideas to contractors in pricing accurately and avoiding from missed item and under-

pricing in preliminaries.

7.2.4 Attention to methods of price determination

In a competitive tender, pricing strategies are often used by contractors to

facilitate their cash flows. Usually, the decisions are based on contractors' experience,

intuition, and personal bias. The existing mark-up or cash-flow forecasting models

simulate the pricing strategies in a simplified manner which may depart from real

situation and therefore could lead to inaccurate cash-flow forecasting.

Under-pricing in construction tenders is a common phenomenon and is

commonly explained by the need of cash flows and penetration strategy. However, these

explanations involve profit cutting and therefore are not plausible in explaining a long-

term persistent phenomenon of under-pricing. When uncertainties of cost items in a

tender exist and choices are available to defer and switch modes of construction, then a

valuable option is available to the bidders. It amounts to about 4% of the lump sum

tendered in our case. The under-priced portion is the options value which the bidder is

willing to pay for the flexibility and the uncertainty. These findings enable contractors to

be more competitive and to estimate construction costs more accurately in devising their

bid strategies.

Page 83: The Importancy of Preliminaries

67

The evidence base on prelims is not extensive and though data is collected, it

appears to relate more to ‘experience in the field’ and the ‘discretion of the contractor’

than does the calculation of fees. Wide variations in prelims appear to occur between

projects in different sub-sectors of the construction industry and variations occur over

time.

In overall terms, we believe prelims should reasonably be no higher than 10%

of the contract sum for the type and scale of work involved in building programmes.

The Pricing Model therefore fixes prelims at 10%. These will vary, i.e. some items of

may attract higher prelims and others will attract none or virtually no prelims.

However, we believe that 10% is a reasonable average on which to base a price

calculation, as it should be a reasonably attainable figure for an efficient RSL with

several thousand houses in need of refurbishment. Although exact figures for the social

building and housing sector do not appear to be widely documented, the direct

experience of construction industry is that 10% is a reasonable (and attainable) figure

for prelims in relation to building and housing in Malaysia. This was proof by previous

survey in previous chapter that most of respondents agreed that 5% to 6% was allowed

for preliminaries items out of overall cost.

Page 84: The Importancy of Preliminaries

68

7.2.5 Tactical considerations in setting prices

It has, however become practice for some contractors to move money around in

tender bills, and it is not usual for the prices inserted in the preliminaries bill to bear

little or no relationship to the contractor’s actual costs. Site overheads may be included

either as a percentage of measured work, in the preliminaries section, or as a

combination of both. According to Solomon (1993), this (preliminaries section) is the

main area within a tender where a contractor can seek to gain a competitive advantage

by adjustment of the tender price. The preliminaries bill the contractor with an

opportunity to make a provision for overheads and profit within his tender. While profit

should not be forbidden fruit, it is a luxury which the contractor can adjust, to provide

the opportunity of winning a contract.

7.3 Conclusion

Based on the discussion contract pricing strategies are very important in

determining the best and competitive price that contractor can offer when pricing

preliminaries. Five elements of strategies were addressed in earlier discussion that needs

to be taken into consideration by contractor before pricing preliminaries. However, the

study found that there were strength relationships between the strategies. Although

based mainly on literature review and in previous discussion, it is expected that the

conceptual model could be very helpful in the development of computer aids for

contractors pricing strategies, while at the same time, enrich contractor’s understanding

of the pricing decision process.

Page 85: The Importancy of Preliminaries

69

CHAPTER 8

CONCLUSION AND RECOMMENDATION

8.1 Introduction

This chapter presents the major findings and conclusion for the research project.

Recommendation is also presented for further research in this area so as to enhance the

level of understanding of contract documentation and ensure the better implementation

of project in the construction industry.

8.2 Major findings

Although the small sample did not provide representative findings, the

questionnaire survey was able to provide important information on the importance of the

preliminaries by knowing the mandatory items and factors that influence in pricing

Page 86: The Importancy of Preliminaries

70

preliminaries. Based on literature search and empirical works the followings are the

findings of this study.

The major findings of the study are:

I. The mandatory item that should be priced by contractors

1) Insurance

2) Workmen’s compensation

3) Performance Bond

4) Setting out

5) Construction Industry Development Board

(Payment for levy)

6) As-built Drawing

7) Work Programmes

8) Hoarding and fencing

9) Client/Employer’s Requirement

i) Vehicles for the S.O

ii) Equipment and facilities

II. The Influencing Factor in pricing preliminaries

1) Availability of resources by the Contractor

2) Plant and equipment to be used

3) Any Obligation or restriction imposed by employer

4) Site condition

5) Commitment number of project

6) Location of site

7) Magnitude of contract

Page 87: The Importancy of Preliminaries

71

8) Lack of understanding of each preliminaries by contractor

9) Contract difficulties and site restriction.

8.3 Conclusion

The study has identified the mandatory items in preliminaries that should be

priced by contractors when pricing preliminaries. It is found that the items listed must be

priced in other greater chances of winning the tender bidding this Is because

preliminaries is important part of overall cost. The study also has identified factors that

influencing pricing preliminaries items. Based on the factor found will help contractor to

be taken into consideration when pricing the preliminaries. Based on the first and second

objective, the strategy in pricing preliminaries has derived. Hopefully the strategies will

give fully benefited to the contractor when pricing and will fully price the items and

cover the whole important without miss it.

Based on the findings of the study it is therefore concluded that the objective of

the study has been achieved. It is also suggested that the findings in this study to be

further digest for considering the present norm of approving the registration of

contractors in our industry so as to achieve the qualified, skill and committed

participants in the industry.

Page 88: The Importancy of Preliminaries

72

8.2 Recommendation for further study

The study has somehow yielded limited achievement. Hence to improve further

the study in this area, it is suggested that further study can be extended to as follows;

a) To expand the whole study to the Malaysia irrespective of the status

of the contractor.

b) To establish guideline by segregate them for infra and building works.

c) To study the impact and important each of preliminaries items.

d) To proposed a conceptual model by development of computer aids for

contractors pricing strategies.

Page 89: The Importancy of Preliminaries

73

BIBLIOGRAFI

Mudd. D.R(1980). Pricing Prelimnaries; Construction Cost Estimate. Second Edition.

Canada. John Miley & Son. Inc

H.E.Pulver, B.S. CE (1985). Construction Estimate and Cost. Forth Edition. Macgraw-

Hill Book Company, New York Toronto London Sydney.

Frank, R. Dagostino (1990). Estimating in Building Construction. Third Edition.

Prentice Hall, Eaglewood Clifft, New Jersey.

George E. Deatherage, P.E (1965). Construction Estimating and Job Planning. Magraw

– Hill Book Company New York San Fransisco Toronto London Sydney.

The Royal Institution of Chartered Surveyor (1978). Standard Method of Measurement

of Building Works. Fifth Edition. The Royal Institution of Chartered Surveyors.

12 Great George Street Parliament Square London.

R.D Wood (1985). Principles of Estimating. The Estate Gazatte Limited 18 Denmark

Street. London. WC2.

W. Howard Wainwright (1990). Practical Builders’ Estimating. Hutchinson

Educational.

W. Atton (1968). Introduction to Estimating for Builders. GeorgeGodwin Ltd. for The

Builders Ltd 4, London.

J.I.W Bentley (1992). Construction Tendering on Estimating. E & F.N Spon.

John A. Milne (1985). Construction and Estimating Procedure. GeorgeGodwin Ltd. for

The Builders Ltd 4, London.

Akintola Akintoye (2000). Analysis of Factors Influencing Project Cost Estimating

Practice. Routledge, Part of The Taylor & Francis Group. Volume 18,

Number1/Jan 1.

Akintola, Akintoye and Skitmore, Martine R. (1990). A Conceptual Model of

Contruction Contractors’ Pricing Strategies. In Baxeudule; A Proceedings 6th

Annual Conference Association of Researchers in Construction Management.

Page pp 31-47.

Page 90: The Importancy of Preliminaries

74

P.D. Steane, D.H.T. Walker (2000). Competitive tendering and contracting public sector

services in Australia – a facilities management issue. MCB UP Ltd. Volume: 18

Issue: 5/6 Page: 245 – 255

Page 91: The Importancy of Preliminaries

75

APPENDIX 1

(QUESTIONNAIRES FOR THE INDUSTRY SURVEY)

Page 92: The Importancy of Preliminaries

76

To Whom it May Concern The understanding Contract Documentation in Project Implementation You have been chosen to participate in this survey because we know with the vast experience that you have, you are able to provide valuable knowledge into the factors that influence in pricing preliminaries. The intention of our study is to seek opinion and good thoughts pertaining to the level of understanding of preliminaries items referring to the interpretation of contractor according to the importance of each item. The study will focus to the indigenous group of contractors involved directly in building project above 1 mil of project cost. Your opinion and good thoughts through responding to this questionnaire survey are very much appreciated. Your identity remains unknown and your response will be kept confidential and only accessible to our research team. Please return the completed questionnaire using the self addressed envelope for normal mail delivery or you may fax directly to me at the number given below. NORHISHAM BIN ABDUL GHANI Jbb Consultants Sdn Bhd No.43 1st Floor USJ 10/1A, 47301 Subang Jaya, Selangor Your sincere and honest response is highly appreciated. Thank You. Norhisham Bin Abdul Ghani A:Background

Page 93: The Importancy of Preliminaries

77

Please Circle the Appropriate choice Q1. Which of the following Background most accurately describes your organization? 1. Developer 2. Supplier 3. Contractor 4. Government Agency 5. Consultant 6. Others (please indicate) _________________________ Q2. What is your position in your company?

1. Project Director 2. Project Managers

3. Project Planner 4. Engineer 5. Quantity Surveyor 6. Supervisor 7. Others (please indicate) ________________________

Q3. How long has you involved in Construction Industry 1. < 2 years 4. 11-20 years 2 2 – 5 years 5. > 20 years 3. 6 – 10 years

SECTION A

Page 94: The Importancy of Preliminaries

78

Factors Influence the pricing of the preliminary items Please circle your choice where : 1 – Least Agreed 2 – Fairly Agreed 3 – Agreed 4 – Strongly Agree 5 – Very Strongly Agree Least Agreed Very Strongly Agreed

1. Lacking of understanding contract particular and preliminary items by Contractor 1 2 3 4 5

2. Site Condition 1 2 3 4 5 3. Location of the Site 1 2 3 4 5 4. Contract Difficulties and site restriction 1 2 3 4 5 Eg. Dangerous underpinning, deep foundation 5. Magnitude of contract. Eg. Small, simple contract 1 2 3 4 5 6. Plant and equipment to be used 1 2 3 4 5 7. Any obligation or restriction imposed by employer 1 2 3 4 5 8. Commitment number of projects 1 2 3 4 5 9. Availability of resources by the contractor 1 2 3 4 5

Page 95: The Importancy of Preliminaries

79

10. What are other factor(s) that you think influence the Pricing of preliminary

by the contractors. (Please specify your good thoughts) __________________________________________________________________________________________________________________________________________________________________________________________

11. Based on your good experience, normally how much is the percentage approximately allowed in tender irrespective of type of project (please tick)

5 – 6 % 6 – 7 %

8 – 9 % More than 10%

12. Based on your good experience, please provide opinions and Comments on How to ensure that the preliminaries item is fully priced by the Contractor for better competitive cost. ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

We thank you your corporation in completing this questionnaire. We are confident that the information you provided will greatly us in our research. Please return he completed questionnaire in the self-addressed and postage-paid envelope not later than 15 October 2006.

Once again thank you for your support