1
TENDER DOCUMENT
FOR CONSTRUCTION
OF
URDU DEPARTMENT BUILDING
AT
UNIVERSITY OF LUCKNOW
LUCKNOW
DEPARTMENT OF WORKS
UNIVERSITY OF LUCKNOW, LUCKNOW
2
PART – 1
Technical Bid.
FOR
“CONSTRUCTION”
OF
URDU DEPARTMENT BUILDING
DEPARTMENT OF WORK
UNIVERSITY OF LUCKNOW, LUCKNOW.
3
TENDER NOTICE Sealed tender are invited from A Class registered contractors of
Works Department for construction of Urdu Department Building.
The terms and condition along with format of technical and financial bid
respectively (Tender document Set) can be downloaded from
www.lkouniv.ac.in along with this notice.
The tender bids (separate technical and financial bids double seated
in one envelope) addressed to the Executive Engineer, University of
Lucknow-226007 shall be deposited in the office of Registrar by the last
date of October 12, 2017 (2.00pm). The bids shall be opened at 3.00pm in
the office of the Proctor, University of Lucknow.
Executive Engineer University of Lucknow.
4
INFORMATION & INSTRUCTIONS FOR THE TENDERER
1. The application should be type-written. The applicant should sign
each page of the application.
2. Over Writing should be avoided. Correction, if any, should be
made by neatly crossing out, initialing, dating & re-writing.
3. The applicant may furnish any Additional information which he
thinks is necessary to establish is capabilities to successfully
complete the envisaged work. He is however advised not to furnish
superfluous information. No information shall be ever advised not
to furnish superfluous information. No information shall be
entertained after submission of pre-qualification document unless it
is called for by the Employer.
4. Any information furnished by the applicant found to be incorrect
either immediately or at a later date, would render him liable to be
debarred from tendering/ taking up of work at University of
Lucknow.
5. The tender shall be submitted as two bid system in accordance with
the procedures specified. Documents shall be submitted in
envelope of appropriate size, which shall be duly sealed.
6. “Conditional tender” shall not be considered.
7. Tender document are to be submitted in two separate envelopes.
Envelope marked no-1 shall contain the technical bid and marked
on-2 for financial bid (price bid).
8. Both envelopes 1 & 2 shall be kept in one Large envelope with
“name of work, date of tender, details of earnest money, full
address and contact number of tenderer”.
5
SUBMISSION OF TENDER
The detail of document to be submitted with each envelope is given
below:
ENVELOPE MARKED-1 (TECHNICAL BID)
1. Demand Draft of Rs. 5000.00 being cost of tender from has to be
attached with tender form in the made of Bank Draft in favour of
Finance Officer, University of Lucknow payable at Lucknow
which is not refundable in any case.
2. Earnest money @ 2% of the value of Rs. 80.00 Lakh in the shape
of NSC/FDR/Bank Guaranty duly pledged in favour of Finance
Officer, University of Lucknow.
3. Duly filled up technical bid document appended with the tender.
4. List of works satisfactorily completed during previous years in
Govt./Semi-Govt./Public Sector undertaking and reputed private
limited companies along with certificates (Attested copy). List of
ongoing work of the same type of job.
5. Latest income tax clearance certificate valid till date (original or
attested copy) clearly indicating turn over of last three assessment
years.
6. List of technical staff with their qualification professional
experience and length of the service with the firm as detailed ahead
in document.
7. Attested copy of the partnership deed if it is partnership firm and
registration certificate in case of company, sole proprietorship
declaration in case of proprietorship firm. Joint ventures shall not
be accepted.
6
8. Authority letter, if the firm/ tenderer in favour of the person who
has signed the tender document with telephone no., complete postal
address and E-mail address.
9. Annual turnover.
ENVELOPE NO-2 (PRICE BID)
a. Price bid duly filled in all respects in the original tender
documents.
b. Non-Judicial stamp paper of Rs. 10/- (Rs. Ten Only) of UP along
with Rs. 1/- revenue stamp.
SYSTEM TO OPEN TENDERS:
a. Envelope No-1 containing the earnest money and pre-qualification
document shall be opened first on specified date & time before the
renderers present at the time of opening.
b. Envelope No-2, containing the offer/price bid, of tenderers who
quality the technical bid, shall be opened on date & time fixed. The
quoted rates of various tenders will be read out. Tenderers desirous
to be present shall be allowed at the time of opening of price bid.
GENERAL CONDITIONS OF WORK
All the work shall be carried out as per detailed C.P.W.D./
U.P.P.W.D. specifications for Building.
EXTENT OF CONTRACT
The contract comprises construction and completion of the
specified job and the provisions of all labour, materials, T & P etc. and
transport temporary works etc. whether of temporary or permanent in
nature required for the construction, completion and maintenance of the
work.
INSPECTIONS OF THE SITE
The tenderer (s) must inspect and examine the site of work and its
surroundings and satisfy himself/ themselves before submitting his/their
7
tender. He/they has/have to make sure of the positions of availability of
required material.
ENTRIES IN TENDER
All entire by the tendered should be in one ink and one hand/ on
prescribed bill of quantity only. Erasers and overwriting are not
permissible. All corrections should be neatly written and signed by the
tenderer. Rate should be written in figures as well as in words. In case
there is any variation, lower rate shall be treated as Tender rate.
CONDITIONAL/INCOMPLETE TENDER
Conditional, incomplete, unsigned tenders shall not be considered.
Only those bidders who supply necessary proof/documents in their bids
shall be considered as responsive for further evaluation.
ADDRESS OF CONTRACTOR
The contractor shall give his full permanent postal address. The
postal receipt of the letters sent to him on this address shall be considered
sufficient proof that they have been delivered to him.
ACCEPTANCE OF TENDER
Subject to conditions of bid document, the Employer will award
the Contract to the Bidder whose Bid has been determined:
i. to be substantially responsive to the bidding documents and
who has offered the lowest evaluated Bid price, provided that
such Bidder has been determined to be (a) eligible and (b)
qualified in accordance with the provisions of bid document.
ii. to be within the available bid capacity adjusted to account for
his bid price which is evaluated the lowest in any of the
packages opened earlier than the one under consideration.
The University of Lucknow shall have the right to accept or
reject any or all the tenders or part thereof, without assigning
8
any reason to contractor and no claim whatsoever shall be
entertained on this account.
AWARD OF CONTRACT
The bidder whose Bid has been accepted will be notified of the
award by the department prior to expiration of the Bid validity period by
phone/ confirmed by registered letter. This letter (hereinafter called the
“Letter of Acceptance”) will state the sum that the Employer will pay to
the Contractor in consideration of the execution, completion by the
Contractor as prescribed by the Contract (hereinafter and in the Contract
called the “Contract Price”).
The notification of award will constitute the formation of the
Contract, subject only to the furnishing of a performance security in
accordance with the provisions of Security money.
SECURITY MONEY
Within 10 (ten) days after receipt of the Latter of Acceptance, the
successful Bidder shall deliver a Performance Security to the department.
The Security money of five percent of the Contract Price, of the period of
the time for completion of works.
The security shall be either in the form of a Bank Guarantee or
fixed deposit Receipts, in favour of Finance Officer University of
Lucknow from a Scheduled Commercial Bank.
Failure of the successful Bidder to comply with the requirements
security money shall constitutes grounds for cancellation of the award
and forfeiture of the Earnest Money. He will also be debarred from
participating future bids in University of Lucknow.
SIGNING OF TENDER DOCUMENTS
The Agreement will incorporate all agreements between the
Employer and the successful Bidder. It will be signed by the Employer
9
and the successful Bidder after the performance security is furnished.
Required stamp duty on the contract deed will be borne by the contractor.
EXECUTION OF AGREEMENT
Successful Tenderer shall have to execute an agreement on stamp
paper of value as applicable, through its authorized representative within
a week from date of receipt of acceptance letter/ work order.
RUNNING PAYMENT
Contractor shall be entitled for payment running bills on monthly
basis. However, if required by the contractor, running bills in a lesser
period may be considered for payment but the value such payment should
not be less than 5% of contract value.
COPY OF CONTRACT
On request, the Executive Engineer may furnish the contractor with
a copy of the contract.
TIME OF COMPLETION
The entire work is to be completed in 06 months.
The contractor has to ensure that minimum 7 days advance
intimation to be sent in writing to University in case of any delay for need
of any drawings or clarification. No extension will be granted to the
contractor if intimation is not sent in timely manner or if the clarification
is given within a week.
ROYALTIES AND TAXES ETC.
The contractor shall pay all royalties, license fee, labour cess and
all other charges at quarry, octroi duties, custom duties, toll taxes, labour
cess and any other local taxes as may be levied. No passes for octri or toll
levied by local bodies on toll bridges shall be issued by the Department.
Rate shall inclusive of the same. Nothing extra shall be paid due to
fluctuations in the cost of materials, labour and all types of taxes etc.
Only G.S.T. shall be paid separately.
10
DAMAGES BY RAINS, ACCIDENTS OR NATURAL
CALAMITIES
No payment will be made to the contractor for damage caused by
rains, accidents or other natural calamities during the progress of work.
No claim whosoever shall be entertained on this account.
DEFAULT OF CONTRACTOR IN COMPLIANCE
Constant defiance of the instructions of Engineer-in-charge on the
part of the contractor or his authorized agent will make the contract will
liable to be terminated.
CLEARANCE OR SITE ON COMPLETION
The contractor shall at all times keep the premises free from
accumulated waste materials or rubbish caused by his employees on the
works and on completion of the work, he shall clear away and remove
from site all surplus materials, rubbish and temporary work of any kind
and fill up borrow pits dug by him. He shall leave whole of the site and
work clean and in a workmanlike condition of the entire satisfaction of
the Engineer-in-charge.
DEFECTS AFTER COMPLETION
The contractor shall make good at his own cost and to the
satisfaction of the Employer all defects, shrinkage, settlements or the
faults which may appear within 12 months after completion of the work.
ESCALATION
The rate quoted shall be FIRM throughout the tenure of the
contract (including extension of time, if any, granted) and will not be
subject to any fluctuation due to increase in cost of materials, labour, tax,
octrioi etc.
11
PROFORMA FOR TECHINAL BID
I. Detail of tender cost Enclosed. Draft No.- Date- Amount- Issuing Branch and Bank.
II. Detail of Earnest money Enclosed FDR/NSC/ Bank Guarantee/Amount FDR/NSC/Bank Guarantee Number Issuing branch & bank.
III. General Information 1. Name of the firm 2. Address 3. Contact person
Phone Email
Cell Phone 4. Place and year of incorporation of the firm : 5. Registration No./G.S.T.N. No. (copy to be enclosed) : 6. Details of Registration (State PWD/CPWD/MES) :
a. Class b. State c. Date of Registration d. Validity
7. Constitution of the firm (Public, Proprietary etc.). 8. Name & qualification of the Chief Executive
of the firm IV. Financial Information
1. Turn over for the last three years : 2. Permanent Account No. (IT) : 3. GST Registration No. : 4. Income Tax Clearance Certificate :
(Enclose copies for the last three years) 5. Solvency Certificate issued by :
12
Annexure-I Details of completed projects
Project/ Work Name
Name of the Client
Value of Contract (Rs. In Lakhs)
Stipulated time of
completion
Actual time of
completion
Remarks, Explain
reasons for delay, if any.
Enclose satisfactory completion certificate and date of completion
from the concerned Engineer-in charge not below the rank of Executive Engineer in the case of Govt. or Chief Executive in the case of Private Organization.
SIGNATURE OF BIDDER
13
Annexure-II Details of existing and ongoing projects.
Project/ Work Name
Name of the
Client, Place and
state
Value of Contract (Rs. In Lakhs)
Stipulated time
completion
date of
start
Date of Completion
Value of work’s
Remaining to be
completed
Anti cipated time of
completion
Enclose a progress certificate from the concerned Engineer-in-Charge not below the rank of Executive Engineer in the case of Govt. or Chief Executive in the case of Private Organization.
SIGNATURE OF BIDDER
14
Annexure - III
TURN OVER FOR THE LAST THREE YEARS Sl.No. Year Turn Over
(Rs. in lakhs) Remarks
1. 2014 – 2015
2. 2015 – 2016
3. 2016 - 2017
Enclose certificate from the concerned Engineer-in-charge not below the rank of Executive Engineer or from Chartered Accountant.
SIGNATURE OF BIDDER