Upload
vinod-mahajan
View
80
Download
8
Embed Size (px)
Citation preview
NTPC LIMITED
SUPERCRTICAL TECHNOLOGYSUPERCRTICAL TECHNOLOGY
SELECTION OF BOILERAND
ITS AUXILIARIES
PRESENTATION BY PROJECT ENGINEERINGPANKAJ KR GUPTA
WHY SUPERCRITICAL TECHNOLOGY
WHAT IS THE ADVANTAGE AND DISADVANTAGE OF THIS TECHNOLOGY FROM SUBCRITICAL
TECHNO ECONOMICS
SELECTION OF SUPERCRITICAL PARAMETERS
WHAT IS THE DIFFERENCE BETWEEN SUPERCRITICAL AND SUBCRITICAL IN MAJOR EQUIPMENTS/ COMPONENTS
BOILER EFFICIENCY, TURBINE EFFICIENCY,CYCLE EFFICIENCY
PART-I: SUPER CRITICAL TECHNOLOGY
PART-II: TECHNO ECONOMIC STUDY
PART-III DESIGN OF BOILER & ITS AUX.
PART-IV : SIPAT- I BOILER FEATURES
PARTPART--II
SUPERCRITICAL TECHNOLOGYSUPERCRITICAL TECHNOLOGY
0
10
20
30
40
50
60
1880
1900
1920
1940
1960
1970
1980
1990
2000
2020
Ther
mal
Efficien
cy (%
)
Rankine Barrier
Supercritical boiler IGCC
PFBC
AGMCFC
IGHAT
Pulverised Coal
First Station
USPCFIGMCF
SUPC
SUPCF: Sub Critical Pulverised Coal FiredPFBC: Pressurised Fluidised Bed CombustionIGCC: Integrated Gasification Combined CycleIGHAT: Integrated Gasification Humid Air TurbineUSPCF: Ultra Super Critical Pulverised Coal FiredIGMCFC: Integrated Gasification Molten Carbonate Fuel CellAGMCFC: Advanced Gasification Molten Carbonate Fuel Cell
Evolution Of The Coal Fired Plant
Rankine Cycle Efficiency
net workn = --------------
Qin
Cycle thermal efficiency is improved by increasing the mean temperature of heat addition process. This temperature is increased because the boiler inlet pressure sets the saturation temperature in Rankine cycle.
Total fuel inputHeat Rate =------------------
Electrical generation (KW)
860= ------------------- Kcal/Kwh
n
T em
p er a
ture
( C)
Enthalpy
538
Expansion Line
170 kg/cm2
240 kg/cm2
Critical Point 225 kg/cm2
Condensation
EFFECT OF SUPERCRITICAL PARAMETERSEFFECT OF SUPERCRITICAL PARAMETERS
THERMAL EFFICIENCY IMPROVEMENTTHERMAL EFFICIENCY IMPROVEMENT
169 246 310STEAM PRESSURE (kg/cm2)
Base Efficiency 38.6%
%
0.69
0.27
0.35
0.33
0.32
5380C/5380C
5380C/5660C
5660C/5660C
5660C/5930C
6000C/6000CE
ffic
ienc
y In
crea
se
0.41
5660C/5660C
SUPERCRITICAL PLANTSSUPERCRITICAL PLANTS--WORLDWIDE TRENDSWORLDWIDE TRENDS
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
1968
1971
1974
1977
1980
1983
1986
1989
1992
1995
1998
2001
2004
2007
2010
2013
CALENDER YEAR
CA
PAC
ITY
(MW
)
Total Steam Capacity
Source ABB
Supercriticalplants
TECHNOLOGY ADOPTION STATUSTECHNOLOGY ADOPTION STATUS
0 50 100 150 200 250
CISUSA
JAPAN
GERMANY
KOREA
CHINA
DENMARK
IRAN
ITALY
SPAINNETHERLANDS
TAIWAN
THAILAND
CUBA
FINLAND
1950s 1960s 1970s 1980s 1990s
Number of UnitsNumber of Units
Estimated World Total
600 Units
Size Range 300-399 400-499 500-599 600-799 800+Sub-critical 76.5 77.4 76.3 78.5 77.2
Super critical 64.4 74.6 73.8 74.2 75.6
AVAILABILITY : SUPERCRITICAL VS SUBCRITICALAVAILABILITY : SUPERCRITICAL VS SUBCRITICALEPRI
EAF 1982-84Low availability in 1960s:
• Rapid unit size escalation• Low fuel quality tolerance• Inflexibility for cyclic
loading
Year 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998Subcritical 84.2 82.5 84.1 84.9 84.5 82.0 83.8 83.7 86.6 88.5 84.4
Supercritical 80.2 74.9 84.2 85.2 87.1 89.8 83.0 84.7 79.5 90.3 84.0
VGB
Report Concludes Report Concludes --No difference in availability with No difference in availability with .. present day design.. present day design.
JEPIC/FEPC Data- Supercritical units higher than subcritical unitsEPDC Experience- EPDC own plants do not show any difference.CIS Countries- Russian units have high availability.
SUPPLIERS OF SUPERCRITICAL PLANTSUPPLIERS OF SUPERCRITICAL PLANT
BOILER• B&W, USA• ABB-CE• MHI, JAPAN• PODOLSK, RUSSIA• FOSTER WHEELER, USA• IHI, JAPAN• ANSALDO, ITALY• TAGANROG, RUSSIA• BABCOCK HITACHI, JAPAN• STEIN MULLER, GERMANY• STEIN INDUSRIE, FRANCE• EVT, GERMANY• DEUTCHE BABCOCK,
GERMANY• MBEL, U.K.
TURBINE• GE,USA• LMZ, RUSSIA• WESTING HOUSE, USA• TOSHIBA, JAPAN• ABB, GERMANY• HITACHI, JAPAN• MHI, JAPAN• ANSALDO, ITALY• SIEMENS AG
SUPERCRITICAL PLANT BOILER SUPERCRITICAL PLANT BOILER TECHNOLOGY STATUSTECHNOLOGY STATUS
Type Construction Manufacturer Remarks
Spiral woundSmooth tubing
Stien/EVT Stienmuller Deustche Babcock
Benson/Siemens
Vertical Ribbedtubing
Under Indroduction
Suitable for variablepressure operation
Technology licenced bySiemens
Spiral woundSmooth tubing
CE, IHI, MHISulzer
Vertical Ribbedtubing
ABB-CE MHI
Suitable for slidingpressure operation
Vertical tube designdeveloped jointly bySulzer/CE/MHI
European Design
UniversalPressure type
Verticalbare tubing
B&W, FosterWheeler
IHI, Hitachi Babcock Taganrog & Podolsk
Used primary in USAand CIS countries
Am
ericanD
esign
Boiler SupercriticalType Once through, Single/ Two passFurnace
• Water walls
• Tube material• Tubing dia• Circulation
Pressure Parts
Startup system
Start up rate
Load following capability
Tolerance to coal quality
-Spiral bare tubing-Vertical bare/rifled tubing-Low alloy steel-31-38 mm-Forced once thru
-Increase in thickness of tubing-Increase use of Stainless steeland P-91 material in SH/RH
-Drain to condenser-Recirculation thru pump-Drain with regenerative heating
Higher
Better
Higher
MAJOR DIFFERENCES IN SUPERCRITICAL PLANT MAJOR DIFFERENCES IN SUPERCRITICAL PLANT
Critical Piping SupercriticalMain Steam piping• Size
• Thickness• Material
HRH piping
• Size• Thickness
• Material
Feed piping
Reduction in diameter due tolower specific volumeIncrease in thicknessChange in material P-22/X-20 toP-91
No change in diaNo change in thickness due to P-41 materialChange in material from P-22,X-20 to P-91
Increase in thickness
MAJOR DIFFERENCES IN SUPERCRITICAL PLANT MAJOR DIFFERENCES IN SUPERCRITICAL PLANT
Steam Turbine SupercriticalCasings• Thickness
• Material
Rotor
Blade
Stop/control valves andInterconnecting piping
• Marginal increase inthickness
• Change in material 2 ¼ Cr 1Mo to 12 Cr
Change in material for part ofthe rotor (specific to Mfg)
Change in material for first fewrows to austinitic steel
Marginal change in thicknessand change in material 2 ¼ CrMo to 9 Cr steel.
MAJOR DIFFERENCES IN SUPERCRITICAL PLANT MAJOR DIFFERENCES IN SUPERCRITICAL PLANT
Turbine Feed Cycle SupercriticalBoiler Feed Pump
HP Feed Water Heaters
• Increase in motor power• Increase in thickness of
casing• Increase in discharge
pressure of pump
Increase in thickness of tubesheet, tubes and waterbox.
MAJOR DIFFERENCES IN SUPERCRITICAL PLANT MAJOR DIFFERENCES IN SUPERCRITICAL PLANT
Balance of plant Supercritical
Coal HandlingPlant
Ash handling Plant
CW System
Capacity Reduction by40t/hr
Capacity reduction by10t/hr
Capacity reduction by1%
MAJOR DIFFERENCES IN SUPERCRITICAL PLANT MAJOR DIFFERENCES IN SUPERCRITICAL PLANT
MATERIAL APPLICATION FOR HIGH STEAM TEMPERATURESMATERIAL APPLICATION FOR HIGH STEAM TEMPERATURES
538 C 566 C 593 CCOMPONENT
2 1/4 Cr MoSH HDR MS PIPE
SH TUBE (HOT PARTS)
RH HDR RH PIPE
RH TUBE (HOT PARTS)
9 Cr steel 12 Cr steel
HP/IP ROTOR
HP/IP CASING
MAIN VALVE
18 Cr steel 20-25 Cr steel
2 1/4 Cr Mo steel 9 Cr steel
9 Cr steel 18 Cr steel
2 1/4Cr M V steel 12 Cr steel
2 1/4 Cr Mo steel 12 Cr steel
2 1/4 Cr Mo steel 9 Cr steel
TURBINETURBINE
BOILERBOILER
ENVIRONMENTAL ASPECTSENVIRONMENTAL ASPECTS
• Reduction in CO2, SO2 and NOx between 1.79% to 4.24%
• Reduction for 500 MW at 68.5% PLF per year is - CO2 78300 tons - SO2 365 tons - Nox 71 tons
SUPERCRITICAL ADVANTAGESSUPERCRITICAL ADVANTAGES
Enhancements• Plant efficiency 0.69% to 1.64%• Fuel tolerance More tolerant to coal
quality changes
Reductions• Coal Consumption • Ash production • CO2
• SO2
• Nox
Improvements• Startup time • Sliding Pressure Operation• Load following capability
1.79% to 4.24%
STEAM CONDITION DEVELOPMENT TRENDSTEAM CONDITION DEVELOPMENT TREND
1960s 1970s 1980s 1990s 2000s 2010s
MatureTechnology
MatureTechnology
Current Market Introduc-tion
R&D-USC
R&D-Advanced USC
(EUROPE)(EUROPE)
Subcritical 170 K/540oC/540o
Super critical 245/540/540
245/546/565
245-580/600
285-600-620
285-630/650
382-700/720ULTRA SUPERCRITICAL
Para
met
e rs
Year
SUPERCRITICALSUB-CRITICAL
SELECTION OF RATED PARAMETERSELECTION OF RATED PARAMETER
01020304050607080
246-
538/
538
246-
538/
566
246-
566/
566
300-
580/
580
NO
OF
UN
ITS
(%)
SELECTED PARAMETERS
MSP 246 kg/cm2
MST 5380C
RST 5660CUltr
a su
perc
ritic
al
PARTPART--IIII
TECHNOECONOMIC STUDYTECHNOECONOMIC STUDY
CASE STUDY FOR PIT HEAD CASE STUDY FOR PIT HEAD AND AND
LONG LEAD STATIONSLONG LEAD STATIONS
Base Price EstimatesBase Price EstimatesEquipment Unit
per MWCase-1169-538/538
Case-2246-538/538
Case-3246-538/566
Case-4246-566/566
Case-5246-566/593
Boiler Rs mill 8.32 8.63 8.69 8.86 9.04Turbine Rs mill 4.96 5.12 5.16 5.29 5.41Coal Handling Rs mill 2.36 2.36 2.36 2.36 2.36Ash Handling Rs mill 1.74 1.74 1.74 1.74 1.74BOP Rs mill 13.10 13.10 13.10 13.10 13.10Total Rs mill 30.48 30.95 31.05 31.35 31.65Difference % Base 1.54 1.87 2.85 3.84
Note- Cost given are in Rs.Millions/MW
Difference in boiler cost w.r.t. supercritical plant (case-3) is 4.5%.Difference in turbine cost w.r.t. supercritical plant (case-3) is 4.0%Difference in total cost w.r.t. supercritical plant (case-3) is 1.87%.
EFFICIENCY GAINEFFICIENCY GAIN(Indian ROM coal)
Unit Case-1 Case-2 Case-3 Case-4 Case-5Boiler Efficiency
% 87.5 87.5 87.5 87.5 87.5
Turbine Heat Rate
Kcal/Kwhr
1947 1913 1900 1883 1868
Gross Heat Rate
Kcal/Kwhr
2225.7 2186.6 2171.7 2152.7 2135.05
GrossEfficiency
% 38.64 39.33 39.60 39.95 40.28
Differential Base 0.69 0.96 1.31 1.64
SELECTION OF PARAMETERS FOR STUDYSELECTION OF PARAMETERS FOR STUDY
CASE MSP(Ksc)
MST(deg C)
RST(deg C)
1 169 538 538
2 246 538 538
3 246 538 566
4 246 566 566
5 246 566 593
Matured technologies
Current Market Introduction
Recommended Option
TECHNO ECONOMIC EVALUATION OF ALTERNATIVESTECHNO ECONOMIC EVALUATION OF ALTERNATIVES(246 kg/cm2 , 538 / 566)(246 kg/cm2 , 538 / 566)
Total six alternatives are discussed.
S.No. EconomicFactors
Pithead Stations Long LeadStations
1. Plant Sipat Cheyyur
ROM WASHED Washed2. Type of coalAlt-I Alt-II Alt-III Alt-IV Alt-V Alt-VI
3. Coal cost (Rs.) 441 441 441 700 700 1912
4. Coal costEscalation (%)
7 10 10 10 10 7
5. PLF(%) 68.5 68.5 85 68.5 85 68.5
TECHNO ECONOMIC FACTORS CONSIDEREDTECHNO ECONOMIC FACTORS CONSIDEREDSIPAT STAGESIPAT STAGE--I ROM COALI ROM COAL
ECONOMIC FACTORS• Debt Equity Ratio 70:30• Return on Equity 16%• Interest on loan 11.19• Depreciation 7.53%• O&M charges 2.5%• Inflation Rate 7%• Interest on working capital 16.25%
OTHER MAJOR FACTORS• Heat Rate 2225 Kcal/kwh (Base)• Auxiliary Power Consumption 8% (Base)• Fuel Oil Consumption 3.5 ml/kwh (Base)• Oil Cost 7275 Rs/kL• Coal calorific value 3200 kcal/kg
TECHNO ECONOMIC EVALUATIONTECHNO ECONOMIC EVALUATION--ASSUMPTIONSASSUMPTIONS
• Technology cost in total capital cost is zero• Capital cost of equipment is based on
competitive International prices.• Coal cost is based on administered pricing
mechanism
ANALYSIS OF SIPATANALYSIS OF SIPAT-- ROM COALROM [email protected]% PLF, COAL COST @68.5% PLF, COAL COST RsRs. 441 PER TON AND 7% COAL COST ESCALATION. 441 PER TON AND 7% COAL COST ESCALATION
S lCOAL Indian ROM Coal
Sub critical Super criticalCase-1 Case-2 Case-3 Case-4 Case-5
Parameter OptionBar –oC/oC
169-538/538 246-538/538 246-538/566 246-566/566 246-566/593Total Cost (Rs.crs) 1891.17 1918.12 1924.50 1943.85 1962.86
Cost Base 26.95 33.33 52.68 71.69
1.
CA
PITA
LC
OST
PE
R50
0MW
AdditionalCapital(Rs.crs) Yearly Servicing Cost Base 5.17 6.37 10.08 13.74
Heat rate (Kcal/kWh) 2225.7 2186.6 2171.7 2152.7 2135.05
Coal consump. (mt/year) 2.0538 2.0171 2.0032 1.9853 1.9688
Coal cost Rs./ton 441 441 441 441 441 Levelized value 157.22 154.42 153.35 151.99 150.71
2.
CO
ALC
ON
SUM
PTIO
N P
ER50
0 M
W
Yearlycoal bill(Rs.Crs) Reduction Base 2.81 3.88 5.24 6.51
3.Levelised COG Paisa/kWh 199.92 200.60 200.61 201.39 202.21
Total cost 1891.17 1905.92 1911.44 1918.88 1925.56Capital Costs(Rs crs.) Additional cost Base 14.75 20.27 27.27 34.394.
ImputedcostsPer 500MW
Coal Cost (Rs/T) 441.0 801.0 717.0 838.0 917.0
1. Sub critical Plant is most economical2. At coal cost of Rs. 717/- the supercritical plant becomes economical3.Imputed capital cost for supercritical plant is 1911 crores.
ANALYSIS OF CHEYUR ANALYSIS OF CHEYUR -- WASHED COALWASHED [email protected]% , COAL COST Rs.1912 PER TON AND 7% COAL COST [email protected]% , COAL COST Rs.1912 PER TON AND 7% COAL COST ESCALATION
SlNo
COAL Indian Washed Coal
Sub critical Super critical
Case-1 Case-2 Case-3 Case-4 Case-5
Parameter Option
Bar –oC/oC
169-538/538 246-538/538 246-538/566 246-566/566 246-566/593
Total Cost (Rs.crs) 1841.18 1870.08 1875.97 1895.21 1913.65
Cost Base 28.90 34.78 54.03 72.47
1.
CA
PIT
ALC
OST
PER
500
MW
AdditionalCapital(Rs.crs)
YearlyServicing Cost
Base 5.31 6.35 9.94 13.39
Heat rate (Kcal/Kwh) 2209.0 2170.00 2155.00 2136.00 2119.00
Coal consump. (mt/year) 1.7163 1.6855 1.6737 1.6587 1.6453
Landed Coal costRs./ton
1912 1912 1912 1912 1912
Levelizedvalue
569.65 559.43 555.50 550.52 546.07
2.
CO
AL
CO
NSU
MPT
ION
PER
500
MW
Yearlycoal bill(Rs.Crs)
Reduction Base 10.22 14.15 19.13 23.58
3. COG Paisa/Kwhr 349.72 347.68 346.52 345.91 345.47
Total cost 1841.18 1895.33 1916.11 1942.51 1966.13Capitalcost(Rs/crs) Additional
costBase 54.15 74.93 101.33 124.95
4. Imputedcostsper500 MW
Coat cost (Rs/ton) 1912 1022.0 890.0 1021.0 1111.0
1.Subcritical plant is most economical.2.Imputed capital cost for supercritical plant is 1916 crores.
SUPERCRITICAL TECHNOLOGYSUPERCRITICAL TECHNOLOGY-- ECONOMIC EVALUATIONECONOMIC EVALUATION
441 717 1912
3.8
6.3
Coal cost (Rs/ton)
Add
n.C
ap. S
ervi
ce C
ost
(Rs c
rs)
Yr.
Sav i
ng in
Coa
l Bill
(Rs.
Crs
)
CASECASE--3 : 246 kg/cm3 : 246 kg/cm22--53853800C/566C/56600CC
Shortfall
Cushion for Technology Cost
(-)
(+)
SupercriticalSubcritical
Breakeven
14.1
68.5% PLF , 7% Escalation
Addn capital of Rs. 33.3 crs
6.3
20.3
33.3
74.9
Add
n.C
ap. C
ost
(Rs c
rs)
MAIN CONCLUSIONMAIN CONCLUSION
• Technology - Mature and establish• Availability - Same as sub-critical• Project Implementation- Essentially same as sub-critical• O&M - By & large same as sub-critical• Reduced Environmental Impact • Most preferred parameters- 246 Kg/cm2-538oC/566oC• Materials proven and already in use• Technology cost for Indian OEM is not possible to assess.
SUPERCRITICAL VS SUBCRITICALSUPERCRITICAL VS SUBCRITICALMAJOR DESIGN DIFFERENCE
• Boiler- Once Through instead of drum type and use of superior material in certain pressure parts
• Piping- Reduced diameter. Superior Material.• Turbine- Increase in thickness of various parts to suit higher parameters• Feed Heaters-Increased thickness of tubes, water boxes and tube plate• BFP-Increased motor rating. Higher thickness of certain parts• Boiler Control- Change in philosophy• Water Chemistry- No blow down. 100% flow CPU. Different chemistry
control.• No new superior material is used. Only the quantity of superior material
increases.
PARTPART--IIIIII
SELECTION OF BOILER & ITS SELECTION OF BOILER & ITS COMPONENT COMPONENT
SELECTION OF BOILER
TYPE OF BOILER
Based on steam parameter- Subcritical/ Supercritacal
Based on steam/ water circuit-Once throuh/ drum type
Based on air/ flue gas path- Tower/Two path/ T-type
Type of fuel- Coal fired/ oil fired
Type of draft system-
Type of burner arrangement- Tangential/Front/ opposed
Selection of Firing system- Type of mills
Single reheat/ double reheat
Type of water wall tube- Plain, rifled
Type of tubing arrangement- Spiral/ straight
Mode of Operation
Sliding pressureConstant pressure
Selection of steam parameter
SH pressure, temperatureRH pressure, temperature
Rating of boiler (BMCR)
SH flowRH flow
Means of SH/RH Temperature Control
SprayGas biasing damper
Burner tilt
Start up system
S.no.
Description Benson Boiler (VariablePressure)
UP Boiler (Constantpressure)
1. Operability Start up time (Hot Start)
120-130 min (with 30%Turbine bypass)
250-300 min [withoutTurbine bypass](Complicated operation isrequired)
2. Daily Start &Stop (DSS)Operation
Suitable (Smooth shiftbetween start up bypasssystem and circulationsystem)
Not suitable (Because ofslightly complicated shiftoperation.)
3. Load ChangeRate (50-100%MCR)
3~4%/min 3~4%/min.
4. Part loadefficiency
better base
5. Start up bypasssystem
• Simplified start-up bypasssystem
• Shift operation of start upvalves is not necessary
• Operation of drain valvesand vent valves isnecessary
• Main valve is installed inthe main steam line
• Shift operation of start upvalves is necessary
• Operation of drain valvesand vent valves isnecessary
COMPARISON OF BENSON AND UP BOILER
S.no.
Description Benson Boiler (VariablePressure)
UP Boiler (Constantpressure)
6. Heat loss duringstart up
Warming of start up bypasssystem Heat recovery of circulatedwater by BCP
Warming of start up bypasssystem
7. Mixing Bottles Mixing bottled are notnecessary due to small fluidtemperature unbalance.
Mixing bottled are necessaryto cancel large fluidtemperature unbalance.
8. Sliding pressureoperation(Range)
Acceptable( Sub- Critical –Super Critical region)
Limited (Max=20 kg/cm2)
Sliding pressure V/s Constant pressure
In sliding operation, turbine inlet valves remains fully open during normal operation. As a result the live.
Advatageslower thermal stresses
The control range of the reheater final steam is extended.
Reduce pressure level at low loads prolong the life span of plant components.
Overall reduction in power consumption
Disadvantages
No storage in the drum hence for any load change difficult to meet requirement immediately.
Modified sliding pressure operation with active turbine valves .
Pressure Operation Mode
140
160
180
200
220
240
260
280
30 50 70 90 110
Boiler Load (%)
Pre
ssur
e(ba
r)
Constant pressure mode
Sliding pressure
Modified Sloding pressure
BOILER DESIGN
The design of boiler requires proper selection from a number of major options. The most important of these options which have significant impact on the design are:
•Waterwall system design
•Arrangement of convective surfaces
LOAD VS PRESSURE
0
50
100
150
200
250
300
0 20 40 60 80 100 120
LOAD
PRES
SUR
E
Thermal behaviour of water walls
The proportion of heat needed for evaporation and superheating changes with load. At low load the heat required for evaporation is high and superheat the steam is small. In subcritical the evaporation end point is fixed. In once through boiler, the evaporation end point is also changing within the waterwalls. So there is no division between superheater and evaporator.
Enthalpy Vs Boler Load
500
1000
1500
2000
2500
3000
3500
20 40 60 80 100
Boiler Load (% )
Enth
alpy
(Kj/K
g)
h”
h’
ECO inlet
WW Inlet
WW outlet
SH outlet
WATER WALL SYSTEMSpiral wall arrangementMany variable pressure units are running and basic idea
behind it to reduce the number of tubes required to envelope the furnace wall without increasing the spacing between the tubes.
Adv1. By spiraling around the furnace, every tube is part of all four
walls which means that not only the difference in the length of the parallel tube is minimized but also the heat pick up of individual tubes is particularly equalised.
2. At low load also sufficient cooling of the tubes can be assured.
Dis advantage1. Complicated manufacture, constructionRifled vertical tube
Start-up System Comparison
Increasing Heat RecoveredIncreasing Heat Recovered
Incr
easi
ng C
apita
l Cos
tIn
crea
sing
Cap
ital C
ost
Simplified Drain Discharge
Recirculation Pump System
Heat Exchanger System
Three types of start-up systems offered to suit
operation profile.
Three types of start-up systems offered to suit
operation profile.
Start-up System with Recirculation
Minimum Economizer
Flow Control Valve (MEFCV)
Separator
Feedwater Control
Separator HighLevel Ctl.
Block Valve
Pump
Mixing Tee
START UP SYSTEM
PARTPART--IVIV
SIPATSIPAT--I 660 MW DATAI 660 MW DATA
Start up system with one no. circulating pump is with alternate drain flow to condenser through flash tank .
Start up system
GCV range 3000 to 4000 Kcal/kg with 10-16% moisture and 32 to 48% ashFuelFlue gas temperature at air-heater outlet- 125 Deg C
52.05681740At RH Outlet
2565402225At SH Outlet
Pressure Kg/Cm2(a)
Temperature Deg C
Flow (T/Hr)Rating
Supercritical, suitable for variable pressure operation with spiral or rifled/plain water wall tubingTower type or two pass type
Type
Salient Features of the Steam Generator
Austenitic Stainless steel,T91/P-91 material up to 590 Deg C, Super 304 H, SA-213T92, SA335 P92
Above 550 Deg C
Alloy steel to ASME SA213 T-11/T-22/T91, SA335 P-11/P-22,SA-213T23, SA335 P23
Above 400 but below 550 deg C
Carbon steel to ASME SA210C, SA106 Gr C, SA302CUp to 400 Deg C
Boiler Pressure Parts Material
Major Furnace Sizing Criteria
2.0 Sec(Min)Furnace residence time1.8X105 kcal/hr/m2(Max)Furnace cooling factor600X 105 kcal/hr (Max)Heat input per burner1.36x106 kcal/hr/m2 (Max)Burner zone heat release rate106920 Kcal/hr/m3(maxHeat liberation rate4.75X106 Kcal/hr/m2 (Max)Net Heat Input/Plan Area
1.05 times the maximum operating pressure, for maximum operating pressure up to separator, additional 5% margin due to scaling to be added.
Design pressure of pressure parts
NEW MATERIAL• In addition to conventional material the following new materials are being
adopted on recent-660MW supercritical units and to take care of higher temperature of steam parameters:
Super 304HSA-213 T23 SA-335 P23SA-213 T92SA-213 P92SA 302 C
Design pressure of Pressure Parts:
1.05 times the maximum operating pressure For maximum operating pressure up to separator, additional 5% margin due to scaling to be added.
Typical Tubing for 568 / 595 °C Steam Temperatures
OR AUSTENITIC
SUPER 304
8000
21,253
26144
CL Top Nozzle
CL Bottom Nozzle
FW = 18,816
FD = 18,144
22,753
14,612
4,877
30 o
50 o
50 o
15 o
ECONOMIZER
ECONOMIZER
ECONOMIZER
ECONOMIZER
HORIZONTAL REHEATER(RH I)
HORIZONTAL REHEATER(RH I)
HORIZONTAL REHEATER(RH I)
15860
31186
PENDANT SH(SH I)
PLATEN SH(SH II)
FINAL RH(RH II)
FINAL SH(SH III)
PENDANT RH(RH I-I)
1,219
18256
SIPAT-I 660MW BOILER
Boiler auxiliaries & ESP
Vertical spindle Bowl/E-type/MPS or equivalent
Coal Mills2.
Redundancy criteria
Worst coal, BMCR- N+1Worst coal, TMCR- N+2Design coal, BMCR- N+2
Criteria50mg/NM3, worst coal with one field out of service
Electrostatic Precipitator
4.
PAPH-2X60% rotary regenerative, Bisector type
SAPH-2X60% rotary regenerative, Bisector type
Air preheaters
3.
Variable pitch axial fan, (2X60%)PA/FD/ID Fans
1.
TypeDescription
S.No.
64.16873.58• Roof to Ring header distance (m)
1690021450• Furnace Volume (m3)
302.9341.4• Plan area (m2)
15.797X19.17718816X18144• W x D (m)
FURNACE2.
540568• RH outlet temperature
540540• SHO temperature
46.149.89• RHO Pressure (kg/cm2)
179256• SHO Pressure at outlet (kg/cm2)
16252225• BMCR SHO Steam flow (T/hr)
BOILER 1.
SIPAT 500 MWSUBCRITICAL
SIPAT 660 MWSUPERCRITICAL
DescriptionSN
1900034170ECONOMIZER AREA (m2)
35324450REHEATER REAR (m2)
318014149+3159REHEATER FRONT (m2)
16157537• PLATEN SH
15882091• Div panel
16157537• FINAL SH
7100+14922153• LTSH
SUPERHEATER AREA (m2)
739110047EPRS (m2)
1010• No. of coal burner elevations
18.5222.75• Distance from center line of top burner to nose arch (m)
10.259• Ring header elevation (m)
74.583• Roof elevation (m)
COMPARISON OF MATERIAL
SA335P23, P91SA335P22RH OUTLET HEADERSA335P91SA335P22SH OUTLET HEADER
SA213T23,91, Super304H
SA213 T22,91 and TP347HFINAL RH
SA210Gr C,SA213T12,23
SA213T11,22LTRH
SA213T11,23,91,92
SA213 T22,91 and TP347HFINAL SH
SA213T11,22,91DIVISIONAL SHSA213T11,23,91
SA213T11LTSH
SA302CSA299DRUM/SEPERATOR
SA213T22SA210Gr CWATER WALL
SA210Gr CSA210Gr A1ECONOMISER
660MW500MWDescription
THANK YOUTHANK YOU