Substation L1/ Booster Substation Y-BE2 Update #3. August 15,2012. Status of Procurement. Substation L1 Transformer fully tested Delivery expected in 1-2 weeks Pictures of completed substation will be sent prior to shipment Booster Transformer Y-BE2 RFP placed early August - PowerPoint PPT Presentation

Citation preview

Page 1: Substation L1/  Booster Substation Y-BE2 Update #3

Substation L1/ Booster Substation Y-BE2

Update #3August 15,2012

Page 2: Substation L1/  Booster Substation Y-BE2 Update #3

Status of Procurement Substation L1

Transformer fully tested Delivery expected in 1-2 weeks Pictures of completed substation will be sent prior to shipment

Booster Transformer Y-BE2 RFP placed early August All proposals due by 8/31/2012

Temporary Wiring 350 MCM cable is hung and wired for temporary panel board Other temporary wiring will begin towards the end of August

Panelboard 1 assembled 1 needs to be assembled

Page 3: Substation L1/  Booster Substation Y-BE2 Update #3

Status of Procurement (Cont.) Safety Switches

Delivered Temporary installation will begin late August

Cable Supports Delivered Installation will occur late August to early September

Junction Box Built Will be shipped with substation

Page 4: Substation L1/  Booster Substation Y-BE2 Update #3

Substation Pictures

Page 5: Substation L1/  Booster Substation Y-BE2 Update #3

Substation Enclosure

Page 6: Substation L1/  Booster Substation Y-BE2 Update #3

Project Schedule September 17-28 General Cleanup 2-3 weeks prior to shutdown of substation Temporary electrical power will be completed the weekend

prior (September 15th) It could take riggers several days to remove and install

substations Small clearances Large weights

Discussions are underway to move forward with cutting a hole in LINAC’s roof Contractors will be in this week to give a cost estimate

Page 7: Substation L1/  Booster Substation Y-BE2 Update #3

Temporary Power Plan “Siphon” power from panel DHP-L2-2 Circuit #1 Cable will be run on temporary supports

4 conductor 350 mcm cable is heavy (~7 lbs./ft.) and will need an open area to lay

Some cable will be put on the floor but will be covered by a cable bridge

Setup 2 temporary panel board(s) Run cable to individual loads

DHP panels, MCC loads DHP panels will have potential

hazards removed (mains, MCC, etc.)

13.8 kV lines will be disconnected MCC loads will have configuration

control locks We will check current prior to using

any MCC loads to ensure they will not trip off during operation

Power will be provided 24 hours a day

Page 8: Substation L1/  Booster Substation Y-BE2 Update #3

Installation Costs 1 Crew of Riggers (4-6 men)

Could be as much as $30k Will remain unknown until a finalized roof plan is put in place

2 Week of Electricians $100/manhour x 2 electricians x 80 hours = $16,000

Cable 2/0 - $3,500 2 – $3,700

House Power $4,200 for panelboard

$2,000 for assembly Miscellaneous Stock purchases

$2,100

Total Cost : $31,500 -> excluding rigging and roofPrevious Estimate: $23,000 -> excluding rigging and roof

Increase can be attributed to increased electrician time and panelboard cost

Page 9: Substation L1/  Booster Substation Y-BE2 Update #3

Future Create Site Wide Monitoring NetworkIn

trane

tLINAC

Profibus

LINAC Profibus Section 1 (This Install)

LINAC Profibus Section 2 (MCC L2) $65k

BoosterProfibus

Booster Profibus West(Specifications Written)

Booster Profibus East(RFP placed)

Cross GalleryProfibus

Substation CG-1(Specification Written) $200k

PIP Project

PIP Project

HQ

PIP Project

????

Note: CG-1 has been movedfrom PIP schedule, and will now be handled by headquarters

Page 10: Substation L1/  Booster Substation Y-BE2 Update #3

Booster Y-BE2 Update Replaced bad transformer

Working well Decreased noise Less heat

New transformer RFP Estimated cost of $150k Expect bids by end of August Procurement will begin within 30 days of receiving bids

Will likely be much quicker Install

Early next year Several days