13
Contents lists available at ScienceDirect Renewable and Sustainable Energy Reviews journal homepage: www.elsevier.com/locate/rser Stochastic pre-event preparation for enhancing resilience of distribution systems Qianzhi Zhang a,, Zhaoyu Wang a , Shanshan Ma b , Anmar Arif c a Department of Electrical and Computer Engineering, Iowa State University, Ames, IA 50011, USA b School of Electrical, Computer and Energy Engineering, Arizona State University, Tempe, AZ 85287, USA c Department of Electrical Engineering, King Saud University, Riyadh 11451, Saudi Arabia ARTICLE INFO Keywords: Extreme weather events Pre-event preparation PV penetration Resilience Resource allocation Two-stage stochastic model ABSTRACT Extreme weather events are the common causes for power supply interruptions and power outages in electrical distribution systems. Improving the distribution system and enhancing its resilience is becoming crucial due to the increased frequency of extreme weather events. Preparation and allocation of multiple flexible resources, such as mobile resources, fuel resources, and labor resources before extreme weather events can mitigate the effects of extreme weather events and enhance the resilience of power distribution systems. In this paper, a two-stage stochastic mixed-integer linear programming (SMILP) is proposed to optimize the preparation and resource allocation process for upcoming extreme weather events, which leads to faster and more efficient post-event restoration. The objective of the proposed two-stage SMILP is to maximize the served load and minimize the operating cost of flexible resources. The first stage in the optimization problem selects the amounts and locations of different resources. The second stage considers the operational constraints of the distribution system and repair crew scheduling constraints. The proposed stochastic pre-event preparation model is solved by a scenario decomposition method, Progressive Hedging (PH), to ease the computational complexity introduced by a large number of scenarios. Furthermore, to show the impact of solar photovoltaic (PV) generation on system resilience, three types of PV systems are considered during a power outage and the resilience improvements with different PV penetration levels are compared. Numerical results from simulations on a large-scale (more than 10,000 nodes) distribution feeder have been used to validate the effectiveness and scalability of the proposed method. 1. Introduction 1 In recent years, the relationship between climate change, extreme 2 weather events, and power outages have become the focus of discussion 3 worldwide [1,2]. The aging infrastructure of the electric grid combined 4 with the increase in severe weather events have highlighted the harsh 5 reality of how vulnerable the distribution grid is. For example, high 6 temperatures from heatwaves will limit the amount of energy that can 7 be transferred [3], lightning strikes cause faults on the lines [4], and 8 the high winds from storms may damage overhead lines [5]. In the 9 U.S., extreme weather events have caused 50% to 60% of the power 10 interruptions [6] and $20 to $55 billion annual economic losses [7]. 11 To mitigate the impacts of extreme weather events on electric infras- 12 tructures and power grids, extensive efforts have been devoted toward 13 proposing the concept of resilience. In [8], resilience was defined as a 14 property of systems representing their response to and recovery from 15 low probability and high impact events. The measurements of system 16 Corresponding author. E-mail addresses: [email protected] (Q. Zhang), [email protected] (Z. Wang), [email protected] (S. Ma), [email protected] (A. Arif). resilience are disciplined into ecological resilience [9], psychological 17 resilience [10], risk management [11], and energy security [12]. 18 About 90% of weather-related power interruptions and outages 19 are led by failures in distribution systems [13]. Various resilience- 20 enhancing strategies have been studied in distribution systems [14], 21 such as the long-term planning, the pre-event preparation, and the 22 post-event restoration. The long-term planning provides utility compa- 23 nies the actionable resilience-enhanced methods to upgrade infrastruc- 24 tures in the long-term [15]. For example, the optimal line hardening 25 strategies against extreme weather-related hazards are developed to 26 physically improve electric infrastructure and enhance the long-term 27 resilience of the distribution system in [1619]. The post-event restora- 28 tion is used by utility companies to prioritize service restoration efforts, 29 schedule repair crews and manage network reconfiguration after the 30 extreme weather events [20]. For example, the dynamic formation of 31 microgrids (MGs) and optimal coordination between multiple MGs are 32 https://doi.org/10.1016/j.rser.2021.111636 Received 23 March 2021; Received in revised form 19 July 2021; Accepted 27 August 2021

Stochastic pre-event preparation for enhancing resilience

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Stochastic pre-event preparation for enhancing resilience

1

23456789

10111213141516

Contents lists available at ScienceDirect

Renewable and Sustainable Energy Reviews

journal homepage: www.elsevier.com/locate/rser

Stochastic pre-event preparation for enhancing resilience of distributionsystemsQianzhi Zhang a,∗, Zhaoyu Wang a, Shanshan Ma b, Anmar Arif c

a Department of Electrical and Computer Engineering, Iowa State University, Ames, IA 50011, USAb School of Electrical, Computer and Energy Engineering, Arizona State University, Tempe, AZ 85287, USAc Department of Electrical Engineering, King Saud University, Riyadh 11451, Saudi Arabia

A R T I C L E I N F O

Keywords:Extreme weather eventsPre-event preparationPV penetrationResilienceResource allocationTwo-stage stochastic model

A B S T R A C T

Extreme weather events are the common causes for power supply interruptions and power outages in electricaldistribution systems. Improving the distribution system and enhancing its resilience is becoming crucial due tothe increased frequency of extreme weather events. Preparation and allocation of multiple flexible resources,such as mobile resources, fuel resources, and labor resources before extreme weather events can mitigate theeffects of extreme weather events and enhance the resilience of power distribution systems. In this paper, atwo-stage stochastic mixed-integer linear programming (SMILP) is proposed to optimize the preparation andresource allocation process for upcoming extreme weather events, which leads to faster and more efficientpost-event restoration. The objective of the proposed two-stage SMILP is to maximize the served load andminimize the operating cost of flexible resources. The first stage in the optimization problem selects theamounts and locations of different resources. The second stage considers the operational constraints of thedistribution system and repair crew scheduling constraints. The proposed stochastic pre-event preparationmodel is solved by a scenario decomposition method, Progressive Hedging (PH), to ease the computationalcomplexity introduced by a large number of scenarios. Furthermore, to show the impact of solar photovoltaic(PV) generation on system resilience, three types of PV systems are considered during a power outage and theresilience improvements with different PV penetration levels are compared. Numerical results from simulationson a large-scale (more than 10,000 nodes) distribution feeder have been used to validate the effectiveness andscalability of the proposed method.

17181920212223242526272829303132

1. Introduction

In recent years, the relationship between climate change, extremeweather events, and power outages have become the focus of discussionworldwide [1,2]. The aging infrastructure of the electric grid combinedwith the increase in severe weather events have highlighted the harshreality of how vulnerable the distribution grid is. For example, hightemperatures from heatwaves will limit the amount of energy that canbe transferred [3], lightning strikes cause faults on the lines [4], andthe high winds from storms may damage overhead lines [5]. In theU.S., extreme weather events have caused 50% to 60% of the powerinterruptions [6] and $20 to $55 billion annual economic losses [7].To mitigate the impacts of extreme weather events on electric infras-tructures and power grids, extensive efforts have been devoted towardproposing the concept of resilience. In [8], resilience was defined as aproperty of systems representing their response to and recovery fromlow probability and high impact events. The measurements of system

∗ Corresponding author.E-mail addresses: [email protected] (Q. Zhang), [email protected] (Z. Wang), [email protected] (S. Ma), [email protected] (A. Arif).

resilience are disciplined into ecological resilience [9], psychologicalresilience [10], risk management [11], and energy security [12].

About 90% of weather-related power interruptions and outagesare led by failures in distribution systems [13]. Various resilience-enhancing strategies have been studied in distribution systems [14],such as the long-term planning, the pre-event preparation, and thepost-event restoration. The long-term planning provides utility compa-nies the actionable resilience-enhanced methods to upgrade infrastruc-tures in the long-term [15]. For example, the optimal line hardeningstrategies against extreme weather-related hazards are developed tophysically improve electric infrastructure and enhance the long-termresilience of the distribution system in [16–19]. The post-event restora-tion is used by utility companies to prioritize service restoration efforts,schedule repair crews and manage network reconfiguration after theextreme weather events [20]. For example, the dynamic formation ofmicrogrids (MGs) and optimal coordination between multiple MGs are

https://doi.org/10.1016/j.rser.2021.111636Received 23 March 2021; Received in revised form 19 July 2021; Accepted 27 Aug

ust 2021
Page 2: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

1

2

3456789

Notations

List of abbreviations

CI Confidence intervalDERs Distributed energy resourcesDGs Distributed generatorsEF Extensive formESS Energy storage systemMEGs Mobile emergency generatorsMESs Mobile storage devicesMRP Multiple replication procedurePH Progressive hedgingPV Photovoltaic generationSOC State of chargeSMILP Stochastic mixed-integer linear program-

ming

Indexes

𝑐 Index of conductor between poles𝑖, 𝑗 Index of bus𝑖𝑗 Index of line between bus 𝑖 and bus 𝑗𝑘 Index of conductor or line𝑙 Index of network loop𝑝 Index of pole𝑠 Index of scenario𝑡 Index of time instant

Sets

𝛺B Set of line switches𝛺CN Set of candidate buses for MEGs and MESs𝛺DL Set of damaged lines𝛺EG Set of buses that have fuel-based emergency

generators𝛺ES Set of buses with ESSs𝛺ESC Set of buses with all types of storage units𝛺G Set of generators𝛺K Set of lines𝛺loop Set of network loops𝛺N Set of buses𝛺R Set of network regions𝛺PV Set of PV systems𝛺G

PV Set of grid-following PV systems𝛺H

PV Set of hybrid on-grid/off-grid PV systems𝛺C

PV Set of grid-forming PV systems

Parameters

𝑎, 𝑏𝑠 Coefficients associated with the compactfirst stage variable 𝑥 and compact secondstage variable 𝑦𝑠

𝐶F Unit cost of fuel consumption of generators(L∕kWh)

𝐶SW Unit cost of line switches ($)𝐶D𝑖 Unit cost of load shedding ($/kWh)

𝑑p𝑖,𝜙,𝑡 Active power demand of bus 𝑖, phase 𝜙 andtime 𝑡

𝐸Cap𝑖 Maximum capacity of ESSs of bus 𝑖

considered to restore the critical loads and services during power out-

ages in [21–23]. In this paper, we focus on the pre-event preparation,

𝐸SOC,max𝑖 , 𝐸SOC,min

𝑖 Maximum and minimum permissible rangeof SOC of bus 𝑖

𝑃Ch,max𝑖 , 𝑃Dis,max

𝑖 Maximum charging and discharging powersof ESS of bus 𝑖

𝑃K,max𝑘 , 𝑄K,max

𝑘 Active and reactive power flow limits𝑃G,max𝑖 , 𝑄G,max

𝑖 Active/reactive power output limits of gen-erator

𝑃 PV𝑖,𝜙,𝑡,𝑠 Active power output of PV systems of bus 𝑖,

phase 𝜙, time 𝑡 and scenario 𝑠𝑃 rate𝑖 Rate capacity of PV systems of bus 𝑖

𝑃 𝑟𝑓𝑙,𝑖𝑗 (𝑤(𝑡)) Failure probability of the overhead line 𝑖𝑗with wind speed 𝑤 at time 𝑡

𝑃 𝑟𝑓𝑝,𝑖𝑗,𝑝(𝑤(𝑡)) Failure probability of the pole 𝑝 at line 𝑖𝑗with wind speed 𝑤 at time 𝑡

𝑃 𝑟𝑓𝑐,𝑐 (𝑤(𝑡)) Failure probability of conductor 𝑐 betweentwo poles with wind speed 𝑤 at time 𝑡

𝑃 𝑟𝑓𝑤,𝑐 (𝑤(𝑡)) Direct wind-induced failure probability ofconductor 𝑐 with wind speed 𝑤 at time 𝑡

𝑃 𝑟𝑓𝑡𝑟,𝑐 (𝑤(𝑡)) Fallen tree-induced failure probability ofconductor 𝑐 with wind speed 𝑤 at time 𝑡

𝑃 𝑟𝑢,𝑐 Probability that conductor 𝑐 is underground𝑃𝑟(𝑠) Probability of occurrence for scenario 𝑠𝑝𝑖𝑗,𝜙 Phases 𝜙 of line between bus 𝑖 and bus 𝑗𝑄ESS,max

𝑖 Maximum limit of reactive power output ofESS

𝑤(𝑡) Wind speed at time 𝑡𝑚𝑅 Median capacity of conductor𝑁MEG Number of available MEGs𝑁MES Number of available MESs𝑁MU

𝑖 Number of mobile units𝑁Fuel

𝑖 Amount of available fuel𝑁Crew Total number of crews.𝑁Crew,max

𝑟 , 𝑁Crew,min𝑟 Maximum and minimum number of avail-

able repair crews of region 𝑟𝑁𝑐𝑜𝑛𝑑𝑢𝑐𝑡𝑜𝑟 Number of conductor wires between two

adjacent poles𝑁𝑝𝑜𝑙𝑒 Number of distribution poles supporting

line�̂�𝑖𝑗 , �̂�𝑖𝑗 Unbalanced three-phase resistance matrix

and reactance matrix of line 𝑖𝑗𝑟F Rate between fuel consumption and power

output of generators (L/kWh)𝑆PV𝑖 PV capacity of bus 𝑖

𝐼𝑟 Solar irradiance𝑈min𝑖 , 𝑈max

𝑖 Maximum and minimum limits of squaredvoltage of bus 𝑖

𝛼 Average tree-induced damage probability ofoverhead conductor

𝜉𝑅 Logarithmic standard deviation of intensitymeasurement

𝜂Ch, 𝜂Dis ESS charging and discharging efficiencies

which helps utility companies to prepare resources in advance and mit-igate the upcoming extreme weather events. The pre-event preparationcan not only avoid high investment cost in long-term planning, but alsoefficiently reduce the outage duration in post-even restoration.

There are existing studies that have investigated pre-event prepara-tion and resource allocation problems for the resilience enhancementof electric distribution systems. In [24–26], pre-event resource manage-

ment in MGs and pre-event operation strategies in distribution systems 10
Page 3: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

123456789

101112131415161718

e 19a 20T 21a 22e 23r 24p 25

26t 27s 28r 29c 30s 31s 323 33t 34i 35

36p 37c 38n 39s 40t 41m 42s 43

44l 45p 46F 47f 48P 49p 50l 51t 52p 53H 54t 55m 56t 57

5859606162636465666768697071

𝜏 Iteration number of PH𝜌 Penalty factor of PH𝜖 Termination threshold of PH

Continuous Variables

𝐸SOC𝑖,𝑡,𝑠 SOC of ESS of bus 𝑖, time 𝑡 and scenario 𝑠

𝐹𝑖,𝑠 Total fuel consumption of generators𝑃K𝑖𝑗,𝜙,𝑡,𝑠, 𝑄

K𝑖𝑗,𝜙,𝑡,𝑠 Active/reactive power flows of line 𝑖𝑗,

phase 𝜙, time 𝑡 and scenario 𝑠𝑃G𝑖,𝜙,𝑡,𝑠, 𝑄

G𝑖,𝜙,𝑡,𝑠 Active/reactive power outputs of fuel-based

generator of bus 𝑖, phase 𝜙, time 𝑡 andscenario 𝑠

𝑃Ch𝑖,𝜙,𝑡,𝑠, 𝑃

Dis𝑖,𝜙,𝑡,𝑠 Active charging/discharging power output

of ESS of bus 𝑖, phase 𝜙, time 𝑡 of scenario𝑠

𝑄ESS𝑖,𝜙,𝑡,𝑠 Reactive power output of ESS of bus 𝑖, phase

𝜙, time 𝑡 and scenario 𝑠𝑄PV

𝑖,𝜙,𝑡,𝑠 Reactive power output of PV of bus 𝑖, phase𝜙, time 𝑡 and scenario 𝑠

𝑛Fuel𝑖 Amount of fuel allocated to the generator ofbus 𝑖

𝑛Crew𝑟 Number of repair crews of region 𝑟𝑈𝑖,𝜙,𝑡,𝑠 Square of voltage magnitude of bus 𝑖, phase

𝜙, time 𝑡 and scenario 𝑠𝑣S Virtual source𝑣f𝑘 Virtual flow of line 𝑘𝑥, 𝑦𝑠 Compact first stage and second stage vari-

ables�̄� Expected value of first stage variable

Discrete Variables

ℎ𝑖,𝑡,𝑠 Binary variable indicating if ESS is charg-ing/discharging (1) or not (0) of bus 𝑖,phase 𝜙, time 𝑡 and scenario 𝑠

𝑛MEG𝑖 , 𝑛MES

𝑖 Binary variable indicating if an MEG or MESis allocated (1) or not allocated (0) to bus 𝑖

𝑢𝑘,𝑡,𝑠 Binary variable indicating if line 𝑘 is ener-gized (1) or not (0) of time 𝑡 and scenario𝑠

𝑦𝑖,𝑡,𝑠 Binary variable indicating if load is restored(1) or not (0) of bus 𝑖, phase 𝜙, time 𝑡 andscenario 𝑠

𝑧𝑘,𝑡,𝑠 Binary variable indicating if line 𝑘 is beingrepaired (1) or not (0) of time 𝑡 and scenario𝑠

𝛾𝑖𝑗,𝑡,𝑠 Binary variable indicating if switch is closed(1) or not (2) of line 𝑖𝑗, phase 𝜙, time 𝑡 andscenario 𝑠

𝜒𝑖,𝑡,𝑠 Binary variable indicating if bus 𝑖 is ener-gized (1) or not (0) of time 𝑡 and scenario𝑠

are considered to enhance system resilience during extreme events.In [27], the position and number of depots are determined, and theavailable resources are managed at the pre-event stage. In [20], repaircrews are pre-allocated to depots and integrated with the restora-tion process for enhancing the response after a disaster. A two-stagestochastic model is developed in [28] to determine staging locationsand allocate repair crews for disaster preparation while consideringdistribution system operation and crew routing constraints. In [29],

the authors developed a stochastic model for optimizing pre-event

operation actions. The study optimized the topology of the network andthe position of crews for upcoming disturbances. In [30] and [31], atwo-stage framework is developed to position mobile emergency gener-ators (MEGs) for pre- and post-disasters. Mobile energy storage devices(MESs) are investigated in [32] and [33] for the resilience enhancementof power distribution systems. However, there are limitations in theabove studies on pre-event preparation and resource allocation. Theselimitations are described in the following:

(1) Pre-event allocation of various flexible resources: In practice, pre-vent preparation includes allocating various flexible resources, suchs MEGs, MESs, fuel resources for diesel generators, and repair crews.he optimal allocation of those flexible resources can help utilities tochieve faster and more efficient post-event power restoration. How-ver, previous studies mainly focused on allocating specific flexibleesources, rather than formulating a complete optimization problem tore-allocate various flexible resources together.

(2) Impacts of solar PV power on system resilience: Due to intermit-ent characteristic of traditional distributed energy resources (DERs),uch as solar power, PV systems are not considered as a reliableesilient solution [34]. However, the distributed nature of PV poweran contribute to a more resilient power system [35]. In practice, PVystems can be coupled with energy storage technologies to enable grid-upporting capability [36], continuous operation during outages [37,8], and economic operation [39,40]. Different types of PV systems andhe impacts of different PV penetration levels on system resilience aregnored in most existing research works.

(3) Scalability of the solution algorithm: On one side, the stochasticre-event preparation model may suffer from computational ineffi-iency due to a large number of scenarios; on the other side, a limitedumber of scenarios may influence the stability and quality of theolutions. Therefore, the trade-off between computation time and solu-ion accuracy needs to be studied for stochastic pre-event preparationethods. In addition, a large-scale system is needed to verify the

calability of solution algorithms.To address these challenges, a two-stage stochastic mixed-integer

inear program (SMILP) is proposed for pre-event preparation with there-allocation of mobile resources, fuel resources and labor resources.urthermore, the proposed pre-event preparation model considers dif-erent types of PV systems and facilitates the benefits of leveraging highV penetration for improving the resilience of distribution grids. In thisaper, resilience improvement is quantified by the increased servedoad and reduced outage duration. To deal with the massive compu-ation burden, the proposed two-stage stochastic pre-event preparationroblem is solved by a scenario decomposition method, Progressiveedging (PH) [41], while maintaining the accuracy and stability of

he solution [42]. Also, the quality of the solution is validated by theultiple replication procedure (MRP) [43]. The main contribution of

his paper is three-folded:

• A two-stage SMILP model is proposed for pre-event preparationfor upcoming extreme weather events, where the first stage allo-cates MEGs, MESs, fuel, and repair crews. The second stage con-siders distribution system operation and repair crew schedulingconstraints.

• The proposed pre-event preparation model considers three typesof PV systems during a power outage, including grid-followingPV system, hybrid on-grid/off-grid PV system and grid-formingPV system. The improvements of resilience and the reductionof outage duration with different PV penetration levels are alsopresented.

• The proposed solution algorithm is tested through a solutionvalidation method to show its quality. In addition, a large-scalesystem, consisting of more than 10,000 nodes, is used to verifythe scalability of the proposed pre-event preparation model.

72
Page 4: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

12345

6

789

101112131415161718192021

22

232425262728

29

30

𝑃31

3233343536373839404142434445464748495051

52

53545556575859606162

63

646566

676869707172737475

76

77

78

79

80

81828384858687

8889909192

93

94

95

96979899

100101

The remainder of the paper is organized as follows: Section 2describes the proposed two-stage SMILP for pre-event preparation andresource allocation. Section 3 presents the PH solution algorithm, con-vergence analysis and solution validation. Case study and results dis-cussion are given in Section 4. Conclusions are provided in Section 5.

2. Two-stage stochastic pre-event preparation model

The general framework of the proposed two-stage stochastic pre-event preparation model is shown in Fig. 1. Damage scenarios ofextreme weather events are generated based on the following infor-mation: (1) identification of extreme weather events, such as flood,hurricane and winter storm; (2) extreme weather event data and metric;(3) fragility model of test systems, which describes the behavior ofcomponents under extreme weather events; (4) damage status of com-ponents in test systems subject to specific extreme weather events. Toapproximate the impact of extreme weather events to grid infrastruc-tures, damage scenarios can be generated by mapping the weather dataset to the failure probability of grid infrastructures. The Monte Carlosampling technique can be used to generate a manageable numberof scenarios. Adopted from [44], for wind speed 𝑤(𝑡), the relatedfailure probability 𝑃𝑟𝑓𝑙,𝑖𝑗 (𝑤(𝑡)) of overhead line 𝑖𝑗 can be formulatedas follows:

𝑃𝑟𝑓𝑙,𝑖𝑗 (𝑤(𝑡)) = 1 −𝑁𝑝𝑜𝑙𝑒∏

𝑝=1

(

1 − 𝑃𝑟𝑓𝑝,𝑖𝑗,𝑝(𝑤(𝑡)))

𝑁𝑐𝑜𝑛𝑑𝑢𝑐𝑡𝑜𝑟∏

𝑐=1

(

1 − 𝑃𝑟𝑓𝑐,𝑐 (𝑤(𝑡)))

(1)

where 𝑃𝑟𝑓𝑝,𝑖𝑗,𝑝(𝑤(𝑡)) and 𝑃𝑟𝑓𝑐,𝑐 (𝑤(𝑡)) are the failure probability of pole𝑝 at line 𝑖𝑗 and the failure probability of conductor 𝑐 between twopoles, respectively. 𝑁𝑝𝑜𝑙𝑒 represents the number of distribution polessupporting line 𝑖𝑗 and 𝑁𝑐𝑜𝑛𝑑𝑢𝑐𝑡𝑜𝑟 represents the number of conductorwires between two adjacent poles at line 𝑖𝑗, respectively. In Eqs. (2)and (3), 𝑃𝑟𝑓𝑝,𝑖𝑗,𝑝(𝑤(𝑡)) and 𝑃𝑟𝑓𝑐,𝑐 (𝑤(𝑡)) can be expressed as follows:

𝑃𝑟𝑓𝑝,𝑖𝑗,𝑝(𝑤(𝑡)) = 𝛷[

ln(𝑤(𝑡)∕𝑚𝑅

𝜉𝑅)]

(2)

𝑟𝑓𝑐,𝑐 (𝑤(𝑡)) = (1 − 𝑃𝑟𝑢,𝑐 ) max(

𝑃𝑟𝑓𝑤,𝑐 (𝑤(𝑡)), 𝛼𝑃 𝑟𝑓𝑡𝑟,𝑐 (𝑤(𝑡)))

(3)

where 𝛷 is the operator of the log-normal cumulative distributionfunction (CDF). 𝑚𝑅 and 𝜉𝑅 are the median capacity and the logarithmicstandard deviation of intensity measurement, respectively; 𝑃𝑟𝑓𝑤,𝑐 (𝑤(𝑡))represents the direct wind-induced failure probability of conductor 𝑐and 𝑃𝑟𝑓𝑡𝑟,𝑐 (𝑤(𝑡)) represents the fallen tree-induced failure probability ofconductor 𝑐. 𝑃𝑟𝑢,𝑐 is the probability that conductor 𝑐 is underground,which is more invulnerable to extreme weather events. 𝛼 representsthe mean probability of tree-induced damage for overhead conductors.More details of weather forecasting methodologies, line fragility modelsand scenario generation can be found in [45].

As shown in Fig. 1, the proposed SMILP pre-event preparationmodel has two stages: (i) Flexible resources are pre-allocated for up-coming extreme weather events in the first stage, including the optimaldecisions of pre-position and number of MEGs, MESs and repair crewsto depots, and allocation of available fuel to generators. (ii) The sec-ond stage determines the optimal hourly operation of the distributionsystems and assigns repair crews to the damaged components afterthe extreme weather events. Constraints in the second stage includeunbalanced optimal power flow constraints, network reconfigurationand isolation constraints, and repair crew scheduling constraints.

2.1. Objective function

The objective function (4) is set to minimize operating cost andmaximize the served loads. There are three unit cost coefficients inthe objective, unit cost of fuel consumption 𝐶F (L∕kWh), unit cost of

switching operation 𝐶SW ($), and unit cost of load shedding 𝐶D𝑖 at bus

𝑖 ($/kWh). The objective is formulated as follows:

min∑

∀𝑠𝑃𝑟(𝑠)

(

𝐶F𝑟F∑

∀𝑡

∀𝜙

∀𝑖𝑃G𝑖,𝜙,𝑡,𝑠 + 𝐶SW

∀𝑡

∀𝑘∈𝛺SW

𝛾𝑖𝑗,𝑡,𝑠

+∑

∀𝑡

∀𝜙

∀𝑖𝐶D𝑖 (1 − 𝑦𝑖,𝑡,𝑠)𝑑

p𝑖,𝜙,𝑡

)

(4)

where 𝑃𝑟(𝑠) is the probability of occurrence for scenario 𝑠. Based onthe total number of scenarios 𝑁𝑠, 𝑃𝑟(𝑠) can be calculated as 1∕|𝑁𝑠|. 𝑟Fis the rate between fuel consumption and energy output of generators.The unit of 𝑟F is 𝐿∕𝑘𝑊 ℎ, which represents the fuel consumption in 𝐿per energy generation in 𝑘𝑊 ℎ. 𝑃G

𝑖,𝜙,𝑡,𝑠 is the active power output forfuel-based generator at bus 𝑖, phase 𝜙, time 𝑡, and scenario 𝑠. Binaryvariable 𝛾𝑖𝑗,𝑡,𝑠 represents the status of each switch, if a switch on line 𝑖𝑗is operated at time 𝑡, and scenario 𝑠, then 𝛾𝑖𝑗,𝑡,𝑠 = 1. The binary variable𝑦𝑖,𝑡,𝑠 represents the status of load at bus 𝑖, time 𝑡, and scenario 𝑠. If thedemand 𝑑p𝑖,𝜙,𝑡 is served, then 𝑦𝑖,𝑡,𝑠 = 1.

2.2. First stage constraints

The first stage constraints revolve around pre-allocating four impor-tant resources that will be utilized after an extreme event: (i) MEGs, (ii)MESs, (iii) fuel and (iv) repair crews.

2.2.1. Mobile resources allocation constraintsMobile resources can be used to restore energy for isolated areas

that are not damaged, and to restore critical loads. In addition, fuelmanagement is important after an extreme event to operate emergencygenerators. Distributing fuel after an extreme event may be difficultdue to road conditions. As for repair crews, pre-assigning them todifferent locations provides a faster and more organized response. Theconstraints for allocating the mobile resources are modeled as follows:

∀𝑖∈𝛺CN

𝑛MEG𝑖 = 𝑁MEG (5)

∀𝑖∈𝛺CN

𝑛MES𝑖 = 𝑁MES (6)

𝑛MEG𝑖 + 𝑛MES

𝑖 ≤ 𝑁MU𝑖 ,∀𝑖 ∈ 𝛺CN (7)

where binary variables 𝑛MEG𝑖 and 𝑛MES

𝑖 equal 1 if a MEG or MES areallocated to bus 𝑖, respectively. The set 𝛺CN represents the set ofcandidate buses for MEGs and MESs. Constraints (5) and (6) indicatesthat the number of installed MEGs and MESs are equal to the numberof available devices (𝑁MEG and 𝑁MES). In this work, it assumes thateach bus can only have a limited number of mobile units 𝑁MU

𝑖 , whichis enforced by (7).

2.2.2. Fuel resources allocation constraintsDefine the set 𝛺G = 𝛺EG ∪ 𝛺CN, where 𝛺EG is the set of buses

that have fuel-based emergency generators. The fuel allocated to 𝛺Gmust be limited to the available amount of fuel. The fuel allocationconstraints are presented as follows:∑

∀𝑖∈𝛺𝐺

𝑛Fuel𝑖 ≤ 𝑁Fuel (8)

𝐹G𝑖 ≤ 𝑛Fuel𝑖 ≤ 𝐹max

𝑖 ,∀𝑖 ∈ 𝛺G (9)

Constraint (8) limits the total amount of allocated fuel to the avail-able amount of fuel (𝑁Fuel), where 𝑛Fuel𝑖 is the amount of fuel allocatedto the generator at bus 𝑖. In this work, it assumes that not all theavailable fuel needs to be allocated. Constraint (9) limits the amountof fuel on each site, where 𝐹G

𝑖 is the amount of fuel already present forthe generator at bus 𝑖, and 𝐹max represents the maximum capacity of

𝑖
Page 5: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

12345

6789

101112131415161718192021

22

23

24

252627282930313233

34

3536

Fig. 1. The proposed two-stage stochastic pre-event preparation model.

3738

3940

r 41o 42

43444546474849505152535455565758

59

60

61

62

63

64

65

66c 67o 68w 69

fuel at bus 𝑖. Note that the aim of fuel allocation is to decide how muchfuel should be allocated to the generators, which have defined locationsin the system. Therefore, the logistic process of transferring the fuel tothe generators is not considered in this paper, as this problem can besolved as a separate problem.

2.2.3. Repair crew allocation constraintsTo allocate the repair crews, our model divides the network into

different regions 𝛺R. Each region will be assigned with different crews,who will conduct the repairs in that region. Note that the buses in asingle region should be relatively close to each other. These regionsshould be determined based on the physical distances between thebuses. Then the crews are allocated to the regions, where the crewswould be stationed at a depot. Therefore, the distance is not explicitlyconsidered in the mathematical model, but it is considered in thepreprocessing step of determining the regions.

Constraint (10) states that the total crews deployed to all regionsis equal to the number of available crews. This constraint can berelaxed by replacing the equality with an inequality if some crews arerequired on standby. This work assumes that all available crews willbe deployed. Constraint (11) sets a minimum and maximum number ofcrews that can be stationed in each individual region.∑

∀𝑟∈𝛺R

𝑛Crew𝑟 = 𝑁Crew (10)

𝑁Crew,min𝑟 ≤ 𝑛Crew𝑟 ≤ 𝑁Crew,max

𝑟 ,∀𝑟 ∈ 𝛺R (11)

where 𝑛Crew𝑟 is the number of repair crews in region 𝑟 and 𝑁Crew isthe total number of crews. The number of repair crews is limited ineach region, using 𝑁Crew,min

𝑟 and 𝑁Crew,max𝑟 , depending on the size and

capacity of the staging locations.After allocating the fuel in the first stage, each generator can be

operated in the second stage based on how much fuel is available.Similarly, once the pre-position decisions of mobile resources andrepair crews are obtained in the first stage, the second stage can decidethe mobile resource operation and repair schedule.

2.3. Second stage constraints

In the second stage of the proposed pre-event preparation model,the constraints of PV systems and repair crew dispatch are mainly

(

discussed. The model also considers unbalanced power flow constraints,voltage constraints, and network reconfiguration constraints [43,46].

2.3.1. PV system constraintsTo thoroughly investigate the impact of PV systems on system

esilience, three types of PV systems are considered with differentperation modes in the second stage [43], 𝛺PV = 𝛺G

PV ∪ 𝛺HPV ∪ 𝛺C

PV.The main differences between those three types of PV systems are theirdifferent behaviors during an outage: (i) Type 1: on-grid PV with grid-following operation mode (𝛺G

PV), where the PV will be switched off anddisconnected during an outage. (ii) Type 2: hybrid on-grid/off-grid PV+ energy storage system (ESS) (𝛺H

PV), where the PV system operateson-grid in normal condition or off-grid during an outage (serves localload only). (iii) Type 3: grid-forming PV + ESS with grid-formingcapability (𝛺C

PV), this system can restore part of the network thatis not damaged if the fault is isolated. There are several benefits ofconsidering different types of PV systems during a power outage. Forexample, this kind of model is more like a real-world application withmultiple PV systems. In addition, the PV systems are mostly consideredas power supply resources in previous research works, while the grid-forming and black-start capability of PV systems during outages shallalso be explored and discussed. The output power of the PV systems isdetermined using the following equations:

0 ≤ 𝑃 PV𝑖,𝜙,𝑡,𝑠 ≤

𝐼𝑟𝑖,𝑡,𝑠1000 W∕m2

𝑃 rate𝑖 ,∀𝑖 ∈ 𝛺PV∕𝛺G

PV, 𝜙, 𝑡, 𝑠 (12)

0 ≤ 𝑃 PV𝑖,𝜙,𝑡,𝑠 ≤ 𝜒𝑖,𝑡,𝑠

𝐼𝑟𝑖,𝑡,𝑠1000 W∕m2

𝑃 rate𝑖 ,∀𝑖 ∈ 𝛺G

PV, 𝜙, 𝑡, 𝑠 (13)

(𝑃 PV𝑖,𝜙,𝑡,𝑠)

2 + (𝑄PV𝑖,𝜙,𝑡,𝑠)

2 ≤ (𝑆PV𝑖 )2,∀𝑖 ∈ 𝛺PV∕𝛺G

PV, 𝜙, 𝑡, 𝑠 (14)

(𝑃 PV𝑖,𝜙,𝑡,𝑠)

2 + (𝑄PV𝑖,𝜙,𝑡,𝑠)

2 ≤ 𝜒𝑖,𝑡,𝑠(𝑆PV𝑖 )2,∀𝑖 ∈ 𝛺G

PV, 𝜙, 𝑡, 𝑠 (15)

The PV active power output 𝑃 PV𝑖,𝜙,𝑡,𝑠 depends on the solar cell rating

apacity 𝑃 rate and the solar irradiance 𝐼𝑟𝑖,𝑡,𝑠 [47]. The active powerutputs of Type 2 𝛺H

PV and Type 3 𝛺CPV PVs can be determined in (12),

hile the active power outputs of Type 1 𝛺GPV PVs is calculated in

13). The binary variable 𝜒 = 0 if bus 𝑖 is not energized at time

𝑖,𝑡,𝑠 70
Page 6: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

123456789

10111213141516171819202122232425

26

27

28

29

30

31

32

33

34

3536373839404142434445464748495051

5253545556575859

6061

62

63

64

65

66

676869

d 707172

p 73t 74t 75

2 76

bcu

77

78

79

80

81

0 82

83

0 84

85

0 86

87

88

89

90

91

92

93

𝑡 and scenario 𝑠. Using advanced PV smart inverters [48], the PVscan provide reactive power support 𝑄PV

𝑖,𝜙,𝑡,𝑠, which is constrained bythe capacity 𝑆PV

𝑖 in (14) and (15). During an outage, on-grid PVs aredisconnected and the on-site load is not served by the PVs, therefore,constraints (13) and (15) are multiplied by 𝜒𝑖,𝑡,𝑠. PV systems of types𝛺C

PV and 𝛺HPV can disconnect from the grid and serve the on-site load.

An example network with a damaged line is given in Fig. 2, wherethe network is divided into three islands due to the damaged line. Thegrid-forming sources in 𝛺C

PV ∪𝛺G has the black start capability and canrestore the network. While PV system in types 𝛺G

PV or 𝛺HPV can connect

to the grid only after the PV bus is energized. Island A has a grid-forming generator, therefore, a microgrid is created and the PV systemcan participate. Island B must be isolated because of the damaged line.Island C does not have any grid-forming generators; hence, it will notbe active and the grid-tied PV will be disconnected.

To determine the connection status of the PV systems, a virtual net-work is designed in parallel to the distribution network. The examplenetwork shown in Fig. 2 is transformed into a virtual network shown inFig. 3. To identify if an island network can be energized and restoredby grid-forming sources 𝛺C

PV∪𝛺G, a virtual network is built with virtualsources, virtual flows, and virtual loads. Each grid-forming generator isreplaced by a virtual source with infinite capacity. Other power sourceswithout grid-forming capability (e.g., grid-tied PVs) are removed. Thevirtual loads with magnitude of 1 replace the actual loads. The virtualnetwork scheme is modeled using constraints (16)–(20).

∀𝑗∈𝛺CPV∪𝛺G

𝑣S𝑗,𝑡,𝑠 +∑

∀𝑘∈𝛺K (.,𝑖)𝑣f𝑘,𝑡,𝑠 = 𝜒𝑖,𝑡,𝑠 +

∀𝑘∈𝛺K (𝑖,.)𝑣f𝑘,𝑡,𝑠,∀𝑖, 𝑡, 𝑠 (16)

− (𝑢𝑘,𝑡,𝑠)𝑀 ≤ 𝑣f𝑘,𝑡,𝑠 ≤ (𝑢𝑘,𝑡,𝑠)𝑀,∀𝑘 ∈ 𝛺K , 𝑡, 𝑠 (17)

0 ≤ 𝑣S𝑘,𝑡,𝑠 ≤ (𝑛MEG𝑖 + 𝑛MES

𝑖 )𝑀,∀𝑖 ∈ 𝛺CN, 𝑡, 𝑠 (18)

𝜒𝑖,𝑡,𝑠 ≥ 𝑦𝑖,𝑡,𝑠,∀𝑖 ∈ 𝛺N∕{𝛺CPV ∪𝛺H

PV ∪𝛺G}, 𝑡, 𝑠 (19)

𝜒𝑖,𝑡,𝑠 + 𝑛MEG𝑖 + 𝑛MES

𝑖 ≥ 𝑦𝑖,𝑡,𝑠,∀𝑖 ∈ 𝛺CN, 𝑡, 𝑠 (20)

A power balance equation is added for each virtual bus, whichmeans that if the virtual load at a bus is served, then that bus is ener-gized. Therefore, for islands without grid-forming generators, all buseswill be de-energized as the virtual loads in the island cannot be served.Constraint (16) is the node balance constraint for the virtual network.Virtual source 𝑣S is connected to buses with power sources that have thecapability to restore the system. The variable 𝑣f𝑘 represents the virtualflow on line 𝑘 and each bus is given a load of 1 that is multiplied by 𝜒𝑖.Therefore, 𝜒𝑖 = 1 (bus 𝑖 is energized) if the virtual load can be servedby a virtual source and 0 (bus 𝑖 is de-energized) otherwise. The virtualflow is limited by (17). The limits are multiplied by the status of theline (𝑢𝑘,𝑡,𝑠) so that the virtual flow is 0 if a line is disconnected. Thevirtual source can be used only if a generator is installed, as enforcedby (18). Define 𝛺N as the set of all buses. If bus 𝑖 is de-energized,then the load must be shed (19), unless bus 𝑖 has a local power sourcewith disconnect switch. Constraint (20) is similar to (19) but with thepresence of mobile sources.

2.3.2. Repair crews constraintsThe second stage of the proposed pre-event model assigns repair

crews to damaged components that are in the area at where the crewsare positioned. Note that the travel time is neglected in this study, asthe travel distances between components in the same area is assumedto be small. An example for crew assignment is given in Fig. 4, wheretwo working areas are assigned for the crews. In this example, fourdamaged lines in Area 1 will be repaired by crews 1–3, while crews 4

and 5 are responsible for the two damaged lines in Area 2. The repaircrews constraints can be presented as follows:

∀𝑘∈𝛺DL(s)

𝑧𝑘,𝑡,𝑠 ≤ 𝑛Crew𝑟 ,∀𝑟, 𝑡, 𝑠 (21)

∀𝑡𝑧𝑘,𝑡,𝑠 ≤ 𝑇 𝑟

𝑘,𝑠,∀𝑘 ∈ 𝛺DL(s), 𝑠 (22)

1𝑇 𝑟𝑘,𝑠

𝑡−1∑

𝜏=1𝑧𝑘,𝜏,𝑠 − 1 + 𝜖 ≤ 𝑢𝑘,𝑡,𝑠 ≤

1𝑇 𝑟𝑘,𝑠

𝑡−1∑

𝜏=1𝑧𝑘,𝜏,𝑠,∀𝑘 ∈ 𝛺DL(s), 𝑡, 𝑠 (23)

where 𝑧𝑘,𝑡,𝑠 is a binary variable, 𝑧𝑘,𝑡,𝑠 = 1 means that line 𝑘 is beingrepaired at time 𝑡 on scenario 𝑠, and 𝛺DL(s) is the set of damaged lineson scenario 𝑠. Constraint (21) limits the number of repairs being con-ucted in each area according to the number of crews 𝑛Crew𝑟 available.

Constraint (22) defines the repair time for each damaged line. The linestatus 𝑢𝑘,𝑡,𝑠 equals 0 until the repair process is conducted for 𝑇 𝑟

𝑘,𝑠 timeeriods. Based on constraint (23), let 𝑇 𝑟

𝑘,𝑠 = 3, 𝑧𝑘,𝑡,𝑠 = {0, 0, 1, 1, 1, 0, 0},hen 𝑢𝑘,𝑡,𝑠 = {0, 0, 0, 0, 0, 1, 1}. For example, when 𝑡 = 6 and 𝜖 = 0.001,hen constraint (23) becomes 0.668 ≤ 𝑢𝑘,6,𝑠 ≤ 1, therefore, 𝑢𝑘,6,𝑠 = 1.

.3.3. Network operational constraintsThe next set of constraints are related to the operation of distri-

ution systems, including unbalanced power flow equations, radialityonstraints, fuel consumption, and energy storage constraints. Thenbalanced distribution system constraints are given below:∑

𝑏∈𝛺K (𝑖,.)𝑃K𝑏,𝜙,𝑡,𝑠 −

𝑘∈𝛺K (.,𝑖)𝑃K𝑘,𝜙,𝑡,𝑠 = 𝑃G

𝑖,𝜙,𝑡,𝑠 + 𝑃 PV𝑖,𝜙,𝑡,𝑠

+ (𝑃Ch𝑖,𝜙,𝑡,𝑠 − 𝑃Dis

𝑖,𝜙,𝑡,𝑠) − 𝑦𝑖,𝑡,𝑠𝑑𝑃𝑖,𝜙,𝑡,∀𝑖, 𝜙, 𝑡, 𝑠 (24)

𝑏∈𝛺K (𝑖,.)𝑄K

𝑏,𝜙,𝑡,𝑠 −∑

𝑘∈𝛺K (.,𝑖)𝑄K

𝑘,𝜙,𝑡,𝑠 = 𝑄G𝑖,𝜙,𝑡,𝑠 +𝑄PV

𝑖,𝜙,𝑡,𝑠

+ 𝑄ESS𝑖,𝜙,𝑡,𝑠 − 𝑦𝑖,𝑡,𝑠𝑑

𝑄𝑖,𝜙,𝑡,∀𝑖, 𝜙, 𝑡, 𝑠 (25)

− 𝑢𝑘,𝑡,𝑠𝑃K,max𝑘 ≤ 𝑃K

𝑘,𝜙,𝑡,𝑠 ≤ 𝑢𝑘,𝑡,𝑠𝑃K,max𝑘 ,∀𝑘 ∈ 𝛺K , 𝜙, 𝑡, 𝑠 (26)

− 𝑢𝑘,𝑡,𝑠𝑄K,max𝑘 ≤ 𝑄K

𝑘,𝜙,𝑡,𝑠 ≤ 𝑢𝑘,𝑡,𝑠𝑄K,max𝑘 ,∀𝑘 ∈ 𝛺K , 𝜙, 𝑡, 𝑠 (27)

≤ 𝑃G𝑖,𝜙,𝑡,𝑠 ≤ 𝑃G,max

𝑖 ,∀𝑖 ∈ 𝛺EG, 𝜙, 𝑡, 𝑠 (28)

≤ 𝑄G𝑖,𝜙,𝑡,𝑠 ≤ 𝑄G,max

𝑖 ,∀𝑖 ∈ 𝛺EG, 𝜙, 𝑡, 𝑠 (29)

≤ 𝑃G𝑖,𝜙,𝑡,𝑠 ≤ 𝑛MEG

𝑖 𝑃G,max𝑖 ,∀𝑖 ∈ 𝛺CN, 𝜙, 𝑡, 𝑠 (30)

0 ≤ 𝑄G𝑖,𝜙,𝑡,𝑠 ≤ 𝑛MEG

𝑖 𝑄G,max𝑖 ,∀𝑖 ∈ 𝛺CN, 𝜙, 𝑡, 𝑠 (31)

𝑈𝑖,𝜙,𝑡,𝑠 − 𝑈𝑗,𝜙,𝑡,𝑠 ≥ 2(�̂�𝑖𝑗𝑃K𝑖𝑗,𝜙,𝑡,𝑠 + �̂�𝑖𝑗𝑄

K𝑖𝑗,𝜙,𝑡,𝑠)

+ (𝑢𝑘,𝑡,𝑠 + 𝑝𝑖𝑗,𝜙 − 2)𝑀,∀𝑘, 𝑖𝑗 ∈ 𝛺K , 𝜙, 𝑡, 𝑠(32)

𝑈𝑖,𝜙,𝑡,𝑠 − 𝑈𝑗,𝜙,𝑡,𝑠 ≤ 2(�̂�𝑖𝑗𝑃K𝑖𝑗,𝜙,𝑡,𝑠 + �̂�𝑖𝑗𝑄

K𝑖𝑗,𝜙,𝑡,𝑠)

+ (2 − 𝑢𝑘,𝑡,𝑠 − 𝑝𝑖𝑗,𝜙)𝑀,∀𝑘, 𝑖𝑗 ∈ 𝛺K , 𝜙, 𝑡, 𝑠(33)

min max

𝜒𝑖,𝑡,𝑠𝑈𝑖 ≤ 𝑈𝑖,𝜙,𝑡,𝑠 ≤ 𝜒𝑖,𝑡,𝑠𝑈𝑖 ,∀𝑖, 𝜙, 𝑡, 𝑠 (34) 94
Page 7: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

1

2

3456789

1011121314151617181920212223242526

Fig. 2. A single line diagram of an example network with one damaged line.

Fig. 3. A virtual network created for the example network in Fig. 2.

Fig. 4. A crew assignment example with 2 depots and 5 crews.

2728

29

30313233

34

35

36

37

38

39

40

41

42

43

𝑘∈∈𝛺B(l)

𝑢𝑘,𝑡,𝑠 ≤ |𝛺B(l)| − 1,∀𝑙 ∈ 𝛺loop, 𝑡, 𝑠 (35)

Constraints (24) and (25) are nodal power balance constraints ofactive and reactive powers, where 𝑃K

𝑖𝑗,𝜙,𝑡,𝑠 and 𝑄K𝑖𝑗,𝜙,𝑡,𝑠 are active and

reactive power flows, and 𝑃G𝑖,𝜙,𝑡,𝑠 and 𝑄G

𝑖,𝜙,𝑡,𝑠 are the power outputs of thegenerators. The active charging/discharging and reactive power out-puts of energy storage systems are denoted by 𝑃Ch

𝑖,𝜙,𝑡,𝑠, 𝑃Dis𝑖,𝜙,𝑡,𝑠 and 𝑄ESS

𝑖,𝜙,𝑡,𝑠.Constraints (26)–(27) represent the active and reactive power limits ofthe lines, where the limits (𝑃K,max

𝑘 and 𝑄K,max𝑘 ) are multiplied by the

line status binary variable 𝑢𝑘,𝑡,𝑠. Therefore, if a line is disconnected ordamaged, power cannot flow through it. Constraints (28)–(29) limit theoutput of the generators to 𝑃G,max

𝑖 and 𝑄G,max𝑖 . Similarly, the output of

the MEGs is limited in (30)–(31) if an MEG is installed (𝑛MEG𝑖 = 1).

Constraints (32) and (33) calculate the voltage difference alongline 𝑘 between bus 𝑖 and bus 𝑗, where 𝑈𝑖,𝜙,𝑡,𝑠 is the square of voltagemagnitude of bus 𝑖. The big-M method is used to relax constraints (32)and (33), if lines are damaged or disconnected. �̂�𝑖𝑗 and �̂�𝑖𝑗 are theunbalanced three-phase resistance matrix and reactance matrix of line𝑖𝑗, which can be referred to [48]. The vector 𝑝𝑖𝑗,𝜙 represents the phasesof line 𝑖𝑗. Constraint (34) guarantees that the voltage is limited withina specified region (𝑈min

𝑖 and 𝑈max𝑖 ), and is set to 0 if the bus is in an

outage area. Constraint (35) can guarantee the radiality network duringthe network reconfiguration. This model assumes that all the possibleloops can be identified by the depth-first search method. The set ofloops are given by 𝛺loop, and the set of switches in loop 𝑙 is given by

𝛺B(l). For each fuel-based generator, the total fuel consumption 𝐹𝑖,𝑠

is limited by the available fuel resources 𝑛Fuel𝑖 in constraint (36), asfollows:

𝐹𝑖,𝑠 = 𝑟f∑

∀𝑡

∀𝜙𝑃G𝑖,𝜙,𝑡,𝑠 ≤ 𝑛Fuel𝑖 ,∀𝑖 ∈ 𝛺G, 𝜙, 𝑡, 𝑠 (36)

The operation constraints for ESSs and MESs include the change instate of charge (SOC), charging and discharging limits, and reactivepower limits. Let 𝛺ES be the set of buses with ESSs, and 𝛺ESC =𝛺ES ∪𝛺CN.

𝐸SOC𝑖,𝑡,𝑠 =𝐸SOC

𝑖,𝑡−1,𝑠+

𝛥𝑡(∑

∀𝜙 𝑃Ch𝑖,𝜙,𝑡,𝑠𝜂Ch −

∀𝜙 𝑃Dis𝑖,𝜙,𝑡,𝑠∕𝜂Dis)

𝐸Cap𝑖

,∀𝑖 ∈ 𝛺ESC, 𝜙, 𝑡, 𝑠(37)

𝐸SOC,min𝑖 ≤ 𝐸SOC

𝑖,𝑡,𝑠 ≤ 𝐸SOC,max𝑖 ,∀𝑖 ∈ 𝛺ESC, 𝑡, 𝑠 (38)

0 ≤ 𝑃Ch𝑖,𝜙,𝑡,𝑠 ≤ ℎ𝑖,𝑡,𝑠𝑃

Ch,max𝑖 ,∀𝑖 ∈ 𝛺ESC, 𝜙, 𝑡, 𝑠 (39)

0 ≤ 𝑃Dis𝑖,𝜙,𝑡,𝑠 ≤ (1 − ℎ𝑖,𝑡,𝑠)𝑃

Dis,max𝑖 ,∀𝑖 ∈ 𝛺ESC, 𝜙, 𝑡, 𝑠 (40)

−𝑄ESS,max𝑖 ≤ 𝑄ESS

𝑖,𝜙,𝑡,𝑠 ≤ 𝑄ESS,max𝑖 ,∀𝑖 ∈ 𝛺ES, 𝜙, 𝑡, 𝑠 (41)

Ch MES Ch,max

0 ≤ 𝑃𝑖,𝜙,𝑡,𝑠 ≤ 𝑛𝑖 𝑃𝑖 ,∀𝑖 ∈ 𝛺CN, 𝜙, 𝑡, 𝑠 (42) 44
Page 8: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

1

2

3

4

5𝐸6E7p8𝐸9m10(11a12i13p14c15s16a17

318

1920212223242526

27

2829

30

31

32

33343536373839404142434445464748495051525354

1

55

56s 57f 58

59

60

61s 62f 63s 64( 65M 66𝑠 67a 68s 69

4 70

71s 72r 73E 74i 751 76𝐶 77T 78

0 ≤ 𝑃Dis𝑖,𝜙,𝑡,𝑠 ≤ 𝑛MES

𝑖 𝑃Dis,max𝑖 ,∀𝑖 ∈ 𝛺CN, 𝜙, 𝑡, 𝑠 (43)

− 𝑛MES𝑖 𝑄ESS,max

𝑖 ≤ 𝑄ESS𝑖,𝜙,𝑡,𝑠 ≤ 𝑛MES

𝑖 𝑄ESS,max𝑖 ,∀𝑖 ∈ 𝛺CN, 𝜙, 𝑡, 𝑠 (44)

Constraint (37) calculates the state of charge (SOC) of ESSs (𝐸SOC𝑖,𝑡,𝑠 ).

Cap𝑖 is the maximum capacity of the storage system. To ensure safeSS operation, the SOC and charging (𝑃Ch

𝑖,𝜙,𝑡,𝑠) and discharging (𝑃Dis𝑖,𝜙,𝑡,𝑠)

ower of ESSs are constrained as shown in (38)–(40). Here, 𝐸SOC,min𝑖 ,

SOC,max𝑖 , 𝑃Ch,max

𝑖 and 𝑃Dis,max𝑖 define the permissible range of SOC, and

aximum charging and discharging power, respectively. In constraints39)–(40), the binary variable ℎ𝑖,𝑡,𝑠 indicates that ESSs cannot chargend discharge at the same time instant. The ESS charging and discharg-ng efficiency are represented by 𝜂Ch and 𝜂Dis, respectively. The reactiveower of ESS, 𝑄ESS

𝑖,𝜙,𝑡,𝑠, is kept within maximum limit, 𝑄ESS,max𝑖 , through

onstraint (41). For MES units, the constraints (42)–(43) are presentedo that if 𝑛MES

𝑖 = 0, the output power is 0 at bus 𝑖. The same method ispplied for the reactive power in (44).

. Solution algorithm

When the number of scenarios is finite, a two-stage stochasticproblem can be modeled as a single-stage large linear programmingmodel, where each constraint in the problem is duplicated for eachrealization of the random data. As discussed before, the Monte Carlosampling technique can be used to generate a manageable number ofscenarios for problems where the number of realizations is too large orinfinite. In this work, the scenario decomposing method PH is used tosolve the proposed two-stage stochastic pre-event preparation problem.

3.1. Two-stage progressive hedging algorithm

The proposed two-stage stochastic pre-event preparation model (4)–(44) can be compactly reformulated as follows:

𝜉 = min𝑥,𝑦𝑠

𝑎𝑇 𝑥 +∑

∀𝑠𝑃𝑟(𝑠)𝑏𝑇𝑠 𝑦𝑠 (45)

s.t. (𝑥, 𝑦𝑠) ∈ 𝑄𝑠,∀𝑠 (46)

In objective (45), the vectors 𝑎 and 𝑏𝑠 include the coefficientsrelated with the compact first stage variable 𝑥 and compact secondstage variable 𝑦𝑠, respectively. The compact constraint (46) can en-sure the feasibility for solutions from each subproblem and scenario.When the non-anticipativity of the first stage variables is relaxed, thenthe PH algorithm decomposes the extensive form (EF) (45)–(46) intoscenario-based subproblems. Therefore, the proposed stochastic pre-event preparation problem with the total number 𝑆 of scenarios canbe decomposed into 𝑆 subproblems. In Algorithm 1, the proposedstochastic pre-event preparation problem is solved by PH algorithm.In Step 1, we initialize the problem. In Step 2–3, the subproblems withindividual scenarios are solved. In Step 4, we obtain the expected value�̄� of the first stage solution by aggregating the solutions from Steps2–3. Step 5 calculates the value of the multiplier 𝜂𝑠. In Step 8, thesubproblems are solved by augmenting two terms: one linear term,which is proportional to the multiplier 𝜂𝜏−1𝑠 ; one squared two normterm of the difference between 𝑥 and �̄�𝜏−1, which is penalized by 𝑟ℎ𝑜.Steps 9–10 are similar as Steps 4–5. The algorithm terminates once allfirst stage decisions 𝑥𝑠 converge to a common �̄�. Note that the two-stage model has been reformulated to a single-level problem for eachindividual scenario. In Algorithm 1, 𝜏 is the iteration number, 𝜌 is apenalty factor and 𝜖 is the threshold value for termination.

p

Algorithm 1 PH Algorithm for Solving Stochastic Pre-event PreparationProblem1: Initialization: the iteration 𝜏.2: For each individual scenario 𝑠 ∈ 𝑆, solve.3: 𝑥(𝜏)𝑠 ∶= argmin𝑥{𝑎𝑇 𝑥 + 𝑏𝑇𝑠 𝑦𝑠 ∶ (𝑥, 𝑦𝑠) ∈ 𝑄𝑠}.4: �̄�(𝜏) ∶=

∀𝑠∈𝑆 𝑃𝑟(𝑠)𝑥(𝜏)𝑠 .5: 𝜂(𝜏)𝑠 ∶= 𝜌(𝑥(𝜏)𝑠 − �̄�(𝜏)).6: 𝜏 ∶= 𝜏 + 1.7: For each individual scenario 𝑠 ∈ 𝑆, solve.8: 𝑥(𝜏)𝑠 ∶= argmin𝑥{𝑎𝑇 𝑥+ 𝑏𝑇𝑠 𝑦𝑠 + 𝜂(𝜏−1)𝑠 𝑥+ 𝜌

2‖𝑥(𝜏)𝑠 − �̄�(𝜏)‖2 ∶ (𝑥, 𝑦𝑠) ∈ 𝑄𝑠}.

9: �̄�(𝜏) ∶=∑

∀𝑠∈𝑆 𝑃𝑟(𝑆)𝑥(𝜏)𝑠 .10: 𝜂(𝜏)𝑠 ∶= 𝜂(𝜏−1)𝑠 + 𝜌(𝑥(𝜏)𝑠 − �̄�(𝜏)).11: if ∑∀𝑠∈𝑆 𝑃𝑟(𝑠)‖𝑥(𝜏)𝑠 − �̄�(𝜏)‖ ≤ 𝜀 then12: Go to Step 5.13: else14: terminate.15: end if

Algorithm 2 Multiple Replication Procedure1: Initialization: Set 𝛼 ∈ (0, 1) (e.g., 𝛼 = 0.05), sample size 𝑛,

replication size 𝑛𝑔 and a candidate solution �̂� ∈ 𝑋.2: For 𝑘 = 1, 2, ..., 𝑛𝑔 .3: Sample i.i.d. observations 𝜁𝑘1 , 𝜁𝑘2 , ..., 𝜁𝑘𝑛 from the distribution of 𝜁 .4: Solve (SPn) using 𝜁𝑘1 , 𝜁𝑘2 , ..., 𝜁𝑘𝑛 to obtain 𝑥𝑘∗𝑛 .5: Calculate 𝐺𝑘

𝑛 (�̂�) ∶= 𝑛−1∑𝑛

𝑗=1(𝑓 (�̂�, 𝜁𝑘𝑗 ) − 𝑓 (𝑥𝑘∗𝑛 , 𝜁𝑘𝑗 )).

6: End for.7: Calculate gap estimate 𝐺𝑛(𝑛𝑔) ∶=

1𝑛𝑔

∑𝑛𝑔𝑘=1 𝐺

𝑘𝑛 (�̂�).

8: Calculate sample variance 𝑠2𝐺(𝑛𝑔) ∶=1

𝑛𝑔−1∑𝑛𝑔

𝑘=1(𝐺𝑘𝑛 (�̂�) − 𝐺𝑛(𝑛𝑔))2.

9: Let 𝜖 ∶= 𝑡𝑛𝑔−1,𝛼𝑆𝐺(𝑛𝑔)∕√

𝑛𝑔 .10: Obtain one-sided CI on [0, 𝐺𝑛(𝑛𝑔) + 𝜖𝑔].1: Output: Approximate (1−𝛼) as the level confidence interval on 𝜇�̂�.

3.2. Convergence analysis and solution validation

As shown in Algorithm 1, the convergence metric 𝑔𝜏 for the progres-ive hedging algorithm at each iteration 𝜏 is expressed as the deviationrom the mean summed across all first stage variables 𝑥𝑠(𝜏) and the

average value of the first stage variable �̄�𝜏 as follows:

𝑔𝜏 =∑

𝑠∈𝑆𝑃𝑟(𝑠)‖𝑥𝑠(𝜏) − �̄�𝜏‖ (47)

Since the solution is obtained using a limited number of damagecenarios, the quality of the solution requires verification. Adoptedrom [49], the MRP can be applied to repeat generating 𝑆 scenarios andolving the proposed model for 𝑆 times. Then the confidence intervalCI) is constructed to calculate the optimality gap. The detailed steps inRP are shown in Algorithm 2, where 𝐺𝑛(𝑛𝑔) is the gap estimate and

2𝐺(𝑛𝑔) is the sample variance. Numerical results for the convergencenalysis and solution validation of the test case are given in the nextection.

. Case study

This section uses a large-scale system as a test case to verify thecalability and effectiveness of the two-stage stochastic pre-event prepa-ation model. This large-scale system consists of 3 existing test systems,PRI ckt5, ckt7 systems [50], and IEEE 8500 bus system [51], Follow-ng the suggestions from [15], the unit costs in the simulation are 𝐶D =4$/kWh for load shedding at all buses, 𝐶SW = 8$ for each line switch,F = 1$/L and 𝑟F = 0.3 L/kWh for fuel consumption of generators.he Pyomo and Gurobi mixed-integer solver [52] are used to solve theroposed stochastic model. All experiments are implemented on the

79
Page 9: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

12

3

45678

Fig. 5. Resource allocation of large-system with the proposed model.

Fig. 6. The convergence metric comparison with and without soft-start solutions.

91011121314151617

Iowa State University Condo cluster, whose individual blade consists oftwo 2.6 GHz 8-Core Intel E5-2640 v3 processors and 128 GB of RAM.

4.1. Pre-event preparation results

This case study include 9 depots that are hosting a total of 27 crews,9 dispatchable DGs, 8 MEGs, 3 MESs, 123 switches, 5 small PVs, 15large PVs, and 12 ESSs. The active and reactive power capacities of the9 DGs are 300 kW and 250 kVAr. The active power capacity of smallPVs ranges from 11 kW to 22 kW. The active power capacity of large

PVs is 500 kW. The 12 ESSs are rated at 500 kW/ 3500 kWh. The pre-event preparation model of the large-scale system is solved in 10.2 hwith 10 damage scenarios. The locations of MEGs, MESs, and numberof crews are shown in Fig. 5. 27 crews are allocated to 9 differentdepots. The value inside the crew depot in Fig. 5 represents the numberof crews assigned to that depot. Areas with a large number of crewsindicate that the lines in the area have high damage probabilities.

As discussed in Section 3.2, the convergence metric can be used toevaluate the convergence speed of the proposed model. At the sametime, the computational speed with and without a soft-start solution are

18
Page 10: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

123456789

1011121314

Fig. 7. Aggregated damaged areas.

Fig. 8. Comparison between the base model and the proposed method.

15161718192021222324252627

compared. In this paper, a soft-start solution means that the previouslycomputed solution in other instances will be used as the starting point.The comparison result is shown in Fig. 6. If the convergence metricreaches the convergence threshold of 0.01, the algorithm will stopand obtain the optimal solution. The instance with a soft-start solutionconverges at 57 iterations and takes 10.2 h. The case without a soft-start solution converges after 100 iterations and takes 24.3 h. Totest the solution quality with MRP, based on the limited number ofgenerated damage scenarios, the one-sided CI of the obtained solutionis [0, 12.48%]. This small gap indicates that the damage scenarios arerepresentative and the solution is stable with high quality.

To evaluate the performance of the developed pre-event preparationmodel, the model is compared to a base model. The base case isgenerated by the following steps: (i) one MEG is pre-positioned at each

substation. (ii) Extra MEGs are pre-positioned at high-priority loads.(iii) PV and ESS are not considered. (iv) Fuel is allocated to the MEGssuch that the MEGs can operate for at least 24 h. (v) Crews are allocatedevenly between depots. In this work, the average outage duration iscalculated by dividing the sum of outage duration for the loads bythe total number of loads. To compare the proposed model and thebase model, a random scenario is generated and test the response ofthe system. The generated scenario has 103 damaged lines, which areaggregated to 34 damaged areas in Fig. 7. Each circle represents therepair time needed for the specific damaged area considering all theaggregated damaged lines.

The comparison between the base model and the proposed methodis shown in Fig. 8. In the base model, the total restored energy is231,422.38 kWh and the average outage duration is 14.69 h. In the

28
Page 11: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

1234

5

6789

10111213

Fig. 9. Pre-event resource allocation results with different PV penetration levels.

141516171819202122232425262728

proposed method, the total restored energy is 291,727.48 kWh and theaverage outage duration is 11.28 h. Therefore, approximately 20.67%more loads are served by the proposed method and the outage durationdecreased by 30.22%.

4.2. Impacts of solar PV on system resilience

To show the advantages of the PV systems, the responses of thesystem with the proposed pre-event preparation method and differentPV penetration levels are tested. Three rated capacities of PV systemsare considered: (i) Capacity 1 PV, which represents residential PVpanels and the rated capacity is assumed to be 6 kW; (ii) Capacity 2 PV,which represents mid-size PV systems and the rated capacity is assumedto be 48 kW; (iii) Capacity 3 PV, which represents large utility PV farm

and the rated capacity is assumed to be 2000 kW. Based on the number

of different types of PVs, 6 PV penetration levels are defined as 9%,27%, 45%, 63%, 81%, and 99%. The number of Capacity 1, 2, and 3PVs for each PV penetration level is summarized in Table 1. To bettercollaborate the setting of PV penetration, the number of dispatchableDGs has been changed to 10 and the positions of those DGs have beenchanged accordingly.

Based on the results of Fig. 9, it can be observed that differentPV penetration levels have different allocation results for the flexibleresources, including the positions of MEGs, MESs, and the number ofrepair crews.

Fig. 10 shows the percentage of power served during the event, andafter the repair process starts. Tables 2 and 3 compare the amount ofload served and average outage duration with different levels of PVpenetration.

Based on the results from Fig. 10, Table 2, and Table 3, it can

be seen that the penetration of PV contributes to enhancing system 29
Page 12: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

TP

12345

Fig. 10. Load served percentage comparison of the proposed model with various PV penetration levels and the base model.

6

789

10111213141516171819202122232425262728293031323334353637383940414243

44

45

able 1V penetration levels and the number of PV systems with different rated capacities.PV penetrationlevel

Capacity 1PV

Capacity 2PV

Capacity 3PV

9% 8 1 127% 24 4 345% 40 7 563% 63 9 781% 72 12 999% 88 15 11

Table 2The amount of load served and resilience improvement with different PV penetrationlevels.

PV penetrationlevel

Load served(kWh)

Resilience improvementpercentage (%)

0 251,210.72 –9% 318,668.37 26.8527% 335,525.77 33.5645% 336,710.74 34.0463% 344,588.22 37.1781% 360,668.04 43.5799% 364,785.93 45.21

Table 3The amount of average outage duration and outage decreased percentage with differentlevels of PV penetration.

PV penetrationlevel

Average outageduration (h)

Outage decreasedpercentage (%)

0 14.69 –9% 12.33 16.0727% 11.72 20.2245% 11.65 20.6963% 11.21 23.6981% 10.45 28.8699% 10.12 31.11

resilience. Approximately 31.13% more loads are served than the basemodel when the proposed method with 99% PV penetration is used.Also, the average outage duration decreased by 31.12%. However,compared with 81% PV penetration level, the proposed method with99% PV penetration does not have significant improvement.

5. Conclusion

Extreme weather events may severely impact the electric grid infras-tructures, causing major damage and faults in the system. This leads topower outages for an extended period. It is up to the electric utilityto plan how to prepare for such an event and restore power to thecustomers after the event. When an extreme weather event hits thedistribution system, the damaged network may hinder the physicaldelivery of mobile resources and repair crews. In addition, withoutproper preparation, utilities will be overwhelmed with the numberof tasks that must be conducted, including assigning tasks to crews,managing crews coming from different areas, and dispatching portablegenerators to supply critical customers. Therefore, to achieve fast andefficient response, it is critical to pre-position crews, equipment, andother resources before the severe event occurs. In this paper, a two-stage stochastic pre-event preparation and resource allocation methodis proposed for upcoming extreme weather events, which enhancesthe system resilience and enables more efficient post-event restoration.The proposed pre-event method leverages the pre-allocation of mobileresources, fuel resources, and labor resources. By considering differentoperation modes of distributed PV systems, the proposed model alsofacilitates the benefits of solar powers in the resilience improvement ofdistribution grids. According to the case studies, the following obser-vations are found: (i) Compared to the base model without pre-eventresource allocation, the proposed pre-event preparation model canserve more loads and reduce the outage duration. (ii) Based on theresponse of the system with different PV penetration levels, it canbe observed that the proposed pre-event preparation model with highPV penetration can further improve system resilience and reduce theoutage duration. Therefore, PV systems can play a critical role inimproving distribution grid resilience and further promote renewableenergy deployment. (iii) By considering the trade-off between solutionaccuracy and computation efficiency, the result of MRP indicates thatthe proposed model’s solutions with a limited number of scenarios canbe very stable and of high quality. The scalability of the proposedpre-event preparation model is verified with a large-scale system. Thetrade-off between the cost of pre-event resource allocation and therisk associated with damage loss will be considered under upcomingextreme weather events in future work.

CRediT authorship contribution statement

Qianzhi Zhang: Conceptualization, Methodology, Software, Writ-

ing - original draft, Validation. Zhaoyu Wang: Supervision, Project 46
Page 13: Stochastic pre-event preparation for enhancing resilience

Q. Zhang et al.

123

4

567

8

910

11

121314151617181920212223242526272829303132333435363738394041424344454647484950515253545556575859606162636465666768

69707172737475767778798081828384858687888990919293949596979899

100101102103104105106107108109110111112113114115116117118119120121122123124125126127128129130131132133134135136137138139140141142143144145

administration, Funding acquisition. Shanshan Ma: Writing - review& editing, Software, Validation, Methodology. Anmar Arif: Writing -review & editing, Software, Validation, Methodology.

Declaration of competing interest

The authors declare that they have no known competing finan-cial interests or personal relationships that could have appeared toinfluence the work reported in this paper.

Acknowledgment

This work was supported by the U.S. Department of Energy WindEnergy Technologies Office under Grant DE-EE0008956.

References

[1] Craig MT, Cohen S, Macknick J, Draxl C, Guerra OJ, Sengupta M, et al. A reviewof the potential impacts of climate change on bulk power system planning andoperations in the United States. Renew Sustain Energy Rev 2018;98:255–67.

[2] Feldpausch-Parker AM, Peterson TR, Stephens JC, Wilson EJ. Smart grid elec-tricity system planning and climate disruptions: A review of climate and energydiscourse post-superstorm sandy. Renew Sustain Energy Rev 2018;82:1961–8.

[3] Abdin L, Fang Y, Zio E. A modeling and optimization framework for powersystems design with operational flexibility and resilience against extreme heatwaves and drought events. Renew Sustain Energy Rev 2019;112:706–19.

[4] Pantrli M, Mancarella P. Influence of extreme weather and climate change onthe resilience of power systems: Impacts and possible mitigation strategies. ElectrPower Syst Res 2015;127:259–70.

[5] Martin N, Rice J. Power outages, climate events and renewable energy: Review-ing energy storage policy and regulatory options for Australia. Renew SustainEnergy Rev 2021;137:110617.

[6] Salman AM, Li Y, Stewart MG. Evaluating system reliability and targetedhardening strategies of power distribution systems subjected to hurricanes. ReliabEng Syst Saf 2015;144:319–33.

[7] Campbell RJ, Lowry S. Weather-related power outages and electric systemresiliency. Congressional Research Service, Library of Congress Washington, DC;2012.

[8] Das L, Munikoti S, Natarajan B, Srinivasan B. Measuring smart grid re-silience: Methods, challenges and opportunities. Renew Sustain Energy Rev2020;130:109918.

[9] Molyneaux L, Brown C, Wagner L, Foster J. Measuring resilience in energysystems: Insights from a range of disciplines. Renew Sustain Energy Rev2016;59:1068–79.

[10] Sharifi A, Yamagata Y. Principles and criteria for assessing urban energyresilience: A literature review. Renew Sustain Energy Rev 2016;60:1654–77.

[11] Emenike SN, Falcone G. A review on energy supply chain resilience throughoptimization. Renew Sustain Energy Rev 2020;134:110088.

[12] Tari AN, Sepasian MS, Kenari MT. Resilience assessment and improvement ofdistribution networks against extreme weather events. Int J Power Energy Syst2021;125:106414.

[13] Executive Office of the President. Economic benefits of increasing electric gridresilience to weather outages. White House Tech. Rep., 2020.

[14] Mishra DK, Ghadi MJ, Azizivahed A, Li L, Zhang J. A review on resilience studiesin active distribution systems. Renew Sustain Energy Rev 2021;135:110201.

[15] Ma S. Resilience-Oriented Design and Proactive Preparedness of ElectricalDistribution System (Ph.D. thesis), 2020.

[16] Lin Y, Bie Z. Tri-level optimal hardening plan for a resilient distribution systemconsidering reconfiguration and DG islanding. Appl Energy 2018;211:1266–79.

[17] Dehghani NL, Jeddi AB, Shafieezadeh A. Intelligent hurricane resilience enhance-ment of power distribution systems via deep reinforcement learning. Appl Energy2021;285:116355.

[18] Zhang G, Zhang F, Zhang X, Wu Q, Meng K. A multi-disaster-scenario distri-butionally robust planning model for enhancing the resilience of distributionsystems. Int J Power Energy Syst 2020;122:106161.

[19] Shahbazi A, Aghaei J, Pirouzi S, Shafie-khah M, Catalao JP. Hybrid stochasticrobust optimization model for resilient architecture of distribution networksagainst extreme weather conditions. Int J Power Energy Syst 2021;126:106576.

[20] Arif A, Wang Z, Wang J, Chen C. Power distribution system outage managementwith co-optimization of repairs, reconfiguration, and DG dispatch. IEEE TransSmart Grid 2018;9(5):4109–18.

[21] Mousavizadeh S, haghifam M-R, Shariatkhah M-H. A linear two-stage methodfor resiliency analysis in distribution systems considering renewable energy anddemand response resources. Appl Energy 2018;211:443–60.

[22] Amirioun M, Aminifar F, Lesani H, Shahidehpour M. Metrics and quantitativeframework for assessing microgrid resilience against wind storms. Int J PowerEnergy Syst 2019;104:716–23.

[23] Zhang Q, Ma Z, Zhu Y, Wang Z. A two-level simulation-assisted sequentialdistribution system restoration model with frequency dynamics constraints. IEEETrans Smart Grid 2021;12(5):3835–46.

[24] Gholami A, Shekari T, Grijalva S. Proactive management of microgrids forresiliency enhancement: An adaptive robust approach. IEEE Trans Sustain Energy2019;10(1):470–80.

[25] Wang C, Hou Y, Qiu F, Lei S, Liu K. Resilience enhancement with sequentiallyproactive operation strategies. IEEE Trans Power Syst 2017;32(4):2847–57.

[26] Panteli M, Mancarella P, Trakas D, Kyriakides E, Hatziargyriou N. Metrics andquantification of operational and infrastructure resilience in power systems. IEEETrans Power Syst 2017;32(6):4732–42.

[27] Wang S, Sarker B, Mann L, Triantaphyllou E. Resource planning and a depotlocation for electric power restoration. European J Oper Res 2004;155(1):22–43.

[28] Arif A, Wang Z, Chen C, Chen B. A stochastic multi-commodity logisticmodel for disaster preparation in distribution systems. IEEE Trans Smart Grid2020;11(1):565–76.

[29] Taheri B, Safdarian A, Moeini-Aghtaie M, Lehtonen M. Enhancing resilience levelof power distribution systems using proactive operational actions. IEEE Access2019;7:137378–89.

[30] Lei S, Wang J, Chen C, Hou Y. Mobile emergency generator pre-positioning andreal-time allocation for resilient response to natural disasters. IEEE Trans SmartGrid 2018;9(3):2030–41.

[31] Lei S, Chen C, Zhou H, Hou Y. Routing and scheduling of mobile powersources for distribution system resilience enhancement. IEEE Trans Smart Grid2019;10(5):5650–62.

[32] Kim J, Dvorkin Y. Enhancing distribution system resilience with mobile energystorage and microgrids. IEEE Trans Smart Grid 2019;10(5):4996–5006.

[33] Samara S, Shaaban M, Osman A. Optimal management of mobile energygeneration and storage systems. IEEE Access 2020;8:203890–900.

[34] Okoye CO, Taylan O, Baker DK. Solar energy potentials in strategically locatedcities in Nigeria: Review, resource assessment and PV system design. RenewSustain Energy Rev 2016;55:550–66.

[35] Emmanuel M, Rayudu R. Evolution of dispatchable photovoltaic system inte-gration with the electric power network for smart grid applications: A review.Renew Sustain Energy Rev 2017;67:207–24.

[36] Ranaweera I, Midtgard O-M. Optimization of operational cost for agrid-supporting PV system with battery storage. Renew Energy 2016;88:262–72.

[37] Belding S, Walker A, Watson A. Will solar panels help when the power goesout?. National renewable energy tech. rep., 2020.

[38] Schmitz WI, Schmitz M, Canha LN, Garcia VJ. Proactive home energy storagemanagement system to severe weather scenarios. Appl Energy 2020;279:115797.

[39] Rosales-Asensio E, de Simon-Martin M, Rosales A-E, Comenar-Santos A. Solar-plus-storage benefits for end-users placed at radial and meshed grids: Aneconomic and resiliency analysis. Int J Power Energy Syst 2021;128:106675.

[40] Zhang C, Wei Y-L, Cao P-F, Lin M-C. Energy storage system: Current studies onbatteries and power condition system. Renew Sustain Energy Rev, Early Access.

[41] Rockafellar RT, Wets RJ-B. Scenarios and policy aggregation in optimizationunder uncertainty. Math Oper Res 1991;16(1):119–47.

[42] Watson J-P, Woodruff DL. Progressive hedging innovations for a class ofstochastic mixed-integer resource allocation problems. Comput Manag Sci2011;8(4):355–70.

[43] Arif A, Wang Z, Chen C, Wang J. Repair and resource scheduling in unbal-anced distribution systems using neighborhood search. IEEE Trans Smart Grid2020;11(1):673–85.

[44] Ma S, Chen B, Wang Z. Resilience enhancement strategy for distribution systemsunder extreme weather events. IEEE Trans Smart Grid 2018;9(2):1442–51.

[45] Ma S, Li S, Wang Z, Qiu F. Resilience-oriented design of distribution systems.IEEE Trans Power Syst 2019;34(4):2880–91.

[46] Chen B, Chen C, Wang J, Butler-Purry K. Sequential service restorationfor unbalanced distribution systems and microgrids. IEEE Trans Power Syst2018;33(2):1507–20.

[47] Melhem F, Grunder O, Hammoudan Z, Moubayed N. Energy management inelectrical smart grid environment using robust optimization algorithm. IEEETrans Ind Appl 2018;54(3):2714–26.

[48] Zhang Q, Dehghanpour K, Wang Z. Distributed CVR in unbalanced distributionsystems with PV penetration. IEEE Trans Smart Grid 2019;10(5):5308–19.

[49] Ma S, Su L, Wang Z, Qiu F, Guo G. Resilience enhancement of distribution gridsagainst extreme weather events. IEEE Trans Power Syst 2018;33(5):4842–53.

[50] EPRI. OPENDSS test circuits. 2019, URL https://sourceforge.net/p/electricdss/discussion/beginners.html.

[51] Arritt R, Dugan R. The IEEE 8500-node test feeder. In: IEEE PES T&D Conference.2010, p. 1–6.

[52] Hart WE, Laird CD, Watson J-P, Woodruff DL, Hackebeil GA, Nicholson BL, etal. Pyomo-optimization modeling in Python, vol. 67. Springer; 2017.