Tim Hayler 1
Step IV Infrastructure update
STFCTim Hayler
Eddie HoltomNorbert CollombGraham Stokes
14th December 2011MICO170 meeting
Tim Hayler 2
MICE major Infrastructure milestonesTask Baseline Status
Downstream spectrometer solenoid base plate installation complete
31/12/11 Complete
He window manufacture complete
30/6/12 Detail drawings complete, currently out for Quotation.
TOF cage and Virostek plate bracket design complete
31/12/11 Detail drawings complete,currently out for Quotation
AFC rolling platforms tested 31/12/11 Complete
Radiation shield manufacture and testing complete
30/3/12 Design review held at the Technical board meeting 21st November, some open issues.
Ready for AFC & SS installation
30/3/12 Depends on the MICE hall schedule of events
Tim Hayler 3
Downstream spectrometer solenoid base plate installation complete
All step IV base plates installed:Upstream spectrometer base plate (in beam and out of beam)AFC base plate (in beam and out of beam)Downstream spectrometer base plate (in beam only, there will be no possibility of moving the downstream spectrometer out of beam)
Tim Hayler 4
He window manufacture, currently out for quotation
Tim Hayler 5
TOF cage and Virostek plate bracket design completeDetail drawings of the bracket design are complete.
We have worked closely with the Spectrometer team to make sure all the necessary compliance is in the design e.g. The way the brackets fasten to the Spectrometer and positioning of the TOF cage.
Currently going through the tendering process.
Expect delivery in march 2012
Tim Hayler 6
TOF cage and Virostek plate test support standSupport frame to test:
• The bracket assembly to the TOF cage and Virostek plate.
• TOF detector assembly, movement of the detector on the sliding mechanism.
• The mechanical arm for removing the split ring
•Expect the need to do some re-work on the Virostek plates, split rings, drill and tap holes, some machining
Expect to start the build in March 2012
Tim Hayler 7
AFC rolling platform tests completeTesting specification for the MICE Moving Platform:
• Ensure the platform raises and lowers and moves horizontally
• Leak check/pressure drop check (Hydraulic system)
• Ensure the platform raises sufficiently to permit moving the unit without interference
• Visual inspection of components under load regarding deformation
• There are no unforeseen failures of components
• The moving of the platform along its intended path
Tim Hayler 8
AFC rolling platform tests complete
4 tonne load test done at Daresbury Lab
Hydraulic jacks raise the platform.
Roller stakes move the platform in and out of the beam.
Final testing needs to be done in the MICE hall early 2012
Tim Hayler 9
The Radiation ShieldThe review presentation is on the technical board website, meeting minutes 21st November 2011. http://mice.iit.edu/tb/Meetings/2011-11-21/
Tim Hayler 10
Actions from the radiation shield review
Action Date Responsible Status
A test plan devised for all operating scenarios (in vacuum)
02/Jan/2012 Norbert Collomb
WIP
Manual method to open and close the shutter doors
02/Jan/2012 Norbert Collomb
WIP
Add radiation monitor to the design
01/Feb/2012 Tim Hayler and Norbert Collomb
Need specification from the collaboration
Tim Hayler 11
Spectrometer Solenoid stand
Support frame design is being worked on at RAL with close collaboration with the Spectrometer team
Tim Hayler 12
Spectrometer Solenoid stand
The frame will be built in the UK and installed in the MICE hall as part of the Step IV build
The Spectrometer team will now provide the SS with just the four support feet shown. This helps with shipping issues.
Tim Hayler 13
Local magnetic shielding for the MICE hall compressors and beyond
Prototype being made in mild steel for a fit check
Tim Hayler 14
Ready for AFC and SS installation30/03/2011
• The readiness date for the AFC and SS installation is very much dependant on the MICE hall schedule of events.
• We want to install all the moving platforms for step IV• Can we move the KL detector downstream to progress the
Engineering build in the first SS position? First raised at the TB, 21st Nov meeting, slides by Ken Long http://mice.iit.edu/tb/Meetings/2011-11-21/
• Are we taking beam in the first quarter of 2012?• What is the Hydrogen project doing?• What other work is scheduled for the first quarter 2012? • In building up the Infrastructure we would expect unknowns,
items lost and unforeseen events. It would be very useful to start the work in January.