11
Status of TTF HOM Project Aug 9, 2005 Project Scope: Instrument both couplers for all SC cavities in the TTF2. (80 channels). System expected to operate as BPM system Expect <~few micron resolution (train average) Expect <~30 micron resolution (bunch to bunch) Expect readout rate ~1 Hz for all BPMs (5Hz May be possible) Want full integration into TTF2 control system.

Status of TTF HOM Project Aug 9, 2005

  • Upload
    fai

  • View
    22

  • Download
    0

Embed Size (px)

DESCRIPTION

Status of TTF HOM Project Aug 9, 2005. Project Scope: Instrument both couplers for all SC cavities in the TTF2. (80 channels). System expected to operate as BPM system Expect

Citation preview

Page 1: Status of TTF HOM Project Aug 9, 2005

Status of TTF HOM ProjectAug 9, 2005

• Project Scope: Instrument both couplers for all SC cavities in the TTF2. (80 channels).

• System expected to operate as BPM system– Expect <~few micron resolution (train average)– Expect <~30 micron resolution (bunch to bunch)– Expect readout rate ~1 Hz for all BPMs (5Hz May be

possible)• Want full integration into TTF2 control system.

Page 2: Status of TTF HOM Project Aug 9, 2005
Page 3: Status of TTF HOM Project Aug 9, 2005
Page 4: Status of TTF HOM Project Aug 9, 2005
Page 5: Status of TTF HOM Project Aug 9, 2005

Hardware Status – Downmix Chassis

• First Prototype board completed / stuffed Aug 5. • Preliminary tests of Gain, Noise, linearity “look

good”, should have numbers in a few days.• Board designed for machine assembly

– Parts ordered– In principal, just ship parts to vendor for assembly– In practice, probably more involved that that, but no

serious problems expected• Chasses now simplified due to lower board

power consumption (~5 W / board).– 5 Chasses + spare, to be assembled at SLAC– No problems anticipated

Page 6: Status of TTF HOM Project Aug 9, 2005

Other Hardware• VME crate / digitizers: All commercial parts, but

need to decide on control hardware.• LO source: Synthesizer, amplifier, Fan-out:

Straightforward.• Calibration reference: Must produce ~1700 MHz

tone, locked to harmonic of beam with ~1 picosecond stability– Not designed yet (ideas only) – technically

challenging.– Needs to use TTF triggers, timing signals to produce

clean reference

Page 7: Status of TTF HOM Project Aug 9, 2005

Timing

• The software / hardware must allow the HOM signals measurements to be correlated with specific conventional BPM measurement pulses.

• HOM system probably will not run at full 5Hz beam rate, so need method to identify which pulses are measured

Page 8: Status of TTF HOM Project Aug 9, 2005

Software

• This probably represents >3/4 of the entire project effort!!!

• Software architecture determines which VME hardware to purchase

• Architecture will depend on which group does which part of the work (software can have a steep learning curve).

• Need to make decisions soon!

Page 9: Status of TTF HOM Project Aug 9, 2005

Software Components• Data Download: 10, 8 channel, 100Ms/s (12 or 14 bit) VME digitizers.

– For 1 millisecond, get 8M samples / pulse, Can produce up to 80MByte/second data rate.

– Can run slower, but then this is limits bpm update rate• Data Digital Downconversion, filtering to produce I,Q data for each bunch.

Matrix multiply (small) to produce X,Y for each cavity. – Very approximately 1 Gflop maximum processing required. ~1Gbyte memory.

• DOOCS Server: 1000 pulses, with X,Y, X’, Y’ for 40 cavities, at 5Hz beam rate.

– Total possible rate 800KWords / second. • Calibration Software: Same concept as existing HOM system but much

more complex.– Must move correctors, read conventional and HOM BPMs throughout machine.– Use MIA, and model dependant analysis to determine cavity BPM calibration

coefficients, download to DOOCS server.– Does not need real time, but calculations can be complex.

Probably have 1 computer as front-end, separate computer for calibration.

Page 10: Status of TTF HOM Project Aug 9, 2005

Front End• Data Download,Digital Down Conversion, DOOCS

server. 2 Reasonable Options

1. Standard DOOCS, VME crate controller (Force SPARC-56 CPU)

• Easy integration with TTF2• Easy Support, (need new driver for digitizers)• Low performance (250 specfp2k)

2. SIS VME-PCI bridge• Existing drivers for LINUX pc from SIS• 80MB/sec transfer demonstrated by SIS• ~1600 specfp2k for PC. • VME-2e• Unique hardware – difficult support

Page 11: Status of TTF HOM Project Aug 9, 2005

Calibration Computer

• LINUX PC with Matlab probably the most reasonable solution.

• Interface with front end computer through DOOCS. – Are large data transfers (1GB) in DOOCS

OK?• If we use a PC (PCI-VME bridge) for front

end, can probably use same computer for calibration.