Sri Lanka Tsunami Operation Water and Sanitation Mexico 13 th – 14 th March, 2006 Fidel Pena, WatSan Coordinator

Sri Lanka Tsunami Operation

  • Upload
    jonco

  • View
    54

  • Download
    0

Embed Size (px)

DESCRIPTION

Sri Lanka Tsunami Operation. Water and Sanitation Mexico 13 th – 14 th March, 2006 Fidel Pena, WatSan Coordinator. In the previous annual meeting…. National Society response Federation response ERU’s Deployment (Specialized Water, Distribution and trucking modules) PNS’s response. - PowerPoint PPT Presentation

Citation preview

Page 1: Sri Lanka  Tsunami Operation

Sri Lanka Tsunami Operation

Water and Sanitation

Mexico 13th – 14th March, 2006

Fidel Pena, WatSan Coordinator

Page 2: Sri Lanka  Tsunami Operation

In the previous annual meeting…..

National Society response Federation response

ERU’s Deployment (Specialized Water, Distribution and trucking modules)

PNS’s response

Page 3: Sri Lanka  Tsunami Operation

In previous Tsunami Meetings’s …..

June 2005, Sri Lanka

• Emergency phase was almost over….

• Transition phase just taking off

• Rehabilitation and Development in planning phase

Page 4: Sri Lanka  Tsunami Operation

Coordination is still a very big issue …

During emergency and even now….

Page 5: Sri Lanka  Tsunami Operation

Emergency phase“Outside the RC movement…..”

AffectedAffectedPopulationPopulation

IFRC

ICRC

PrivateNGOs

WFPNGOs

UNDP

MIL

OCHA

Humanitarian Coordinator

Local Authorities

LTTE FACT

Embassies

Donors

NGOsPNS

UNHCR/CARUN

UNICEF

NGOs

TAFREN

UNDAC

Media

Sri Lanka Red Cross

NGOs

NGOs

WHO

NGOs

NGOs

NGOs

Page 6: Sri Lanka  Tsunami Operation

In November 2005, (Maldives)Sri Lanka presentation Coordination role of IFRC:

Concept papers Project proposals Technical Committee Liaison with ICRC, SLRCS and PNS’s Signature of MoU with NWS&DB

Implementation of multilateral projects 4 Districts

Page 7: Sri Lanka  Tsunami Operation

Conclusions (challenges….)

• Technical expertise

• Coordination inside Red Cross Movement

• SLRCS new activity

• Risk to be involved in high-tech vs IFRC approach

• Clear exit strategy in future

Page 8: Sri Lanka  Tsunami Operation

So far what has been achieved?RC Movement platform

• More coherent intervention between RC actors• In almost all the cases good coordination in sharing and updating information• Procedures are almost establish for everybody

Page 9: Sri Lanka  Tsunami Operation

Implementation of IFRC funds

• Short list of consultant’s for big projects • Galle 1 phase 1 is on going• Rehab of WTP in Ampara contract is to be signed this month• Transitional shelter intervention (3 Districts)• Jaffna 02 project approved by RC Mov.

Page 10: Sri Lanka  Tsunami Operation

Jaffna 02 project Supply of water to 18 new resetlement areas in

Jaffna

• 18 Tsunami resettlement sites of which 4 are SLRCS / ARC housing projects

• 3,211 families (approx 12,504 beneficiaries),

• 18 resettlement sites,• 1 Hospital, and• 5 Schools.

Page 11: Sri Lanka  Tsunami Operation

Future activities•Coordination

WatSan Coordinator WatSan Software Delegate PNS implementationCapacity Building of SLRCS

• Implementation Deputy WatSan Coordinator Hygiene promotion in IFRC projects Expand projects up to 6 in 4 Districts