85
Social Monitoring Report Post-Evaluation Report April 2016 VIE: Northern Power Transmission Expansion (Sector) Project Prepared by the Northern Power Project Management Board for the Asian Development Bank (ADB). This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

Embed Size (px)

Citation preview

Page 1: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

Social Monitoring Report Post-Evaluation Report April 2016

VIE: Northern Power Transmission Expansion

(Sector) Project

Prepared by the Northern Power Project Management Board for the Asian Development Bank

(ADB).

This social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Page 2: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION PROJECT

ADB LOAN No. 2225-VIE (SF)

POST EVALUATION REPORT

Submitted to:

THE ASIAN DEVELOPMENT BANK

Prepared by:

NORTHERN POWER PROJECT MANAGEMENT BOARD

Hanoi, December 2015

Page 3: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 2

TABLE OF CONTENT

1. PROJECT BACKGROUND 5

1.1. Project components and locations 6

1.2. Project components with resettlement impacts. 10

1.3. Categories of resettlement impact and payment of compensation 12

1.3.1. Categories of resettlement impact 12

1.3.2. payment for compesation 13

2. OBJECTIVES OF POST EVALUATION 15

3. METHODOLOGY 15

4. FINDINGS 17

4.1. Basic information about displaced persons’ households 17

4.1.1. Profile of Affected household 17

4.1.2. Income sources, Income separation and Distribution 20

4.1.3. Livelihood and Subsistence Economy 22

4.1.4. Houses and House styles 23

4.1.5. Access to Infrastructure and Social Services 23

4.1.6. Participation in neighborhood or community groups 23

4.2. Compensation and resettlement 24

4.2.1. Resettlement and livelihood restoration 24

4.2.2. Before and after land acquisition and resettlement comparison 26

4.3. Restoration of livelihoods 27

4.3.1. Income restoration models/programs 27

1. 28

4.3.2. Restoration of livehoods 29

4.4. Public, participation, consultation and Grievance resolution 32

4.4.1. Public Consultation, Disclosure, and Participation 32

4.4.2. Grievance Resolution 33

4.5. Effectiveness of resettlement planning 38

4.5.1. Resettlement Objects 38

4.5.2. Executing Agency and Implementation Agency and RP implementation progress40

4.5.3. Time frame and budget arrangements 41

5. LESSONS LEARNT 41

Page 4: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 3

5.1. Monitoring and Evaluation 42

6. CONCLUSIONS, LESSONS LEARNT 42

ANNEXES 43

Annex 1:Relevant Documents on Resettlement and Compensation 44

Annex 2: Status of Land Clearance and Compensation of Subprojects until December

31 2014. 47

Annex3. Status of the implementation of Corrective Action Plans 51

Annex 4. List of Participants and Interviewees 62

Annex 5. Some photographs about the field work 68

Annex 6. Socio-economic Questionnaires of Affected Households 78

Annex 7: List of people in department of NPMB 83

LIST OF TABLES

Table 1: Summary of Subprojects ............................................................................................ 7

Table 2: Number of households and the impacts on land by sub project ................................ 10

Table 6: Number of AHs interviewed in socio-economic survey in project L2225.................... 17

Table 7: Total AHs collecting data by subproject .................................................................... 17

Table 8: Gender and Age of people collecting data ................................................................ 18

Table 9: Erthic minority rate of collecting people..................................................................... 18

Table 10: Education level of respondent ................................................................................. 19

Table 11: Occupation of surveyed HH .................................................................................... 20

Table 13: Average income by ethnic group ............................................................................. 21

Table 14: Resettlement status of AHs in subprojects .............................................................. 25

Table 15: Comparision income ratio, occupation ratio before and after project implementation26

Table 16: Allowances of Project for AHs ................................................................................. 28

Table 17: Status of compensation implementation of L2225 subprojects (up to December/2015)

............................................................................................................................................... 29

Table 18. Status of Issuance LURC........................................................................................ 31

Table 19: All complaints in the subprojects L2225 ............................................................ 35

Table 20: Quantities of AHs by RP/DDR and actual ............................................................... 38

Page 5: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 4

LIST OF BOX

Box 1: Local citizens 'opinions about the project impacts........................................................ 22

Box 2: Model of change of job structure in Hiep Hoa – Bac Giang .......................................... 26

Box 3: opinion by local citizens in project area ....................................................................... 31

Box 4: Feedback of people on grievance redress ................................................................... 34

Box 5: Opinion on compensation for AHs in project area ........................................................ 38

ACRONYMS

ADB Asian Development Bank

AP Affected Person

CPC Commune People’s Committee

DMS Detailed Measurement Survey

DCARB District Compensation and Resettlement Board

EM Ethnic Minorities

LIC Local Implementation Consultant

GoV Government of Viet Nam

PPCs Provincial People’s Committees

RPF Resettlement Policy Framework

ROW Right of Way

RP Resettlement Plan

RS Resettlement site

NPPMB Northern Power Project Management Board

VND Viet Nam Dong

TNA Training need assessment

TOR Terms of Reference

T/L Transmission line

Page 6: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 5

1. PROJECT BACKGROUND

1. The Project represents a 5-year time slice of Electricity of Viet Nam’s (EVN) transmission expansion program, covering 500 kilovolt (kV) and 220 kV transmission lines and associated

substations. The Project covers the northern part of Viet Nam, which is relatively poor. The Project

will enable power to be supplied to the planned industrial zones in the region, thereby facilitating

employment and income-generating opportunities. Thus, it will benefit the poor and ethnic minorities

living in the project area.

Map of L2225 Project area

Page 7: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 6

2. The Project is to (i) strengthen the northern transmission network to improve system

reliability and quality of supply, (ii) facilitate power transfers by removing transmission bottlenecks,

(iii) reduce transmission losses, and (iv) facilitate efficient utilization of existing and planned power

plants.

3. EVN is the Executing Agency (EA) responsible for overall implementation of the Project. The

Project will be implemented as a sector loan, and additional subprojects will be introduced during

implementation. NPPMB and CPPMB, as the implementing agencies, will be responsible for the day-

to-day implementation of the 500 kV and 220 kV project substations and transmission lines.

Adequately staffed project offices have been established in the Hanoi headquarters of NPPMB and

CPPMB to supervise the Project. The loan was approved on 21 December 2005, signed on 22

August 2006 and declared effective on 24 November 2006 for a total amount of $360 million.

Original loan closing date was 30 June 2010 which was extended thrice until 31 December 2013, 30

June 2014 and 31 December 2014.

1.1. Project components and locations

4. The Project scope included twelve 500 kilovolt (kV)& 220 kV transmission lines and

substations in Northern Viet Nam, and provision of spare substation equipment/materials (power

transformers, switchgear, tele-thermal cameras and transformer oil filters). There were

twelvesubprojectsimplemented under the sector loan, comprising three core subprojects (appraised

prior to loan approval) and ninenon-core subprojects (appraised during project implementation), as

follows: (i) Son La–Hoa Binh and Son La–Nho Quan 500 kV transmission lines; (ii) Thanh Hoa–Nghi

Son–Vinh 220 kV transmission line;(iii) expansion of Van Tri 220 kV substation*; (iv) Son La–Hiep

Hoa 500 kV transmission line; (v) expansion of Thuong Tin 500 kV substation**; (vi) Hiep Hoa 500

kV new substation; (vii) expansion of Nho Quan 500 kV substation***1; (viii) Tuyen Quang 220 kV

new substation; (ix) Bim Son 220 kV new substation; (x) Hai Duong 2 220 kV new substation; (xi)

Kim Dong 220 kV new substation; and (xii) Thuong Tin–Kim Dong 220 kV transmission line.

Subprojects (i) to (iii) are the core subprojects.

5. All the 12 subprojects were completed by the loan closing date, except several towers in

Thuong Tin–Kim Dong transmission lines which were completed inAugust 2015after resolving

compensation issues. It is expected to energizeabove transmission line by the end of September

2015.The Project has helped the Government in adequate and reliable transmission of electricity,

including evacuation of powerfrom new power plants that have come into operation during the

project period.

1 *; ** and ***: 3 subprojects do not have affected household, no compensation and resettlement

Page 8: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 7

Table 1: Summary of Subprojects

No. Subproject Commune/district Started Date Completion Date Actual cost

$million

Transmission Lines

i Son La–Hoa Binh and Son La–Nho Quan 500 kV transmission lines*

282.9 km (177km ofdouble circuitand 28.6 km and 77.3 km single circuit

36 communes of 11 districts in03 provinces:

- Son La province: Muong La, Mai Son, Yen Chau and Moc Chau districts. - Hoa Binh province: Cao Phong, Mai Chau, Hoa Binh city, Lac Son, Yen Thuy and Tan Lac districts

- Ninh Binh province: Nho Quan district

November 2008 December 2010 110.77

ii SonLa–Hiep Hoa 500 kV transmission Line

264.7 km double circuit

18 districts of 5 provinces: - Son La province: Muong La, Mai Son, Bac Yen and Phu Yen districts. The length of the section traversing Son La was 125.26 km. - Phu Tho province: Tan Son, Thanh Son, Yen Lap and Tam Nong districts and Phu Tho town and Phu Ninh district. The length of the section traversing Phu Tho was 81.97 km. - Vinh Phuc province: Lap Thach, Song Lo, Tam Duong, Tam Dao, Binh Xuyen districts and Phuc Yen town. The length of the section traversing Vinh Phuc was 42.44 km. - Thai Nguyen province: Pho Yen district with the length of 16.58 km.

- Bac Giang province: Hiep Hoa district with the length of 2.32 km.

November 2009 March 2012 153.20

iii Thanh Hoa–Nghi Son–Vinh 220 kV transmission lines*

147km double circuit

10 districts of 2 provinces:

- Thanh Hoa province: Thieu Hoa, Dong Son, Nong Cong, Tinh Gia and Trieu Son

- Nghe An province: Vinh city, Nghi Loc, Dien Chau, Quynh Luu and Yen Thanh districts

October 2011 July 2014 35.88

iv Thuong Tin–Kim Dong 220 kV transmission line

03 districts of 02 provinces:

- Ha Noi city: Thuong Tin district

May 2013 December 2014 10.56

Page 9: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 8

No. Subproject Commune/district Started Date Completion Date Actual cost

$million

27 km double circuit - Hung Yen province: Kim Dong and Khoai Chau districts

Substations

v Hiep Hoa 500 kV new substation

Total 1,800 MVA (2900MVA Transformers)

Hop Thinh and Dai Thanh communes, Hiep Hoa district November 2009 TF1: March 2011

TF2: March 2013

48.80

vi Expansion of Thuong Tin 500 kV substation

450 MVA

Thuong Tin district December 2009 January 2011 7.36

vii Expansion of Nho Quan 500 kV substation

450 MVA

Nho Quan district June 2011 March 2012 5.25

viii Bim Son 220 kV new substation

1x125 MVA with provision for 2

nd

transformer

Bim Son town, Thanh Hoa province August 2012 July 2014 7.09

ix Tuyen Quang 220kV new substation

1x125 MVA with provision for 2

nd

transformer

Kim Phu commune, Yen Son district, Tuyen Quang city December 2012

July 2014 8.75

x Hai Duong 2 220 kVnew substation

1x250 MVA

An Phu commune, Kinh Mon district, Hai Duong provine August 2013 substantially completed as of Dec 2014, commissioned in Feb 2015

9.90

Page 10: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 9

No. Subproject Commune/district Started Date Completion Date Actual cost

$million

xi Kim Dong 220 kV new substation

1x250 MVA

Toan Thang commune, Kim Dong district March 2013 substantially completed as of Dec 2014, commissioned in 2015

7.79

xii Expansion of Van Tri 220 kV substation*

1250 MVA

Van Tri commune,Dong Anh district, Ha Noi city September 2010 September 2013 2.34

* appraised during project design (core subprojects)

Page 11: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 10

1.2. Project components with resettlement impacts.

6. The Northern Power Transmission Expansion Project (the Project or NPTEP) represents a 5-

year time slice of Electricity of Viet Nam’s (EVN) transmission expansion program, covering 500 kilovolt (kV) and 220 kV transmission lines and associated substations. The Project covers the

northern part of Viet Nam, which is relatively poor. The Project will enable power to be supplied to the

planned industrial zones in the region, thereby facilitating employment and income-generating

opportunities. Thus, it will benefit the poor and ethnic minorities living in the project area.

7. The Project is to (i) strengthen the northern transmission network to improve system reliability

and quality of supply, (ii) facilitate power transfers by removing transmission bottlenecks, (iii) reduce

transmission losses, and (iv) facilitate efficient utilization of existing and planned power plants.

8. There are 9409 affected households in projects in there 4,983,138 m2 affected kinds of land in

provinces Son La, Hoa Binh, Ninh Binh, Thai Nguyen, Phu Tho, Vinh Phuc, Bac Giang, Hai Duong,

Hung Yen, hanoi, Thanh Hóa, Nghe An… There are 2826 household erthic minority and 746 women household. . The project has been implemented 23 resettlement site for 758 affected household focus

in 500kV Son La – Hiep Hoa subproject with 21 resettlement site.

Impact on land

9. The project affected different types of land:.The total land area affected by the project is

4,983,138 m2, including 2,043,526 m2 of agricultural land. The rest is mainly forest land (2,903,101

m2) and garden land (36,511 m2).

Impact on structure

There are 34 household affected the infrastructure, 758 household resettlement in 23 resettlement

sites.

Impact on tree and crops

Having 9362 household affected the tree and agriculture land…

Table 2: Number of households and the impacts on land by sub project

No. Subprojects AHs Impact of Land (m

2)

Resettlement Sites

1 Bim Son 220 KV Substation 24 43,000 0

2 Tuyen Quang 220 kV Substation 93 72,677 1

3 Son La-Nho Quan-Hoa Binh 500kV T/L 2,911 1,811,232 1

4 Thanh Hoa - Vinh 220kv T/L 950 291,453 0

5 Hai Duong 2 220 kV Substation 90 33,397 0

6 Son La – Hiep Hoa transmission line 4115 2,500,961 21

7 Hiep Hoa SS 770 180.713 0

8 220 Kim Dong SS 187 33.715 0

9 220kV Thuong Tin – Kim Dong T/L 269 15.990 0

10 Extension of Nho Quan 500 kV Substation 0 0 0

11 Expansion of Thuong Tin 500 kV substation 0 0 0

12 Expansion of Van Tri 220 kV substation 0 0 0

Total 9,409 4,752,950 23

(Source: consolidated from RP/DDRs and data on compensation from NPPMB, 2014)

10.

Page 12: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 11

11. The project affected different types of land: agricultural land...Beside, the project affected crops

and trees and structures of the households during the project implementation.

Table 3: Types of land and assets of Ahs

No Subprojects

Total affected land

area (m2) Garden *(m2)

Agricultural land (m2)

Forestland (m2)

Affected crops/ trees (HHs)

Affected structures

(HHs)

1 Son La- Hiep Hoa 500 KV T/L 2,500,961 23,860 727,460 1,749,641 4115 0

2 Hiep Hoa 500 KV substation 180,713 0 180,713 0 770 0

3 Kim Dong 220 KV substation 33,715 0 33,715 0 187 0

4 Thuong Tin- Kim Dong 220 KV T/L 15,990 0 15,990 0 222 11

5 Bim Son 220 KV Substation 43,000 0 43,000 0 24 23

6 Tuyen Quang 220 KV Substation 72,677 0 72,677 0 93 0

7 Son La-Nho Quan-Hoa Binh 500kv T/L 1,811,232 12,651

645,121 1,153,460 2,911 0

8 Thanh Hoa - Vinh 220kv T/L 291,453 0 291,453 0 950 0

9 Hai Duong 2 220 kV Substation 33,397 0 33,397 0 90 0

Total 4,983,138 36,511 2,043,526 2,903,101 9,362 34

Source: Socio-economicsurvey by LIC, December, 2015

12. The total land area affected by the project is 4,983,138 m2, including 2,043,526 m2 of

agricultural land. The rest is mainly forest land (2,903,101 m2) and garden land (36,511 m2).

The details infomation by subprojects in below:

Son La-Nho Quan-Hoa Binh 500kv T/L is the subproject with the largest number of AHs

(316 resettled HHs out of 2,911 AHs) and involved 1,811,232 m2 impacted land of different

types i.e. agricultural land, forestland, garden. Most resettled HHs arranged for self-

resettlement on the area left after land acquisition or move to a nearby place. There was only

01 Resettlement Site constructed in Tan Lac district for resettled HHs here. No HHs had

more than 10% of their agricultural land affected.

Tuyen Quang 220 kV Substation involved 04 resettled HHs and 72,677 m2 land of different

types (mostly forestland and agricultural land). However, there were only 02 HHs building

houses on the land lot assigned by the project. No HHs had more than 10% of their

agricultural land affected.

Bim Son 220 KV Substation had no resettled HHs but impacted 43,000 m2 land of different

types(agricultural land). There were 02 HHs having more than 10% of their agricultural land

affected.

Hai Duong 220 kV Substation had no resettled HHs but impacted 33,397 m2 land of

different types (mostly agricultural land). There were 29 HHs having more than 10% of their

agricultural land affected

Page 13: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 12

Thanh Hoa - Vinh 220kv T/L caused impacts to 950 HHs with 291,453 m2 land agriculture.

Nevertheless, there was no HH having more than 10% of agriculture land affected and no

resettled HH.

500 KV Son La- Hiep Hoa transmission line: The subproject crosses 19 districts of five

provinces: Son La, Phu Tho, Vinh Phuc, Thai Nguyen and Bac Giang. The total length of the

T/L was 268,47km. The starting point of Son La – Hiep Hoa 500kV T/L was the Son La

500KV substation and the ending point was Hiep Hoa 500KV substation. The number of

affected households (AHs) is 4115, in which 438 AHs were subject to relocation.

Resettlement activities have been undertaken and relocation is basically completed.

Hiep Hoa SS: The Hiep Hoa 500kV Substation Subproject traverses 2 communes (Dai

Thanh and Hop Thinh) of Hiep Hoa district, Bac Giang province. Total 770 HHsareaffected

by the subproject in Dai Thanh and Hop Thinh communes. There are 244 AHs losing more

than 10% of their agricultural land and no AH being relocated or resettled, no AH having their

houses/structures affected as well as no AH having their business affected.

220 KV Kim Dong SS: The subproject is located in Toan Thang commune, Kim Dong

district, Hung Yen province. Total of 187 HHs are affected by the substation.

220 KV Thuong Tin- Kim Dong T/L: passing 3 districts in Hung Yen province (Khoai Chau

and Kim Dong districts) and Hanoi City (Thuong Tin district). There are 3 districts with 16

communes in 2 provinces affected by the subproject. The number of affected households

(AHs) is 269, in which 7 AHs losing more than 10% of productive land.

13.

1.3. Categories of resettlement impact and payment of compensation

1.3.1. Categories of resettlement impact

The project is Category A, but there are 2 subproject in Category A 500kV Son La –

Hiep Hoa TL and 500kV Son La – Nho Quan – Hoa Binh TL, 7 subproject in Category B

and 3 subproject in Category C (Detail in the Tabole No 4).

14. Since February 2010, VICA Consultants International Company Ltd. (VICA) has been

engaged by NPPMB to provide services in preparation of safeguards (resettlement and

environment) documents. VICA has helped NPPMB to supervise the implementation safeguard

policies of ADB in every subproject during the construction and operation.

15. During its implementation, the project acquired land and non-land assets for the construction

and maintenance. The social safeguards policies applied under the Project are: (i) Involuntary

Resettlement,(1995) guided by the Operations Manual on Involuntary Resettlement (OM/F2, 2006);

(ii) other relevant policies and guidelines of ADB, i.e., Gender (1998), Indigenous Peoples (1998),

Accountability (2003), Public Communications (2005), and Incorporating Social Dimensions on ADB

Operations (2007); and (iii) current regulations of Government of Viet Nam (GoV) related to land

acquisition, compensation, assistance and resettlement (i.e. Land Law 2003; Decree No.

197/2004/ND-CP; Decree No. 84/2007/ND-CP; Decree No. 69/2009/ND-CP and other relevant

Circulars to guide the implementation of the Decrees etc.).

16. There are 24 RPs and EMDPs, 23 DDRs have been prepared for project since 2005 to 2014

by PB Power in PPTA, VICA, CEFACOM and LICs

There are 2 Local Implementation Consultant working in this loan. The first LIC covers 05 subprojects

namely (i) Son La – Hoa Binh – Nho Quan 500kV T/L, (ii) 220kV Thanh Hoa – Vinh T/L; (iii) 220kV

Bim Son substation; (iv) 220kV Tuyen Quang substation; (v) Hai Duong 2 220 KV substation; and the

Page 14: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 13

second LIC covers 04 subprojects namely (vi) Son La – Hiep Hoa 500kV T/L; (vii) 500kV Hiep Hoa

substation; (viii) 220kV Kim Dong substation; (ix) Thuong Tin – Kim Dong 220kV T/L.(x) Expansion of

500kV Thuong Tin Substation; (xi) Expansion of 500kV Nho Quan substation; (xii) Expansion of 220kV

Van Tri substation.

17. International and national experts assisted NPPMB and CPPMB in undertaking the

resettlement and environmental management plans.

1.3.2. payment for compesation

18. As it could be seen from the data in RP/DDRs and compensation data provided by NPPMP,

the total amount of compensation and assistance for AHs in 12 subprojects was roughly VND

539,798,000,000 (equivalent to US $25,218,313.482). Such amount covered compensation for land,

trees/crops, structures and assistance for AHs in their relocation, house construction, temporary

assistance during relocation, electricity fee etc.

Table 4: Compensation and assistance for AHs under 9 subprojects

No. Subprojects Actual Level of Impact3

Compensation and assistance (million

VND) DPs Relocated

1 Bim Son 220 KV

Substation 24 0 B

7,519,000,000

2 Tuyen Quang 220 KV

Substation 93 4 B

6,713,000,000

3 Son La-Nho Quan-Hoa

Binh 500kv T/L 2,911 316 A

185,350,000,000

4 Thanh Hoa - Vinh 220kv

T/L 950 0 B

25,726,000,000

5 Hai Duong 2 220 kV

Substation 90 0 B

7,315,000,000

6 Son La – Hiep Hoa

transmission line 4115 438 A 251,170,000,000

7 Hiep Hoa SS 770 0 B 37,500,000,000

8 220 Kim Dong SS 187 0 B 8,860,000,000

9 220kV Thuong Tin – Kim

Dong T/L 269 0 B 9,645,000,000

10 Extension of Nho Quan

500 kV Substation

0 0 C

0

11 Expansion of Thuong Tin

500 kV substation

0 0 C

0

12 Expansion of Van Tri 220

kV substation

0 0 C

0

Total 539,798,000,000

(Source: synthesized by LIC from the actual compensation payment for the subprojects in L2225, 2015)

2 Provisional exchange rate on 15 December 2014, US$1 equal to VND 21,405

3 Level of impact: (i) Group A consists of 200 and above severely affected persons (APs) (resettled and

lose more than 10% of their agricultural land or income-generating assets); (ii) Group B consists of less than 200 severely APs; (iii) Group C has no APs.

Page 15: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 14

19. The scope of impact caused by 09 subprojects was significant and thus, the number of AHs

was large with various types of impacts such as resettled HHs, HH only losing assets of trees/crops,

structures and lands of types i.e. agricultural land, forestland, garden, residential land. In addition,

there were direct impacts on vulnerable groups such as female-headed HHs and ethnic minority

HHs: Mường, Thái, Mông, Sán Rìu... The details of such impacts are presented in the table below:

Table 5: Number of AHs in sub-projects of Project L2225

No. Subprojects

Total AHs

Severely

affected househ

olds

Ethnic minority

household

Single woman headed

households

AHs receivin

g compensation

AHs not yet

receiving

compensation

Resettled

households

Resettlement sites

1 Bim Son 220 KV Substation 24 2 0 4 24 0 0 0

2 Tuyen Quang 220 kV Substation 93 0 0 4 93 0 4 1

3 Son La-Nho Quan-Hoa Binh 500kV T/L 2,911 316 955 131 2,911 0 316 1

4 Thanh Hoa - Vinh 220kv T/L 950 0 0 128 950 0 0 0

5 Hai Duong 2 220 kV Substation 90 29 0 2 90 0 0 0

6 Son La – Hiep Hoa transmission line

4115 438 871 427 4114 1 438 21 7 Hiep Hoa SS

770 244 0 40 770 0 0 0 8 220 Kim

Dong SS 187 57 0 42 187 0 0 0

9 220kV Thuong Tin – Kim Dong T/L

269 7 0 40 264 5 0 0

Total 9409 1093 1826 746 9403 6 758 23

Source: Socio-economicsurvey by LIC, December, 2015

Payment for compensation has implemented from 2009 to 2015. At the end of 2015 there are 5

household don't receive compensation (05 household in Le Loi commune, Thuong Tin district,

Hanoi and the household Mr Tran Thanh Tung in Phu Tho town)

20. As of December 2014, all 12 subprojects have been basically completed. Given previous

results of the resettlement monitoring; there wasno significant resettlement issues observed.

21. According toADB’s SPS 2009 and GoV’s policies on compensation, assistance and

resettlement, the implementation of subprojects shall ensure that all affected people will be

compensated for their damages at replacement cost and propose life rehabilitation methods to help

them to improve or at least maintain living standards and income generation capability to the pre-

Page 16: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 15

project level. Thus, the evaluation report covers the present monitoring results of corrective action

plan for all subprojects of Loan L2225 as of 30th December, 2015.

2. OBJECTIVES OF POST EVALUATION

22. The key purpose of this report is to evaluate the project’s compliance with ADB’s Safeguards policies via some specific objectives including:

Restoration income of affected household:

Compensation, payment for compensation and allowance for affected household.

Restoration livehood for affected household.

Compliant and claim of affected household.

Attaining the goal in RP/DDR about resettlement…

Evaluation about heavy affected household: Full receiving the allowance payment and the

policies of restoration income;

Lessons learn to implement the similar projects.

3. METHODOLOGY

23. The post evaluation for resettlement has been used the methodologies below:

Documents study: Loan Agreement, Project documents: Project Feasibility

Study, RPs of the subprojects (Son La – Hoa Binh transmission line, Hiep Hoa

substation, Kim Dong substation, Thuong Tin-Kim Dong transmission line,

DDR of Son La- Hiep Hoa transmission line subproject, Hiep Hoa substation

subproject; Memorandum of Understanding from ADB’s missions (2012, 2013, 2014 and 2015); ADB‘s SPS 2009; ADB’s Guideline on resettlement

assessment, Land Law 2003 and Decree 69 (guiding Land Law 2013); LIC's

quarterly reports and Policy framework and entitlement matrix for AHs in

project L2225.

Document analysis: Studying legal documents, internal reports on safeguards

and document reflecting results of compensation, assistance and resettlement

to obtain diverse information to analyze and assess the relevant issues during

the RP implementation. LIC randomly checked the documents and papers

related to compensation, assistance and resettlement of Compensation and

Resettlement Board/Center for Land Fund Development and studied the

documents related to livelihoods

Qualitative analysis:

Interview: The consultant has interviewed the division concerned to collect information.

Interviewing implement with: (i)Leaders in Division of Compensation and Resettlement

under NPPMB (2 persons); (ii) Leaders of Compensation and Resettlement Board in the

sub-projects i.e. 500kv Son La – Hiep Hoa, 500kV Son La- Hoa Binh, 500kV Hiep Hoa

substation, 220kV Kim Dong substation, 220kV Bim Son substation, 220 Tuyen Quang

substation and the districts where the 220kV Thanh Hoa – Vinh transmission line going

through (1 person/unit); (iii) Commune leaders in the affected communes in the

subprojects of 500kV Son La – Hiep Hoa substation, 500kV Son La – Hoa Binh

transmission line, communes of Dai Thanh and Hop Thinh - Hiep Hoa, communes in

220kV Thanh Hoa – Vinh subproject,….. (1 person/unit);(iv) In-depth interviews AHs in

Page 17: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 16

21 resettlement sites (one per site), besides, we interviewed 7 single woman headed

households, 5 households loosing assets, and 10 households loosing less than 10% of

total land area. LIC conducted in-depth interview with AHs, project officers and persons

in charge during the RP implementation according to the prepared questions: (i)

advantages and difficulties during the project implementation; (ii) positive and negative

impacts of the project; (iii) resettlement related issues; (iv) effects of livelihoods models

deployed; (v) lessons learnt during the project etc…

Group discussion: Organized 07 focus group discussion, each include 8-10 persons:02

FDG male and female discussion groups in 500kV Son La – Hiep Hoa transmission line

subproject; (poor households, single woman householders, ethnic minority households

…); 01 FDG male and female discussion group in 500kV Hiep Hoa substation

subproject;02 FDG female discussion group in 500kV Son La – Hoa Binh substation

subproject and 02 FDG male discussion groups in 200kV Bim Son substation and

200kV Tuyen Quang substation

Observation: LIC directly interviewed AHs at their houses, while observing their living

standards and the convenience. In addition, LIC interviewed AHs on how they use the

money and the methods to restore livelihoods of AHs after the project

24.

Quantitative analaysis: Collect the information of affected household, 100% of

heavy affected household and 20% of other affected household.

25. The methods were applied throughout the following process: (i) Sampling process (sample

selection and size); (ii) Data collection and analyzing; and (iii) Implementation arrangement.

Sampling and sample size

Sampling

26. AHs were the target group, including: (i) resettlers, (ii) households loosing more than 10% of

agricultural land, (iii) households loosing agricultural land and/or forestland and/or garden …LIC chosen to interview 20% of total AHs including about 20% severely affected households (resettlers and

households loosing more than 10% land).

27. The selection of interviewees was made in two steps: (i) selecting surveyed districts and (ii)

selecting AHs in the communes. In the selected districts, AHs were selected based on simplified

random selection method, from the list of AHs by subproject. In the selected households, the

interviewer prioritized heads of the households. In case they could not do not, the interviewers asked

other family members (who are from 18 to 60 years old, in their right mind, etc. In case they could not

meet AHs (working elsewhere, not at home after two visits, etc) the interviewer replaced them with

other AH next to that AH.

Sample size

The sample size was selected to represent the total AHs in the project. In this survey, the sample size

was identified based on the following principles: (i) 20% of total AHs (ii) 20% of total severely AHs

(resettlers, more than 10% agricultural land area). 10% samples were added (about 160 households)

of the interviewed households in case the selected AHs refuse to answer or working elsewhere or for

any reasons of not answering the questions. The sampling is as follows:

Page 18: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 17

Table 3: Number of AHs interviewed in socio-economic survey in project L2225

Subprojects

Total surveyed affected people

Total HHs

Survey

Severely

Affected HH

Insignificantly

Affected HHs

Son La- Hoa Binh- Nho Quan 172 84 88

Thanh Hoa-Vinh 220kV T/L 42 16 26

Hai Duong 220kV Substation 10 5 5

Bim Son 220kV Substation 6 4 2

Tuyen Quang 220kV Substation 10 6 4

Son La- Hiep Hoa T/L 824 149 675

500 KV Hiep Hoa SS 154 40 114

220 KV Thuong Tin- Kim Dong T/L 123 1 122

220 KV Kim Dong SS 35 0 35

Total 1,376 305 1,071

(Source: Socio-economic survey by LIC, August, 2014)

28. AHs in the sub-projects were interviewed in a revolving mode, means that after enough

interviews were made in one subproject, we moved to another subproject and continued until all the

interviews in all subprojects were done.

4. FINDINGS

4.1. Basic information about displaced persons’ households

4.1.1. Profile of Affected household

Demographic charactesistics

29. The Consultant did collect information from 1376 AHs, including 305 severely affected HHs

and 1071 insignificantly affected HHs. Total number of number of surveyed HH members was 5,978

(3122 males and 2856 females). The average scope of survey HH was 4.3 people per HH. Among

those, 68,2% of HHs had 5-8 members/HH.

30. The consultant has collected information with 1376 Ahs in there 305 heavy AHs and 1071

other Ahs. Total 5978 people – 3122 men and 2856 women. Average is 4,3 people / AH. The group

5-8 people in 1 AH 62,8%. AH is less than 4 people 21,6% and more 8 people 10,2%.

Table 4: Total AHs collecting data by subproject

Subprojects

Total surveyed affected people Avera

ge HH’s size

(pers./HH)

Distribution of APs by HH’s size (pers./HH)

Total HHs

Survey

severely

affected HH

insignificantly affected HHs Male

Female Total

<4 perso

ns

From 5 to 8 perso

ns

>8 perso

ns

Son La- Hoa Binh- Nho Quan

172 84 88 370 371 741 4.3 24.8 69.8 5.5

Thanh Hoa-Vinh 220kV T/L

42 16 26 79 92 171 4.1 13.9 86.1 0.0

Hai Duong 10 5 5 25 22 47 4.7 40 60 0

Page 19: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 18

Subprojects

Total surveyed affected people Avera

ge HH’s size

(pers./HH)

Distribution of APs by HH’s size (pers./HH)

Total HHs

Survey

severely

affected HH

insignificantly affected HHs Male

Female Total

<4 perso

ns

From 5 to 8 perso

ns

>8 perso

ns

220kV Substation

Bim Son 220kV Substation

6 4 2 14 10 24 4 16.7 83.3 0

Tuyen Quang 220kV Substation

10 6 4 24 21 45 4.5 20 80 0

Son La –Hiep Hoa 500kV 824 149 675 1.884

1.689 3.573 4.6 22.1 67.8 15.7

500 KV Hiep Hoa SS

154 40 114 358 335 693 4.5 22.5 64.8 12.7

220 KV Thuong Tin- Kim Dong T/L

123 1 122 283 236 519 4.3 18.7 64.3 17.0

220 KV Kim Dong SS

35 35 85 80 165 4.7 22.5 70 7.5

Total 1,376 305 1,071 3122 2856 5978 4.3 21.6 68.2 10.2

(Source: Socio-economicsurvey by LIC, August, 2014)

Population and ethnicity, ager distribution

Table 5: Gender and Age of people collecting data

Subprojects

Total HHs

Survey

Sex ratio (%) Distribution of the surveyed population by

age group (%)

Male Femal

e <20 20-35 36-40 41-60 >60

Son La- Hoa Binh- Nho Quan

172 50.8 49.2 15.3 28.3 9.8 35.0 11.6

Thanh Hoa-Vinh 220kV T/L

42 46.6 53.4 25.4 23.9 10.6 36.3 3.8

Hai Duong 220kV Substation

10 53.2 46.8 29.6 23.1 14.2 25.8 7.3

Bim Son 220kV Substation

6 58.3 41.7 31.2 29.8 2.9 30.2 5.9

Tuyen Quang 220kV Substation

10 53.3 46.7 37.1 35.3 10.9 9.9 6.8

Son La- Hiep Hoa 824 57.4 42.7 19.4 20.9 27.7 28.2 6.8

500 KV Hiep Hoa SS 154 51.7 48.3 22.5 17.6 28.5 26.5 4.9

220 KV Thuong Tin- Kim Dong T/L

123 53.5 46.5 20.6 21.9 26.1 26.8 4.7

220 KV Kim Dong SS 35 51.5 48.5 15.3 23 32.5 24.8 4.4

Total 1.376 52.7 47.3 19.4 23.1 20.3 30.0 7.2

Source: Socio-economicsurvey by LIC, August, 2014

31. In total 1376 people have been collected data, rate of men is 52,7% and women is 47,3%. In

there age from 3-40 is highest rate 30%, 20-35 age 23,1%, group 36-40 age 20,3% and over 60 age

7,2%.

Table 6: Erthic minority rate of collecting people

Subprojects Total HHs

Survey

Ethnic minority (%) (APs)

Kinh Muong Thai Mong Sán Rìu

Page 20: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 19

Subprojects Total HHs

Survey

Ethnic minority (%) (APs)

Kinh Muong Thai Mong Sán Rìu

Son La- Hoa Binh- Nho Quan 172 21.0 41.3 34.4 3.3 0.0

Thanh Hoa-Vinh 220kV T/L 42 100.0 0.0 0.0 0.0 0.0

Hai Duong 220kV Substation 10 100 0 0 0 0

Bim Son 220kV Substation 6 100 0 0 0 0

Tuyen Quang 220kV Substation 10 100 0 0 0 0

Son La – Hiep Hoa 824 80.0 3.1 15.6 0.9 1.4

500 KV Hiep Hoa SS 154 100 0 0 0 0

220 KV Thuong Tin- Kim Dong T/L

123 100.0 0.0 0.0 0.0 0.0

220 KV Kim Dong SS 35 100 0 0 0 0

Total 1.376 68.8 11.7 17.7 1.2 0.6

Source: Socio-economicsurvey by LIC, August, 2014

32. Out of the 1376 people surveyed, the majority of the affected people are Kinh, accounting

68.8% of the respondents. However, the project also affects EMs such as Muong, Thai, Mong and

San Diu. These EMs mainly concentrated in two subprojects of Son La - Nho Quan Hoa Binh and Son

La - Hiep Hoa.

33. EMs affected by the project is distributed in the provinces of Son La, Hoa Binh, and a few

districts in Phu Tho. EMs has seperated language and culture. Most of the project areas are

convenient to transport links, infrastructure, as well as basic social services. Agriculture is their main

source of income including annual agricultural crops as well as the type of product to be harvested

from the forest: wood, mushrooms, bamboo shoots, as well as the exploitation of non-timber products

to serve their life.

34. Today, EMs has access to all production activities, animal husbandry as well as the business

of the Kinh (agricultural trade, handicrafts, as well as models of agriculture production...). Most of them

go to school and are able to communicate in Vietnamese (except for some elderly and illiterate).

Therefore, they also contribute to the development of the region in general and in particular projects.

Education

Table 7: Education level of respondent

Subprojects

Total HHs

Survey

Distribution of the surveyed population by academic level (%)

Primary Lower

Secondary Upper

Secondary College/

University

Son La- Hoa Binh- Nho Quan 172 32.3 43.3 20.9 4.6

Thanh Hoa-Vinh 220kV T/L 42 24.2 35.0 30.3 10.5

Hai Duong 220kV Substation

10 33.4 27.8 22.7 16.1

Bim Son 220kV Substation 6 39.2 37.8 19 4

Page 21: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 20

Tuyen Quang 220kV Substation 10 41.2 36.7 16.6 5.5

Son La – Hiep Hoa 824 27.1 29.9 39.2 8.9

500 KV Hiep Hoa SS 154 21 7.3 58 13.7

220 KV Thuong Tin- Kim Dong T/L 123 18.0 28.6 38.8 13.3

220 KV Kim Dong SS 35 18 12 55 15

Total 1376 27.3 32.1 32.3 8.3

Source: Socio-economicsurvey by LIC, August, 2014

35. Out of 1376 surveyed people, the education level of secondary school and high secondary

school was similar (32.3% and 32.1% of respondents). Besides, 27.3% of respondents have primary

school, and only 8.3% of the respondents have college degree or higher. This also reflects the

education level of the project affected areas, mainly rural and mountainous areas.

4.1.2. Income sources, Income separation and Distribution

Table 8: Occupation of surveyed HH

Subprojects Total HHs

Survey

Occupation/income sources of APs members (%)

Agriculture Trading/Busi

ness Wage and hire

Labor

Son La- Hoa Binh- Nho Quan 172 75.3 7.7 17.0

Thanh Hoa-Vinh 220kV T/L 42 73.7 8.3 18.0 Hai Duong 220kV Substation

10 70.1 8.2 21.7 Bim Son 220kV Substation

6 75.4 5.1 19.5 Tuyen Quang 220kV Substation 10 80.7 6.0 13.3

Son La – Hiep Hoa 824 82.5 7.1 15.7

500 KV Hiep Hoa SS 154 69 7.5 23.5 220 KV Thuong Tin- Kim Dong T/L 123 69.7 11.0 20.4

220 KV Kim Dong SS 35 72 12.4 15.6

Total 1376 72.6 10.8 16.6

Source: Socio-economicsurvey by LIC, August, 2014

36. It can be seen that main occupation of serveyd HH is agriculture. Because project area goes

through provinces of the midland northern and mountainous and some provinces of the Red River

delta, the affected area is largely agricultural and forest land. Thus, the job of affected people are

agriculture, 72.6% of the respondents work as agriculture, the number of business / services and

salary/employees is 10.8% and 16.6% of the total surveyed HH.

37. There is a big change in comparision with pre-project implementation, the proportion of people

engaged in agriculture has decreased (72.6% and 79%; the percentage of business and trade has also

increased to 10.8% compared with about 4.8%. The ratio of income from wage / salaried workers also

increased significantly from 9.7% previously to 16.6%. The reseon leading the change is due to the

impact of the project, in the fact, project provinces are where implemented various projects funded by

the government, such as northern mountainous poverty reduction project, 30A programs, 135

programs ... and some other programs.

Page 22: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 21

Table 9: Average income of surveyed HHs

Subprojects

Surveyed population n (person

Monthly per capita income

Average income by sex of HHs (thousand VND)

Male Female

Son La - Hoa Binh Nho Quan 172 647 661 632

Thanh Hoá _ Vinh 42 663 667 660

Hai Duong 220kV Substation 10 975 980 970

Bim Son 220kV Substation 6 655 660 650

Tuyen Quang 220kV Substation 10 670 680 660

Son La - Hiep Hoa 500kV 824 672 683 661

500 KV Hiep Hoa SS 154 975 890 830

Thuong Tin - Kim Dong 220Kv 123 989 987 936

220 KV Kim Dong SS 35 879 857 810

1376 792 785 757

Source: Socio-economicsurvey by LIC, August, 2014

38. Average income of the interviewees has difference between areas of project implementation,

for example, in Thuong Tin Kim Dong sub-project has the highest average income of 989 thousand

VND / person / month, whereas 2 subprojects of Son La - Hiep Hoa and Bim Son, Thanh Hoa, have

the lowest income, respectively 670 thousand and 672 thousand VND / person / month. Besides, the

average income for men is higher than women around tens of thousand VND / month.

Table 10: Average income by ethnic group

Subprojects

Surveyed population n (person

Average income by ethnic group of HHH(thousand VND)

Kinh Muong Thai Hmong Sán Dìu

Son La - Hoa Binh Nho Quan 172 682 419 278 70 0

Thanh Hoá _ Vinh 42 663 0 0 0 0

Hai Duong 220kV Substation 10 975 0 0 0 0

Bim Son 220kV Substation 6 655 0 0 0 0 Tuyen Quang 220kV Substation 10 670 0 0 0 0

Son La - Hiep Hoa 500kV 824 694 698 555 350 320

500 KV Hiep Hoa SS 154 980 0 0 0 0 Thuong Tin - Kim Dong 220Kv 123 936 0 0 0 0

220 KV Kim Dong SS 35 879 0 0 0 0

1376 793 124 93 47 36

Source: Socio-economicsurvey by LIC, August, 2014

39. However, there was difference in income per capita among ethnic groups when Kinh and

Muong people had highest monthly income of VND 694,000 and VND 698,000 per person

respectively while Hmong people only got around VND 350,000/person/month.

40. The surveyed female household heads accounted for 26.5% of surveyed people and the rest

73.5% was occupied by male household heads. The percentage of household heads engaged to

Page 23: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 22

agriculture was 81.6% while that of hired labors was 17.6% and only 1% of surveyed household heads

were traders but they only had small stores selling necessary goods with limited capital.

41. The survey reveals no difference in access to social, educational and health care services

among ethnic groups. Such social services were accessible to all surveyed people in their living

places. Besides, ethnic AHs were also entitled with Governmental preferential policies for ethnic

minority groups and for northern mountainous region.

42. Relocated HHs also rebuilt their houses upon their desires as well as in line with their own

traditions (stilt house for Muong and Thai people). HHs having their assets or agricultural land

affected often spent a part of compensation on repairing their houses. The survey showed that most

AHs still have agricultural land for cultivation and thus, productive land for AHs is still guaranteed.

43. During public consultation, most AHs attended activities in their living places organized in

village meetings or local festivals and ceremonies. Most surveyed people admitted that there was no

impact caused by the project on their traditions and culture.

Box 1: Local citizens 'opinions about the project impacts

“The ethnic minority people now benefit from many Government’s preferential policies such as periodic provision of rice, money etc on annual basis. No matter which ethnic group they are from, all little

children are encouraged to attend school and arranged into the same class without any discrimination.

In addition, ethnic people are also provided with medical insurance certificate so that they could visit

the district’s general hospital when needed at no charge etc” In-depth interview, Project staff in

Thuong Coc commune, Lac Son, Hoa Binh

“The transmission line causes no impact on Muong people’s traditional culture as even in the event of relocation, we still live near our old living place. We might be afraid of being infected by the magnetic

field” In-depth interview with Bui Van Tien, Phu Cuong commune, Tan Lac, Hoa Binh

“We still have farming and forest land as the project only acquired small area for poles and there are some areas on which perennial tree plantation is limited given possible impact cause to the gridline.

Compensation receivers also rebuilt their houses or rehabilitate their kitchen, yard for better living

conditions etc ” In-depth interview with Ngan Van Phan, Mai Son, Son La.

(Source: Socio-economic survey by LIC, August, 2014)

4.1.3. Livelihood and Subsistence Economy

(i) Agricultural activities

44. The agricultural activities of HH concentrated in activities such as: (i) cultivation; (Ii) livestock.

Agricultural production is the main economic activity of HH. Therefore, agricultural activity is the main

source of income of the local people in general and in particular project areas. The survey data

showed that 66.6% of those surveyed have a job and main source of income from agricultural

activities. Agricultural production activities usually associated with crops such as rice, maize, cassava

or timber tree from forests. Other products include bamboo and other plant species diversity. Howeer,

now, resources are being overexploited.

(ii) Livestock raising

45. Livestock is also an active production, however breeding purposes only small scale and mainly

used for their family. The main livestock inlcude cattle, goats, pigs and chickens, however the qualily is

small, mainly serve for needs of the family, or the livestock accordingly traditional methods, so the

value is not big. Pets play an important role in the income of households, an average of 2.4 buffaloes /

cattle / household. Livestock graze freely; there is not hay or pasture is planted. The average time for

livestock is by 2.7 pigs in a year. Cattle manure, poultry are often used as organic fertilizer.

Page 24: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 23

(iii) Forest resources

46. The income from forest and non-timber products also brings significantly income for HHs.

Forest land assigned to households for management and using in accordance with the law. Local

people plant crops such as bamboo, acacia. In addition, people also make use of non-timber products

such as rattan ... to cater to the needs of traditional crafts.

(iv) Non-agricultural activities

47. The non-agricultural sources of income: the business of HH is small scales with products such

as basic necessities, daily living supplies. In addition, some households do traditional handicrafts such

as rattan, bamboo weaving, baking, art ... purchase agricultural and forestry products of the household

4.1.4. Houses and House styles

48. According to the survey result, the ownership of housing includes wooden housing, bricks or

traditional housing. Basically, accordingly characteristics customs of their people: Kinh often build

bricks housing with or flat roofs, groups of Thai, Muong often use stilt houses, and the San Diu, Hmong

groups use the wooden housing with the architecture of their ethnicity.

52. The surveyed resultes presented that the ownership and the form of the households changes in

comparision with pre-project implementation. Especially for relocation HH. Most of resettlement HH

have rebuilt a new house, in the resettlement areas, as well as their land accordingly their needs. The

observation results showed that the new housings of resettlement HH are better than the on in the

past. Working with these HHs, they said they felt happy about their new home. Households only have

affected land, property, some HH use the money to repair and rebuild their homes.

4.1.5. Access to Infrastructure and Social Services

49. 23 resettlement sites of the sub-projects are built in project communes and they are near with

old places. Therefore, the access to basic social services, including health, transport, electricity and

schools are favorable. Moreover, in the project provinces, during 10 years of project implementation of,

the government of Vietnam has implemented some programs and projects to improve the

infrastructure, inclduing transportation projects, Northern mountainous poverty reduction programs, the

new rural program, 135, ... has invested in subprojects districts / communes. All districts and

communes have inter- district and inter-commune road. Besides, many districts also developed

waterways, transported by boat, raft for commodities such as bamboo, wood or sand mining in the

river ....

53. Health services: All the project communes have health stations, districts has the general hospitals

to meet the health care needs of local people. Households can access health services through this

channel. Also, communes and villages also have other private clinics else.

50. Market: subproject areas have marketplaces for trading, buying and selling. Markets are

arranged depending on the local and meetings rotate periodically. People can access the market via

the transport system of communes and districts.

55. Schools: communes have nursery schools, primary schools, secondary school and high

secondary school. The high secondary school is arranged for the village cluster or in a location

convenient for transportation. Most of the people in these areas have access to education, especially

for young people.

4.1.6. Participation in neighborhood or community groups

51. The project's impact caused by T/L is small and mostly relocated households selected self

relocation. For the displaced households in resettlement areas, HH are consulted to select locations to

Page 25: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 24

build resettlement areas and entire resettlement sites are located in the communities of the displaced

households, so the displaced people are not much affected by the loss of relationships, the

connections in the community.

52. The survey results presented that 80% of respondents participated in the mass organizations

at the local movement: farmer’s union, women union, youth union, veteran’s union.The project

information are also informed and disclosure in community meetings, thus HH know fully about the

project information.

4.2. Compensation and resettlement

4.2.1. Resettlement and livelihood restoration

53. The compensation for land affected by project was applied regulation and law. After the 2003

Land Law put in use, Project province People’s Committees issue the regulation related to annual unit

price of land, trees and crops and structures for compensation calculation. The DMS results presented

that there is not business affected by the project.

54. During the resettlement of AHs, they had been informed about the involuntary resettlement

policy and involved in selecting and preparation of resettlement sites. The RPs and compensation

plans had been disclosed to APs during community meetings and loudspeakers. APs were also

consulted on safety while working under the high voltage transmission lines.

55. DMSs were conducted for the assets of AHs (land, crops and trees and structures). Most of

the assets were adequately counted (some case of inadequacy, additional DMS was carried out upon

the request of AHs).

56. Compensation plan for AHs included the amounts for compensation and assistance for AHs

which were very clear and detailed (compensations for land, crops and trees, and structures) and the

assistance together with compensation were paid to all AHs.

57. Payment of compensation and assistance was conducted in a public and transparency way, at

the coordination and witness of NPPMB staff and local staff as well as AHs. Documents related to the

project were relayed to the AHs, both the husband and wife had been signed in the payment receipts.

58. In general, the payment of compensation did not meet with difficulties thanks to consultation

and consensus with the local people in advance. There was no incident during compensation.

59. Payment of compensation was conducted in line with the procedures and processes (with the

participation of local leaders, Center for Land Fund Development, NPPMB, Bank, Police …).

60. All entitlements of APs including compensation and allowances have been delivered to them

prior to displacement from their houses, land, and assets. In some cases, where construction of

resettlement site could not be completed before displacement the rent has been provided for relocated

household until a plot has been allocated in the resettlement site. For vulnerable affected households

including poor and ethnic minority people, addition to compensation, special allowances have been

provided to help them improve their socio-economic status. Severely affected households have been

also provided allowances of job training and subsistence so that they have restored and improved their

living standard.

61. After receiving the compensation payment, during consultation process of RP implementation,

all relocation HH wanted to build thier new houses accordingly their needs. For households received

plots in resettlement sites, they carried out building houses. Some households have not built or selling

to another person. For households who did no receive plots in resettlement sites, they built houses on

the remaining land. LIC found that, there is not impact on livelihood restoration for households in

Page 26: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 25

resettlement sites or built houses, in the fact, the resettlement sites are near the old place where they

live in the past.

Table 11: Resettlement status of AHs in subprojects

District

Total AHs AHs

Compensated

Notes Total

HH Relocati

on

Nho Quan - Son La - Hoa Binh 500kV T/L

Son La province

Muong La 120 4 120 4 HHs self-resettled Complete

Mai Son, 94 18 94 12 HHs self-resettled Complete

Yen Chau 245 18 245 9 HHs moving voluntarily, 9 HHs voluntarily resettled in concentration

Complete

Moc Chau, 220 34 220 34 HHs moved houses Complete

Hoa Binh province

Hoa Binh city

444 61 444 Complete

Cao Phong 238 31 238 30 HHs required to resettle separately

Complete

Tan Lac 873 68 873 60 HHs required to resettle separately

Complete

Mai Chau 54 9 54 in which : 7 hộ sử dụng đất công ; 9 HHs self-resettled

Complete

Lac Son 444 36 444 36 HHs required to resettle on their land

Complete

Yen Thuy 171 29 171 24 HHs required to resettle on their land

Complete

Ninh Binh Province

Nho Quan 8 8 8 Complete

Tuyen Quang 220kV substation

Yen Son 93 4 93 2 HHs received land for resettlement

Complete

Son La- Hiep Hoa T/L

Muong La, 284 12 284 12 HHs self-resettled Complete

Mai Son 97 21 97 21 HHs self-resettled Complete

Bac Yen 195 31 195 31 HHs self-resettled Complete

Phu Yen 447 26 447 26 HHs self-resettled Complete

Tam Nong 553 26 553 17 HHs self-resettled and 9 HHs in Hien Quan RS

Complete

Phu Tho town

196 23 195 23 HHs in Ha Thach RS

Not yet

Phu Ninh 215 59 215 05 RSs Complete

Song Lo 175 33 175 03 RSs Complete

Lap Thach 221 14 221 01 RSs Complete

Tam Duong

368 98 368 11HHs self-resettled and 10 RSs

Complete

Tam Dao 82 24 82 01 RSs Complete

Binh Xuyen 137 9 137 01 RSs Complete

Pho Yen 444 69 444 54 HHs self-resettled , 02 Complete

Page 27: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 26

District

Total AHs AHs

Compensated

Notes Total

HH Relocati

on

RSs

(Source: Socio-economic survey by LIC, August, 2014)

4.2.2. Before and after land acquisition and resettlement comparison

62. The survey results presents that there is a change both income and job of AHs.The socio-

economic survey of RP implementation shows that the average incomes of AHs is 600 thousand /

person / month. At the time of evaluation, the average income has increased by about 792 thousand /

person / month. In the fact, these households have used the compensation payment to continue

agricultural production and investment in farming or business.

Table 12: Comparision income ratio, occupation ratio before and after project implementation

Before (%) After (%)

Income from business/trade 4,8 10,8

Change for occupation structure

Agriculture 80,5 68,2

Service 9,3 12,5

Salary/Hired worker 10,2 19,3

Source: Socio-economicsurvey by LIC, August, 2014

63. The survey results present that the change of job structure is quite obvious for AHs. The ratio

of employees has increased from 10.2% to 19.3%, the ratio of agriculture reduced, accounting for

68.2% of total surveyed households. In project areasl, in addition to L2225 project, there are some

programs and projects, this led to this change. For example, in Hiep Hoa 500kV station subproject,

who are beolw 40 year-olds or younger were involved in secondary job, such as masonry, motor-bike

repairment, carpentry ... Those people who are in the age group of 20-30 often do as workers for

industrial areas such as Yamaha, Samsung, or Pho Yen industrial zone ...

Box 2: Model of change of job structure in Hiep Hoa – Bac Giang

Currently, Bac Giang has 39 traiditional handicraft villages (to the end of 2015, 2 more villages) recognized by PPC; including 14 traditional handicraft villages, in addition to nearly 14.3 thousand of handicraft workshops with processing industries such as agriculture and forestry product; mechanical production; building materials; crafts, weaving, paper making do ... attract significant local labor and labor from other places. In the past, mostly rural labor resources have low education levels, seasonal workers are low disciplined. By implementing the criteria of employment and education structure mentioned in the national criteria of new rural has contributed to reduce the percentage of workers in the field of agriculture - forestry – fishery, it is expected at the end of 2015 was 56% ; the trained-employment rate reached 47% (up 13.5% compared to 2011), in which trained worker reached 30.5%, meet 2015 target sooner 1 year. This is annually addition labor resource and provide to local enterprises.

The success of the expansion and development of industry, handicraft and traditional craft villages has contributed to change of economic and labor structure, land accumulation and consumption of agricultural products. This is an important making change of economic and labor structure, the ratio of agricultural labor is transferred workers. This helps to improve income for rural people.

Source:http://baobacgiang.com.vn/bg/kinh-te/151648/xay-dung-nong-thon-moi-o-bac-giang--thuc-day-cong-nghiep--dich-vu--lang-nghe.html

64. There are employment opportunities in garment and other factories in the provinces/ districts

and there are existing training courses offered by the Department of Labor, Invalids and Social

Page 28: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 27

Affairs (DOLISA) to help members of AHs to obtain employment. However, shifting to non-

agricultural work remains a challenge for people who are more than 50 years old due to the

preference of factories to hire younger applicants. Trading is another opportunity, but would require

good planning, location and capital. Because of these challenges, many older APs are resigned to

the idea of not finding alternative jobs, and relying only on the capacity of the younger members of

their HHs to find better paying and sustainable jobs, thereby adding economic strain to the

household.

65. The success of resettlement planning in restoring living conditions is thus inextricably bound

to income restoration, and effective income restoration in turn necessitates a clear understanding of

livelihoods, capacities and risks faced by those displaced.

66. The crucial role that women play in the socio-economic well-being of the HH can often be

overlooked when AHs’ livelihoods are only examined at the HH level. The nature of women’s work can often be quite different to that of men. The implications for resettlement are that these

differences in the general characteristics of productive work mean that women can experience

different risks and impacts on livelihoods compared to men. Work located close to the home tends to

be the income source most severely affected by resettlement. Women’s separate incomes, while generally lower than those of men, are an important element for empowerment within the HH and

make a significant contribution to HH wellbeing. Overall, lost incomes for women pose significant

risks in terms of increased time, poverty, disempowerment within the family as well as

impoverishment of HHs.

4.3. Restoration of livelihoods

4.3.1. Income restoration models/programs

67. Following Decision No. 1956/QD-TTg dated 27 November 2009 of the Prime Minister, and

Decision No. 1201/QD-TTG dated 31 August 2012 of the Prime Minister approving the National Target

Program on Employment and Training for the period of 2012–2015, local authorities in subproject area:

Organize annual surveys on labor supply and demand and develop a database of households within the communes;

Established a steering committee to oversee the implementation of the employment and training plan in the commune;

Conduct information dissemination on the vocational training scheme for rural laborers;

Guide departments, divisions and missions in implementing the vocational training program; and

Monitor the implementation of vocational training classes in the commune.

68. Vocational training and job referrals have been implemented widely, resulting in significant

improvement in skills development, job creation, and increasing income of people in the commune.

This program is carried out for people under working age affected resulting from land acquisition by

various projects in the province/district. Members of AHs) losing agricultural land under the Project

are eligible to participate in one short term vocational training course (up to 6 months) free of charge.

The main State provider of vocational training is the Provincial DOLISA as stated in Decision

1956/QD-TTg.

69. In the fact, income restoration program for the AHs has not implemented in project area. The

reason is that the ratio of severely affected households is small (less than 10% of total AHs) and not

focus (only 21 resettlement sites of Project). Aside from compensation for tác assets Costs Applying

the unit stipulated by PPC, những HHs received assistances phụ thuộc on Regulations in each

province, như relocation assistance, and temporary housing assistance, and finding new residence and bonus for themselves.

Page 29: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 28

70. In the project areas have some programs and projects, includinge 30A, 135, ... of the

government. Therefore, programs of job training, job change have combined into these programs. AHs

have not only received support from L2225 project but also receied from nother projects done in local

areas.

Table 13: Allowances of Project for AHs

Subprojects

Assistance

self-resettlement

assistance

Relocation

assistance

Incentive for

relocation by progre

ss

Resettlement house

leveling

Occupation

change and life stabilization

Assistance for house rent

Assistance for vulnera

ble HHs

Assistance to HHs

temporally affected during project

construction

Assistance to HHs

electric Son La- Hiep Hoa 500 KV T/L x x x x x x x x x Hiep Hoa 500 KV substation

No require

No require x

No require x x x

No require No require

Kim Dong 220 KV substation

No require

No require x

No require x x x

No require No require

Thuong Tin- Kim Dong 220 KV T/L

No require

x x x x x x x

No require

Bim Son 220 KV Substation

No require

No require

No require

No require X

No require

No require

x No

require

Tuyen Quang 220 KV Substation

x x x x x x x x No

require

Son La-Nho Quan-Hoa Binh 500kv T/L x

No require

x

No require x x x x

x

Thanh Hoa - Vinh 220kv T/L

No require

No require

No require

No require x

No require

No require x

No require

Hai Duong 2 220 kV Substation

No require

No require

No require

No require

x No require x

x No

require

Source: Socio-economicsurvey by LIC, December, 2015

71. The vulnerable groups had chances of income improvement in construction time (hire local

labour) or receive allowances from the project, such as vocational training and particularly allowance

for vulnerable groups and priority access to microfinance loans for economic development. In general,

vulnerable groups felt quite happy with the project allowance. The implementation of the project

activities has brought quite sustainable opportunities for vulnerable groups. They can have access to

various resources through local organizations and unions

72. Generally, resettled HHs received same assistances such as relocation assistance,

assistance to self-resettled HHs, incentive for relocation by progress; assistance for occupation

change and job creation, assistance for electricity fee, assistance for vulnerable HHs etc…Mostly

HH did have any complaint (excepts HH of Mr Trần Thanh Tùng under Sơn La – Hiêp Hoà

subproject).

73. For the resettled HH received plots in resettlement sites felt happy, because the location is not

far from their old home. Thus, there is not difference for their relationship and livelihood. These

households who did not receive land in resettlement sites often built houses in the remaining area,

they also receive compensation amount as well as project allowance.

74. Those HHs only having their land and assets affected were provided with assistance for

occupation change and job creation. In addition, HHs who were temporally affected during project

construction were provided with assistance for their affected assets (for example: soil, sand filled on

Page 30: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 29

productive land, damages caused to trees etc). All AHs did directly receive compensation in

payment meetings with participation of NPPMB, DCRB and local commune/village’s authority at the appointed time which was notified to HHs. The receivers all signed for confirmation in the list of

compensation payment receivers. For households losing of asset, land, crop and tree, compensation

payment completed. There is not any compalints (except five/5 HH of Trại village, Lê Lợi commune,

Thường Tín district, Hanoi).

75. The project had no impacts on public and spiritual works and thus, no impacts on the

community’s benefits in local activities. Therefore, traditional and cultural features suffered no influence.

Table 14: Status of compensation implementation of L2225 subprojects (up to December/2015)

Subproject

Total AHs

HH Compensation Current Status Total

HH Relocation

Thanh Hoa-Vinh 220kV T/L

950 0 950 All AHs received compensation

Son La- Hoa Binh- Nho Quan 500kV

2911 316 2911 All AHs received compensation

Tuyen Quang 220 kV substation

93 4 93 All AHs received compensation

Bim Son 220 kV substation

24 0 24 All AHs received compensation

Hai Duong 220 kV Substation

90 0 90 All AHs received compensation

Son La- Hiep Hoa T/L

4115 451 4114 Tran Thanh Tung did not receivecompensation payment andallowance

500 KV Hiep Hoa substation

770 0 All AHs received compensation

220 KV Thuong Tin- Kim Dong T/L

607 0 602 05 HH of Pole No 32 in Xom Trai, Tu Van hamlet, Le Loi commune Thuong Tin district, Hanoi did not receive compensation payment

220 KV Kim Dong substation

176 0 176 All AHs received compensation

Source: NPMB report, December, 2015

76. In order to ensure the entitlement of severely AHs, NPPMB should closely coordinate with

local authority to prepare a list of severely AHs which then shall be sent to District Agriculture

Extension Center (agriculture extension services) and the district Vocational Training Centre

(training).

4.3.2. Restoration of livehoods

77. The income restoration has been implemented through allowances in cash as RPF required,

including: job training, job change for wholly project.

78. Vulnerable Groups: According to the RPF, vulnerable groups include the (i) female-headed

households with dependents; (ii) disabled household heads; (iii) poor households; (iv)landless

elderly households with no means of support; and (v) households without security of tenure.

Vulnerable group have to receive a cash allowance equivalent to 30 kg of rice per family member

per month for a minimum period of six months as per RPF. LIC found the number of vulnerable

households through DMS data. The data of vulnerable groups presented that (i) Son La-Hiep Hoa

Page 31: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 30

T/L has 146 poor HHs; (ii) Hiep Hoa substation has 95 poor HH; 40 female-headed HHs ; (iii) Kim

Dong substation had 15 poor HH; 42 female-headed HHs and (iv) Thuong Tin- Kim Dong T/L had 3

poor HHs, 40 female-headed HHs and these two subprojects had none ethnic minorities HHs. They

received a specific allowance equivalent to 2.000.000 VND/AH.

79. For households losing of asset and land, the remaining land is enough to produce, there is not

much difficulty. Resettled HHs has disruption due to housing rebuilding. However, LIC found, the

remaining land area is combined with project allowances, their livelihoods are restored.

80. It can be seen that, some findings related to livelihood restoration of subproject presents

following paragraphs:

Son La - Hiep Hoa subproject: Households received allowances for r livelihoods

restoration. In this sub-project, there were some households losing more than 10% of

productive land. However LIC found, their livelihood restored. The infrastructure works

in the resettlement sites completed and handed over to the household here. Currently,

only case of Mr. Tran Thanh Tung still lives under operated transmission lines, and has

not built new house in resettlement sites. Phu Tho town PC coordinated with

stakehoders settle this case.

Hiep Hoa 500kV Substation subproject: completed payment of additional alowance for

200 seriously affected households losing more than 10% of total gricultural land in the

end of 2013. The surrounding fence of station made difficulties for sewerage. Thus,

stakeholder should study to construct a pumping station to ensure drainage in rainy

season. Besides, the operation of the substation use regular light system at nigh, this

attracts worms, butterflies and affects agricultural production. NPPMB should consider

to solve this situation.

220kV Thanh Hoa - Vinh T / L: Completed compensation and assistance payment for

households in 10 districts / cities in 2 provinces of Thanh Hoa and Nghe An.

220kV Tuyen Quang substation: Completed compensation and assistance payment,

especially severely AHs and 04 resettled AHs (issued LURC for resettlement plots)

based on DMS result. Both husband and wife were named in LURC. Besides, some

HH felt unhapply for temporarily affected land used by the contractors, because the

contractor used land without their acceptance ( they provided compensation payment

for affected asset on land).

500kV Son La - Nho Quan – Hoa Binh T/L : Completed compensation and assistance

payment.

Hai Duong 220kV station: Completed compensation and assistance payment

220kV Bim Son: Completed compensation and assistance payment (including 2 HHs

of Nguyen Thi Nhuong and Le Thi Voi). The contractors handled land spill out some

land in the construction time.

220kV Kim Dong: Completed compensation and assistance payment

220kV Thuong Tin - Kim Dong: Completed compensation and assistance payment. AT

this moment, only 5 households in Tari villafe, Le Loi commune, Thuong Tin District

requires land for land. LFDC has coordainted with stakeholders to soon settle.

81. The full package of compensation resulted in all interviewed households being able to live

better condition than previous. The AHs received compensation for the structures and no deductions

were made for the value of the salvageable material from their former houses. It was noted that new

houses built were larger and of better quality than their original houses. For Son La – Hoa Binh –

NhoQuan T/L, Son La – Hiep Hoa T/L and 4 HHs of subproject Tuyen Quang 220 kV substation,

Page 32: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 31

some of the affected houses have been relocated onto remaining land owned by the affect

households. Therefore, compensation provided to AHs appears to be satisfactory. With the

compensation received, AHs were able to buy an equivalent plot of land in a RS or at an individual

site in the same vicinity. They were also able to build a larger house and of better quality.

Box 3: opinion by local citizens in project area

‘In Tien village Thung Nai commune, many affected HHs converted land use purpose from farm land

to residential land. Districts must be adjusted annual price fluctuations. The Red Book is done in

parallel with to compensation payment for land and new house construction.’ (Dinh Van Thanh, CPC chairmen Binh Thanh Commune, Cao Phong district, Hoa Binh province)

"You can see, most households which have been relocated have relocated onto remaining land.

Relocated houses were reconstructed on the AH’ land owned by themselves and they were safe and

far away the transmission lines.Where AHs were relocated off their own property, they were able to

use compensation money to purchase land in the immediate vicinity of their original house, and to

build a new house’’. (Vu Dinh Viet, Chairman of DRC and Vice Chairman CPD of Cao Phong

district, Hoa Binh province.)

((Source: Socio-economic survey by LIC, August, 2014)

82. In summary, most HHs were satisfied with the project compensation and assistance. Self-

relocated HHs did reconstruct their houses, which were mostly better than their old one. There was

no enterprise/trading HH affected by the project. Vulnerable groups were able to access job creation

opportunities via project compensation and assistance.

83. Issuanceof Land Use right Certificate (LURC), which serves as ownership document for the

new plot of land, in a resettlement site or for individual plot, has not been provided to all relocated HH

due to slow process. Currently, only 8 RS completed issuance of LURC.

Table 15. Status of Issuance LURC

No List of Resettlement site No of plot Status of issuance of

LURC (December 2015)

I/I/ PHU THO 71

1 Hien Quan, Tam Nong dis 11 Completed

2 Ha Thach 4,Phu Tho town 10 1 AHs had LURC

Ha Thach 11,Phu Tho town 13 7 AHs had LURC

3 Phu Loc commune, Phu Ninh dis 6 Not completed

4 Phu Nham commune Phu Ninh dis 6 Not completed

5 Phu Ninh commune, Phu Ninh dis 14 Not completed

6 Tien Du commune, Phu Ninh dis 5 Not completed

7 Tu Da commune, Phu Ninh dis 6 Not completed

II/ VINH PHUC 187

8 Yen Thach Song Lo dis 13 Completed

9 Dong Thinh 1, Song Lo dis 12 Not completed

10 Dong Thinh 2, Song Lo dis 20 Not completed

11 Xuan Loi commune, Tam Duong dis 13 Completed

12 Tien Lu commune, Tam Duong dis 5 Completed

13 Dong Ich commune, Tam Duong dis 2 Completed

14 An Hoa commune Tam Duong dis 6 Completed

15 Noi Bai - Lao Cai resettlement site

Page 33: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 32

No List of Resettlement site No of plot Status of issuance of

LURC (December 2015)

Roadsize 2C Tam Duong dis 11 Not completed

Le village, Tam Duong dis 1 Not completed

Kim Long, Tam Duong dis 2 Not completed

16 Dong Ban, Tam Duong dis 7 Not completed

17 Long Son Tam Duong dis 2 Not completed

18 2C street Not completed

19 Go village Tam Duong dis 45 Not completed

20 Village No 8 Tam Duong dis 16 Not completed

21 Trai Khong, Tam Dao dis 24 Completed

22 Trung My commune, Binh Xuyen dis 8 Completed

III/ THAI NGUYEN 12

23 Trung Thanh, Pho Yen dis 7 Not completed

24 Thuan Thanh, Pho Yen dis 5 Not completed

(Source: Socio-economic survey by LIC, December, 2015

84. For the issuance of LURC of resettled households in resettlement sites, as LIC knows that

Department of Natural Resources and Environment of District (or LFDC) is repsonsible for issurance of

LURC. However, the procedures for change of land use purpose local needs appraisal, thus, this leads

to extended time. In addition, some resettled households said that they do not need to use LURC due

to in the process of life restoration, so, the time of LURC issurance may take longer than they

expected. Currently, local government has mobilized quickly households to soon complete the

procedure to LURC issurance, to ensure their entitlement.

4.4. Public, participation, consultation and Grievance resolution

4.4.1. Public Consultation, Disclosure, and Participation

85. The main objectives of information disclosure, stakeholders participation and consultation with

APs aim: (i) provide AHs project information, both project components and operation; (Ii) collect

information on the needs and desire of AHs and affected communities, their views to project policies

and activities; (iii) mobilize the cooperation and participation of AHs in the proposed activities related to

the preparation and implementation of RP; (iv) ensure AHs can participate and express their direct

opinions to income and life restoration; and (v) ensure transparency in the process of land acquisition,

relocation and life restoration.

93. The information disclosure has been made for all AHs. AHs understand fully about the

implementation project as well as the grivance mechanism, compensation and allowance of the

project. However, the implementation of information disclosure is not uniform and frequently, because,

project areas goes through many provinces/districts/communes. Mostly commune staffs are part-time

workers ... Overall, the project gets effectiveness to provide the information to AHs.

94. The consultation results present that, the meeting was held for AHs. In addition, the project

information is combined into community meetings, village meetings. The meeting time is flexible and

they are usually in the evening to ensure the participation of AHs. Participants in community meeting

included both men and women. These meetings often held in house of the village heads or community

house. LIC reliazed that, all AHs fully informed about the project and the project's impact

95. At the project area where ethnic minorities live, in addition to arrangement of suitable meeting

Page 34: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 33

time, the use of language is also particularly considered. In the fact, LIC reliazes that mostly ethnic

minorities in the project areas can understand and speak Kinh language. The project areas have also

implemented many projects/program so they know fully about project cycle. In addition, selling of

agricultural products also helps to reduce the gap of language of EMs group in the project area.

Therefore, Kinh language is used in community meetings (only a small number of elderly people, the

use of Kinh language is limited - such as project staff used local interpreters to consult with them .

96. In addition, project information is often consulted on compensation and resettlement regulation

according to the current regulations of Vietnam. Very few people can understand ADB policy. Local

AHs only care about the money and where are their resettlement plots?

97. AHs also involved in DMS and they signed in the inventory minutes of the project. However,

the inventory records can present a part of affected asset, not clarify that households belonging to

which groups (vulnerable households, resettled households ...). Thus, LIC met some difficulties to

check allowance accordingly project RPF.

4.4.2. Grievance Resolution

86. During the consultation process, project staff informed grivance mechanism for affected

households. Besides, during the DMS, to avoid complaints, public disclosure was made at the office of

CPC. Since then, complaints will be collected and processed, resolved in the meeting. These

complaints often involve to the lack of inventored assets and additional requirements. Mostly these

complaints settled.

87. According to the regulation of the Law on Complaints in 2011, and Decision No 75 on the

implementation of the Law on Complaints, all complaint must be recorded to solve. The settlement

results must be publicly posted at the CPC’s office Howeve, mostly sub-projects are not carried out this

process, working with District Compensation Board of the Project presents that the implementation of

this issue is not good. Besides, NPPMB did not consider this issue, thus, LIC met difficulties to

synthese the complainants.

88. Some problems during the compensation, resettlement and site clearance of the sub-projects

are as follows: (i) provision of allowance for 83 vulnerable households in Hiep Hoa substation, (ii)

compensation for small and not viable remaining land area affected by Thuong Tin-Kim Dong

transmission line, (iii) disagreement of 16 AHs on low compensation price for land in Nghi Loc district,

Nghe An province and Nong Cong district, Thanh Hoa province under Thanh Hoa-Vinh transmission

line, (iv) complaint of Mr. Tran Thanh Tung about compensation price and relocation in Phu Tho town

under Son La-Hiep Hoa transmission line, and (v) issuance of LURC for relocated HHs. At time of this

mission, all above pending issues have been resolved by responsible agencies, except issuance of

LURC:

83 vulnerable AHs have been provided allowance by cash equal to 30kg of rice per person per month

for 6 months for all members of the HHs.

In Thuong district, Ha Noi PC has approved compensation plan for the small and infeasible remaining

land area, payment for AHs has been done.

Nghe An and Thanh Hoa provinces have recruited independent appraisers to evaluate the market land

price and paid compensation for the complainants according to the market price.

NPPMB agreed to pay 100% compensation amount for Mr. Tran Thanh Tung’s affected house (not 50% as proposed). He agreed but still asking allocation of 3 plots in resettlement site for his household

whereas he is eligible for one plot of 400m2 only. Currently, he is building a new house in the

resettlement site.

Page 35: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 34

Box 4: Feedback of people on grievance redress

"We sent our complaints to the commune. The commune endorsed and relayed to the project about our case. We

waited for about 30 days, before we received feedback from the Project on the assistance policy for our family. We

agreed with the compensation rate and handed over the site to the construction unit” (Tran Van Lam, Tung Lam

commune, Tinh Gia district, Thanh Hoa Province).

"Out family mostly doing agriculture. Now the land is acquired, we afraid that the farming is not enough. We want

land-for-land compensation to ensure the production. However, the project informs us that due to the local land

fund is not available so they cannot arrange land-for-land compensation. Also other agencies and organizations

visited us to talk to us about that. After sometime we agree because we think we should let go some of the benefits

to contribute to the work of the country” (Nguyen Van Thu, Dien Chau district, Nghe An Province).

"We ready to move, however we should have 3 resettlement lots, since our children got married still living with us,

so we need more land for them. Regarding affected land and assets, we want to be compensated properly

according to the law. We sent our letter to Provincial Peoples Committee of Phu Tho for consideration.” (Tran

Thanh Tung, Phu Thu town, Phu Tho Province).

(Source: Socio-economic survey by LIC, August, 2014)

Page 36: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 35

Table 16: All complaints in the subprojects L2225

Subprojects Issue How to resolve Agencies in charge Target

completion

date

Bim Son 220 KV Substation No written complaint logged

Tuyen Quang 220 KV

Substation

No written complaint logged

Son La-Nho Quan-Hoa Binh

500kv T/L

No written complaint logged

Thanh Hoa - Vinh 220kv T/L 2 HH in Tower position 125a (Dien Chau

District) want to receive land for land

compensation. For small areas, it may

bedifficult to provide land for land; in

addition, compensation for small areas of

land has been done by cash for the sub-

project

In Dien Chau District Nghe An Province

compensation for land is based on 2012

compensation rates

From tower positions 51 to 52(G9-G9a)

Nong Cong district 8 HHs refused

compensationbecause they do not agree

with current compensation price because

it is too low; Cong

From tower positions 116 to 118 (G20a-

G21a) Tinh Gia district, Thanh Hoa

province: 02 HHs claim to move out of

transmission line because they are afraid

their health may be affected by the power

lines.

If land for land is not possible,

NPT/NPPMB in coordination

with CARB Dien Chau to

provide explanation to these

HH in order for them to

accept cash compensation.

Document the consultations

and the results

NPT/NPPMB to ensure that

Dien Chau districtupdates

compensation rates based on

2013 rates and pay the

balance to the affected

households

NPT/NPPMB to ensure that

Nong Cong district updates

compensation rates based on

2013 rates and pay the

balance to the affected

households

NPT/NPPMB in coordination

with the CARB Tinh Gia

district to ensure that in the

NPT/NPPMB in

coordination with CARB

Nong Cong, Tinh Gia,

Dien Chau district

Complete

Page 37: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 36

Subprojects Issue How to resolve Agencies in charge Target

completion

date

CPC andAHs are informed

that the distance from the

houses to the power lines

poses no health impacts.

Hai Duong 2 220 kV

Substation

No written complaint logged

Son La – Hiep Hoa

transmission line Compensation of Mr. Tran Thanh Tung

(Phu Tho Province, Phu Tho Town)

Mr. Tran Thanh Tung refused compensation

and didn’t hand over his land to the project. He is still living under the transmission line.

According to legal documents, Mr. Tung is

living on forest land. He considers that he is

living stably and wants to be compensated

as for residential land. Compensation for

forest land is 35,000 VND/m2, while

compensation for residential land in RS is

70,000/m2. He required 3 plots of land free

in the RS. NPPMB/DCRB proposed to

provide free one plot of land in the RS of

400 m2 but he refused. AH have usually to

buy the plot of land. He lodged a complaint

to the Phu Tho Town Court which was

dismissed. He is living under the operated

line since 1 year.

In April, 2013 he lodged a complaint to the

Province Court which was also rejected.

Phu Ninh RS (Phu Tho Province, Phu

Ninh District)

- NPPMB to ensure that the

offer to allocate a plot of

land of 400 m2 in the RS

- NPPMB to compensate for

all other assets (trees,

crops, structures) at

replacement costs

NPPMB to confirm whether

the splitting of the family into

three separate households

was done before the cut-off

date. If so, two additional

households should be

provided two plots in the

resettlement site, otherwise,

the Phu Tho Town people’s committee should consider

selling the additional plots for

his family.

- NPT/ NPPMB in

coordination with

DPC Phu Tho Town

Pending

Phu Tho

Township

People’s Committee will

continue

tracking this

case.

Page 38: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 37

Subprojects Issue How to resolve Agencies in charge Target

completion

date

In Phu Ninh RS, there is risk of landslide

due to steep slope without erosion

protection. Landslide could affect properties

and infrastructures (drainage ditch).

NPPMB to study options to

protect slope against erosion

and implement these

protective measures.

Hiep Hoa SS No written complaint logged

220 Kim Dong SS No written complaint logged

220kV Thuong Tin – Kim

Dong T/L

05 households in Thuong Tin district did

not receive compensation since they

asked all their small and scattered

remaining land areas acquired since the

land area were not viable for cultivation.

Ha Noi PC has approved

compensation plan for the

small and unviable remaining

land area, payment for AHs

has been done.

NPT/NPPMB in

coordination with CARB

Thuong Tin district

complete

(Source : Socio-economicsurvey by LIC, August, 2014)

Page 39: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 38

4.5. Effectiveness of resettlement planning

4.5.1. Resettlement Objects

According to the Consultant’s assessment, agencies responsible for preparation of RP / DDR (VICA,

CEFACOM) conducted the resettlement plan rather than the actual situation. According to RP / DDR

and actual situation, there are 9309/9409 AHs for the project. In addition, resettled HH determined in

the first phase, this helps to prepare the capital, resettlement sites as well as implementation plan to

better support these AHs.

Table 17: Quantities of AHs by RP/DDR and actual

No. Subprojects RPs/DDRs Actual

AHs Relocated AHs Relocated

1 Bim Son 220 KV Substation 24 0 24 0

2 Tuyen Quang 220 kV Substation 93 4 93 4

3 Son La-Nho Quan-Hoa Binh 500kV T/L 2,911 316 2,911 316

4 Thanh Hoa - Vinh 220kv T/L 850 0 950 0

5 Hai Duong 2 220 kV Substation 90 0 90 0

6 Son La – Hiep Hoa transmission line 4115 438 4115 438

7 Hiep Hoa SS 770 0 770 0

8 220 Kim Dong SS 187 0 187 0

9 220kV Thuong Tin – Kim Dong T/L 269 0 269 0

Total 9309 758 9409 758

Source: Socio-economicsurvey by LIC, August, 2014

89. Subproject Son La-Hoa Binh- Nho Quan 500 kV transmission lines showed were that for this

transmission line resettlement activities have been well implemented. The seriously AHs are also

discussed and advised for their resettlement from NPPMB and DCRB. The AHs received

compensation for the structures and no deductions were made for the value of the salvageable

materials from their original house. It was noted that new houses built were larger and of better

quality than their original houses. DCRB also provided specific allowance to relocated HH to drill

wells. For Son La – Hoa Binh –Nho Quan TL, some of the affected houses have been relocated onto

remaining land owned by the AH. Compensation provided to AHs appears to be satisfactory. With

the compensation received, AHs were able to buy an equivalent plot of land in a RS or at an

individual site in the same vicinity. They were also able to build a larger house and of better quality.

Therefore, basically, in the subproject 500 KV Son La - Hoa Binh - Nho Quan, the social safeguard

requirements of the ADB have been well complied with. The construction component of subproject

was completed and the line put in use in December of 2010. The transmission line was fully

energized in November 2010 and has been evacuating power from Son La hydropower since

December 2010.

Box 5: Opinion on compensation for AHs in project area

‘‘In the past, I lived with my parent. When our residential land was affected, our family was compensated with some money and a piece of resettlement land. We were then supported to buy land to build a new house, so now I have a

new one. Now my wife and I only do business. I think we're very lucky’’ (Bui Van Tien, Tan village, Phuc Lai

commune, Yen Thuy district, Hoa Binh province).

“I received VND 600 million, (70% value of compensation) in May /2012. I used the money to buy my father's land. He half sold but also half gave me for free, so I had land to build a new house. I also received the remaining compensation amount. Although I have used all amount of compensation for house, but a new building is large and beautiful like this, we're glad to investment in this beautiful home” (Hoang Thi Duc, village 13, Kim Phu

Page 40: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 39

commune, Yen Son district, Tuyen Quang province)

(Source: Socio-economic survey by LIC, August, 2014)

90. Interviewed AHs confirmed that they were very happy, because the compensation provided

by the District/Project as well as the infrastructure provided allowed them to improve their living

conditions. Examples include that where two households lived in one house (parents and a son and

his family) both the parents and the son and his family were provided with land and compensated

and after that they can build two houses and operated live. The result is that for them, the post

project condition is better than the pre-project condition.

91. It is considered by LIC that the entitlements of AHs as well as relocated HHs were all

secured when they did receive compensation for their lost assets and assistances. Vulnerable

groups were identified and paid with assistance in accordance with decisions approving

compensation plans.

92. At the time of evaluation, in some cases, AHs who have stable incomes from some

employments, such as: staff, employee… can well settle down in their new accommodation. These AHs usually are civil servants for state offices, or working as permanent staff for private sectors. In

general, these AHs settled down well in their new accommodations, and did not complain much.

They also get used to the life in RS.

Gender and Ethnic Minority Issues

93. Monitoring results presents that stakeholders consultation and HHs interviews discussions

revealed that local women, generally are treated in an equitable way with males. Females/ ethnic

minority HHs are invited and actively participate in different social, economic events, meetings,

agricultural extensions, etc held in the communes. In the preparation of RP and DDR, women

attended in detailed measurement survey, community consultation meetings. This is to ensure that

all information and opinions can be collected and that they include the women’s perspectives. Women also presented when compensation payments are made to ensure that any decisions

regarding use of compensation monies will be open to decisions made by husband and wife. Sex-

disaggregated data was collected in the socio-economic survey and inventory of loss.

94. Regardless of fairly good status of women observed in the affected communes, to ensure

gender equity, the following points has been implemented to obey the gender strategy for the

subproject:

Ensure registration of land-use rights in the names of both husband and wife in instances

where households are allocated alternative agriculture and/or residential land.

Husband and wife attended to receive compensation payment from RC and local PPMU

95. Monitoring results didn’t find inequality in land holdings nor reasonable differences of subproject impacts between male and female.

96. Besides, the contractors hired female in subproject area for simple works at site, in which

woman also participated in odd-jobs in construction time (cooks for worker, auxiliary workers)

97. Son La has different ethnic groups live in the region, where the most populous ethnics

include Thai and Muong minorities, other named ethnic groups including Hmong and Dao. During

process of technical design, preparation of RP different measures and many efforts were taken by

NPPMB and its consultant, in conjunction with local authorities and concerned agencies, to minimize

land acquisition and resettlement impacts on the local population. The measures taken included

selection of route or alignment that crosses the residential, historical and preserved areas.

Page 41: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 40

98. There is no specific ethnic minority development plan prepared for Son La, Hoa Binh

province. In the fact, action plans applied for EM were mentioned and mixed in RP to ensure the

entitlement of EM.

99. Relating ethnic minority issues, there is notEM in 3 subprojects of 500 KV Hiep Hoa

substation, Kim Dong substation and Thuong Tin- Kim Dong T/L, except 500kv Son La- Hiep Hoa

hasEM (in Son La province)

100. During process of technical design, preparation of RP different measures and many efforts

were taken by NPPMB and its consultant, in conjunction with local authorities and concerned

agencies, to minimize land acquisition and resettlement impacts on the local population. The

measures taken included selection of route or alignment that crosses the residential, historical and

preserved areas.

101. There is not specific ethnic minority development plan prepared for Son La. In the fact,

action plans applied for EM mentioned and mixed in RP to ensure the entitlement of EM.

4.5.2. Executing Agency and Implementation Agency and RP implementation progress

102. Ministries, Departments: MOF, MONRE, MPI coordainted to provide guidance as required

laws.

103. Implementing Agency - NPPMB:

NPMB has strengthened implementation ability to and coordination for resettlement

activities through training courses by the project before proceeding. Project

Preparation Technical Assitance (PPTA) organized training courses for NPPMB,

training in combination with job performance.

NPPMB established Department of Environment and Society, specialized staff

qualified will monitor and implement resettlement, compensation activities, closely

coordinate with the project districts, the Council of Compensation and Resettlement

(CARB); and guide and support the districts/ communes. NPPMB are responsible for

preparing and implementing the RPs. NPPMB appoint at least 3 staff with social

science qualification and / or working experience in social safeguard to working with

CARB. If there is disagreement between CARB and NPPMB staff, NPPMB and

EVNNPT will participate to solve the problem if any.

However, during implementation of the project, due to overload work, the project

area extends on many provinces/districts and the number of staffs of Compensation

department under NPPMB is limited (26 people - Annex 5) and they are responsible

for many projects. Thus, complaints have not yet recorded fully. In general, NPPMB

solved arising problems during the project implementation.

104. People’s Committee at province/district level

PPC: direct departments or authorize the DPC to solve the problems in project

implementation.

District PC: as direct agency repsonsible for inventory, arrangement of resettlement

sites and livelihood restoration programme for AHs through CARBs. These CARBs

support PC at all level to implement compensation, allowance and resettlement.

Chairman of DPC is head of CARB of District and representative from Finance,

client, department of natural resoures and environment, CPC, AHs and other people.

In coordination with NPPMB, CARB set up compensation cycle for AHs: (i) inform

payment work plan for AHs at least 2 weeks; (ii) prepare the list of AHs and the

entitlement and compensation amounts for AHs; (iii) prepare 03 copies of

Page 42: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 41

compensation document (for AH, PPC and NPPMB); prepare and update the list of

AHs, including payment date and data. However, the munite of comaplants have not

yet recored fully.

CPC: as direct agency to coordinate with local people and CARB to implement

project. Basically, the CPC has completed the task.

105. RP and DDR preparation consultants : VICA and CEFACOM are agencies to prepare RP and

DDR for L2225 subprojects. Basically, these agencies have completed accordingly required TOR.

106. LIC: carry out basic survey and submit progress report once/6 months and give out

recommendations related to certificated issues after 6-12 months of resettlement activities

107. Project monitoring consultant: this is one loan project, thus, mobilize monitoring consultant and

improve capacity to ensure effectiveness of land acquisition. Monitoring consultants include a

international expert (working for a short time ) and a national expert (working for overall project)

108. In general, agencies implemented well proposed objectives. However, the enhance of capacity

is limited: only used for IEE preparation without resettlement.

4.5.3. Time frame and budget arrangements

109. As workplan and budget are sufficient to meet the objectives of this project. Based on the

approved RP, NPMB registried the capital plan for the implementation of compensation. The cost of

compensation is from the counterpart funds of National Power Transmission Corporation (EVNNPT).

110. Every year, based on recommendations of agencies, EVNNPT assess and assign the capital

plan for the unit members including full cost of compensation and site clearance for each sub project.

111. National Power Transmission Corporation uses annual, quarterly, monthly capital to prepare

the budget to meet the timely compensation implementation. When CARB has approval decision,

NPMB will report to EVNNPT to issue the cost for compensation payment.

5. LESSONS LEARNT

112. All subproject provinces have put a lot of efforts on undertaking compensation, site

clearance and all accomplishments have been analyzed above. DCRCs are very experienced in

compensation and resettlement in line with Government’s policy, if training on ADB’s policy is given, it is sure that they can handle it well too.

113. NPPMB is coping with a great deal of obstacles during the implementation of compensation

and resettlement which is attributable to the deficiency in fulfilling its responsibility in the project

activities at both provincial and district levels. The subprojects were carried out in significantly large

area which spreads through many remote areas; its staffing for compensation is insufficient which is

exacerbated by its plurality to lots of different subprojects so NPPMB has to hire consulting units for

compensation and assistance, it is the result why the quality management of these units leaves

much to be desired.

114. Information disclosure on Vietnam’s resettlement policy at local level has been carried out

relatively well; however, ADB’s compensation policy for this project has been yet made known to the

district level and especially AHs and other stakeholders at district level.

115. Compensation staff at the sample districts have not yet been trained on the ADB’s policy for compensation and resettlement under which NPPMB should pursue a plan to improve this issues;

Page 43: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 42

116. The information of Project policy and grievances mechanism has not been fully disclosed to

the APs.People also said that there is a need to inform them the complaint process before payment

of compensation amounts.

117. In order to facilitate women’s involvement in the project implementation process, LIC recommend that the requirements on gender which set out in the Resettlement Plan should be fully

complied with.

118. NPPMB has not provided enough guidance and/or supervision at all stages of the ADB’s resettlement process, as well as there is an absence of external independent monitoring and

evaluation of either activities or outcomes.

119. From starting every project, NPPMB and stakeholders should be together introduction of

livelihood programs on seriously affected HHs and vulnerable groups in project regions.

5.1. Monitoring and Evaluation

120. For external monitoring, at the time of assessment, NPPMB has not hired any agency (or

individual consultant) to carry out independent monitoring assignment; therefore, no independent

monitoring and evaluation report is available to submit to stakeholders on the implementation of RP

and compensation payment for AHs.

6. CONCLUSIONS, LESSONS LEARNT

121. All subproject provinces have put a lot of efforts on undertaking compensation, site

clearance and all accomplishments have been analyzed above. DCRCs are very experienced in

compensation and resettlement in line with Government’s policy, if training on ADB’s policy is given, it is sure that they can handle it well too.

122. NPPMB is coping with a great deal of obstacles during the implementation of compensation

and resettlement which is attributable to the deficiency in fulfilling its responsibility in the project

activities at both provincial and district levels. The subprojects were carried out in significantly large

area which spreads through many remote areas; its staffing for compensation is insufficient which is

exacerbated by its plurality to lots of different subprojects so NPPMB has to hire consulting units

forcompensation and assistance, it is the result why the quality management of these units leaves

much to be desired.

123. Information disclosure on Vietnam’s resettlement policy at local level has carried out rather well; however, ADB’s compensation policy for this project has been yet made known to the district

level and especially AHs and other stakeholders at district level.

Page 44: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 43

ANNEXES

Annex 1: Relevant Documents

Annex 2: Status of Land Clearance and Compensation of Subprojects until

December 31 2014.

Annex 3: Status of the implementation of Corrective Action Plans

Annex4: List of Participants and Interviewees

Annex 5: Some photo field work

Annex 6: Socio-economic Questionnaires of Affected Households

Annex 7: List of People in Compensation department of NPMB

Page 45: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 44

Annex 1:Relevant Documents on Resettlement and Compensation

1. As being mentioned above, all surveyed districts comply with the policies of GoV related to

land acquisition, compensation, assistance and resettlement. The key laws, Decrees, Circulars all

the districts applied to 4 subprojects are as below.

Land Law 13/2003/QH11.

Decree 197/2004/ND-CP dated 3 December 2004, on compensation, assistance and

resettlement when the land is recovered by the State, as amended by Decree 17/2006/ND-

CP.

Decree 188/2004/ND-CP and 123/2007, specifying the methods for land pricing and land

price framework in the event of land recovery by the State.

Decree 84/2007/ND-CP, dated May 25, 2007 supplementary stipulations on issue of land

acquisition, land use right, procedure of compensation, assistance in the event of land

recovery by the state and grievance redress.

Circular 116/2004/TT-BTC, December 7, 2004 guiding the implementation of Decree 197.

Circular 116/2004 TT-BTC setting out in detail the types of compensation for different types

of users and losses; assistance policies; provisions for individual and group resettlement;

and the roles and responsibilities for the implementation of resettlement projects.

Circular 114/2004/TT-BTC elaborating the methods (direct comparison and income methods)

for determining land prices.

Decree No. 69/2009/NĐ-CP issued by Government dated 13/08/2009 supplementary

stipulations on land use right, land price, land acquisition, compensation, allowance and

resettlement.

2. All surveyed districts comply with national policies on compensation, assistance and

resettlement as set forth in Land Law 2003, Decree 197/2004, Decree 84/2007, Circular 114/2004;

Circular 116/2004, Decree No. 69/2009/NĐ-CP etc, and decisions of the provinces on

compensation, assistance and resettlement. No district applied project’s RPF, consequently, DMSs and compensation plans were in conformity with legal requirements on compensation and

resettlement policies of the Viet Nam Government.

3. The differences between the Project’s RPF and the actual implementation are (i) compensation and other payments have been calculated and paid in accordance with the project

provinces’ regulations rather than at market prices as being requested in RPF (in our experience, the

replacement price is usually higher than the prices as the one being issued by the Project PPCs); (ii)

eligibility for compensation and assistance (legal basis); (iii) special assistance to the vulnerable

groups, female headed household etc). The main gaps between the implemented entitlement by the

districts and the ADB policies are shown in Table 4below.

Page 46: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 45

Discrepancies between the implemented entitlement by the districts and the sub project

policies

Type of impact 197/2004/ND-CP, 69/2009/ND-CP Subproject Policy

Severely

impacted DPs

losing

productive

land

Decree 69, Art 20: For significantly

impacted DPs, livelihood restoration

measures cut in when DP loses at least 30%

of productive agriculture land.

Losing 10% or more of the household’s assets shall be considered as threshold.

DPs without

LURC

Decree 69: Article 23: Persons whose main

income is derived from agricultural

production whose land is acquired by the

Government and cannot satisfy LURC and

compensation conditions stipulated in Article

8 of Decree No. 197/2004/ND-CP and

Articles 44, 45 and 46 of Decree No.

84/2007/ND-CP will be referred to the

Provincial Peoples’ Committee for consideration of the level of assistance to be

provided in conformity with the locality’s actual conditions

Subproject affected people, without legal or

recognizable legal claims to land acquired, will

be equally entitled to participation in

consultations and subproject benefit schemes

where possible, and be compensated for their

lost non-land assets such as dwellings and

structures occupied before cut-off date. They will

be entitled to resettlement assistance and other

compensation and social support to assist them

to improve or at least restore their pre-subproject

living standards and income levels.

Compensation

for lost land

Article 9, Decree 197: The compensation

rates for land shall be determined by the

PPC in accordance with the Government

regulations for the type of land which has

been used for at the time of land acquisition.

Decree 69, Art 11, Art 16, Compensation is

land for same-use land or if not available the

DP can be compensated in cash based upon

the market transfer price of such land at the

time of the decision to acquire.

Compensation limited to the allowable land

quota, unless land over limit due to

inheritance or legally transferred from other

persons, or unused land developed

according to the land use plan approved by

the authorities. If not, compensation only for

improvements on that land.

Where appropriate land-based compensation is

not viable, replacement cost surveys will be

carried out by the subproject staff to ensure that

subproject rates for all categories of loss will be

equivalent to replacement cost at current market

value. This work will be updated at the time of

compensation and will combined with other

assistance and livelihood restoration measures

to ensure full restoration and improvements.

Provided DP has legal or recognizable claim,

compensation will be for full amount of land

acquired.

Based on the ADB SPS 2009 land-for-land

compensation strategy is mandatory in the case

of involuntary resettlement impact on Ethnic

Minorities.

Differences

between

compensation

rates and

market rates

Dec 69 Art 14(2): If compensation is through

new land or allocation of land at a

resettlement area or by housing and the

replacement is valued at less than the land

acquired, the price difference will be paid in

cash. Dec 69 Art 14(2a) If replacement

residential land or the amount compensated

to purchase a replacement house is more

than the actual replacement cost, the DP still

receives the full amount. Dec 69 Art 14(2b)

if the compensated amount is less than the

replacement residential land and house the

DP will pay the difference themselves except

for cases covered by Art 19(1) – this will not

apply to (poor) DPs who will be assisted by

the State. If the DP does not receive land or

house at the resettlement site the DP will

receive the cash difference.

Physically displaced (relocated) DPs are to

receive relocation assistance, secured tenure to

relocated land, with comparable access to

production and employment opportunities, and

civic infrastructure and community services as

required, transitional support and development

assistance such as land development, credit

facilities, training or employment opportunities.

Page 47: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 46

Type of impact 197/2004/ND-CP, 69/2009/ND-CP Subproject Policy

Compensation

for structures

Dec 69 Art 24– Compensation for House,

Structures on Acquired Land.

Clause (1) – Compensation for DPs

residential structures based on value of

newly constructed house/structure equal to

technical standard issued by MoC and

based on house area and unit prices issued

by PPC. Clause (2) other structures

compensation equal to: a) total present

value using unit costs for newly constructed

house/structure using MoC technical

standards and depreciated to present value

of acquired house/structure. Maximum value

cannot exceed 100% of new value of

acquired house/structure

Full compensation at replacement cost will be

paid for all affected structures without any

deductions for salvageable materials or

depreciation, full replacement costs, based upon:

i) fair market value, ii) transaction costs, iii)

interest accrued, iv) transitional and restoration

costs, v) other applicable payments

Compensation

for registered

businesses

Articles 26, Decree 197: Only registered

businesses are eligible for assistance.

Decree 69 Art 20(2) if business must be

suspended DP is compensated with max

30% of after tax income in one year,

averaged over last 3 years as certified by

Tax Dept.

Affected business owners are entitled to i) costs

of re-establishing commercial activities

elsewhere, ii) the net income lost during the

transition period, iii) costs of transferring and

reinstalling plant, machinery and equipment.

Compensation

for non-

registered

businesses

Decree 69 only recognizes formal registered

businesses as entitled to compensation for

lost income based upon Tax Office records

The DPC must certify that the DP has a business

in current operation and approve the level of lost

income.

Monitoring No monitoring indicators indicated The EA must appoint an independent external

monitor and undertake internal monitoring

according to the critical indicators.

Page 48: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 47

Annex 2: Status of Land Clearance and Compensation of Subprojects until December 31 2014.

Subproject RP/DDR Total AHs AHs

Compensation

AHs

Relocated Current Status

Total HH Relocation

I. Thanh Hoa-Vinh 220kV T/L

Trieu Son. Thanh Hoa RP 39 None 39 0

All AHs received

compensation

Dong Son, Thanh Hoa RP 30 None 30 0

Nong Cong, Thanh Hoa RP 236 None 236 0

Tinh Gia, Thanh Hoa RP 25 None 125 0

Quynh Luu, Nghe An RP 241 None 241 0

Yen Thanh, Nghe An RP 27 None 27 0

Dien Chau, Nghe An RP 151 None 151 0

Vinh, Nghe An RP 19 None 19 0

Nghi Loc, Nghe An RP 82 None 82 0

II. Nho Quan-Son La-Hoa Binh 500kV T/L

Mai Son, Son La RP 94 18 94 18 All AHs received

compensation Moc Chau, Son La RP 220 36 220 36

Cao Phong, Son La RP 238 31 238 31

Hoa Binh city, Hoa Binh RP 444 61 444 61

Tan Lac, Hoa Binh RP 873 70 873 70

Lac Son, Hoa Binh RP 444 36 444 36

Yen Thuy, Hoa Binh RP 171 29 171 29

III. Tuyen Quang 220 kV substation

Page 49: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 48

Subproject RP/DDR Total AHs AHs

Compensation

AHs

Relocated Current Status

Total HH Relocation

Yen Son, Tuyen Quang RP 90 0 0 All AHs received

compensation

Tuyen Quang city, Tuyen Quang RP 3 0 0

IV. Bim Son 220kV substation

Bim Son, Thanh Hoa RP 24 None 24 0

V.Nho Quan 220kV substation

Nho Quan, Ninh Binh RP 0 None 0 0

VI. Hai Duong 220 kV Substation

Kinh Mon, Hai Duong RP 90 None 90 0

Page 50: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 49

Data Required for Project Impacts4

Province District/Town/city

Foundations RoW Total

AHs Loss of

productive land >10%

Relocated HH

AHs Loss of

productive land >10%

Relocated HH

I.Son La- Hiep Hoa T/L 4115

Son La

Muong La, 86 198 12 284

Mai Son 39 58 5 21 97

Bac Yen 77 0 0 118 31 195

Phu Yen 151 0 0 296 0 26 447

Phu Tho Tan Son 85 27 124 209

Thanh Son 119 8 94 213

Tam Nong 497 2 56 26 553

Phu Tho town 107 89 27 196

Yen Lap 11 5 32 43

Phu Ninh 158

4 57 59 215

Viet Tri town 12 4 12

Vinh Phuc

Song Lo 175 33 175

Lap Thach 157 64 14 221

Tam Duong 156 212 98 368

Tam Dao 35 7 47 17 82

Binh Xuyen 48 6 89 3 137

Phuc Yen 12 23 35

Thai Nguyen

Pho Yen 308 8 136 69 444

Bac Giang Hiep Hoa 102 2 87 2 189

II. 500 KV Hiep Hoa substation 770

Bac Giang Hiep Hoa 770 244 770

III. 220 KV Thuong Tin- Kim Dong T/L

607

Hung Yen

Khoai Chau 98 7 124 222

Kim Dong, 24 33 57

Hanoi Thuong Tin 147 181 328

IV.220 KV Kim Dong substation 176

Hung Yen Kim Dong 176 51 176

4 Sources: Updated data of LIC from NPPMB/DCRC

Page 51: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 50

The list of vulnerable group of 04 subprojects5

Subproject Poor HH Female headed HH with dependents

Disabled HH heads

Ethnic Minority HH

I. 500 KV Son La- Hiep Hoa substation 146 0 0 871

Muong La, Son La 0 0 0 2846

Mai Son, Son La 0 0 0 97

Bac Yen, Son La 0 0 0 136

Phu Yen, Son La 0 0 0 354

Tan Son, Phu Tho 8 0 0

Thanh Son, Phu Tho 19 0 0

Tam Nong , Phu Tho 12 0 0

Phu Tho town, PhuTho 14 0 0

Yen Lap, Phu Tho 13 0 0

Phu Ninh, Phu Tho 17 0 0

Viet Tri town, Phu Tho 1 0 0

Song Lo, Vinh Phuc 15 0 0

Lap Thach, Vinh Phuc 7 0 0

Tam Duong, Vinh Phuc 22 0 0

Tam Dao , Vinh Phuc 5 0 0

Binh Xuyen, Vinh Phuc 0 0 0

Phuc Yen, Vinh Phuc 0 0 0

Pho Yen, Thai Nguyen 11 0 0

Hiep Hoa, Bac Giang 2 0 0

500 KV Hiep Hoa substation 95 40

Hiep Hoa, Bac Giang 95 40 0 0

Thuong Tin- Kim Dong T/L 3 40

Thuong Tin district, Hanoi 0 35 0 0

Kim Dong district, Hung Yen 1 1 0 0

Khoai Chau district, Hung Yen 2 4 0 0

220kV Kim Dongsubstation 15 42

15 42 0 0

5 Source: RAP, DDR reports and DMS of 04 subprojects

6 SES and DMS of RAP reports shows that about 90% of AHs belong to ethnic group in subproject districts in Son La

province, mainly is Hmong, Muong, Dao and Thai ethnic minorities.

Page 52: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 51

Annex3. Status of the implementation of Corrective Action Plans

Thanh Hoa Vinh Transmission Line

Findings Actions to Take Status as of 30 May 2014 Responsibility Target

completion date

Compensations not completed in some of the affected communes. In Tuong Lam commune has compensated 35 out of 41 AHs; TungLam commune 8 out of 11 AHs; Phu Lam communeis 9 out of 12 AHs.

NPT/NPPMB to complete

compensation payments

Compensations fully completed for all AHs in 3 communes and the line is energized on 24 Mar 2014

LIC monitor and report to ADB

completed

07 AHs in Nghi Van commune and 01 AH in Nghi Thuan commune, Nghi Loc district, Nghe An province have not received compensation due to low compensation price for land.

NPT/NPPMB and Nghi Loc DRC provide actions for resolving

Nghi Loc DRC has recruited an independent appraiser to verify land price, then revise compensation plan accordingly and submit to PPC for approval

NPT/NPPMB and Nghi Loc DRC

completed

Two HHs in Tower position 125a (Dien Chau District) want to receive replacement land as compensation for their affected land. For small areas, it may bedifficult to provide land for land; in addition compensation for small areas of land has been done by cash for the sub-project

If land for land is not possible, NPT/NPPMB in coordination with CARB Dien Chau to provide explanation to these HH in order for them to accept cash compensation. Document the consultations and the results

Only Land without houses/structures is affected by the transmission line. Support for limitation of land use, equal to 80% of compensation price was prepared and submitted to district PC for approval. Payment will be done on 30 April 2014

NPT/NPPMB in coordination with CARB Dien Chau.

LIC will monitor and report to ADB

it’s done

In Dien Chau District Nghe An Province compensation for land is based on 2012 compensation rates

NPT/NPPMB to ensure that Dien Chau districtupdates compensation rates based on 2013 rates and pay the balance to the affected households

Additional compensation was prepared and payment will be done on 30 April 2014

NPT/NPPMB in coordination with CARB Dien Chau. LIC will monitor and report to ADB

it’s done

From tower positions 51 to 52(G9-G9a) Nong Cong district, eight HHs refused compensationbecause they do not agree with current compensation price because it

NPT/NPPMB to ensure that Nong Cong district updates compensation rates based on 2013 rates and pay the balance to the affected

Compensation price was increased, 8 HHs received compensation in Nov 2013

LIC will monitor and report to ADB

completed

Page 53: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 52

Findings Actions to Take Status as of 30 May 2014 Responsibility Target

completion date

is too low; households

From tower positions 116 to 118 (G20a-G21a) Tinh Gia district, Thanh Hoa province: 02 HHs claim to move out of transmission line because they are afraid their health may be affected by the power lines.

NPT/NPPMB in coordination with the CARB Tinh Gia district to ensure that in the CPC andAHs are informed that the distance from the houses to the power lines poses no health impacts.

NPT/NPPMB to conduct consultations

NPT/NPPMB in coordination with CARB Tinh Gia district should consult local people and explain

it’s done

Page 54: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 53

Tuyen Quang Sub-station

Findings Actions to Take Status as of 30 December2014

Responsibility Target

completion date

The content of the Resettlement Policy Framework has not been understood and in particular the grievance redress mechanism is still unclear to AHs

NPT/NPPMB to immediately prepare a public information booklet (PIB) which summarizes the main content of the RF and especially the grievance redress mechanism with contact numbers of relevant agency and disseminate

PIB prepared and disseminated

NPT/NPPMB confirm

LIC will monitor and report to ADB

it’s done

No income restoration program was implemented

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC to inform HH (losing more than 10% of productive land) and the vulnerable HHs on existing programs such as Program 1956 and assist them to register to these programs.

NPPMB and DCRC will coordinate with local implementing agencies, such as the district Agriculture Extension Center (agriculture extension services) the district Vocational Training Centre (training), to provide necessary assistance.

Four relocated HHs loose more than 10% of productive land. Tuyen Quang DCRC has provided resettlement allowances for them.

The allowances for leveling house foundation has provided for 02 self-relocated HHs.

Job Training/creation allowance has been provided for these AHs

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC

LIC will monitor and report to ADB

Completed

Only poor and special policy HHs were identified during DMS.

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC to check in the DMS list and with local organization (Farmer’s Union, Women’s Union) if potential vulnerable HH ;

As per agreed RF all poor and vulnerable APs, even if they are not severely affected, should receive a cash allowance equivalent to 30 kg of rice per family member per month for a minimum period of six months (amount to be determined by Yen Son District PC). Please ensure the implementation.

Three poor AHs received allowance

One woman headed HH was paid allowance in mid-May 2014.

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC

LIC will monitor and report to ADB

It’s done

Page 55: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 54

Findings Actions to Take Status as of 30 December2014

Responsibility Target

completion date

Four AHs received rental allowance only for 6 months but have to rent a house for 11 months.

NPT/NPPMB to ensure rental allowance paid to 4 affected households cover the actual rental period. Make pending additional allowances.

LIC has checked and confirm that there is not delay of allocation of land plot for relocated HHs, so 6 month renting allowance provided is compliance with the RF

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC

Completed

Gender and ethnic minorityissues have not been covered

As per agreed RF, NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC to conduct specific consultation meetings with female headed HHs, and poor women and ethnic minority AH to identify their concerns and needs. Following this assessment, prepare a socioeconomic program in order to maintain and/or improve their income generation potential and implement.

NPT/NPPMB in coordination with Yen Son and

Tuyen Quang DCRC to ensure joint registration

of land use rightsfor 4 relocated HH

Implementation of Gender action plan and EMDP has been incorporated in RP implementation.

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC

It’s done

Impacts during construction (agriculture lands filled with sand)

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC to follow-up if compensation received was sufficient for HH to cover their loss of incomes and report any discrepancies. In the case of any discrepancy ensure additional compensation.

31 AHs were paid in

February 2014

LIC monitors Completed

Many households who temporarily lost use of land during the construction of service roads were getting upset because the contractors occupied their land without reaching agreements for compensation

NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC to ensure that contractors reach agreements with AHs and pay compensation.

It has been resolved NPT/NPPMB in coordination with Yen Son and Tuyen Quang DCRC

Contractor

Done

Page 56: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 55

Bim Son Sub-station

Findings Actions to Take Status as of 30 December2014

Responsibility Target completion date

No public information on project policy and on grievance process

NPT/NPPMB to prepare a public information booklet (PIB) which includes information on project policy and grievance process and contact numbers of relevant agencies. NPT/NPPMB need to disseminate the PIB as stipulated in the RP

It’s done LIC will monitor Completed

There are two women headed HHs affected from the project, They are also the most affected losing more than 10% of their land. No specific assistance was given to them

NPT/NPPMB in coordination with

Bim Son DCRC to conduct an

assessment of the income

restoration needs for two AHs

(Mrs. Le Thi Voi and Nguyen Thi

Nhuong) and implement actions for

income restoration.

These HHs used plantation lands. They received support equal to 100% of compensation value. Payment was done. Assessment of their socioeconomic conditions showed that these 2 HHs don’t need specific assistance

LIC will monitor Completed

During construction, there was land filling on pineapple fields of some households. Local authorities provided assistance, however information is not clear.

NPT/NPPMB to ensure that LIC

follow up if the compensation

received was satisfactory to AHs

and report the status.

Contractor paid compensation for additional impacts

LIC will monitor Completed

Gender issues have not been taken into account.

NPT/NPPMB in coordination with

Bim Son DCRC to conduct

consultation meetings assess if

there are any complaints and

grievances and take actions.

Report on the status

It was integrated in resettlement implementation

LIC will monitor Completed

Page 57: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 56

Hai Duong 2 S/S

Findings Actions to Take Status as 20 May 2014 Responsibility

Target completion date

No livelihood restoration programs are established and implemented for severely affected households; however AH don’t rely only on agriculture activities from their affected land; they have additional sources of income;

AHs are generallyaware of existing programs for agriculture improvement and vocational training provided by the government;

HHs received allowance for occupation change (2 times compensation rate for agriculture land)

Confirm through monitoring that

AHs have several sources of

income and don’t rely only on their productive land;

Inform HH (losing more than 10%

of productive land) on existing

programs such as Program 1956

and assist them to register to

these programs.

To be assessed

To be done

Resettlement Committee of Kinh Mon District

LIC during monitoring

NPPMB, DRC, CPC Vocational Training Centers

Done

Done

Page 58: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 57

Son La – Hiep Hoa T/L

Findings Actions to Take Status as of 30 December 2014

Responsibility Target

completion date

Restoration of livelihoods.

Along the transmission line there can be households (HH) losing more than 10% of their total productive land.

- Identify through DMS list, the number of affected HHs (AH) losing more than 10% of their productive land in each district, town or city;

- Assess if these HHs could restore their livelihoods.

- Prepare adapted incomerestoration measures and implement

NPPMBconfirmed there are no any HHs losing more than10% of productive land, so corrective actions is not applicable

NPT/NPPMB

confirmed the status

Completed

Completion of Infrastructures in Thuan Thanh Resettlement Site

In Thuan Thanh Resettlement Site (RS) in Thai Nguyen Province, Pho Yen District, drainage, inner roads and electricity are not completed; no activity occurred on this RS.

- Preparedisbursementdetailsanddisburse funds

- Complete all the infrastructure

- Inform the HHs regularly of the schedule of work

- Extendallowanceforrentinghousesuntil completion of the resettlement site

- Completed all the infrastructure

- Paid extendallowanceforrentinghousesuntil completion of the resettlement site

NPT/NPPMB in

coordination withContractor, PMU

Construction &Investment Pho YenDistrict, DRCBPhoYen/Contractor, DRCB PhoYen,DCRBPho Yen

Not completed disbursement for the resettlement areas

Vulnerable

Except poor, no other vulnerable people have been identified

Check the DMS list and with local organization (Farmer’s Union, Women’s Union) if potential vulnerable HHs are ((i) female headed HH with dependents, (ii) disabled HH heads, (iv) children and the elderly HH who are landless and with no other means of support, and (v) landless HH. Determine the allowances as necessary and provide the allowances to the AHs.

No other vulnerable people identified, except poor HHs. They have been provided special allowance.

NPT/NPPMB

confirmed

Completed

Issuance of Land Use Right Certificate

The Land Use Right Certificate (LURC), which serves as ownership document for the new plot of land (in a resettlement site or for individual plot) has not been provided to all

Issuance of LURC for HHs which have already been allocated a plot of land and who have paid their land use fees.

Not completed NPT/NPPMB in

coordination with District People’s Committee

Page 59: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 58

Findings Actions to Take Status as of 30 December 2014

Responsibility Target

completion date

relocated HH due to slow processes. The LURCisissuedbytheDistrictPeople’s Committee.

Slow Process of disbursement of Funds. Delays in transfer of funds from NPPMB to DCRB have been observed in most of the districts. These delays hamper the resettlement activities and especially the completion of RS. Disbursement documents are prepared first by the contractor and send through the PMU of Construction and Investment (DPC) to NPPMB forreview, approval and disbursement. According to NPPMB, contractors don’t send documents to DPC.

NPPMB to continue assisting contractors and PMU of Construction and Investment to prepare acceptable disbursement documents;

- NPPMB to transfer remaining funds

Paid 100% for DCRB, NPPMB will check whether contractors got the money for disbursement to the affected people

NPT/NPPMB

confirmed

Not completed disbursement for the resettlement areas.

Compensation of Mr. Tran Thanh Tung (Phu Tho Province, Phu Tho Town)

Mr. Tran Thanh Tung refusedcompensation, didn’t hand over his land for the project construction and still living under the transmission line. According to legal documents, Mr. Tung has been living in a forest land. His arguments are that he and his family have been living stably for a long time and he wants to be compensated at residential landrate.Compensationforforestlandis

35,000 VND/m2, while compensation

for residential land in RS is

- NPPMB to ensure allocation or 400 m2

plot in the RS

- NPPMB to compensate for all other assets (trees, crops, structures) at replacement costs

- NPPMB to confirm whether the splitting of the family into three separate HHs was done before the cut-off date. If so, two additional HHs should be provided two plots in the resettlement site, otherwise, the Phu Tho Town people’s committee should consider selling the additional plots for his family.

- Compensated for houses/structures at replacement costs;

- The splitting of the family into three separate HHs was done after the cut-off date (2011).

Additional compensation for house/structure at 100%

instead of 50% have done. NPT/NPPMB

shall provide evidence on the additional payment made

Not completed

Page 60: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 59

Findings Actions to Take Status as of 30 December 2014

Responsibility Target

completion date

70,000/m2. He also

demands3plotsoflandfreeintheRS.

NPPMB/DCRB offered to provide one plot of land 400 m

2 in the RS but

he refused. Usual practice is that AHs should buy the plot of land

using the compensation. The resettlement site is just adjacent to his old house.

He lodged a complaint to the Phu Tho Town Court which was dismissed. He is living under the energized line.

In April, 2013 he lodged a complaint to the Province Court which was also rejected.

Phu Ninh RS (Phu Tho Province, Phu Ninh District)

In Phu Ninh RS, there is a risk of landslide due to steep slope without erosion protection. Landslide could affect properties and infrastructures (drainage ditch).

NPPMB to study options to protect slope against erosion and implement these protective measures.

NPPMB and LIC

consultant will check the site and report to ADB on 15 April 2014

NPT/NPPMB

and LIC

Completed

Grievance Process

The grievance process is followed; there is however some delays in the information to Affected people (AP) who made complaints.

NPPMB to review complaints in all affected districts/towns/cities and review how grievances were addressed, and resolve any residual grievances. All grievances must be addressed within the time regulated by the law (30-45 days after receiving the official complaints).

- NPPMB to ensure APs raising complaints are informed about the results of the decision within the timeframe indicated in the RP. Please continue redressing the grievances

Comply with grievance mechanism NPT/NPPMB

confirmed

Completed

Page 61: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 60

Findings Actions to Take Status as of 30 December 2014

Responsibility Target

completion date

and report

Monitoring

External monitoring to be conducted by LIC

- NPPMB to list each monitoring activity conducted as stipulated in the agreed RF;

- NPPMB to pay special attention to the needs of women and ethnic minority people and ensure all consultation and participation processes with affected people are coordinated in a participatory manner.

LIC will conduct regular monitoring and report to ADB

NPT/NPPMB

Page 62: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 61

Hiep Hoa substation

Findings Actions to Take Status as of 30 December 2014

Responsibility Target completion date

Only some HH were identified during DMS and received assistance. Other vulnerable HH were not identified

As per agreed RPF all poor and vulnerable APs, even if not severely affected, should receive a cash allowance equivalent to 30kg of rice per family member per month for a minimum period of six months (amount to be determined by Hiep Hoa district PC)

LFDC to check in the DMS list and through local organization (Farmer’s Union , Women’s Union) if potential vulnerable HH: (i) female- headed HH with dependent; (ii) disabled HH heads; (iii) poor HHs; (iv) HH without with no means of support; and (v) HH without security of tenure; are present and provide the agreed allowance

Completed additional allowance forvulnerable HH

CPPMB Completed

Following construction, drainage is not adequate and led to frequent flooding to the cultivation area of Ha Noi, Dai Mao and Huong Ninh hamlets despite some work (drainage channel, dykedone to reduce flooding )

NPT/ CPPMB to ensure that support to localities for drainage installation and pumping stations in the areas affected by flooding is provided

LIC has worked with local authority about this. In the fact, typical terrain of project area is low land. Thus, flooding situation usually occurred here before project implementation.

Working with local authority and people, they wants to have a assistance (if any) from project to construct a pumping station to prevent this flooding.

During operation. Lights from the substation attracts butterfly and worms at right affecting crop productivity

NPT/ CPPMB to coordinate with various stakeholders and ensure that a solution for the butterfly and worms attracted by the light from the substation is found. CPPMB ensure that the protective measures are implemented immediately

This is not impact on production and lives of local people

Page 63: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 62

Annex 4. List of Participants and Interviewees

No Name Address Position

1. Bui Cao Cuong AMB Clearance staff

2. Nguyen Van Ha LILAMA join stock company(

construction unit)

Vice technical

department

3. Trinh Xuan Toan CARB Bim Son Vice of CARB

4. Vu Thi Thu Hang CARB Bim Son Member of CARB

5. Nguyen Khoa Truong 10 group Bac Son Ward, Bim Son Affected person

6. Do Luong Chinh 10 group Bac Son Ward Affected person

7. Cu Thi Thuy 10 group Bac Son Ward Affected person

8. Hoang Thi Hoi 10 group Bac Son Ward Affected person

9. Nguyen Thi Phuong 10 group Bac Son Ward Affected person

Yen Son district, Tuyen Quang province

10. Doan Khac Muoi Kim Phu commune Chairman of CPC

11. Luu Van Khang Hoang Khai commune Chairman of CPC

12. Ha Thi Than village 13, Kim Phu commune village 13 leader

13. Dinh Thi Luong village 13, Kim Phu commune Affected person

14. Au Van Doai 15 village, Kim Phu commune Affected person

15. Au Xuan My 15 village, Kim Phu commune Affected person

16. Tieu Van Phuc 15 village, Kim Phu commune Affected person

17. Tran Tien Hong 15 village, Kim Phu commune Affected person

18. Ngo Ba Cu 26 village, Kim Phu commune Member of DRC

19. Hoang Van Nhan Che Den village, Hoang Khai C. Village leader

20. Nguyen Mai Huy Che Den village, Hoang Khai C. Affected person

21. Luong Thi Chanh Che Den village Hoang Khai C. Affected person

T/L Thanh Hoa-Vinh 220KV

Nghi Loc district, Nghe An province

22. Nguyen Ba Diep Nghi Loc district, Nghe An Vice CARB Nghi Loc

district

23. Nguyen Van Toan IEC company Construction unit

24. Dang Ba Hai Nghi Dien commune Cadastral officials

25. Nguyen Van Chanh IEC( construction unit) Clearance staff of IEC

Page 64: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 63

No Name Address Position

26. Mr. Vuong IEC( construction unit) Technical staff of IEC

27. Dang Huu Quang Quan Hanh ward Affected person

28. Nguyen Thi Ly Hamlet 7 Nghi Dien commune Affected HH

29. Luong Duc Hoan Nghi Hoa commune Cadastral officials

30. DangVanHoa Hamlet 10 Nghi Hoa C. Affected HH

31. DangVanLuu Hamlet 10 Nghi Hoa C. Affected HH

32. DangThiHien Hamlet 10 Nghi Hoa C. Affected HH

33. Phan CongVan Nghi Van commune Vice-president CPC

34. Thai Thi Khiem Hamlet NamBo Son Nghi Van C. Affected HH

35. NguyenVanDuc Hamlet Cho Nghi Van C.

Affected HH

36. LeVan Kieu Hamlet Thinh Lac Nghi Van C. Affected HH

37. LeVanHoang Hamlet Thinh LacNghi Van C. Affected HH

38. Nguyen Quoc Hung Nghi Thuan commune Cadastral officials

39. Bui KhacToan Hamlet 11 Nghi Hung C. Affected HH

40. HoVan Huong Hamlet 12 Nghi Hung C. Affected HH

41. Nguyen Phu Hoan Hamlet 12 Nghi Hung C. Affected HH

Dien Chau district, Nghe An province

42. LeVan H Dien Phu C., Dien Chau district Cadastral officials

43. Hoang Huu Canh Hamlet 9 Dien Phu commune Affected HH

44. Vo Xuan Trong Hamlet 9 Dien Phu commune Affected HH

45. Tran Ngoc Hoa Hamlet 9 Dien Phu commune Affected HH

46. Dang Xuan Long Hamlet 1 Dien Phu commune Affected HH

47. Nguyen Huu Nhan Hamlet 16 Dien Loc commune Affected HH

48. LeVan Manh Hamlet3 DienQuang commune Affected HH

Tinh Gia district, Thanh Hoa province

49. Nguyen Trong Nam Tan Truong commune Chairman of CPC

50. Pham Xuan Tu Tung Lam commune Chairman of CPC

51. Le Trong Ngan Phu Lam commune Affected person

52. Le Trong Ngo Phu Lam commune Affected person

Page 65: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 64

No Name Address Position

53. Pham Van Chu Truong Lam commune Vice chairman of CPC

54. Luong Quoc Dot Truong Lam commune Affected person

55. Le Thi Toi Truong Lam commune Affected person

56. Ha Van Duc Phu Son commune chairman of CPC

57. Mai Van Do Phu Son commune Affected person

58. Le Ngoc Dung Phu Son commune Affected person

59. Le Dinh Sang Phu Son commune Affected person

Nong Cong district, Thanh Hoa province

60. Tran Thi Ngan Van Thien commune Affected person

61. Le Van Hung Van Thien commune Affected person

62. Nguyen Van Thon Van Thien commune Affected person

63. Nguyen Van Quyt Van Thien commune Affected person

64. Le Xuan Nguoc Te Loi commune Office staff of CPC

65. Tran Van Uu Te Loi commune Affected person

51 Hoang van Tau Te Loi commune Affected person

52 Le Van Ban Trung Chinh commune Cadastral Officers

53 Hoang Thi Hoan Trung Chinh commune Affected person

54 Nguyen Xuan Nghia Trung Chinh commune Affected person

220kV Hai Duong 2 substation

Kinh Mon district, Hai Duong province

55 Nguyen Duc Tinh Hue Tri village, An Phu C. Affected person

56 Duong Dang Hop Hue Tri village, An Phu C. Affected person

57 Nguyen Van Tuan Hue Tri village, An Phu C. Affected person

SON LA- HIEP HOA

Mai Son district, Son La

Ms Doan Thi Xuan

Mai Son district Vice director of PC, Head of DCRC

Mr. Vu Huu Dung

Mai Son district

Deputy head of Division of Natural resources and environment, member of DCRC

Page 66: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 65

No Name Address Position

Giang A Tua Chieng Sung commune, Mai Son district Relocation HHs

Mua Pao Cua Chieng Chan commune, Mai Son district APs

Mua A Po Chieng Chan commune, Mai Son district APs

Phu Yendistrict, Son La

Mr. Ngo Duc Duong Deputy head of Division of Natural resources and environment, member of DCRC

Mr. Vi van Truong Huy Ha commune, Phu Yen district Relocation HHs

Mr. Vi Van Chon Huy Ha commune, Phu Yen district APs

MS Sa Van Anh Huy Ha commune, Phu Yen district APs

Tam Nong district, Phu

Tho

Mr. Tran Quoc Thuy Tam Nong district Deputy of District Finance, member of DCRC

Mr. Tran Van Chinh Tam Nong district Member of DCRC

Mr. Ngo Quang Truong Hien Quan commune, Tam Nong district Relocation HH

Phu Ninh district, Phu Tho

Mr. Vu Tien Dung Phu Ninh district Deputy of District Finance, member of DCRC

Mr. Nguyen Xuan Cac Phu Ninh district Vice-chairman of DPC

Mr. Ngo Van Quang Phu Ninh commune,Phu Ninh district Relocation HH

Mr. Nguyen Van Vinh Phu Ninh commune,Phu Ninh district APs

Mr. Nguyen Ba Dung Phu Ninh commune,Phu Ninh district APs

Phu Nhamcommune, Phu

Ninh district, Phu Tho

Mr. Nguyen Ton Hung Phu Nham commune

Vice-chairman of CPC, member DCRC

Mr. Huynh Van Tam Phu Nham commune Commune cadastral,

Mr. Dao Van Bien Phu Nham commune APs

Mr. Nguyen Van Long Phu Nham commune Relocation HH

Page 67: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 66

No Name Address Position

Phu Loc commune, Phu

Ninh district, Phu Tho

Ms Duong Thi Tong Phu Loc commune Relocation HH

Mr. Ngo Van Hau Phu Loc commune Relocation HH

Tu Da commune, Phu

Ninh district, Phu Tho

Mr. Vu Van Lieu Tu Da commune Relocation HH

Ms Nguyen Thi Thu Ha Tu Da commune Relocation HH

Thanh Son district, Phu

Tho province

Ms Nguyen Thi Lan Thanh Son district Deputy of District Finance, Vice Head H of DCRC

Mr. Tran Dinh Tuan Son Hung commune APs

Ms Nguyen Thi Kim Ngan Son Hung commune APs

Mr. Nguyen Duc Tan APs Self- relocation HH

Tam Duongdistrict,Vinh

Phuc

Mr. Nguyen Van Cuong Vice Head of DPC, Head of DCRC Tam Duong

Mr. Nguyen Hoang Thai Member of DCRC Tam Duong

Ms Nguyen Thi Xuan Self- relocation HH Dao Tu commune

Mr. Pham Van Duyen Self- relocation HH Dao Tu commune

Ms Phan Thi Hoa Self- relocation HH Dao Tu commune

HIEP HOA SUBSTAITON

Mr. Tran Van Dong Head of Dai Thanh

CPC

Mr. Ngo Van Tuyen Dai Thanh APs

Ms Nguyen Thi Cu Dai Thanh APs

Mr. Ngo Van Thuan Dai Thanh

KIM DONG SUBSTATION

Mr. Nguyen Ngoc Hoang Chairman of Toan

Thang CPC

Mr. Nguyen Van Am Toan Thang commune APs

Page 68: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 67

No Name Address Position

Ms Nguyen Thi Cuong Toan Thang commune APs

Ms Nguyen Thi Am Toan Thang commune APs

THUONG TIN- KIM DONG

T/L

Mr. Do Hong Quang Thuong Tin district Vice Chairman of

Centre, DCRC .

Mr. Dang Van Thanh Thuong Tin district Member of DCRC

Mr. Nguyen Quoc Viet Thuong Tin district Member of DCRC

Mr. Hoang Van Tuu Khoai Chau, Hung Yen Vice Chairman of Khoai Chau DPC, Chairman of DCRC

Mr. Le Ngoc Dich Khoai Chau, Hung Yen Head of Khoai Chau

DONRE

Mrs.Dao Thi Thuy Khoai Chau, Hung Yen Chairman of Dai Hung

CPC

Mr. Dao Duy Hien Khoai Chau, Hung Yen Cadastral of Dai Hung

CPC

Mr. Dao Ngoc Thach Khoai Chau, Hung Yen Head of village No 3

Mr. Dao Van Dung Khoai Chau, Hung Yen APs

Page 69: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 68

Annex 5. Some photographs about the field work

Pic 5: Representatives of ADB, NPPMB and LIC

met DPMU Cao Phong district, Hoa Binh province

in the site visit on September 2012 (subproject

500 kv Son La- Nho Quan- Hoa BinhT/L)

Pic 6:Mrs. Bui Thi Hiep, Tan village, Phu Lai commune, Yen Thuy district, Hoa Binh Province looks happy to welcome team work in her relocated house (subproject 500 kv Son La- Nho Quan- Hoa BinhT/L)

Pic 8: House of AH Nguyen Thi Voi , the women

is HH leader in Area 10B, Bac Son ward, Bim

Son town( Bim Son S/S)

Pic 9: AH Nguyen Thi Nhuong( Phuong) the women HH leader in Area 10B, Bac Son ward, Bim Son town( Bim Son S/S)

LIC met relocated HH Tieu Xuan Nhat and his wifein their new house in village 13 Kim Phu

Page 70: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 69

Pic 11: LIC Met CPC An Phu commune, Kinh Mon district, Hai Duong province

Pic 12: Mission group staffs met Mr. Tran Ngoc Son, AHH in Hue Tri village, An Phu commune, Kinh Mon district

Pic 13:Mission group staffs met CARB Kinh Mon district

Pic 14:Hai Duong 2 S/S is under construction in May, 2014

Field team met head of AH Nguyen Van Giơi in Field team met head of AH Nguyen Van Giơi in

Page 71: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 70

Ngc Trao ward, Bim Son Ngc Trao ward, Bim Son

Construction Substation Bim Son on the time ADB Mission schedule on March, 2014

Review ADB Mission Schedulefrom 20to 28 February 2014 in substation Bim Son

New house of Bui Van Tien, Tan village,

Phuc Lai commune, Yen Thuy district, Hoa

Binh province

New house of Bui Van Ua, Mun village, Dinh

Giao commune, Tan Lac district, Hoa Binh

province

Page 72: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 71

The construction site of 220 kV transformer stations Tuyen Quang

LIC InterviewedMr. Tieu Minh Thien,AHH in village 13, Kim Phu commune

LIC Interviewed Mrs. Hoang Thi Duc (Tieu Xuan Nhat 'wife), relocated HH in village 13, Kim Phu

Page 73: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 72

commune

Inventory records of village 13 forcultivate land damage from construction unit

Inventory records and list of received compensation payment ( By AMB)

Page 74: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 73

New house of relocated HHTieu Xuan Nhat

Mr. Ngo Ba Cu,relocated HH is promoting construction his new house

Page 75: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 74

Worked with Mai Son DCRC, Son La province

Interviewed Mr. Ly Van Nhuan, Tan Lang commune, Phu Yen dis, Son La

Worked with Song Lo DCRC, Vinh Phuc province Worked with Tam DaoDCRC, Vinh Phuc province

Worked with Tam NongDCRC, Phu Tho Worked with Khoai ChauDCRC, Hung Yen

Page 76: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 75

Worked with Van Phu Commune, Thuong Tin district Worked with Tu Dan Commune, ThuongTin district

Dong Thinh 1 RS, Song Lo district, Vinh Phuc province Phu Nham RS, Phu Ninhdistrict, Phu Tho

Self resettled of Pham Van Duyen, Dao Tu commune, Tam Duong district, Vinh Phu

Page 77: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 76

New house of Mr. Giang A Tua, Chieng Sung commune, Mai Son dis, Son La

New house of Mr. Vi Van Truong, Huy Ha commune, Phu Yen dis, Son La

PHU THO has 09 RS (02 of Phu Tho town; 01 of Tam Nong dis;06 of Phu Ninh dis)

Phu Loc RS, Phu Ninh Tu Da RS, Phu Ninh

Hien Quan RS, Tam Nong Phu Nham RS, Phu Ninh Phu Ninh RS, Phu Ninh

Page 78: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 77

VINH PHUC has 10 RS (01 of

Tam Dao; 05 of Tam Duong

dis; 03 of Song Lo; 01 of Binh

Xuyen)

Dong Thinh 1 RS, Song Lo Yen Thach RS, Song Lo

Trung My, Binh Xuyen Trai Khoong RS, Tam Dao An Hoa RS , Tam Duong

The minutes of inventory of Mr. Nguyen Van Them, Toan Thang commune, Kim Dong (Kim Dong SS)

Page 79: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 78

Annex 6. Socio-economic Questionnaires of Affected Households

Code:

Project Name: ADB Loan 2225-VIE: Northern Power Transmission Expansion

Sector Project

Province: District:

Commune: ………………............Village: ……………………..………………….

Name of Investigator:

Date of survey:............../....../2012

I. GENERAL OF INTERVIEWEE AND HOUSEHOLD:

1. Full Name of Interviewee: ………………………….............

2. Occupation (look at Code (d) in Q. 10): ……

3. Gender: 1. Male 2. Female

4. Year of Birth: ………….

5. Education (look at Code (c) in Q. 10): …………………………....

6. Group:.....................................

7. Vulnerable Household: 1. Yes Q.8 2. No Q.9

8. If YES, in detailed:

1. Poor Household (Certificated) 2. Disabled Household

3. Invalid or “revolution” household 4. Invalid of “revolution” household

5. Loneliness Elder 6. Loneliness Household

7. Single woman (with dependant) 8. Other:...........................

9. Types of household’s impacts: 1. Must relocate

2. Lost income

In which,: 2.1. Lost ≥ 10% of agricultural land area

2.2. Lost of production land and business location

3. Lost land

Include: 3.1. Resident land

3.2. Ponds/Lakes

3.3. Land for Yearly Tree Plant

3.4. None-agricultural land

4. Partly Affected House

5. Totally Affected House

6. Affected Sub-work/objects

7. Affected Tree and Crops

8. Affected Graves

Page 80: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 79

10. Information of Members of the household: Scale of household:....... persons

No

Relationship

with head of

household

(a)

Group Sex

(b)

Year of

birth

Educatio

n (c)

Main

Occupation

(d)

Average

General Income

per month

(dong/ month/

person)

1

2

3

4

5

6

7

8

9

Code: (a): Relationship with head of household: 1.Head; 2.Husband/wife; 3.Children; 4.Father/mother;

5.Grand mother/Grand father; 6.Niece; 7.Sibling; 8.Relative.

(b):Sex: 1.Male; 2.Female

(c):Education:1.Illteracy; 2.Primary; 3. Secondary; 4.High School; 5.College/University; 6. Post

Graduate

(d): Occupation: 1.Farmers; 2.Workers; 3. State Officials; 4.Retires; 5.Businessmen; 6.Solders,

Security; 7. Unstable Employment; 8.Students/Pupil; 9.Handicraft; 10.Under School Age;

11.Unemployment; 12.Housekeeper; 13.Disabled Persons; 14.Elders; 15.Others.

11. Income Source of household:

No Income Source (estimate) Amount (dong/household/month)

1 From Salary

2 From farming/forest/aquaculture

3 From business/service

4 From gift/assistance, etc

5 From other source

6 Total of Income Source

12. Household living standard according to the classification of commune/ward:

1. Poor 2.Near Poor 3. Average 4. Fair 5. Rich

Page 81: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 80

13. Expenditure Average of Households per month (dong/month)

No Expenditure(estimate) Amount

(dong/household/month)

1 Food

2 School

3 Health

4 Electricity

5 Water

6 Sanitation, Security Fees

7 Expenditure for production/business/service

8 Traveling, shopping, wedding, etc.

9 Other cost

10 Total of Expenditure

II. ACCOMODATIONS

14. Available Accommodation of the Household

Name of Asset Quantity Name of Asset Quantity

1. Bicycle 8. Mobile

2. Motorbike 9. Video/CD

3. Car 10. Computer

5. Bed/board/wood furniture 11. Rice Cooker

6. Television 12. Gas Cooker

7. Telephone 13. Fridge

III. INFRASTRUCTURE

15. Using Source of Electricity:

1. Grid electricity with separated meter 3. Small Hydro

2. Sharing with the other family 4. No Electricity

16. Tap water: 1. Yes 2. No

17. Latrine:

1. Septic tank 2. Simple 3. No toilet

18. Fuel:

1. Wood 2. Coal 3. Electricity 4. Gas 5.Oil 6. Other:.........

19. Current house:

19a. Category of house:1.Permanent house; 2. Category IV 3. Temporary4. Other:.....

19b. Year of construction:_________

Page 82: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 81

19c. Total area of house floor:.............m2

19d. State of Own: 1. Permanent 2. Temporary 3. State 4. Other:..........

19e. Type of LURC:

1. Permanent LURC 2. LURC with time limited 3. None-title 4. Other:..........

IV. LAND

20. Total of land area that your household is owning? __ __ __ __ __ m2

a) Area

(m2)

b) LURC

1. Titled

2. Legalizable

3. None-title

1. Agricultural Land

2. Resident land

3. Pond/Lake/Garden

4. Forest/mountain land

5. Other land (detailed):

6. Total of land area

21. Source of land or house:

1. Inheritance 4. Buying

2. Issued by the State 5. Reclaimed land

3. Renting land 5. Other

V. AWARENESS ON THE PROJECT, COMPENSATION, ASSISTANCE AND RESETTLEMENT

- - No

23. What is your information sources? ( please choice one)

- Member of the family

- Neighbors/friends

- Governmental officials

- Member of resettlement committee

- Others (detailed): ……………………………………........................................

24. Do you know your land/house will be affected - - No

25. If your household with income affected, how is your expectation of the income job:

1. Remain the current job

2. Transition and have a new job

3. Do not know

Page 83: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 82

26. Which of rehabilitation measure that you expect?

1.Current job training

2. New job training: …………………………………………………….

3. Support loan for business or production

4. Support loan for agriculture production (such as breed, fertilizer)

5.Support of technique for agriculture production

6. New business

7. Other (detailed): …………………………………………………………

27. If relocate, which option will you choose as the follows:

1. Get compensation by cash and free resettlement

2. Get a land lot in the concentrated resettlement site

3. Get a land lot in the distributed resettlement site

4. Other (detailed): ……………………………………………………………………

28. Three expectation of the household of compensation, assistance and resettlement:

a):.........................................................................................................................

.............................................................................................................................

b):.........................................................................................................................

.............................................................................................................................

c):.........................................................................................................................

.............................................................................................................................

VI. EVALUATION OF THE INVESTIGATOR:

…………………………………………………………………………………………

…………………………………………………………………………………………

…………………………………………………………………………………………

…………………………………………………………………………………………

……….., date_____month_____year

Investigator Head of Hamlet/Quarter

(Signature, name) (Signature, name)

Page 84: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 83

Annex 7: List of people in department of NPMB

No Fullname Position Name of projects

1 Đỗ Đức Mạnh Manager Manager

2 Lê Thái Sơn Vice manager DZ 500kV Sơn La – Hiệp Hòa

3 Bùi Lê Duy Vice manager DZ 220kV Thường Tín – Kim Động; trạm 220kV Kim Động; DZ 220kV Thanh Hóa - Vinh

4 Nguyễn Mạnh Trường Vice manager TBA 220kV Hải Dương 2;

5 Lê Duyên Hạc

6 Phạm Văn Doanh TBA 220kV Hải Dương 2;

7 Lê Văn Nam

8 Nguyễn Ngc Trung TBA 220kV Tuyên Quang

9 Đinh Thị Hồng Minh

10 Vũ Thanh Hà

11 Nguyễn Văn Hùng ĐZ 220kV Thanh Hóa - Vinh

12 Phan Văn Vĩnh DZ 220kV Thường Tín – Kim Động; TBA 220kV Kim Động

13 Phạm Thế Thanh

14 Vũ Mạnh Quân

15 Nguyễn Quốc Khánh

16 Hong Xuân Lẽ

17 Nguyễn Quốc Dũng DZ 500kV Sơn La – Nho Quan – Hòa Bình; DZ 500kV Sơn La – Hiệp Hòa

18 Đỗ Quang Dũng

19 Nguyễn Lê Minh

20 Phạm Đình Linh

21 Bùi Cao Cường DZ 500kV Sơn La – Nho Quan – Hòa Bình; DZ 220kV Thanh Hóa – Vinh; TBA 220kV Bỉm Sơn

22 Bùi Đức Nghĩa DZ 500kV Sơn La - Hiệp Hòa

23 Hà Trng Cường

24 Nguyễn Hong Giang

Page 85: Social Monitoring Report VIE: Northern Power … Northern Power Transmission Expansion ... expansion of Van Tri 220 kV substation*; ... NORTHERN POWER TRANSMISSION EXPANSION SECTOR

NORTHERN POWER TRANSMISSION EXPANSION SECTOR PROJECT Post Resettlement Evaluation Report December 2015

Page 84

25 Nguyễn Lê Tùng

26 Nguyễn Ngc Hưng