21
Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Embed Size (px)

Citation preview

Page 1: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Significant Potential Incident

Arc Flash

Timmins, Ontario, Canada

March 3, 2011

Page 2: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

2

SERIOUS INCIDENT REVIEW

• Equipment: Motor Control Center #1 (MCC Bucket)

• Time/Date: March 3, 2011 @ 13:55

• Location: Penhorwood Mine Site

• Conditions: Normal Running Conditions

• Workgroup: Crushing Operations

• Supervisor: Gerry Rondeau

• Manager: Ross Byron

Page 3: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

3

Scenario description (maximum reasonable consequence)

An arc flash is an electrical breakdown of the resistance of air resulting in an electric arc which can occur where there is sufficient voltage in an electrical system and a path to ground or lower voltage. An arc flash with 1000 amperes or more can cause substantial damage, fire or injury. The massive energy released in the fault rapidly vaporizes the metal conductors involved, blasting molten metal and expanding plasma outward with extreme force. A typical arc flash incident can be inconsequential but could conceivably easily produce a more severe explosion (see calculation below). The result of the violent event can cause destruction of equipment involved, fire, and injury not only to the worker but also to nearby people.In addition to the explosive blast of such a fault, destruction also arises from the intense radiant heat produced by the arc. The metal plasma arc produces tremendous amounts of light energy from far infrared to ultraviolet. Surfaces of nearby people and objects absorb this energy and are instantly heated to vaporizing temperatures. The effects of this can be seen on adjacent walls and equipment - they are often ablated and eroded from the radiant effects.

Page 4: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

4

Risk Score= Consequence × Likelihood

Incident Risk Score

• Likelihood =

• Consequence =

• Maximum Reasonable Outcome (MRO) =

Page 5: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

5

Consequence Descriptors

Page 6: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

6

Likelihood Descriptors

Likelihood Likelihood description Frequency Substance Exposure

ALMOST

CERTAIN

Recurring event during the life-

time of an operation /

project

Occurs more than twice per

year

Frequent (daily) exposure at >

10 x OEL

LIKELY

Event that may occur

frequently during the life-

time of an operation /

project

Typically occurs once or twice

per year

Frequent (daily) exposure at >

OEL

POSSIBLEEvent that may occur during

the life-time of an operation

/ project

Typically occurs in 1-10 years

Frequent (daily) exposure at >

50% of OEL

Infrequent exposure at > OEL

UNLIKELYEvent that is unlikely to occur

during the life-time of an

operation / project

Typically occurs in 10-100

years

Frequent (daily) exposure at >

10% of OEL

Infrequent exposure at > 50%

of OEL

RARE

Event that is very unlikely to

occur very during the life-

time of an operation /

project

Greater than 100 year event

Frequent (daily) exposure at <

10% of OEL

Infrequent exposure at > 10%

of OEL

Page 7: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

7

What Happened

• Crusher operator enters MCC#1 room to sequence start the crushing plant.

• Upon starting rod deck, a loud noise is heard.

• Operator investigates the noise.

• Operator sees that the panel has been blackened.

• He reports incident to Maintenance Supervisor.

Immediate Response• Maintenance Supervisor orders to keep systems down.

• Investigation begins with Electrician, Crusher Operator and HS Coordinator.

Page 8: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Snap Chart (timeline of events)

Page 9: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Snap Chart (timeline of events)

9

Page 10: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Snap Chart (timeline of events)

10

Page 11: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Photos of the incident site and scene

11

Page 12: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Photos of the incident site and scene

12

Page 13: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

Photos of the incident site and scene

13

Page 14: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

14

Photos of the incident site and scene

Page 15: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011
Page 16: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

16

Process review (see notes)

1. Incident / Injury Management:– Emergency process followed ? YES– Further potential minimized ? YES– Employee statements taken ? YES– Injury management process followed ? YES– Alcohol and Drug Test conducted for all parties associated ? N/A– Notifications (Internal & Government agencies etc) carried out accurately in appropriate timeframes ? YES

2. Scene:– Supervisor in attendance? YES– Photos taken ? YES– Scene and evidence preserved ? YES

3. Persons Involved:– Inductions in place and up to date ? YES– Appropriate training up to date ? YES– Experience /familiarity with task ? YES– Pre-existing injury ? NO– Is fatigue / stress a contributing issue ? YES

4. Procedures, instructions & permits– Safe Work Procedure exists for task ? YES– Safe Work Procedure is adequate (covers task hazards involved) ? YES– Was the procedure for the task followed (as per procedure) ? YES– Has there been a formal risk assessment for the task? YES– Did the risk assessment identify the hazards appropriately ? YES– Permits required for task were in place (attach copy) ? YES

Page 17: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

17

5. Contractor Management System: – Safety expectations meeting occurred with contractor principals prior to start of contract ? N/A– Safety expectations briefing occurred with contract employees at start of contract ? N/A– Contractors procedures were reviewed for adequacy prior to commencement ? N/A– Accountability for the contractor is clear (defined contract manager) ? N/A

6. PPE, Tools & Conditions:– Was task specific adequate Personal Protective Equipment (PPE) worn ? YES– Tools/equipment adequate ? YES– Working conditions (light/dark/cold/hot/noise/dust/water/ice/snow) ? NO– Was there a change in task or conditions ? YES

7. Behaviors & risk psychology:– Was the task a “routine task” ? YES– Risk awareness issue (was the person aware of the potential for something undesirable occurring unknown before the event) ? – Risk Judgment issue (was the person aware of the potential for something undesirable to occur, but underestimated the

significance of the event) ?

– Risk acceptance issue (was the person aware of the consequence potential, but the positive consequences for the action outweighed the possible negative consequences) ?

– Were the critical decisions made consciously or subconsciously ? YES– Do others people perform the same actions or behaviors ? NO– Typically what are the consequences for others who perform the same behaviors ?

8. Supervision:– Adequate coverage ? YES– Experienced in specific task work ? YES– Work Load of supervision ? – Had the supervisor visited the task site prior to the incident ? NO– Was a clear task assignment given for the task (CPQQRT) NO– When last had the supervisor visited the task site prior to the incident ?

Process review (see notes)

Page 18: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

18

Mitigating Factors (i.e. factors that prevented the outcome from being more serious)

• The bucket door was closed and secured.

• The MCC room is a restricted area.

Page 19: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

19

Contributing / Causal Factors ( list all factors that are believed to have contributed to the incident occurring – from SnapChart TM )

• Multi tasking, electrician called away during a critical part of this task.

• Electrician did not perform a Take 5 to reflect on where he was in his task once he came back.

Page 20: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

20

Lessons Learned• There is a right time and a wrong time to step away from an unfinished

task.

• The electrician was contacted by production because a piece of

equipment was causing to whole plant to be down and no production

was being made. He chose to leave his task half completed and

started working on the equipment. He then came back to his original

task in the MCC bucket.

• Upon arrival the plate was noticed to be on, so he continued from

there. Never coming back to ensure the plate was indeed screwed in.

Page 21: Significant Potential Incident Arc Flash Timmins, Ontario, Canada March 3, 2011

21

Root Cause & Corrective Actions (what, who and by when)

Root Cause Corrective Action Responsible

Person

Target

Date

Employee distracted at a

critical point in his job

Maintenance Supervisor to

ensure that the Take 5 process

is followed. Employee must be

familiar when a critical

component of a task cannot be

interrupted.

Gerry

Rondeau

March

31,

2011

Electrician did not tighten

the bolts on which secure

the cover.

Maintenance Supervisor to

have a meeting with Electrician

in regards to his actions in this

incident. Meeting to be

documented.

Gerry

Rondeau

March

31,

2011