Upload
rajendrasenapati
View
547
Download
75
Tags:
Embed Size (px)
DESCRIPTION
Short term hydro thermal scheduling, unit commitment
Citation preview
SHORT TERMHYDRO-THERMAL COORDINATION
Presented ByRajendra Narayan Senapati
Roll no-26243Regd. No.-0701105115
22nd MAR 2011
Outline1) Introduction2) Need of Hydrothermal Scheduling3) Classification of Hydro Plants4) Classification of Hydrothermal Scheduling Problem5) Solution for Short-term Scheduling Problem6) Conclusion7) References
22nd MAR 2011
Introductiono Hydro-plants can be easily started and assigned load in
very short time.o Slow response of thermal power due to boiler, super
heater, and turbine system.o Thermal plant base load planto Hydro plant peak load plant
22nd MAR 2011
Need of Hydrothermal Scheduling
•The optimal scheduling problem in a hydro-thermal system stated as to minimize the fuel cost of thermal plants under the constraint of water availability for hydro-generation over a given period of operation•To maintain an optimal balance between fuel cost and water storage level to maintain reliable and uninterrupted operation.• To test these techniques on different problems.
22nd MAR 2011
22nd MAR 2011
Classification of Hydro Plants
•Classification1. Pumped storage plants2. Conventional plants
•Classification on the basis of location1. Hydro plants on different streams2. Hydro plants on the same stream3. Multi-chain hydro plants
•Classification on the basis of Quantity of Water Available1. Run-off- River Plants without Pondage2. Run-off River Plants with Pondage
22nd MAR 2011
Classification of Hydrothermal Scheduling Problem
•Long range problemlong-range scheduling is validity ranges from 1 week to 1 year or several years.Long-term hydrothermal scheduling is used for breaking down the long-term problem into a number of midterm (e.g., monthly) problems.•Short range problemInvolves the hour-by-hour scheduling of all generation on a system to achieve minimum production cost for the given time period.The load, hydraulic inflows, and unit availabilities are assumed known.Reservoir levels is given 22nd MAR 2011
Scheduling problem consists of•Problem characteristics.•Problem formulation. •Solution approach
Scheduling Problems
22nd MAR 2011
Two-unit hydrothermal systems
22nd MAR 2011
For any time period j
However, the energy available from the hydro plant is insufficient to meet the load
22nd MAR 2011
Use here the entire amount of energy from the hydro plant in such a way that the cost of running the steam plant is minimized. The steam-plant energy required is
i.e. (Load energy) - (Hydro energy) = (Steam energy)
It does not require the steam unit to run for the entire interval of Tmax hours. Therefore
22nd MAR 2011
Where
= run period for steam plant Then
The scheduling problem becomes
Subject to
And the Lagrange function is
22nd MAR 2011
Then
The total cost over the interval is
Where
Let the steam plant cost be expressed as
Then
22nd MAR 2011
Also
Where = Optimum value of stem generated powerThen
= /
And
Now we can establish the value of Ps* by minimizing FT:
Or
22nd MAR 2011
Which means the unit should be operated at its maximum efficiency point long enough to supply the energy needed, E.
IfWhere fc is the fuel cost
Now the heat rate is
And the heat rate has a minimum when
Giving best efficiency at
Solution for Short-term Scheduling Problem
22nd MAR 2011
Fixed head hydro thermal scheduling
Variable head hydro thermal scheduling
Problem Characteristics
22nd MAR 2011
Problem Formulation
22nd MAR 2011
Thermal Model
operating cost
fuel cost
Hydro Model
22nd MAR 2011
rate of discharge
Constraints
Classical Method
22nd MAR 2011Hydrothermal system with hydraulic constraints
22nd MAR 2011
Problem
Subject to
Let = length of jth interval
The loads are constant in each interval. Other constraints could be imposed, such as:
The Lagrange function is:
for a specific interval j =k,
22nd MAR 2011
So
Suppose we add the network losses to the problem. Then at each hour
And the Lagrange function becomes
With resulting coordination equations (hour k):
22nd MAR 2011
Flow Chart for Classical Method22nd MAR 2011
Conclusion
•Hydro-thermal scheduling is done when power demand is less than the maximum capacity of power generation by the hydro and thermal plants. The benefit of this scheduling is to save the cost of generation, in addition to meeting the agricultural and irrigational requirements.•The operating cost of thermal plant is very high, though their capital cost is low. On the other hand the operating cost of hydroelectric plant is low, though their capital cost is high. So it has become economical as well convenient to have both thermal and hydro plants in the same grid.
22nd MAR 2011
Referrences•Kothari D.P., Dhillon J.S., “Power System Optimization”, Prentice Hall of IndiaPrivate Limited, New Delhi, 2004.•Elgerd O.I, “Electric Energy Systems theory, An Introduction”, Tata McGraw Hill Limited, New York, 1983.•Grainger J.J., Stevenson W.D., “Power System Analysis”, Tata McGraw Hill Limited, New York,2003.•Fabrício Y. K. Takigawa, Erlon C. Finardi, Edson L. da Silva, “A Decomposition Strategy to Solve the Short-Term Hydrothermal Scheduling Based on Lagrangian Relaxation”,2005.•Hota P.K., Barisal A.K., Chakrabarti R., “An improved PSO technique for short-term optimal hydrothermal scheduling”,2009.•Ramos L.M., Lora A.T., Santos J.R., “Short-term Hydro-thermal Coordination Based on Interior Point Nonlinear Programming and Genetic Algorithms”,2001.
22nd MAR 2011
THANK YOU