Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Chelopech Mine, Bulgaria
SCOTIABANK MINING CONFERENCE
DPM CORPORATE PRESENTATION
December 7, 2016
TSX:DPM 2
FORWARD LOOKING STATEMENTS
This presentation contains “forward looking information” or "forward looking statements" that involve a number of risks and uncertainties.
Forward looking information and forward looking statements include, but are not limited to, statements with respect to the future prices of
gold and other metals, the estimation of mineral reserves and resources, the realization of mineral estimates, the timing and amount of
estimated future production and output, costs of production, capital expenditures (including sustaining capex, non-discretionary capex
and discretionary capex), costs and timing of the development of new deposits, success of exploration activities, permitting time lines,
currency fluctuations, requirements for additional capital, government regulation of mining operations, environmental risks, unanticipated
reclamation expenses, title disputes or claims, limitations on insurance coverage and timing and possible outcome of pending litigation.
Often, but not always, forward looking statements can be identified by the use of words such as “plans”, “expects”, or “does not expect”,
“is expected”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “does not anticipate”, or “believes”, or variations
of such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be
achieved. Forward looking statements are based on the opinions and estimates of management as of the date such statements are
made, and they involve known and unknown risks, uncertainties and other factors which may cause the actual results, performance or
achievements of the Company to be materially different from any other future results, performance or achievements expressed or implied
by the forward looking statements. Such factors include, among others: the actual results of current exploration activities; actual results of
current reclamation activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future
prices of gold; possible variations in ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated;
accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing or in the
completion of development or construction activities, fluctuations in metal prices, as well as those risk factors discussed or referred to in
this presentation under and in the Company’s annual information form under the heading "Risk Factors" and other documents filed from
time to time with the securities regulatory authorities in all provinces and territories of Canada and available at www.sedar.com. Although
the Company has attempted to identify important factors that could cause actual actions, events or results to differ materially from those
described in forward-looking statements, there may be other factors that cause actions, events or results not to be anticipated, estimated
or intended. There can be no assurance that forward looking statements will prove to be accurate, as actual results and future events
could differ materially from those anticipated in such statements. Accordingly, readers are cautioned not to place undue reliance on
forward looking statements.
TSX:DPM 3
AN INNOVATIVE GROWTH ORIENTED GOLD PRODUCER
Offer Investors a deep value investment opportunity
Low cost gold production growth of over 60% by 2019 with the permitted
Krumovgrad Gold Project
Solid EBITDA growth with growing free cash flow
Strong balance sheet with financial flexibility
Strong reserve base with exploration upside potential around existing
assets and regionally
Recognized as a leading innovator in the mining industry
TSX:DPM 4
DPM’S GLOBAL PORTFOLIO OF ASSETS
Unique Assets With Commodity & Geographic Diversity
Avala
Serbia
100%
Tsumeb Smelter
Namibia
100%
Chelopech Mine
Bulgaria
100%
Sabina
Canada
11%
Krumovgrad Gold Project
Bulgaria
100%
Operating assets
Development asset
Exploration assets
TSX:DPM 5
DPM’S VISION AND STRATEGY
Optimize Portfolio Growth Innovation
Increased profitability by
driving operational
excellence, underpinned by
effective leadership and
systems
A progressive gold mining company that unlocks and delivers superior value
through innovation and strong partnerships with stakeholders
Grow the business by
realizing the value of our
pipeline of assets
enhanced by M&A,
exploration and rapid
deployment
Create value through
deployment of technology
and innovation underpinned
by internal capability and
strategic partnerships
Maintain Financial Strength and Flexibility
TSX:DPM 6
ATTRACTIVE VALUE INVESTMENT OPPORTUNITY
Hard Hit Sector Valuations Creating
A Rare Investment Opportunity
$0.00
$1.00
$2.00
$3.00
$4.00
$5.00
$0
$500
$1,000
$1,500
$2,000
2013 2014 2015
Cu price
2012
Au price
2016
$500
$800
$1,100
Dundee Alacer New Gold Alamos Primero
Average = $890/oz
$750-850/oz
Below Average 2016F All-In-Sustaining Mine Cost (3)(4)(10)(11)(12)(14)
3,4,10,11,12,14 See footnotes contained in Appendix on slide 43
Attractive Valuation Metrics
EV/2016F EBITDA (Cons. Est.)
P/NAV (Cons. Est.)(12)
New Gold Alamos Argonaut Alacer DPM Primero
0.56x
0.92x
0.65x0.70x
0.39x0.37x
Avg. 0.60x
2016: $1,275 Au
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
$0.00
$2.00
$4.00
$6.00
$8.00
$10.00
$12.00
20132012 2014
DPM share priceGDXJ performance
2015 2016
Alamos New Gold Alacer Primero Argonaut DPM
8.2x
10.2x
7.2x
6.0x 5.8x5.1x
Avg. 7.1x
TSX:DPM 7
CONSOLIDATED RESULTS AND OUTLOOK
626690
890
725
640
510
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
687
750-
850
153 161 169132-155 143
166
217
270
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
198
195-205
220-250
265-320
370
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
196
46 4340
35.7-39.7
34 36 36 37
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
Payable Copper (Mlbs)Payable Gold (Koz) Smelter Production (Kt)
All-in Sustaining Cost (US$/oz)Capital Expenditures (US$M) Smelter Cash cost (US$/t)
152
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
216 Sustaining CAPEX
Non-discretionary Growth CAPEX
Discretionary Growth CAPEX
184
87
54-65
99
24
380
310275 265
2013 2014 2015 2016F 2017F 2018F 2019F 2020F
27
173
(4) (4) (4)
(3)(4) (3)(4)
(13)(13)
430-
450
409394
479
320-
370
3,4,13,15 See footnotes contained in Appendix on slide 43
(3) (4)
(15) (15)
TSX:DPM 8
STRONG FINANCIAL POSITION
• Net debt at end of Q3 - $32M
• Sale of Kapan - $25M plus working capital adjustment and 2% NSR on future production
• Completion of C$57M equity offering
• Increased Cu and Au hedge positions to the following levels
• Cu hedged 75% and 38% of BOY2016 and 2017 production at avg. price of $2.24/lb
• Au hedged 15% and 30% of BOY2016 and 2017 payable gold production using
collars with avg. floor/cap of $1,200/$1,495 per ounce
• Prepaid forward gold sale – sale of 9% of forecast 2019 & 2020 Au production for upfront
cash prepayment of $50M
Cash &
cash equivalents
$62MUndrawn RCF
$205M
Available liquidity @ September 30, 2016
TSX:DPM 9
STRONG RESOURCES & RESERVES BASE
Mineral Resources Million Tonnes Au (Moz) Cu (Mlbs) Au (g/t) Cu (%)
Chelopech
M&I
Inferred
14.2
2.8
1.533
0.82
329
51
3.37
2.48
1.06
0.82
Krumovgrad
Inferred (upper) 0.3 0.013 1.31
Timok 1
Indicated
Inferred
67.42
4.3
2.48
0.2
1.14
1.0
Tulare 2
Inferred 547 3.8 2.8 billion 0.22 0.23
Total Mineral Resources
Indicated
Inferred
81.62
554.4
4.013
4.833
329
2.8 billion
Mineral Reserves Million Tonnes Au (Moz) Cu (Mlbs) Au (g/t) Cu (%)
Chelopech
Proven
Probable
11.88
9.64
1.167
1.020
266
178
3.06
3.29
1.02
0.84
Krumovgrad
Proven upper zone
Proven wall
Probable upper zone
Probable wall
1.1
1.5
3.5
0.1
0.124
0.325
0.337
0.02
3.46
6.83
3.00
5.54
Total Mineral Reserves 27.72 2.993 444
1. NI 43-101
Technical
Report
dated May
1, 2014
2. Dunav
Press
Release
dated June
23, 2014
TSX:DPM 10
9 MONTHS 2016 OPERATING RESULTS
Bulgaria
50%Namibia
45%
Canada
5%
2016 Asset
Diversification(2)
Tsumeb
25%
Chelopech
75%
2016 Adjusted EBITDA
Generation (3)(5)
2016 Revenue
Diversification (1)
Smelter
35%Gold
45%
Copper
19%
Ag 1%
1,2,3,5 See footnotes contained in Appendix on slide 43
* From continuing operations
Nine Months 2016
Consolidated Mines
Gold production (incl. pyrite) 128,018 oz
All in sustaining costs $788/oz Au
Tsumeb Smelter
Concentrate smelted 139,002 T
Cash cost/T con smelted $471
Consolidated Adjusted EBITDA* $42.8M
Chelopech Mine, Bulgaria
TSX:DPM 12
CHELOPECH 9 MONTH RESULTS
Highlights:
• Copper production – 29.6 million pounds
• Gold production (incl. pyrite) – 121,701 ounces
• Cash cost/ounce Au in Cu Con produced - $376
• Adjusted EBITDA – $58.7 million
Chelopech 9 month results in line with full year guidance
SAG Mill Underground crushing & conveying systems
TSX:DPM 13
CHELOPECH – A WORLD CLASS, LOW COST MINE
Recent Achievements
• Continuing to ramp up production beyond
2M tpy
• Real time operations with underground
wireless technology to optimize
operating performance
• Step change improvements in stope
mucking rates
• Successful reserves replacement
Building on that Success
• Aggressively drilling upper levels around old
cave zones to add additional resources
• Developing mining plans for cave zone
areas to begin mining in 2017
• Regional exploration program for potential
southeast extensions of existing orebodies
on newly acquired Brevene License
1.09
1.31
1.812.03 2.05 2.04
2.0-2.25
2010 2011 2012 2013 2014 2015 2016F
Ore Mined (mt)
(4)
2006 2015
Ore Mined / Reserves (mt)
21.5 21.5
14.1
56 55
46
40 4036 32-36
2010 2011 2012 2013 2014 2015 2016F
Cash Cost / tonne of ore processed (US$/t)(3)
2010 2011 2012 2013 2014 2016F(4)2015
Total ore
mined to date
Ore Reserve
3,4 See footnotes contained in Appendix on slide 43
TSX:DPM 14
Chelopech Real Time Operations
Mining
Planning & Scheduling
Maintenance
Planning & Scheduling
Supply chain / Logistics
Planning & Scheduling
Fe
ed
ba
ck
Info
rma
tionP
lanning
Info
rma
tio
n
Mining Execution Business Processes
Drilling Loading Transportation Crushing Conveying
Support & Maintenance Processes
Real time Process
Monitoring and Control
Mining Operations Management System
Tight Feedback Loop to Minimize Variation and Monitor Schedule Compliance
TSX:DPM 15
CHELOPECH – MOVING CAVE ZONE RESOURCES
INTO MINE PLANS
• Mineral Resource update reclassified 4.2 MT of
resources from inferred to indicated
• Target: start to move these resources into mine
plans in early 2017
Comparison of MRE as at December 31, 2015 with MRE as at December 31, 2014
Mineral Resources exclude all blocks already classified as Mineral Reserves
Resource
Category
2015
MTonnes
2014
MTonnes
Grades
2015 Cu2014
Cu
2015
Au2014 Au
(%) (%) (g/t) (g/t)
Total M+I 14.2 11.3 1.06 1.13 3.37 3.58
Inferred 2.8 8.3 0.82 0.91 2.44 2.66
Chelopech Ore Reserves as at December 31, 2015
Grades
Classification MTonnesGold
(g/t)
Silver
(g/t)
Copper
(%)
Total Proven and Probable 21.51 3.16 7.08 0.94
Chelopech Mine, Bulgaria
TSX:DPM 17
TSUMEB 9 MONTHS OPERATING RESULTS
3
18.5
8.6
2011 2014 2015
26
63
140130
44
24-28
2011 2012 2013 2014 2015 2016F
Total Capital Expenditures (US$M)
2012
2013(4)
Smelter Adjusted EBITDA (US$M)(5)
(2.5) (7)
Highlights:
• Total concentrate smelted – 139,002 tonnes
• Cash cost/T complex con smelted, net of by product credits – $471
• Adjusted EBITDA – $3.1 million
• Acid production – 130 MT
4,5 See footnotes contained in Appendix on slide 43
TSX:DPM 18
TSUMEB - CURRENT SCENARIO
(2)
152,457
198,346 199,000 195k – 205k
240,000
24,825 36,877
45,221 46,000 63,000
0
50,000
100,000
150,000
200,000
250,000
300,000
2013 2014 2015 2016 NormalOperation
Concentrate Smelted and Blister Production
Conc Blister
• New converters were commissioned in Q1 2016
• In Q2 and Q3 we resolved converter blower control constraints
• Q3 was dominated by two Ausmelt outages
• In Q4 we continue to debottleneck the converters
• Introduction of matte storage is planned for mid-year 2017 and this will
provide significant additional process stability
• Approximately 35,000t of smelter operation was lost in 2016 due to
additional Ausmelt outage, new converter optimization and high
pressure oxygen plant constraints. Of these, only converter optimization
is carried into 2017
Matte Holding Furnace
TSX:DPM 19
TSUMEB: SMELTING PERFORMANCE
3,4 See footnotes contained in Appendix on slide 43
(4) (4) (4)(4)(4)
(2)
(3),(4)
198 196
195-205
320-370
120
180
159152
370
312
341
420
479
394409
430-450
380
310
275265
2010 2011 2012 2013 2014 2015 2016F 2017F 2018F 2019F 2020F
Recent Achievements
• Major 5 year capex program now
completed
• Acid plant now capturing all of the
convertor and furnace SO2 offgasses
Building on that success
• Completing Expansion Feasibility Study
to 370,000tpa in Q4
• Negotiating contracts for third party
concentrate feeds
• Completing Environmental Impact
Assessment for submission in Q1 2017
• Exploring partnership options for
expansion funding
Third Party
con supplied
to smelter
(000s)
Chelopech
concentrate
supplied to
smelter
(000s)
Cash cost per
tonne of
concentrate
smelted (net of by
product credits)(3)
220-
250
265-
320
Anticipated
future capacity
(4) (4) (4)(4)(4)
TSX:DPM 20
OUTLOOK FOR COMPLEX CONCENTRATES
Mines In Operation Annual Tonnage As (%)
Chelopech 100,000 5.5%
South America(6) 150,000 – 250,000 4.0% - 8.0%
Blend 30,000 – 50,000 5.5% - 7.0%
TOTAL 280,000-400,000
Not in Production Annual Tonnage As (%)
South America(6) 80,000 6.0+%
Rest of the world 100,000 – 150,000 5.0% - 10%
TOTAL 180,000-230,000
6 See footnotes contained in Appendix on slide 43
Chelopech Mine, Bulgaria
TSX:DPM 22
KRUMOVGRAD BUSINESS OUTLOOK
Chelopech Mine, Bulgaria
Production and Operating Costs
Annual gold production (7) 85,700 oz
Annual silver production (7) 38,700 oz
First concentrate production H2 2018
LOM (7) 8 years
Total Annual Operating Costs / T ore processed (7)
Mining costs
Processing costs
Tailings treatment & IMWF costs
General & administration
Royalty
$45.41
$15.03
$19.39
$1.88
$5.33
$3.78
Capital Costs
Construction capital to complete (7)
Direct Costs
Indirect Costs
Contingency P50 (7.5% of direct + indirect costs)
$178.2 million
$117.1 million
$48.7 million
$12.4 million
Sustaining Capital $6.2 million
Closure and Rehabilitation Costs $6.0 million
Total cash cost per oz AuEq (7) $403
Average Annual EBITDA (5,7) $66 million
Project
economics remain
robust with a 25%
after-tax IRR
5, 7 See footnotes contained in Appendix on slide 43
TSX:DPM 23
KRUMOVGRAD – 2016-2018 PROJECT MILESTONES
Milestone Actual / Expected Completion (4)
Completion of the detailed project execution plan Q1 2016 (complete)
Complete detailed engineering Q1 2016 (complete)
Updated capital cost estimate and baseline project schedule Q1 2016 (complete)
Land re-designation and purchase Q1/2 2016 (both complete)
Approval of technical packages Q2 2016 (complete)
Construction permit RECEIVED AUGUST 9, 2016
Mobilize earthworks contractor to site Q4 2016
Commence main civil/mechanical/electrical construction Q2 2017
Commissioning and start up Q3 2018
First concentrate production Q4 2018
TSX:DPM 24
KRUMOVGRAD – Q4 2016 ACTIVITIES
• Completion of the early works program
• Complete mobilization and set up of the project team
• Complete outstanding geotech drilling (seven holes)
• Complete mobilization and set up of the earth works
contractor at the site
• Complete tree clearing
• Complete temporary access road to the site
• Commence earthworks activity at the site
TSX:DPM 25
KRUMOVGRAD SITE PHOTOS
Chelopech Mine, Bulgaria
Top of the hill
Temporary access road
Foot of the hillEquipment arriving at site
Top of the hill
Temporary access road
TSX:DPM 26
KRUMOVGRAD PROCESS PLANT AND SCOPE OF WORK
Crushing (0100)
Coarse ore
Storage (0100)
and Pebble
Crushing (0200)
Flotation (0300)
Conc Thickening
and Filtration
(0400)
Grinding (0200)
Tailings Thickening
Plant (1400) and HV
Area (0900/1050)
TSX:DPM 27
KRUMOVGRAD MINE PLAN SUMMARY
TSX:DPM 28
KRUMOVGRAD IMWF GENERAL OVERVIEW
Integrated Mine Waste Facility
(IMWF)
Open Pit
IMWF Haul Roads
and sump access
road
Raw and Process Water
Reservoir / Storm water
Overflow Reservoir
Grout Curtain
Pump
station
TSX:DPM 29
KRUMOVGRAD IMWF CONSTRUCTION
Grout Curtain
SumpFirst ‘Lifts’
Chelopech Mine, Bulgaria
TSX:DPM 31
EXPLORATION – BROWNFIELDS - CHELOPECH
Chelopech Mine, Bulgaria
Drilling commenced at SE Breccia pipe zone
TSX:DPM 32
EXPLORATION – BROWNFIELDS - CHELOPECH
Hole No. 555-01 Section
SE Breccia Pipe Zone
Diorite
Diorite
silic
a+d
icki
tep
yro
ph
yllit
e
Cu
-po
or
Cu
-be
arin
g
AAA: kaolinite
AAA: pyrophyllite
AAA: silica-dickite
Orebody #10
Intervals with observedCu-bearing minerals
Southeast Breccia Pipe • First of 7 UG holes commenced in
September.
• 555-01 intersected weak
mineralization hosted by phreato-
magmatic breccia with zones of
advanced argillic alteration (assays
pending).
• Confirms HSE system is open to
southeast beneath the Chelopech
Thrust Fault.
• 555-02 testing eastern extension of
the SE Breccia Pipe on the Brevene
Exploration Licence.
Brevene Exploration License• Granted on September 1
• Comprehensive work program
approved by MOE.
TSX:DPM 33
EXPLORATION – BROWNFIELDS - KRUMOVGRAD
Chelopech Mine, Bulgaria
Kupel North Drill Program
TSX:DPM 34
EXPLORATION – BROWNFIELDS – TIMOK, SERBIA
Chelopech Mine, Bulgaria
Chelopech Mine, Bulgaria
Korkan resource
Bigar Hill resource
BIDD056
Target area 1
BIDD060
Target area 2
Target area 3
2km
• 3000m drill program to find additional
near-surface resources in proximity to
existing resources at Bigar Hill and
Korkan.
• Three near-resource target areas are
being tested during 2016. Results to date
from Target area 1 include:• BIDD056: 5m @ 0.52g/t Au, 0.51% Pb & 0.20% Zn.
• BIDD060: 6m @ 0.64g/t Au, 1.56% Pb & 0.70% Zn.
• Dundee Sustainable Technologies
• Chlorination of ore after oxidation and
acid leaching gave 84% Au recovery.
• CSA resource update in progress.
• Pit-constrained
• Re-reported resource with updated
assumptions
• Updated 43:101 technical report &
statement in time for 2017 AIF.
Near Resource Drill Program
TSX:DPM 35
EXPLORATION – GREENFIELDS – TIMOK & UMKA
Korkan North
Bigar South
Umka license
Bigar Istok
Coka Rakita
Umka“porphyry”
Bkgrd: Au in soils
IP & resistivity surveys (lines)
Infill soil surveys (points)
5km
• Soil survey sampling commenced in August
• Results received for Bigar and Pester areas;
compilation with geophysics planned for Q4.
• IP & resistivity geophysics commenced in August
• Completed over Bigar South, Pester, and Umka
North areas.
• Pending completion over Korkan North.
• Coka Rakita (Au-porphyry target) – trench program
completed; drill targeting underway to expand target
volume.• RATR043: 8m @ 2.61g/t Au, inc. 2m @ 4.53g/t Au.
• RATR045: 10m @ 1.14g/t Au
• Umka license under evaluation, infill soils collected
on western sediment units and along monzonite
contact.
• Technical Review in October – generating drill
targets for 2017.
IP, Soil Geochemistry and Trenching
35
Chelopech Mine, Bulgaria
TSX:DPM 37
SOLID FINANCIAL POSITION HEADING INTO
KRUMOVGRAD CONSTRUCTION
Chelopech Mine, Bulgaria
Chelopech Mine, Bulgaria
• Forecast cash flows and available capital resources support growth projects
• Actions taken in 2016 that have increased financial flexibility
• Amended $275mm RCF to align with Krumovgrad project schedule
• Sale of Kapan - US$25mm plus working capital adjustment and 2% NSR
• Equity offering - C$57mm
• Prepaid forward gold sales - $50mm or ~9% of forecast 2019 & 2020 Au production $50mm
• Increased Cu and Au hedge positions
• Cu – Hedged 75%, 74% and 30% of BOY2016, 2017 and 2018 production at an average price of $2.32,
$2.35 and $2.62 per pound, respectively
• Au – Hedged 15% and 30% of BOY2016 and 2017 payable gold production using collars with an
average floor/cap of $1,200/$1,495
5
0.0
5.0
10.0
15.0
20.0
25.0
Sept. 30, 2016
0.80
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
Sept. 30, 2016
267
0
50
100
150
200
250
300
Sept. 30, 2016
RCFThreshold
32
0
50
100
Sept. 30, 2016
Reported Net Debt ($mm) Net Debt / Capitalization (%) Available Liquidity ($mm) Net Debt / EBITDA (x)
Chelopech Mine, Bulgaria
TSX:DPM 39
KEY MILESTONES
2016 2017 2018Q4 expansion study to
370,000 tpy concentrate
smelted
Smelter
KrumovgradQ4 Commence Earthworks
H2 First concentrate production
Chelopech Expansion study to 2.5 mtpy
ore production
Q4 Financing plan in place
Q2 Expansion study Detailed
Engineering
Q3 Ausmelt Cooling Upgrade
Expansion Implementation
Construction
Production ramp to 2.2 mtpy
Evaluation of mining and
milling intensity constraints
Resource development above
390 level targeted at
increasing reserves
Expansion Implementation
Chelopech Mine, Bulgaria
Corporate Head Office:
One Adelaide Street East, Suite 500
Toronto, Ontario
M5C 2V9
T: 416 365-5191
Investor Relations
T: 416 365-2549
TSX:
DPM – Common Shares
www.dundeeprecious.com
Thank You
TSX:DPM
APPENDICES
TSX:DPM 42
APPENDIX CONTENTS
Footnotes and Disclaimers…………………………………………………………………. 43
Market Cap., Major Shareholders, Analyst Coverage…………………………………… 44
2016 Guidance………………………………………………………………………………. 45
Hedge Positions at June 30, 2016….……………………………………………………. 46
Exploration – Partially Owned Exploration Assets……………………………………….. 47
TSX:DPM 43
FOOTNOTES AND DISCLAIMERS
1. From continuing operations
2. Estimated to end of 2016
3. A non-GAAP measure. Refer to the “non-GAAP Financial Measures” section of the Full Year 2015 MD&A for reconciliations to IFRS
4. Forecast/guidance information is subject to a number of risks. 2016F is based on guidance issued November 9, 2016 and 2017 to 2020 forecast data is based on the completion of several growth
projects within currently contemplated time frames. See “Forward Looking Statements” on slide 2
5. Adjusted EBITDA represents earnings before income tax plus depreciation and amortization, finance costs, losses/gains on impairment provisions and reversals, unrealized losses/gains on
derivative contracts and investments at fair value, realized and unrealized losses/gains on equity settled warrants, minus interest income
6. Additional penalty income available from other deleterious elements
7. Based on 2014 Krumovgrad Technical Report; Project economics based on June 6, 2016 Krumovgrad Update; All costs expressed as Q4 2015 US$ based on a US$ / Euro exchange rate of 1.14
8. Net Debt represents term debt and amount drawn under revolving credit facility, less cash
9. Undrawn portion of RCF and cash
10. Source: company midpoints of AISC per ounce of gold guidance provided in Q4 2015
11. AISC per ounce of gold represents cost of sales at Chelopech less depreciation, amortization and other non-cash items plus treatment charges, penalties, transportation and other selling costs,
sustaining capital expenditures, rehabilitation related to accretion expenses and an allocated portion of the Company’s G&A expenses less by-product revenues in respect of copper and silver
including realized gains on copper derivative contracts divided by the payable gold in copper concentrate sold
12. Source: RBC as at November 24, 2016
13. Reflects payable production and, in the case of gold, includes estimated payable gold in pyrite concentrate sold
14. Excludes metals in pyrite concentrate and where applicable, the treatment charges, transportation and other selling costs related to the sale of pyrite concentrate which is reported separately
15. Excludes Kapan
Without limitation to the foregoing, the following outlines certain specific forward looking statements contained in this presentation and provides certain material assumptions used to develop such forward looking
statements and material risk factors that could cause actual results to differ materially from the forward looking statements (which are provided without limitation to the additional general risk factors discussed
herein and in the Full Year 2015 MD&A).
Sustaining CAPEX, Non-Discretionary CAPEX and Discretionary CAPEX: assumes foreign exchange rates remain at or around current levels, and all capital projects proceed as planned and at a cost that is
consistent with the budget established for each project. Subject to a number of risks, the more significant of which are: technical challenges; delays related to securing necessary approvals, equipment deliveries,
equipment performance, and the speed with which work is performed; availability of qualified labour; and changes in project parameters, timing and decision to proceed with projects and/or any components there
of and estimated costs, including foreign exchange impacts.
Gold and Copper Production: projected levels of metal production assumes grades and recoveries are consistent with current estimates of Mineral Resources and Mineral Reserves and DPM’s current
expectations and construction start-up of Krumovgrad project and decision to proceed with projects and/or any components there of; and ore mined/milled is consistent with planned levels. Subject to a number of
risks, the more significant of which are: lower than anticipated ore grades, recovery rates and ore mined/milled.
Smelted Concentrate: assumes no significant disruption in equipment availability or concentrate supply. Subject to a number of risks, the more significant of which are: unanticipated operational issues; timing and
decision to proceed with expansion projects, including the holding furnace, and/or any components there of; unanticipated issues related to the commissioning and operation of the acid plant and converters and
any further expansion components including a holding furnace; lower than anticipated equipment availability; and disruptions to or changes in the supply of concentrate.
Technical Information related to slide 23 – Krumovgrad Project Economics
The Mineral Resource and Mineral Reserve estimates and other scientific and technical information which supports this presentation was prepared by CSA Global (UK) Ltd. (“CSA”), in accordance with Canadian
regulatory requirements set out in National Instrument 43-101 Standards of Disclosure for Mineral Projects, and were reviewed and approved by, as relates to Mineral Resources, Galen White, BSc (Hons)
FAusIMM FGS, Director and Principal Consultant of CSA, and Julian Bennett, BSc ARSM FIMMM CEng, as relates to Mineral Reserves. Both Galen White and Julian Bennett are independent Qualified Persons
(“QP”), as defined under NI 43-101. The NI 43-101 technical report (the “Krumovgrad Technical Report”) entitled “NI 43-101 Technical Report, Ada Tepe Deposit, Krumovgrad Project, Bulgaria” dated March 21,
2014, in respect of the study for the construction and operation of its Krumovgrad gold project disclosed herein, was filed March 31, 2014 on SEDAR at www.sedar.com. Simon Meik, Processing, and Edgar
Urbaez, formerly Corporate Director, Technical Services, both of DPM, who are QPs and not independent of the Company, have reviewed and approved the contents of this presentation. The Mineral Resource
and Mineral Reserve estimates contained herein may be subject to legal, political, environmental or other risks that could materially affect the potential development of such Mineral Resources. See the
Krumovgrad Technical Report for more information with respect to the key assumptions, parameters, methods and risks of determination associated with the foregoing Mineral Resource estimates.
Cautionary note to U.S. Investors concerning estimates of Mineral Resources. These estimates have been prepared in accordance with the requirements of Canadian securities laws, which differ from the requirements of U.S. securities laws. The
terms “mineral resource”, “measured mineral resource”, “indicated mineral resource” and “inferred mineral resource” are defined in NI 43-101 and recognized by Canadian securities laws but are not defined terms under the U.S. Securities and
Exchange Commission (“SEC”) Guide 7 (“SEC Guide 7”) or recognized under U.S. securities laws. U.S. investors are cautioned not to assume that any part or all of mineral deposits in these categories will ever be upgraded to mineral reserves.
“Inferred mineral resources” have a great amount of uncertainty as to their existence, and great uncertainty as to their economic and legal feasibility. It cannot be assumed that all or any part of an “inferred mineral resource” will ever by upgraded
to a higher category. Under Canadian securities laws, estimates of “inferred mineral resources” may not form the basis of feasibility or pre-feasibility studies. U.S. investors are cautioned not to assume that all or any part of an inferred mineral
resource exists or is economically or legally mineable. Accordingly, these mineral resource estimates and related information may not be comparable to similar information made public by U.S. companies subject to the reporting and disclosure
requirements under the U.S. federal securities laws and the rules and regulations thereunder, including SEC Guide 7.
TSX:DPM 44
MKT CAP, MAJOR SHAREHOLDERS, ANALYST COVERAGE
Share Price (C$ per share) $2.37
Shares Outstanding – Current 161M
Market Capitalization – Current C$382 M
52 week low – high (C$ per share) $0.84 – $4.14
Share Capital @ December 7, 2016 Analyst Coverage
Firm Analyst
BMO **In transition**
CIBC Capital Markets Jeff Killeen
Dundee Capital Partners Josh Wolfson
GMP Securities Oliver Turner
Paradigm Capital Don MacLean
Raymond James **In transition**
RBC Capital Markets Sam Crittenden
Scotia Capital Trevor Turnbull
Dundee Corporation 22.66%
GMT Capital 12.55%
Van Eck Associates 9.70%
USAA Asset Mgmt. 3.53%
Kopernik Global Investors 3.49%
Major Shareholders
TSX:DPM 45
2016 GUIDANCE @ SEPTEMBER 30, 2016
US millions, unless otherwise indicated Chelopech Kapan (5) Tsumeb Consolidated (6)
Ore mined/milled (‘000s tonnes) 2,030-2,250 131 - 2,161-2,381
Complex concentrate smelted (‘000s tonnes) - - 195-205 195-205
Metals contained in copper and zinc concentrates produced (1)(2)
Gold (‘000s ounces) 108-118 6 - 114-124
Copper (million pounds) 35.0-39.0 0.7 - 35.7-39.7
Zinc (million pounds) - 2.8 - 2.8
Silver (‘000s ounces) 204-234 111 - 315-345
Payable gold in pyrite concentrate sold (‘000s ounces) 26-40 - - 26-40
Cash cost per tonne of ore processed ($) (3)(4) 32-36 81 - 32-36
Cash cost per ounce of gold sold, net of by-product credits ($) (1)(3)(4) 550-650 1,136 - 550-650
All-in sustaining cost per ounce of gold ($) (1)(3)(4) - - - 750-850
Cash cost per tonne of complex concentrate smelted, net of by-product credits ($) (3)(4) - - 430-450 430-450
Cash cost per ounce of gold sold in pyrite concentrate ($) (4) 750-850 - - 750-850
General & administrative expenses (3) - - - 17-21
Exploration expenses (3) - - - 5-6
Sustaining capital expenditures (3) 10-12 3 12-16 22-28
1) Excludes metals in pyrite concentrate and, where applicable, the treatment charges, transportation and other selling costs related to the sale of
pyrite concentrate, which is reported separately.
2) Metals contained in concentrate produced are prior to deductions associated with smelter terms.
3) Based on foreign exchange rates and metal prices that approximate current rates and prices. The assumed copper price reflects the impact of 67%
of 2016 copper production being hedged at $2.32 per pound.
4) Cash cost per tonne of ore processed, cash cost per ounce of gold sold, net of by-product credits, all-in sustaining cost per ounce of gold, cash cost
per tonne of complex concentrate smelted, net of by-product credits and cash cost per ounce of gold sold in pyrite concentrate have no standardized meaning under GAAP. Refer to the “Non-
GAAP Financial Measures” section of the Q2 2016 MD&A for reconciliations to IFRS.
5) As a result of the Kapan Disposition, which closed on April 28, 2016, Kapan’s operating results have been treated as a discontinued operation and its production and cost guidance reflects
actual performance for the period January 1 – April 28, 2016.
6) Consolidated guidance for ore mined/milled and metals production includes results from the discontinued Kapan operation. Consolidated guidance for cash cost per tonne of ore processed,
cash cost per oucne of gold sold, net of by-product credits, all-in sustaining cost per ounce of gold and capital expenditures pertains to continuing operations.
TSX:DPM 46
HEDGE POSITIONS AT SEPTEMBER 30, 2016
Year of projected payable copper production Volume Hedged (lbs) % Hedged Average fixed price ($/lb)
Balance of 2016 6,316,236 75% $2.32
2017 14,550,492 38% $2.17
QP Commodity Hedged Volume Hedged % Hedged Average fixed price
Payable gold 31,490 oz 100% $1,327.17/oz
Payable copper 9,479,866 lbs 100% $2.20/lb
Payable silver 24,850 oz 100% $18.76/oz
Year of projected payable
gold in pyrite con productionVolume Hedged (oz)
% Hedged(payable gold in pyrite
con production)
Average fixed price of Pyrite Production
Hedges ($/oz)
Balance of 2016 2,010 29% 1,150.00
Year of projected operating
expensesForeign currency hedged
Amount hedged in
foreign currency% Hedged
Average exchange rate
Foreign currency/US$
Balance of 2016Euro
South African rand
2,925,000
189,000,000
23%
62%
1.1166
13.3230
2017Euro
South African rand
10,800,000
720,000,000
23%
63%
1.1287
13.8699
TotalEuro
South African rand
13,725,000
909,000,000
1.1261
13.7525
Year of projected payable gold production Volume Hedged (oz) Average ceiling
price ($/oz)Floor Price ($/oz)
Balance of 2016 3,300 1,484 1,200
2017 45,000 1,497 1,200
TSX:DPM 47
Sabina Gold & Silver Corp. (TSX:SBB), Nunavut
• Canadian-based, precious metals company with assets in Nunavut
• DPM holds 11.8%
• Assets include:
• High Grade Back River Gold Project:
• September 2015 updated feasibility study*:
o Mill throughput of 3,000 tpd
o Avg. annual gold production of 198,100 oz @ $US534/oz cash cost
o LOM 11.8 years
o Pre-production capital C$415M; Sustaining capital C$185M; Closure capital C$64M
o Post-tax IRR of 24.2% and NPV of C$480.3M
• Hackett River payable silver royalty from Glencore Zinc:
22.5% of first 190M oz Ag, 12.5% thereafter
PARTIALLY OWNED EXPLORATION / DEVELOPMENT ASSETS
*Calculated using US$1,150/oz Au price