36 Years. RURAL ELECTRIFICATION PROGRAM. 5 October 2005 H onesty, E fficiency and S olidarity A uditorium. REPUBLIC ACT 6038 (1969). Created NEA as the Primary Agency to implement the RURAL ELECTRIFICATION PROGRAM (REP) - PowerPoint PPT Presentation
Citation preview
RURAL ELECTRIFICATION PROGRAM
5 October 2005Honesty, Efficiency and Solidarity Auditorium
REPUBLIC ACT 6038REPUBLIC ACT 6038(1969)(1969)
Created NEA as Created NEA as thethe Primary Agency to Primary Agency to implement the implement the RURAL ELECTRIFICATION RURAL ELECTRIFICATION PROGRAM (REP)PROGRAM (REP)
Provided for the organization & supervision by Provided for the organization & supervision by NEA of NEA of ELECTRIC COOPERATIVES (ECs)ELECTRIC COOPERATIVES (ECs) nationwidenationwide
Characteristics of Rural Electrification Characteristics of Rural Electrification During the Early Years of During the Early Years of
ImplementationImplementation
Electrification was made possible by using Electrification was made possible by using small generating units of 30 to 60 kwsmall generating units of 30 to 60 kw
Service was only available in municipal Service was only available in municipal centerscenters
Low voltage of electricity suitable only for Low voltage of electricity suitable only for lightinglighting
Service was available for 3 to 6 hours Service was available for 3 to 6 hours usually in the eveningusually in the evening
STATUS OF RE PROGRAMJune 1969
Northern Nueva EcijaElectric Service Cooperative
Porac Electric Service
Six Mexican BarriosElectric Service Cooperative
Sapang Palay Rural Electric Service Cooperative
Infanta Light & PowerService Cooperative
Cabatuan CommunityElectric Coop Assoc, Inc.
Misamis Oriental Rural Electric Service
Victorias Electric Service Cooperative
Southern Farmers Cooperative
Lubang Electric Service Cooperative
Source:EA Annual Report 1968-1969
MERALCO
Dagupan Elect Corp
Cabanatuan Elect Corp
AEC & SFELAPCOAEC & SFELAPCO
VECO & MECOVECO & MECO
BOHOL Provincial Elect System
PECO
CEPALCO
Davao Light & Power Co., Inc..
COLIGHT
ILPI
PRESIDENTIAL DECREE 269PRESIDENTIAL DECREE 269(1973)(1973)
TRANSFORMED NEA INTO ATRANSFORMED NEA INTO A GOVERNMENT CORPORATION GOVERNMENT CORPORATION
ANDAND DECLARING AS A DECLARING AS A NATIONAL POLICY OBJECTIVE NATIONAL POLICY OBJECTIVE THE TOTAL ELECTRIFICATION THE TOTAL ELECTRIFICATION
OF THE PHILIPPINESOF THE PHILIPPINES
OVER-ALL STATUSOVER-ALL STATUS THEN AND NOW THEN AND NOW
FIRST YEAR (1969)FIRST YEAR (1969)
Status of EnergizationStatus of Energization
Municipalities/Cities (52%)Municipalities/Cities (52%)
PotentialPotential 1,422 1,422
EnergizedEnergized 739 739
Connections (19%)Connections (19%)
PotentialPotential6.210M6.210M
EnergizedEnergized 1.217M1.217M
20052005
Status of EnergizationStatus of Energization
Municipalities/Cities
(100% energized) 1,609
Barangays
Coverage 41,930
Energized 38,978
% Energization 93%
Connections
Potential 17.04M
Served 12.28M
% Energization 72%
Population Served 73M
(Approximate)
ElectricDistribution
Utilities Coverage Energized % Coverage Energized % Potential Served %
Electric Cooperatives 1,451 1,451 100 36,003 33,165 93 11,141,200 6,939,953 62
MERALCO 111 111 100 4,317 4,243 98 4,416,000 4,173,508 95
PIOUs/LGUs/Others 47 47 100 1,610 1,570 98 1,486,000 1,165,363 78
TOTAL PHILIPPINES 1,609 1,609 100 41,930 38,978 93 17,043,200 12,278,824 72
Municipalities/Cities Barangays Connections
PERFORMANCE BY UTILITYAs of July 31, 2005
PERCENT ENERGIZED
90 - 100% - 96 ECs
80 - 89% - 9 ECs
60 - 69% - 4 ECs
PIOUs / LGUs - 26
70 - 79% - 6 ECs
59 & Below - 4 ECs
STATUS OF BARANGAY STATUS OF BARANGAY ENERGIZATIONENERGIZATIONAs of July 2005
BASCO
DMPCD-1/12/05
2000 2001 2002 2003 2004
A+ 42 47 40 45 59
A 18 16 16 16 13
B 12 15 21 15 19
C 11 7 2 10 6
D 14 13 13 13 5
E 22 21 27 20 17
… 1st GOCC to be ISO 9001
Note: Savings due to the restructuring amounts to approximatelyP161 M or 49% reduction in operating expenditures.
%CY 2003 CY 2004 Reduction
965 plantilla positions 422 56
730 warm bodies 314 57
16 departments 10 37
49 divisions 23 53
RESTRUCTURINGRESTRUCTURING
SEC.58. Additional Mandate of the National
Electrification (NEA). – NEA shall develop
and implement programs:
a) To prepare electric cooperatives in
operating and competing under the
deregulated electricity market within five
(5) years from the effectivity of this Act,
specifically in an environment of open
access and retail wheeling;
b) To strengthen the technical capability and
financial viability of rural electric
cooperatives; and
c) To review and upgrade regulatory policies
with a view to enhancing the viability of
rural electric cooperatives as electric
utilities.
Short Term Credit FacilityShort Term Credit Facility aims to aims to finance the ECs’ monthly shortfall on the finance the ECs’ monthly shortfall on the settlement of power accounts with the settlement of power accounts with the NAPOCOR and TRANSCO. Funds NAPOCOR and TRANSCO. Funds allocated for this purpose amounts to allocated for this purpose amounts to P300M.P300M.
Equity Financing SchemeEquity Financing Scheme was was introduced to assist ECs in complying introduced to assist ECs in complying with the Distribution and Grid Code. NEA with the Distribution and Grid Code. NEA will finance the actual equity will finance the actual equity requirement or up to 20% of the total requirement or up to 20% of the total purchase price of the distribution purchase price of the distribution equipment being procured through equipment being procured through financing but not to exceed P8M. The financing but not to exceed P8M. The initial funding allocation is initial funding allocation is P100M.P100M.
FINANCIAL PROGRAMSTECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
Single Digit System Loss ProgramSingle Digit System Loss Program for the for the reduction of the national system loss reduction of the national system loss average by at least 1% annually starting average by at least 1% annually starting 2004 to attain the single digit level before 2004 to attain the single digit level before
2010. The amount of 2010. The amount of P300MP300M was was allocated for this program.allocated for this program.
Enhancement of ECs’ Capital ResourcesEnhancement of ECs’ Capital Resources through the adoption of a policy allowing through the adoption of a policy allowing ECs to secure loans (collateral-sharing) ECs to secure loans (collateral-sharing) outside of NEA to finance their upgrading outside of NEA to finance their upgrading and rehabilitation projects. and rehabilitation projects.
FINANCIAL PROGRAMSTECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
Credit Facility for EC Power Accounts with Credit Facility for EC Power Accounts with GENCOs and Market Operator (WESM) GENCOs and Market Operator (WESM) provides Stand-By Credit Facility for ECs provides Stand-By Credit Facility for ECs which fail to meet the credit worthiness which fail to meet the credit worthiness indicators set in their contracts with the indicators set in their contracts with the GENCOs, and/or to avoid suspension in the GENCOs, and/or to avoid suspension in the WESM and the claim of the security provided WESM and the claim of the security provided to the Market Operator due to default in to the Market Operator due to default in
payment. Initial funding allocation is payment. Initial funding allocation is P500 P500 M.M.
Credit Facility for the Acquisition of Sub-Credit Facility for the Acquisition of Sub-transmission Facilites (69 kv lines) from transmission Facilites (69 kv lines) from TRANSCO TRANSCO aims to finance the ECs’ equity aims to finance the ECs’ equity requirement of up to 20% of the total requirement of up to 20% of the total acquisition cost of the NAPOCOR/TRANSCO acquisition cost of the NAPOCOR/TRANSCO sub-transmission facilities. initial funding sub-transmission facilities. initial funding
allocation of allocation of P100MP100M was established. was established.
FINANCIAL PROGRAMSTECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
BASCO
SYSTEM LOSSSYSTEM LOSSAs of June 2005
SINGLE DIGIT - 8 ECs
10% to 14% - 42 ECs
ABOVE 20% - 16 ECs
15% to 20% - 52 ECs
NO DATA AVAILABLE - 1 EC
24
Macro Engineering Assistance Program Macro Engineering Assistance Program (MEAP)(MEAP) was designed to ensure the was designed to ensure the attainment of single digit systems loss attainment of single digit systems loss before 2010, improve the level of power before 2010, improve the level of power reliability and ensure the ECs’ compliance reliability and ensure the ECs’ compliance to the Grid and Distribution Codes.to the Grid and Distribution Codes.
Systems Loss Segregation ProgramSystems Loss Segregation Program complements the MEAP which aims to complements the MEAP which aims to guide the ECs quantify and segregate the guide the ECs quantify and segregate the technical, non-technical and administrative technical, non-technical and administrative loss. Through this, the ECs shall be able to loss. Through this, the ECs shall be able to determine which priority activities should determine which priority activities should be implemented immediately to maximize be implemented immediately to maximize beneficial effects.beneficial effects.
FINANCIAL PROGRAMS
TECHNICAL PROGRAMSINSTITUTIONAL PROGRAMS
Management Academy for Rural Management Academy for Rural ElectrificationElectrification was established primarily to serve as was established primarily to serve as learning venue for the best practices of successful ECs. learning venue for the best practices of successful ECs.
People Development AcademyPeople Development Academy (Toledo City) (Toledo City) teaches leadership and corporate values to EC leaders teaches leadership and corporate values to EC leaders and employees. To date, a total of 1,408 pax have and employees. To date, a total of 1,408 pax have undergone trainings in 12 multi-disciplines seminars.undergone trainings in 12 multi-disciplines seminars.
Integrated Strategic Planning Seminar-Integrated Strategic Planning Seminar-WorkshopsWorkshops were conducted for 114 ECs to assist were conducted for 114 ECs to assist them in formulating their 5-year operational plans them in formulating their 5-year operational plans (2005-2009). An in-house-developed computerized (2005-2009). An in-house-developed computerized model (ICPM) was designed to harmonize the data for model (ICPM) was designed to harmonize the data for all plans currently existing. It also serves as the basis all plans currently existing. It also serves as the basis for the Distribution Development Plans of 2005-2009.for the Distribution Development Plans of 2005-2009.
FINANCIAL PROGRAMS
TECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
A total of 121 pax from 41 ECs A total of 121 pax from 41 ECs underwent various WESM-related underwent various WESM-related trainings including a WESM Operations trainings including a WESM Operations Seminar with PEMC Officials as Seminar with PEMC Officials as resource persons were attended by resource persons were attended by ALL Luzon Main Grid-Connected ECs ALL Luzon Main Grid-Connected ECs
Competency Training and Certificate Competency Training and Certificate Programs on Electric Distribution Programs on Electric Distribution System Power Engineering through a System Power Engineering through a MOA between NEA and UP Diliman. To MOA between NEA and UP Diliman. To date, a total of 46 participants from date, a total of 46 participants from 35 ECs have been able to complete 35 ECs have been able to complete the program.the program.
FINANCIAL PROGRAMS
TECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
Management Academy for Rural Management Academy for Rural ElectrificationElectrification was established primarily to serve as was established primarily to serve as learning venue for the best practices of successful ECs. learning venue for the best practices of successful ECs.
People Development AcademyPeople Development Academy (Toledo City) (Toledo City) teaches leadership and corporate values to EC leaders teaches leadership and corporate values to EC leaders and employees. To date, a total of 1,408 pax have and employees. To date, a total of 1,408 pax have undergone trainings in 12 multi-disciplines seminars.undergone trainings in 12 multi-disciplines seminars.
Integrated Strategic Planning Seminar-Integrated Strategic Planning Seminar-WorkshopsWorkshops were conducted for 114 ECs to assist were conducted for 114 ECs to assist them in formulating their 5-year operational plans them in formulating their 5-year operational plans (2005-2009). An in-house-developed computerized (2005-2009). An in-house-developed computerized model (ICPM) was designed to harmonize the data for model (ICPM) was designed to harmonize the data for all plans currently existing. It also serves as the basis all plans currently existing. It also serves as the basis for the Distribution Development Plans of 2005-2009.for the Distribution Development Plans of 2005-2009.
FINANCIAL PROGRAMS
TECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
A total of 121 pax from 41 ECs A total of 121 pax from 41 ECs underwent various WESM-related underwent various WESM-related trainings including a WESM Operations trainings including a WESM Operations Seminar with PEMC Officials as Seminar with PEMC Officials as resource persons were attended by resource persons were attended by ALL Luzon Main Grid-Connected ECs ALL Luzon Main Grid-Connected ECs
Competency Training and Certificate Competency Training and Certificate Programs on Electric Distribution Programs on Electric Distribution System Power Engineering through a System Power Engineering through a MOA between NEA and UP Diliman. To MOA between NEA and UP Diliman. To date, a total of 46 participants from date, a total of 46 participants from 35 ECs have been able to complete 35 ECs have been able to complete the program.the program.
FINANCIAL PROGRAMS
TECHNICAL PROGRAMS
INSTITUTIONAL PROGRAMS
Medium-Term Development Plan (2005-2009)
ICPM Summary
Corplan, Engineering, Accounts Management & Guarantee, Finance, Institutional Development, Management Assistance
OUTPUTS
DDP INSTITUTIONAL PROGRAMS FINANCIAL PROJECTIONS 2005 WORKPLAN
BSEP LTDP LF GCP/PIP/REP
Updated, Harmonized, Distinctive
B S E P - BEP - SEP
LTDP LF
GCP/PIP/ REP
factors to consider:
WESM
OPEN ACCESS
DIST. CODE
GRID CODE
ERC COMPLIANCES
MAGNA CARTA
TIME-OF-USE
E.O. 119
DEMAND & SUPPLY
INST’L
ICPM
BARANGAYS TO BE ENERGIZEDTO BE ENERGIZED
(2005 – 2008)(2005 – 2008)
1,594 (51%)
599 (20%)
875 (29%)
Luzon Visayas Mindanao
778 (25%)
455 (15%)
1835 (60%)
Off-Grid Main Grid Waived
EC with most number of unenergized barangays:
LASURECO - 363Waived: 778
3,068 BARANGAYS3,068 BARANGAYS
2005 – 221 2007 - 200
2006 – 200 2008 - 200
NUMBER OF NUMBER OF SITIOS TO BE ENERGIZED
SITIOS = 2,423SITIOS = 2,423
2005 = 8212005 = 821
2006 = 5222006 = 522
2007 = 4402007 = 440
2008 = 3352008 = 335
2009 = 3052009 = 3051422 (58%)
498 (21%)
503 (21%)
Luzon Visayas Mindanao
EC with most number of identified Sitios for energization:
MARELCO - 123
Sitios Electrified from
Jan.03-June 05: 2,559
CONSUMER CONNECTIONS
1,876,000 (91%)
174,621 (9%)
New Add-Ons
YearYear No.No.
20052005 375,575375,575
20062006 367,217367,217
20072007 391,969391,969
20082008 413,518413,518
20092009 502,337502,337
TotalTotal 2,050,6162,050,616
EC with most number of consumers to be connected:NEW – BENECO (11,035)ADD-ONS – ALECO (64,819)
SUBSTATION REQUIREMENT(Additional)(Additional)
155
215
315
100
124
173
8550
145
5050
150
8540
170
0
100
200
300
400
500
600
700
2005 2006 2007 2008 2009
LUZON
VISAYAS
MINDANAO
685685
397397
280280250250
295295
TMVATMVA
TOTAL No. of Units
5 MVA – 92
10 MVA – 96
20 MVA – 13
OTHERS * – 112
EC with greatest S/S capacity requirement: PENELCO – 85 MVA
* 2.5, 3.75, 15, 30 MVA* 2.5, 3.75, 15, 30 MVA
SUBSTATION REQUIREMENT(Rehab/Upgrading)(Rehab/Upgrading)
TOTAL No. of Units
5 MVA – 35
10 MVA – 30
20 MVA – 3
OTHERS * – 1
30
35
135
15
49
75
10
80
25
20
55
2010
50
0
50
100
150
200
2005 2006 2007 2008 2009
LUZON
VISAYAS
MINDANAO
TMVA
TMVA
8080100100
9090
139139
200200
EC with greatest S/S capacity for Rehab:
ISELCO II – 120 MVA
* 2.5, 3.75, 15, 30 MVA* 2.5, 3.75, 15, 30 MVA
Distribution Transformers
10 KVA – 4,37310 KVA – 4,373 50 KVA – 6,32050 KVA – 6,320
15 KVA – 6,88215 KVA – 6,882 75 KVA – 37975 KVA – 379
25 KVA – 12,58925 KVA – 12,589 100 KVA – 674100 KVA – 674
37.5 KVA – 3,87537.5 KVA – 3,875 167 KVA 167 KVA –– 267 267
TOTAL NO. OF UNITS: 35,359
EC with biggest number of dx transformer requirement:
CAGELCO II – 1,365
Kilowatt Hour Meters
1 Phase1 Phase – 1,556,427 – 1,556,427
3 Phase – 5,9213 Phase – 5,921
TOTAL NO. OF UNITS: 1,562,348
EC with greatest number of kwh-mtr requirement:
AKELCO – 120,075
Distribution Facilities
Kilometers of LinesKilometers of Lines
EXPANSIONEXPANSION REHAB/REVAMPREHAB/REVAMP
DC – 39.250DC – 39.250 DC – 0 DC – 0 3Ø – 290.1393Ø – 290.139 3Ø – 615.570 3Ø – 615.570 2Ø – 466.777 2Ø – 466.777 2Ø – 169.510 2Ø – 169.510 1Ø – 5,687.9171Ø – 5,687.917 1Ø – 884.050 1Ø – 884.050 UB – 4,534.618UB – 4,534.618 UB – 1,213.830 UB – 1,213.830 OS – 1,776.087OS – 1,776.087 OS – 665.780 OS – 665.780
EC with longest dx lines for expansion:ZANECO – 690.7 ckt.kms.
EC with longest dx lines for rehab/revamp: ZAMECO II – 360.3 ckt.kms.
SUBTRANSMISSION FACILITIES and
VOLTAGES other than 13.2 kv
EXPANSIONEXPANSION REHABREHAB
69 KV OTHERS2005 584.83 522006 297.26 02007 398.52 02008 117.30 142009 234.95 0TOTAL 1,632.86 66
69 KV OTHERS2005 0 02006 40 02007 0 02008 0 02009 0 0TOTAL 40 0
CENECO is the only EC with subtransmission line for rehab.
EC with longest subtransmission line for expansion:
COTELCO – 110.5 kms.
POLES
25’ 25’ – – 19,83819,838
30’ 30’ – – 62,91862,918
35’ 35’ – – 56,03056,030
40’ 40’ – – 26,10526,105
45’45’ – – 13,12513,125
OTHERS*– OTHERS*– 15,78715,787
GRAND TOTAL: 193,803
* Includes concrete, steel and above 45 footers
EC with most number of Pole Requirements:
ISECO – 12,750
FUNDING FUNDING REQUIREMENT REQUIREMENT (P ‘000)(P ‘000)
2005 – 8,338,5322005 – 8,338,532
2006 – 7,056,2592006 – 7,056,259
2007 – 6,400,6672007 – 6,400,667
2008 – 6,039,0582008 – 6,039,058
2009 – 5,982,4772009 – 5,982,477
GRAND TOTAL: 33,816,993
EC with largest funding requirement:
BATELEC II – 1,175,437
Operational Efficiency
Subsidies and Loans
Rate Adjustments
DOE’s Energy Regulations No. 1-94, as amended
50% of P0.01 per kwh financial benefits Local Government Code of
1991(Chapter II, Sections 289 to 294) 80% of the proceeds maybe used to
construct distribution lines and lower the cost of electricity
Missionary Electrification-Universal Charge
Subsidy to QTPs (alternative service providers)
Government General Appropriations Act (GAA) for DOE,NEA/ECs and SPUG (if any)
WB-GEF under DOE’s Rural Power Project
Available for household and community applications (US$ per Wp)
sources
I. Consumer Connections
2004 2009
6,702,789 8,753,405
Growth Rate = 23%
II. Energy Sales (MWH)
2004 2005 - 2009
9,546,390 Annual Ave: 12,390,656
III. Revenues (P)
2004 2009
47B Annual Ave = 73B
Growth Rate = 36%
Growth Rate = 23%
VOLUME OF BUSINESSVOLUME OF BUSINESS
next steps…
100% Barangay Energization by CY 2008
Single Digit System Loss by CY 2010
90% Energization Rate for Residential Consumers by CY 2017