Upload
meira
View
86
Download
1
Embed Size (px)
DESCRIPTION
Picture of (site) Capstone Team Who we are (Members skills) Maquigr team beyond Shows fractured rocks Pictures displayed . Retaining Wall Design Slope Stability on US-189 MAQuiGr Engineering. Matthew Hakes, Quinton Taylor, Greg Hanks. Site 1. Site Evaluation. Site 2. - PowerPoint PPT Presentation
Citation preview
RETAINING WALL DESIGNSLOPE STABIL ITY ON US-189MAQUIGR ENGINEERING
Matthew Hakes, Quinton Taylor, Greg Hanks
PICTURE OF (SITE)CAPSTONE TEAM WHO WE ARE (MEMBERS SKILLS)MAQUIGR TEAM BEYONDSHOWS FRACTURED ROCKSPICTURES DISPLAYED
Site Evaluation
Site 1
Site 2
SITE 1 IS FEATURED ON TOPSITE 2 ON BOTTOMNOTICE:WATER LOCATIONTEMPORARY SOLUTIONS LOADS CAUSED BY ROAD
Considered Solutions
Sheetpile Tieback
ShotcreteSoil Nail
Gabion Tieback
SHEET PILE PROS RAPID CONSTRUCTIONCONS SHALLOW ROCK MAKES IT IMPOSSIBLE TO DIG IN DEEP ENOUGH TO GET MOMENT
Analysis with SnailPlusAssumptions made:
Two different soil types• Gravel/Sand• Bedrock
Loading• Temporary Max: 700 psf from construction• Permanent Max: 200 psf from traffic
Morgenstern-Price• General limit equilibrium (Moment-force)
FHWA factors of safety used
Analysis with SnailPlus Under construction loading conditions
Under normal traffic loads
Design section Calculation FS Slope Fmax Nails (k) Fmax Nails at Head (k) STR Check Nails STR Check Plates STR Check Facing
No. 4 Calculation successful 1.347 17.3 17.3 0.296 0.89 0.286
No. 3 Calculation successful 2.155 6.8 6.8 0.117 0.353 0.113
Design section Calculation FS Slope Fmax Nails (k) Fmax Nails at Head (k) STR Check Nails STR Check Plates STR Check Facing
No. 4 Calculation successful 1.579 14.9 14.9 0.257 0.856 0.275
No. 3 Calculation successful 3.07 5.5 5.5 0.094 0.331 0.09
Final Design
• 10ft from road edge
• 120ft in length
• 17 Total Soil Nails
• Average height, 6ft
• Max height, 13ft
INITIAL CONCEPTION OF WALL SHAPECREATED SLOPE IN AUTO CADUNIFIED DESIGN 1/2 THE DISTANCE FOLLOW SLOPE OR WHATOPTIMIZED FOR CONSTRUCTION
Phase 1•Conducted during low traffic flow•Close southbound lane•Flaggers to direct flow of trafficthrough single lane
Environmental Impact Reduction (3 lines of defense)•Excavated 5ft bench •1ft silt fence installed 20ft below excavation line•Exposed Shoreline
Site Preparation
Phase 2•5ft bench approximately 10ft out from edge of the road•Excavation of 1,000 cubic feet •Soil relocated to holding site
Excavation Slope Preparation
Phase 3•Williams Geo-Drill Injection Anchor System with rotary percussive drilling•In case of hitting hard rock, a Polyester Resin Rock Anchor System may be used
Soil Nail Installation
Phase 4 Phase 4:•Constructed offsite due to limited space•75 year design life, hot-dip galvanizing
Prefabrication of Rebar Cages
Phase 5•Challenge will be mobility and visibility of excavator
•Guided into place by multiple workers located on bench
Installing Rebar CagesThe key to the project was contstruction speed
8 in mat Number 6 rebarTied together
Bring in on flat bead and then drop in excavator secure them in place
Phase 6
•Two step process using wire mesh as backstop for shotcrete
•First day application spraying towards the road, second day other side is applied
ShotcreteA problem (wall needs concrete)
solution we could pump it with shotcrete
Bench was created for workers to stand on
No wall – wire mesh 2 sided
Phase 7 Installing Drainage SystemPhase 5:•Composite Drainage system•Drainage system includes: geosythetic filtered fabric and molded plastic core
Phase 8•Bearing plate, hardened washers, hex nut, and Geo-Drill Injection Anchor
•75 year design life, galvanizing bearing plate and hardened washers and capped with a steel tube filled with cement grout
Anchor to wall Attachments
Phase 9•Using the soil from the excavation, backfill at 8-12in lifts
•Compact soil with plate compactor attachment while avoiding soil nails
•Increased bar size to improve bending strength in the case of accidental contact with compactor
Backfill
Phase 10 Phase 10:•Last 4-6in of backfill will be filled with cement to cap off the retaining system
•Reduce permeability of surface and prevent corrosion
Capping Phase 11 Cleanup
Phase 11:•Remove silt fencing and any loose material •Add soil to bench to create a more natural slope•Application of hydroseed to slope to promote vegetation growth
Time and Cost Estimates
•Cost estimates are based on the FHWA pricing graph and scheduling was created in 11 phases
Days 17Plans & SurveyingPermits & Fees Construction Loans
1Phase 1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Staging areaSilt FencingMoving BaricadesTraffi c Control Laying gravel Construction Signage
Phase 2 Staking ExcavationSoil Removal
Phase 3 Marking Soil Nail Instalationdrillingadd section groutingcapping
Phase 4 Delivery Rebar, TiesCutting Bending rebartieing rebarInstalling wire meshloading for transit
Phase 5 Drainage FabricDrainage Piping
Phase 6 Marking LocationLeveling Compacting basedelivering from stagingdropping in placeIn place fabricationsecuring soil nails
Phase 7 Shotcreting walls
Phase 8 Attachmen plates
Phase 9 Load for backfillTransport backfillPlace BackfillCompact 10" lifts
Phase 10 Form for concrete cap Pour concrete
Phase 11 CleanupRemoving Traffi c devices
For this Project we will assume that Planning and Surveying, Permits and Fees and Construction Loans are taken Care of at this point. The Schedule will be 17 Days
COST THE FEDERAL HIGHWAY ADMINISTRATIONCHARCTERISTICS THAT COST $$$LOCATION, MATERIAL, NIGHT TIME ECTSCHEDULE HOW WE CAME UPINTEGRATING PHASES TO OPOMIZE TIME
ConclusionA soil nail retaining system is the best option for this project
•Adaptable – Depending on what is encountered during construction this design can easily be modified to meet the needs of the project
•Cost Effective – With little excavation near the road, a temporary wall will be unnecessary
•75 Design Life – Simple methods that can be implicated to increase design life