  • REPORT NO 1895-001

    BASINGSTOKE AND DEANE CYCLE FEASIBILITY STUDY PROJECT REPORT

    FEBRUARY 2017

  • Revision 1 Project no: 70021895 Date: February 17

    WSP | Parsons Brinckerhoff Regus House Southampton International Business Park George Curl Way Southampton SO18 2RZ Tel: +44 (0) 23 8030 2518 Fax: +44 (0) 23 8030 2000 www.wsp-pb.com

    BASINGSTOKE AND DEANE CYCLE FEASIBILITY STUDY Basingstoke and Deane Borough Council

    http://www.wsp-pb.com/

  • Q U A L I T Y M A N A G E M E N T ISSUE/REVISION FIRST ISSUE REVISION 1 REVISION 2

    REVISION 3

    Remarks First Issue Revised following BDBC comments

    Date 10/02/2017

    Prepared by H Littler H Littler

    Signature

    Checked by L Berridge L Berridge

    Signature

    Authorised by M Croucher N Wilkinson

    Signature

    Project number 70021895 70021895

    Report number 1 2

    File reference

    \\uk.wspgroup.com\central data\Projects\700218xx\70021895 - Basingstoke & Deane Cycle Path\C Documents\Reports

    \\uk.wspgroup.com\central data\Projects\700218xx\70021895 - Basingstoke & Deane Cycle Path\C Documents\Reports

  • ii

    Basingstoke and Deane Cycle Feasibility Study WSP | Parsons Brinckerhoff Basingstoke and Deane Borough Council Project No 70021895 February 17

    P R O D U C T I O N T E A M CLIENT

    Transport Officer, Basingstoke and Deane Borough Council Peter Smith

    Design Environment and Infrastructure Manager, Basingstoke and Deane Borough Council

    Mark Lambert

    WSP | PARSONS BRINCKERHOFF

    Project Director Nigel Wilkinson

    Project Manager Louise Berridge

    Project Engineer Helen Littler

  • iii

    Basingstoke and Deane Cycle Feasibility Study WSP | Parsons Brinckerhoff Basingstoke and Deane Borough Council Project No 70021895 February 2017

    TABLE OF CONTENTS 1 INTRODUCTION ...........................................................................1

    1.1 INTRODUCTION ............................................................................................. 1

    1.2 STRUCTURE .................................................................................................. 2

    2 POLICY BACKGROUND AND STUDY OBJECTIVES ................3

    2.1 INTRODUCTION ............................................................................................. 3

    2.2 PLANNING POLICY AND GUIDANCE ........................................................... 3

    2.3 PROPOSED DEVELOPMENTS ...................................................................... 6

    3 STUDY SCOPE AND OBJECTIVES ............................................8

    3.1 SCOPE OF STUDY ......................................................................................... 8

    3.2 STUDY OBJECTIVES ..................................................................................... 9

    3.3 STUDY METHODOLOGY ............................................................................... 9

    4 BACKGROUND INFORMATION AND EXISTING SITUATION .................................................................................10

    4.1 INTRODUCTION ........................................................................................... 10

    4.2 SITE WALKOVER AND AUDIT .................................................................... 10

    4.3 EXISTING SITUATION ................................................................................. 10

    4.4 IMPROVEMENTS AS PART OF OTHER DEVELOPMENTS ........................ 17

    4.5 ACCIDENT DATA ......................................................................................... 19

    4.6 TRAFFIC FLOW DATA ................................................................................. 21

    4.7 KEY ATTRACTORS ..................................................................................... 22

    4.8 SUMMARY ................................................................................................... 22

    5 APPRAISAL CRITERIA .............................................................24

    5.1 INTRODUCTION ........................................................................................... 24

    5.2 INTERVENTIONS ......................................................................................... 25

    5.3 INTERVENTION LEVELS ............................................................................. 25

  • iv

    Basingstoke and Deane Cycle Feasibility Study WSP | Parsons Brinckerhoff Basingstoke and Deane Borough Council Project No 70021895 February 2017

    6 ROUTE OPTIONEERING ...........................................................26

    6.1 INTRODUCTION ........................................................................................... 26

    6.2 CORRIDOR 1................................................................................................ 26

    6.3 OPTIONS CORRIDOR 5 ............................................................................ 30

    6.4 OPTIONS TOWN CENTRE ........................................................................ 38

    BRONZE LEVEL INTERVENTIONS ............................................................................... 39

    SILVER LEVEL INTERVENTIONS ................................................................................. 40

    GOLD LEVEL INTERVENTIONS ................................................................................... 41

    7 STAKEHOLDER ENGAGEMENT ..............................................42

    7.1 INTRODUCTION ........................................................................................... 42

    7.2 FEEDBACK FROM PUBLIC ......................................................................... 42

    7.3 FEEDBACK FROM LOCAL AUTHORITIES ................................................. 42

    7.4 OPTION APPRAISAL ................................................................................... 43

    8 PROPOSED OPTION .................................................................44

    8.1 INTRODUCTION ........................................................................................... 44

    8.2 ROUTE 1 ...................................................................................................... 44

    8.3 ROUTE 5 ...................................................................................................... 46

    9 ROAD SAFETY AUDIT ..............................................................50

    10 COSTING ....................................................................................52

    10.1 INTRODUCTION ........................................................................................... 52

    10.2 ROUTE 1 ...................................................................................................... 52

    10.3 ROUTE 5 ...................................................................................................... 54

    10.4 TOWN CENTRE............................................................................................ 55

    11 OUTLINE DELIVERY PLAN .......................................................58

    11.1 INTRODUCTION ........................................................................................... 58

  • v

    Basingstoke and Deane Cycle Feasibility Study WSP | Parsons Brinckerhoff Basingstoke and Deane Borough Council Project No 70021895 February 2017

    12 CONCLUSIONS ..........................................................................59

    12.1 INTRODUCTION ........................................................................................... 59

    12.2 SUMMARY OF PROPOSALS ....................................................................... 60

    12.3 FUTURE DEVELOPMENT AND OPPORTUNITIES ...................................... 60

    T A B L E S TABLE 2-1 BASINGSTOKE AND DEANE CYCLING STRATEGY SHORT TERM

    ACTIONS .......................................................................................5 TABLE 2-2 BASINGSTOKE AND DEANE CYCLING STRATEGY MEDIUM AND LONG

    TERM CONNECTIVITY AND PERMEABILITY ACTIONS ...............5 TABLE 4-1 SUMMARY OF PROPOSED HCC IMPROVEMENT SCHEMES .................. 19 TABLE 6-1 IMPROVEMENT OPTIONS - NORN HILL & POPLEY ................................. 27 TABLE 6-2 IMPROVEMENT OPTIONS - CHINEHAM BUSINESS PARK ...................... 28 TABLE 6-3 IMPROVEMENT OPTIONS CHINEHAM .................................................. 29 TABLE 6-4 IMPROVEMENT OPTIONS BASINGSTOKE TOWN CENTRE TO

    WINCHESTER ROAD ROUNDABOUT ........................................ 31 TABLE 6-5 IMPROVEMENT OPTIONS WINCHESTER ROAD................................... 33 TABLE 6-6 IMPROVEMENT OPTIONS KEMPSHOTT & HATCH WARREN ............... 35 TABLE 6-7 IMPROVEMENT OPTIONS PACK LANE ................................................. 36 TABLE 6-8 IMPROVEMENT OPTIONS OAKLEY ....................................................... 38 TABLE 9-1 ROAD SAFETY AUDIT GENERAL SUMMARY ........................................... 51 TABLE 10-1 ROUTE 1 SUMMARY OF PROPOSALS ................................................... 52 TABLE 10-2 ROUTE 1 CONSTRUCTION COST SUMMARY ........................................ 53 TABLE 10-3 ROUTE 5 SUMMARY OF PROPOSALS ................................................... 54 TABLE 10-4 ROUTE 5 CONSTRUCTION COST SUMMARY ........................................ 55 TABLE 10-5 TOWN CENTRE SUMMARY OF PROPOSALS ........................................ 56 TABLE 10-6 TOWN CENTRE CONSTRUCTION COST SUMMARY ............................. 57 TABLE 10-7 SUMMARY OF TOTAL COSTS ...............