PEKERJAAN : PEMBANGUNAN RUMAH TINGGALLOKASI : PERUM CANDRAMASTAHUN : 2008

Haraga Satuan Jumlah( Rp ) ( Rp )

1 3 4 5 6 = 3x5

I PEKERJAAN PENDAHULUAN1 Pekerjaan persiapan 1.00 Ls 500,000.00Rp 500,000.00Rp

SUB TOTAL I 500,000.00Rp A PEKERJAAN LANTAI ATAS

II PEKERJAAN BETON BERTULANG1 Kolom beton K 225 pemakaian besi 110 kg 1.08 m3 3,437,580.00Rp 3,697,117.29Rp 2 Ring balok 15/20 beton K 225 pemakaian besi 110 kg 2.07 m3 3,437,580.00Rp 7,115,790.60Rp 3 Plat deck t =10cm beton K 225 pemakaian besi 130 kg 0.72 m3 3,697,100.00Rp 2,676,700.40Rp 4 Balok 20/30 beton K 225 pemakaian besi 130 kg 0.66 m3 3,697,100.00Rp 2,435,649.48Rp

SUB TOTAL II 15,925,257.77Rp III PEKERJAAN PASANGAN & PLESTERAN1 Pas. Bata merah 1pc : 4ps 86.19 m2 71,510.00Rp 6,163,089.35Rp 2 Plesteran halus 1pc : 4ps tebal 1,5 cm 172.37 m2 24,260.00Rp 4,181,696.20Rp 3 Benangan 156.00 m1 7,130.00Rp 1,112,280.00Rp

SUB TOTAL III 11,457,065.55Rp IV PEKERJAAN KERAMIK1 Keramik lantai uk. 30x30cm 28.60 m2 110,950.00Rp 3,173,170.00Rp 2 Keramik lantai uk. 20x20cm (KM/WC) 1.84 m2 113,350.00Rp 208,564.00Rp 3 Keramik dinding uk. 20x25cm ( KM/WC) 7.35 m2 97,670.00Rp 717,874.50Rp

SUB TOTAL IV 4,099,608.50Rp V PEKERJAAN ATAP1 Balok tembok 8/12 kayu bengkirai 0.08 m3 8,130,900.00Rp 622,111.42Rp 2 Kuda-kuda 8/12 kayu bengkirai 0.35 m3 8,130,900.00Rp 2,855,702.17Rp 3 Gording 8/12 kayu bengkirai 0.31 m3 8,130,900.00Rp 2,546,988.16Rp 4 Usuk 5/7 + reng 2/3 kayu bengkirai 50.02 m2 91,120.00Rp 4,557,512.59Rp 5 Genteng karang pilang 50.02 m2 109,540.00Rp 5,478,818.36Rp 6 List plank 3/30 kayu kamper 22.63 m1 101,580.00Rp 2,298,755.40Rp 7 Talang seng BJLS 30 ( lebar 90 cm ) 5.65 m1 107,280.00Rp 606,132.00Rp 8 Talang Pembuluh Pipa PVC 4" Type AW 9.00 m1 40,640.00Rp 365,760.00Rp 9 Plafond eternit 100x100cm rangka kayu kamper 45.33 m2 131,480.00Rp 5,960,172.47Rp

10 List plafond Gypsum 100.71 m1 12,000.00Rp 1,208,520.00Rp SUB TOTAL V 26,500,472.59Rp

VI PEKERJAAN KAYU1 Pas. Kusen pintu/jendela kayu kamper 6/15 cm 0.44 m3 9,180,000.00Rp 4,023,594.00Rp 2 Pas. Daun pintu panil kayu kamper 2.94 m2 476,250.00Rp 1,400,746.50Rp 3 Pas daun jendela kaca rangka kayu kamper 6.05 m2 284,940.00Rp 1,725,083.75Rp

SUB TOTAL VI 7,149,424.25Rp VII PEKERJAAN INST. LISTRIK

1 Pas. Titik lampu 14.00 Ttk 380,500.00Rp 5,327,000.00Rp 2 Pas. Stop kontak 2.00 Ttk 169,900.00Rp 339,800.00Rp 3 Pas. Saklar tunggal 5.00 Ttk 130,000.00Rp 650,000.00Rp 4 Pas. Saklar ganda 1.00 Ttk 60,000.00Rp 60,000.00Rp 5 Pas. Lampu TL 1X40 watt 1.00 Ttk 60,000.00Rp 60,000.00Rp 6 Pas. Lampu downled 10.00 Ttk 70,000.00Rp 700,000.00Rp 7 Pas. Lampu PL 25 watt 3.00 Ttk 40,000.00Rp 120,000.00Rp

SUB TOTAL VII 7,256,800.00Rp VIII PEKERJAAN FINISHING

1 Cat kayu 20.45 m2 37,400.00Rp 764,979.60Rp

2

RENCANA ANGGARAN BIAYA

No Uraian Kegiatan Volume Satuan

1 of 2

Page 2: Rencana Anggaran Biaya

Haraga Satuan Jumlah( Rp ) ( Rp )

1 3 4 5 6 = 3x52

No Uraian Kegiatan Volume Satuan

2 Cat dinding + plafond 217.70 m2 16,800.00Rp 3,657,383.52Rp SUB TOTAL VIII 4,422,363.12Rp

IX PEKERJAAN PENGGANTUNG PENGUNCI1 Pas. Kunci tanam besar 2x putar 2.00 unit 255,700.00Rp 511,400.00Rp 2 Pas. Engsel pintu 6.00 stel 23,550.00Rp 141,300.00Rp 3 Pas. Engsel jendela 6.00 stel 15,450.00Rp 92,700.00Rp 4 Pemasangan Grendel biasa besar (Pintu) 2.00 unit 41,720.00Rp 83,440.00Rp 5 Pemasangan Grendel biasa kecil (jendela) 3.00 unit 20,860.00Rp 62,580.00Rp

SUB TOTAL IX 891,420.00Rp X PEKERJAAN SANITASI DAN RIOLERING1 Pembuatan bak mandi :- Pas. Bata trasram ( 1pc : 3ps ) 0.07 m3 74,590.00Rp 5,370.48Rp - Pas. Keramik dinding bak air 20x25cm 1.39 m2 97,670.00Rp 135,370.62Rp - Pas. Keramik dasar bak air 20x20cm 0.30 m2 113,350.00Rp 33,766.97Rp 2 Pemasangan Kloset jongkok 1.00 unit 467,800.00Rp 467,800.00Rp 3 Pemasangan instalasi air bersih dia.3/4" 10.00 m1 12,990.00Rp 129,900.00Rp 4 Pemasangan instalasi air kotor dia. 4" 10.00 m1 40,640.00Rp 406,400.00Rp 5 Pemasangan instalasi air kotoran dia. 4" 10.00 m1 40,640.00Rp 406,400.00Rp 6 Kran air lokal 1.00 unit 33,350.00Rp 33,350.00Rp 7 Avour 1.00 unit 45,000.00Rp 45,000.00Rp

SUB TOTAL X 1,663,358.07Rp

B PEKERJAAN TERAS DEPANXI PEKERJAAN ATAP1 Gording 8/12 kayu bengkirai 0.15 m3 8,130,900.00Rp 1,248,906.24Rp 2 Asbes gelombang besar 24.00 m2 109,540.00Rp 2,628,960.00Rp 3 Talang seng BJLS 30 ( lebar 90 cm ) 6.00 m1 107,280.00Rp 643,680.00Rp 4 Talang Pembuluh Pipa PVC 4" Type AW 2.70 m1 40,640.00Rp 109,728.00Rp 5 Plafond eternit 100x100cm rangka kayu kamper 24.00 m2 131,480.00Rp 3,155,520.00Rp 6 List plafond Gypsum 20.00 m1 12,000.00Rp 240,000.00Rp

SUB TOTAL XI 8,026,794.24Rp XII PEKERJAAN KERAMIK

1 Keramik lantai uk. 30x30cm 24.00 m2 110,950.00Rp 2,662,800.00Rp SUB TOTAL XII 2,662,800.00Rp

XIII PEKERJAAN FINISHING1 Cat dinding + plafond 65.30 m2 16,800.00Rp 1,097,040.00Rp

SUB TOTAL XIII 1,097,040.00Rp

B PEKERJAAN PAGARXIV PAGAR

1 Pagar minimalis 13.50 m2 550,000.00Rp 7,425,000.00Rp SUB TOTAL XIV 7,425,000.00Rp

XV PEKERJAAN LAIN-LAIN1 Air kerja 1.00 ls 300,000.00Rp 300,000.00Rp 2 Pembersihan lokasi 1.00 ls 500,000.00Rp 500,000.00Rp

SUB TOTAL XV 800,000.00Rp

Jumlah total 99,877,404.08Rp Dibulatkan 99,877,000.00Rp Terbilang : Sembilan puluh sembilan juta delapan ratus tujuh puluh tujuh ribu rupiah rupiah