Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
© Nov.2016 ANDES
Regulations for Decommissioning of Nuclear Power Plants in Japan
~aiming to achieve the safe, smooth, and reasonable decommissioning~
The Association for Nuclear Decommissioning Study
1
Tadamichi Satoh
The Association for Nuclear Decommissioning Study
2016 Sino-Japanese Workshop on NPP Decommissioning Technology
November22, 2016 @ Atomic Energy Council 3F
© Nov.2016 ANDES
Potential Risks of Over-Regulation(過剰規制がもたらす弊害)
1. Reduce worker motivation(作業者の意欲を低下させる)
2. Reduce worker focus on real issues(真の問題への作業者の意識を低下させる)
3. May be in conflict with industrial safety(産業安全と矛盾しかねない)
4. Delay the final goal of site release(廃止措置の完了を遅らせる)
5. Provide the wrong message to the stakeholders and public in
particular (利害関係者や特に公衆に誤った情報を与える)
Avoid unnecessary operation-type burdens
(不必要な運転中の規制負荷を避ける)
2
Harmonization of standards and procedures versus
flexibility of approach
From the panel discussion on ”Emerging issues and trends in regulatory practices
during the decommissioning and dismantling of nuclear power plants”
OECD/NEA/WPDD Topical Session 2006
© Nov.2016 ANDES
Safety consideration
while operation Safety consideration
while decommissioning
- Strict compliance with operation rule and maintenance rule - Control room staffing (24-hours) - Preparedness for Sevier Accident - Extensive inspection of facilities by regulator
【Point】 - Operate reactor safely & SAM - Maintain safety function of facilities (Shutdown system, Core cooling system, Containments) - Safeguard control
【Point】 - Plan and control works safely including industrial safety -Control of radiation & radioactive waste -Confirm final status of the waste and the site to be safe
- Oversight of decommissioning activity
Comparison of Safety consideration
between operation and decommissioning
Protection of - General public health - Workers health
3
© Nov.2016 ANDES
Changes from Operation to Decommissioning ~Changes of Plant Situation 施設状態の変化~
IAEA TRS/No.420 Transition from Operation to Decommissioning of Nuclear Installation(2004)
Operations 運転中 Decommissioning 廃止措置
Safety management systems based on an operating nuclear facility
原子力施設の運転を対象とした安全管理体系
Safety management systems based on decommissioning tasks
廃止措置作業を対象とした安全管理体系
Focus on functioning of systems 系統の機能に集中
Focus on management of material and radioactivity inventory (e.g. for waste minimization)
物や放射能物量に集中(廃棄物の最少化など)
Reliance on permanent structures for the operating life of the facility
恒久の構造物に依存
Introduction of temporary structures to assist dismantling
仮設構造物の導入
Routine amounts of material shipped off-site
一定量の所外搬出
Larger amounts of materials shipped off-site
多量の所外搬出
Established and developed operating regulations
確立された運転中規制
Change of regulatory focus 規制焦点の変化
4
© Nov.2016 ANDES
IAEA TRS/No.420 Transition from Operation to Decommissioning of Nuclear Installation(2004)
Operations 運転中 Decommissioning 廃止措置
Predominant nuclear and radiological risk 核的・放射線危険が中心
Reduction of nuclear risk, changed nature of radiological risk, significantly increased industrial risk
核的危険は低減、放射線危険の特質の変化 労働安全上の危険が増大
Working environment well known 作業環境が良く判っている
Working environment unknowns possible
作業環境が判っていない可能性
Low radiation/contamination levels relatively unimportant
低線量、低汚染は管理上重要度が低い
Low radiation/contamination levels important for material clearance
低線量、低汚染もクリアランスの観点で重要
Access to high radiation/contamination areas unlikely or for a short time
高線量、高汚染の場所への立入は稀で短時間
Access to high radiation/contamination areas for extended periods
高線量、高汚染の場所への長時間の立入
Relatively stable isotopic composition 核種組成は比較的一定
Isotopic composition changing with time 時間と共に核種組成が変化
Changes from Operation to Decommissioning ~Changes of Work Condition 作業環境の変化~
5
© Nov.2016 ANDES
IAEA TRS/No.420 Transition from Operation to Decommissioning of Nuclear Installation(2004)
Operations 運転中 Decommissioning 廃止措置
Production oriented management Objectives 生産指向の運営
Project completion oriented management objectives
事業完遂指向の運営
Permanent employment with routine objectives
定常業務での恒久雇用
Visible end of employment — refocus of the staff’s work objectives
雇用の明確な終了/新たな業務に向けた再意欲
Repetitive activities 反復作業が多い
One-off activities 単発作業が多い
Routine training and refresher training
定例訓練と再訓練
Retraining of staff for new activities and skills or use of specialized contractors
新たな業務、技能の訓練又は専門家の雇用
Routine lines of communication 定常的な対話先
New lines of communication 新たな対話先
Changes from Operation to Decommissioning ~Changes of Human Factor 人的な変化~
6
© Nov.2016 ANDES
1.Health and safety of workforce
Particular regulatory attention to conventional health and safety (increased potential for fire, explosion, failure of partially dismantled structures, accidents associated with lifting and moving heavy items, etc.)
New working environment that involve a changing work force comprised of temporary, contract staff
Lack of attention to the changing of nature and location of hazards
2.Modification of plant and equipment
Regulatory approval process would be modified for decommissioning machinery and ancillary plant
3.Control of radioactive contamination
The matter of nuclear safety becomes negligible during decommissioning
Focus more on matters concerned with control of contamination and minimization of waste creation
⇒ Minimize impact on workers, the public and the environment
7
Achieving a regulatory balance in decommissioning phase
~ the most important point considered by OECD/NEA/WPDD ~ 1
”Regulating the Decommissioning of Nuclear Facilities” OECD/NEA 2008
© Nov.2016 ANDES
4.Control of human and organizational issues
New and different management reflecting the need for greater emphasis on project management, i.e. the management of change, quality control, information retention, contract management
(different from operational phase where activities are generally routine and well practiced by
a stable work force)
The management to be flexible and able to respond quickly to new situations ⇒ Vesting the local site management with a range of powers
(various new decommissioning activities may need closer day-to-day control or supervision)
5.Knowledge retention
Availability of information about operational history of the plant
First-hand knowledge of design, construction and operation of the plant
Knowledge of any unrecorded plant modification and any untoward events during operation
8
Achieving a regulatory balance in decommissioning phase
~ the most important point considered by OECD/NEA/WPDD ~ 2
”Regulating the Decommissioning of Nuclear Facilities” OECD/NEA 2008
© Nov.2016 ANDES
Tokai-1 is the first instance of the decommissioning of a commercial
nuclear power plant in Japan
Mar.1998 Permanent Shutdown (32 years operation)
May 1998 –Mar.2001 Defueling
Jun. 2001 The last shipment of spent fuel
Oct. 2001 Submitted the notification decommissioning plan
Dec. 2001 Commenced decommissioning activities
Dec.2005 Amendment of the “Act on the regulations of nuclear
source material, nuclear fuel material, and reactors”
Mar. 2006 Submitted the application of decommissioning plan
Jun. 2006 Approval of the decommissioning plan
9
Experience of Improvement of Decommissioning Regulations in Japan
© Nov.2016 ANDES 10
At the beginning of Tokai-1 D project
Existing Regulatory Systems & Practices were applied
That was to basically regulate operating plants
aiming to operate reactor safely and maintain
safety function of facilities.
- 24-Hour sift operator arrangement
- Periodical Facility Inspections by regulator and
utility
- Strict Operational Safety Program (OSP) (保安規定) (approved by regulator)
- Rigid regulatory procedure for modification of
facilities (including temporary facilities )
Regulations were not suitable for decommissioning phase
No clear standard was established for decommissioning regulations
© Nov.2016 ANDES 11
Moving from Operation to Decommissioning
Safety function appropriate for plant changing condition Final state of wastes
Final state of the site
Add
Remain
Take out
Objects to be regulated are changed at the situation on No reactor operation and no nuclear fuel Arising of many different types of waste Changing of plant condition as decommissioning
progress
Operate reactor safely Maintain safety function of facilities Safeguard control
Radiation control Waste management OSP for necessary facilities
不要
継続
追加
© Nov.2016 ANDES 12
Key point of the amendment in 2005
Rationalization of regulation for
decommissioning phase
1. Clarification of decommissioning start point
- DP is applied at plant shutdown
- At DP approval, regulations are changed to
decommissioning regulation from operation regulation
2. Exemption of regulation for reactor operation
after DP approval;
- 24-hour sift monitoring
- Annual regulatory inspection by regulator(after defuel)
3.Clarification of DP & OSP description
- describe only key items for safety in
decommissioning phase
© Nov.2016 ANDES 13
Comparison between former & new regulation
Former regulation
(before Dec.2005)
New regulation
(after Dec.2005)
Decommissioning Plan
(DP) (廃止措置計画)
Notification Too detail description
Approval Only safety items description
Operational Safety Program (OSP)(保安規定)
Approval Too detail description
Approval Only safety items description
Mandatory periodic inspection of facility by regulator
Annual NA
(after defueling)
On site inspection of compliance with OSP by regulator
Quarterly
(~2 weeks)
Less than quarterly
(~1 week)
Safety control Daily patrol Monitoring by shift operator
Weekly patrol
No shift operator
Completion of decommissioning
Final report to regulator Confirmation by regulator
© Nov.2016 ANDES 14 14
Summarize of Old/Current Decommissioning Regulations
[Flow Chart of Decommissioning Regulations]
Reactor Operation Fuel Removal Facilities Dismantling/Wastes Shipping
Cessation of Operation Completion of Fuel Removal
License
Termination Dismantling
Notification
Old Before
Dec.2005
Decommissioning Phase Operating Phase
D Completion
Report
Current After
Dec.2005 D Planning
Application/
Approval
Operating
Phase Decommissioning Phase
* Less strict regulations during D Phase according to the facilities status
License
Termination
D Completion
Confirmation by
Government
(It is specifically prescribed under Minister Ordinance)
Alteration of
OSP
Alteration of
OSP
(Amend according to D progress)
(Amend according to D progress)
© Nov.2016 ANDES 15
New Regulations for Operating Plants after the Fukushima Daiichi Accident
New Regulatory Requirements for Light-Water Nuclear Power Plants August 2013 Nuclear Regulation Authority
© Nov.2016 ANDES
Added requirements to the NRA’s standard review
procedure for Decommissioning Plan in 2015
Any decommissioning works shall not have a negative
effect on safety functions of operating plants in same site
including SAM.
Integrity evaluation for spent fuels in cooling pool in case
of loss of coolant.
16
© Nov.2016 ANDES 17
Key points for the safe(安全), smooth(順利), and reasonable(合理的) decommissioning
意識転換 Change your Mindset to Decommissioning from Operation
三現主義 :現場、現物、現実
(Sangen shugi) ‘Three Reals Philosophy’
Go and see by yourself and understand the situation
© Nov.2016 ANDES 18
End of Presentation
Tadamichi Satoh
Secretary-General
The Association for Nuclear Decommissioning Study
Address:
401 Yoshida Bldg., Kudan-kita, chiyoda-ku,
Tokyo 102-0073 Japan
Phone: +81-3-6272-4150
Fax: +81-3-6272-4470
E-mail: [email protected]
URL: http://www.decomiken.org
© Nov.2016 ANDES 19
Current Decommissioning Regulation in Japan
Reference Source : Presentation of Japan Nuclear Regulation Authority “Safety
Regulations for Decommissioning of Nuclear Power Plants in
Japan and Future Challenges”
NRA-NRC Workshop on Decommissioning of Nuclear Power
Plants, April8, 2015
https://www.nsr.go.jp/data/000104112
© Nov.2016 ANDES 20
https://www.nsr.go.jp/data/000104112
© Nov.2016 ANDES 21
Under the rules for installing and operating the commercial power reactors,
the following standards have been prescribed for approving a
decommissioning plan.
Spent fuels shall have been taken out from the reactor core.
(Paragraph 1 of Article 119 of the Rules)
Management and transfer of nuclear fuel materials shall be appropriate.
(Paragraph 2 of Article 119 of the Rules)
Management, processing and disposal of nuclear fuel materials and
radioactive waste shall be appropriate.
(Paragraph 3 of Article 119 of the Rules)
Proper protective measures shall be taken against disaster caused by
nuclear fuel materials, contaminated materials and nuclear reactor.
(Paragraph 4 of Article 119 of the Rules)
NRA shall confirm in a safety review that the decommissioning plan applied by
the licensee conforms to the standards mentioned above.
3-3 Requirements for Approval of Decommissioning Plan (1)
https://www.nsr.go.jp/data/000104112
© Nov.2016 ANDES 22
https://www.nsr.go.jp/data/000104112
© Nov.2016 ANDES 23
https://www.nsr.go.jp/data/000104112
© Nov.2016 ANDES 24
3-4 Requirements for Confirming the Completion of Decommissioning
https://www.nsr.go.jp/data/000104112
The rules provide the following standards for confirming the completion of
decommissioning:
That transfer of nuclear fuel material is completed.
(Article 121, Item 1)
That no measures are needed to prevent damage from radiation in regards
to the soil and remaining facilities on the premises of facilities to be
decommissioned.
(Article 121, Item 2)
That management of radioactive wastes is completed.
(Article 121, Item 3)
That transfer of radiation management records to the institution designated
by the Nuclear Regulation Authority is completed.
(Article 121, Item 4)
Based on documents and on-site surveys, the Nuclear Regulation Authority
verifies that the completion of decommissioning reported by the operator
fulfills the above standards.