Liverpool Street Project – Brodgate Ticket Hall – RAMS Boards performance Delivery on site 2015/04/27 – outdoors position. Construction Site Set Up version. RAMS Board was relocated as site entry has changed – still outdoors – slightly less exposed

RAMS Boards - performance

Embed Size (px)

Citation preview

Liverpool Street Project – Brodgate Ticket Hall – RAMS Boards performance

Delivery on site 2015/04/27 – outdoors position. Construction Site Set Up version.

RAMS Board was relocated as site entry has changed – still outdoors – slightly less exposed

RAMS board – relocated to the same position fully outdoors. Layout changed to suit contractor needs.

Anchors installed – Board fully compliant to EN 1991-1-4:2005. Paper documents inside of the A4 transparent pockets - despite outdoor location quality is good.

Close view of documents in A4 transparent pockets.

Roof providing protection and minimising rain affecting inside part of RAMS Board

Liverpool Street Project – Moorgate Ticket Hall – RAMS Boards performance

Two Construction Site Set Up boards delivered on 2015/04/28 – project has two independent stages.

RAMS Board – after 6 months of demolition being carried out on site

Daily information

Quality of documents in A4 transparent pockets