GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON 17.07.2017 CONTRACT LABOURERS ENGAGED BY POWER PSUs †*4. SHRI P.L. PUNIA: Will the Minister of POWER be pleased to state: (a) the number of contract labourers engaged in Navratna and Maharatna companies of the Ministry along with the details of nature of works they are engaged in; (b) the details of companies or several units of the companies that have been registered as principal employer along with the number of labourers covered by them; and (c) whether the companies propose to regularize such labourers who are working for several years and if not, the reasons therefor? A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a) to (c) : A Statement is laid on the Table of the House. *******

RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

Embed Size (px)

Citation preview

Page 1: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA

STARRED QUESTION NO.04 ANSWERED ON 17.07.2017

CONTRACT LABOURERS ENGAGED BY POWER PSUs

†*4. SHRI P.L. PUNIA: Will the Minister of POWER be pleased to state: (a) the number of contract labourers engaged in Navratna and Maharatna companies of the Ministry along with the details of nature of works they are engaged in; (b) the details of companies or several units of the companies that have been registered as principal employer along with the number of labourers covered by them; and (c) whether the companies propose to regularize such labourers who are working for several years and if not, the reasons therefor?

A N S W E R THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )

(a) to (c) : A Statement is laid on the Table of the House.

*******

Page 2: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

STATEMENT STATEMENT REFERRED TO IN REPLY TO PARTS (a) TO (c) OF STARRED QUESTION NO.04 ANSWERED IN THE RAJYA SABHA ON 17.07.2017 REGARDING CONTRACT LABOURERS ENGAGED BY POWER PSUs.

********* (a) : Under Ministry of Power, there is one Maharatna company i.e. NTPC

Limited; and three Navratna companies, namely, Power Finance Corporation Ltd.

(PFC), Rural Electrification Corporation Ltd. (REC) and Power Grid Corporation of

India Ltd. (PGCIL). 37,455 contract labourers have been engaged by these

companies.

The works/activities outsourced by Power Sector companies are

incidental to the main business and are non-core in nature, which mainly include the

services/activities like housekeeping, horticulture, security, canteen, transport

services, miscellaneous civil maintenance works, maintenance of office equipments

etc.

(b) : Wherever outsourced work is being performed by the contractors’

workers, respective units/projects/stations obtain registration as principal employer

under the Contract Labour (Regulation & Abolition) Act, 1970. PFC, New Delhi

has applied for registration as principal employer. The details of contract labourers

engaged by various units of Navratna and Maharatna companies of the Ministry of

Power are given at Annexure.

(c) : So far as the provisions of Contract Labour (Regulation & Abolition)

Act, 1970 and its Central Rules 1971 are concerned, there is no scheme of

regularization of contract workers under the Act.

************

   

Page 3: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEXURE ANNEXURE REFERRED TO IN PART (b) OF THE STATEMENT LAID IN REPLY TO STARRED QUESTION NO. 04 ANSWERED IN THE RAJYA SABHA ON 17.07.2017 REGARDING CONTRACT LABOURERS ENGAGED BY POWER PSUs.

*********** Contract labourers engaged by various units of Navratna and Maharatna companies of the Ministry of Power ------------------------------------------------------------------------------------------------------- I: NTPC

Sl. No. Plant Name No of Contractors’ Workers Engaged

1 Anta 104 2 Auraiya 49 3 Badarpur 620 4 Dadri 1609 5 Faridabad 101 6 Farakka 1336 7 Jhanor 249 8 Kahalgaon 1840 9 Kawas 95 10 Kayamkulam 72 11 Koldam 189 12 Korba 2327 13 Rihand 2658 14 Ramagundam 679 15 Simhadri 679 16 Singrauli 1132 17 Sipat 2120 18 Talcher Kaniha 1307 19 Talcher Thermal 547 Grand Total 17713

II-PFC No of Contractors’ Workers: 166 III-REC No of Contractors’ Workers: 123

 

..........2.

 

 

Page 4: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 2 -

IV. PGCIL Sl. No. Region-wise details of the establishment Registered as

Principal EmployersNo of Contractors’ Workers Engaged

Eastern Region - I

1717

1 ARA S/S 2 BANKA S/S 3 PUSAULI S/S 4 RHQ PATNA 5 NAMKUM S/S 6 CHAIBASA S/S 7 PATNA S/S 8 GAYA S/S 9 LAKHISARAI S/S 10 BERO S/S 11 PURNEA S/S 12 MUZAFFARPUR S/S 13 BIHAR SHARIF S/S 14 DALTONGANJ S/S 15 CHANDWA S/S 16 JAMSHEDPUR S/S 17 KISHANGANJ S/S 18 Siliguri Substation Eastern Region - II

1429

19 New Siliguri Substation 20 Birpara Substation 21 Durgapur Substation 22 Maithon Substation 23 Malda Substation 24 Dalkhola Substation 25 Gangtok Substation 26 Berhampore Substation 27 Rangpo Substation 28 New Melli Substation 29 Subhashgram Substation 30 RHQ, Kolkata 31 HVDC Alipurduar 32 Rajarhat Project 33 POWERGRID Corporation of India ltd. Odisa Project

207

34 Angul 35 Baripada 36 Bhubneshwar 37 Bolangir 38 Indravati 39 Jeypore 40 Kaniha, (Talchar) 41 Keonjhar 42 Pandiabili 43 Rengali 44 Rourkela 45 Sundergarh

.........3.

Page 5: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 3 -

Western Region -I

1264

46 POWERGRID NAGPUR47 POWERGRID WARDHA48 POWERGRID AURANGABAD49 POWERGRID MAPUSA50 POWERGRID WARORA51 POWERGRID PARLI52 POWERGRID MUMBAI53 POWERGRID PUNE (SHIKRAPUR)54 POWERGRID PUNE (TALEGAON)55 POWERGRID BHADRAWATI56 POWERGRID SOLAPUR57 POWERGRID KOLHAPUR58 POWERGRID RAIPUR (KUMHARI)59 POWERGRID DURG (MADESARA)60 POWERGRID RAIGARH61 POWERGRID KORBA62 POWERGRID BILASPUR63 POWERGRID CHAMPA64 POWERGRID SEONI Western Region -II

3815

65 Baroda,RHQ66 Wagodia GIS67 Boisar.68 Dehgam69 Khandwa70 Indore71 Bina72 Itarsi73 Navsari74 vapi75 Gwalior76 Jabalpur77 Satna78 Rajgarh79 Pirana80 Shujalpur81 Vindyachal82 Banskantha83 Bhachau,rajkot, radhanpur, surendranagar & Bhuj Southern Region - I

2066

84 RHQ, Secunderabad85 Nagarjuna Sagar SS 86 Palasa SS87 Kurnool SS88 Visakhapatnam SS 89 Gooty SS

..........4.

- 4 -

Page 6: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

Southern Region - II

1704

90 ARASUR91 ARIYALUR92 BANGALORE93 BIDADI94 BIJAPUR95 DHARMAPURI96 HASSAN97 HIRIYUR98 HOSUR99 KALIVANDAPATTU100 KARAIKUDI101 KARUR102 KOCHI103 KOLAR104 KOVILPATTI105 KOZHIKODE106 MADURAI107 MYSORE108 NARENDRA109 PALAKKAD110 PAVAGADA111 PONDY112 SALEM113 SOMANAHALLI114 SRIPERUMBUDUR115 TIRUNELVELI116 TRICHUR117 TRICHY118 TRIVANDRUM119 TUMKUR120 UDUMALPET121 VELLORE122 YELAHANKA

Northern Region - I

2739

123 Katwaria Sarai, RHQ124 Meerut125 Roorkee126 Koteshwar127 Saharanpur128 Mandola, Gaziabad129 Bagpat130 Dehradoon131 Dadri, Gaziabad132 Sonipat133 Jind,134 Bahadurgarh135 Hisar136 Bhiwani137 Bhiwadi

 

...........5.

- 5 -

Page 7: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

138 Gurgaon, Fazilpur

139 Neemrana140 Kotputli141 Ballabhgarh142 Kota143 Kankroli,Rajsamand144 Bhinmal145 Jhatikara146 Jaipur South147 Bassi,(Jaipur)148 Sikar, Raj149 Agar, LTS150 Ajmer151 Bikaner152 Chittorgarh

Northern Region - II

1378

153 Narwal154 Wagoora,155 Sarna,156 Samba,157 Patiala,158 Panchkula159 New Wanpoh160 Nalagarh161 Moga,162 Malekotla163 Ludhiana164 Kurukshetra165 Kishenpur166 Kartarpur167 Kargil,168 Kala169 Ambala170 Kaithal171 Bhatinda172 Abdullapur173 Amritsar174 Banala175 Banikhet176 Baramulla177 Batote178 Chamba179 Chandigarh & Manjimajra180 Fatehabad181 Hamirpur182 Panipat183 Leh.

 

.............6

Page 8: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 6 -

Northern Region - III

2116

184 Agra HVDC,HVAC,TLM,Auraiya TLM185 Aligarh 765 KV & TLC186 Allahabad 400 KV, Mirzapur TLM,POP187 Ballia HVDC, 400KV,220KV,Azamgarh TLM188 Bareilly 765KV, 400KV189 Fatehpur 765 KV190 Gorakhpur 400/220 KV191 IPDS, Varanasi192 Kanpur 765 KV & 400 KV193 Lucknow 400 KV & 765 KV194 Mainpuri 400KV195 Orai HVDC, &TLC196 Pithoragarh 220KV, Jauljibi 400 KV197 Raibareilly 220/132 KV198 Rihand HVDC199 Shahjahanpur 400 KV200 Shaktinagar TLM201 Sitarganj 220/132 KV202 Sohawal 400 KV203 Varanasi 765KV,,TL Office204 Vindhyachal HVDC

North Eastern Region

577

205 Shilong, Regional Head Quarters206 Badarpur S/S207 Balipara SS208 Biswanath Chariali209 Bongaigaon210 Dimapur211 Khleriahat212 Silchar213 Guwahati214 Nirjuli215 Kumarghat216 Imphal217 Aizwal218 Haflong219 Jiribam220 Kolasib221 Misa222 Moriani223 Namsai224 Roing 225 Tezu226 Ziro227 Corporate Office and Manesar PAL 441

Total 19453

Grand Total (I+II+III+IV): 37455

*******

Page 9: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.78

ANSWERED ON 17.07.2017

DECLINE IN COST OF POWER 78. SHRI ANIL DESAI: Will the Minister of POWER be pleased to state:

(a) whether the cost of power has come down after the advent of non-conventional energy like wind power, bio-mass, bio-gas and solar power; (b) whether some States are purchasing expensive power from private players when it is available at lower rates elsewhere; (c) whether the Ministry has developed a software to keep track of power costs to enable power utilities to stick to the merit order; and (d) if so, the details thereof and the steps to rein in States?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )   (a): Power is generated from different sources of energy and in different plants at different costs depending on parameters which include inter-alia technology, location, Capital cost, Fuel etc. Cost of power from renewable energy sources also varies accordingly. Lowest tariff of Solar power has been discovered at Rs 2.44/Kwhr during 2017-18 for Bhadla Solar Park, Rajasthan.

(b) : States/power utilities have various power purchase agreement in force and usually follow the cost optimization principle in procuring power to meet their demand.

(c) & (d) : Ministry of Power in association with POSOCO and Central Electricity Authority has developed a Web portal and a Mobile App to bring transparency in Merit order scheduling & despatch and ensure most economic system operation. The web portal ‘MERIT’ (Merit Order Despatch of Electricity for Rejuvenation of Income and Transparency) and Mobile App displays power procurement related data transparently to all Stakeholders.

********** 

 

Page 10: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.79

ANSWERED ON 17.07.2017

PROBLEMS FACED BY MEGA POWER PROJECTS 79. SHRI RAJKUMAR DHOOT: Will the Minister of POWER be pleased to state:

(a) whether it is a fact that absence of fuel linkages and power purchase agreements is hampering as many as 25 mega power projects in the country; (b) if so, the details thereof; (c) whether Government is aware that tax sops alone can not help these mega power projects to survive; and (d) if so, what remedial measures Government proposes to take in this regard?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a) & (b) : Distribution Companies (DISCOMs) bid for Power Purchase Agreements (PPAs) depending on the requirement for Power. Some of the Mega Power Projects do not have Power Purchase Agreements (PPAs) or have part PPAs. Govt. of India has approved New coal allocation policy, 2017 for Power sector on 17.05.2017 viz. SHAKTI (Scheme for Harnessing and Allocating Koyala Transparently in India) under which inter-alia, coal is made available to Independent Power Producers (IPPs) against long-term Power Purchase Agreements (PPAs) and medium-term PPAs to be concluded in future in a transparent bidding process. (c) & (d) : As per Mega Power Policy, the mega power projects are eligible to avail certain fiscal concessions/benefits. The projects which have been granted ‘provisional’ mega power status are also eligible to avail these fiscal concessions/benefits, subject to the condition that the developers of these projects fulfil the conditions stipulated in the ‘provisional’ mega certificates and furnish the final mega certificates to the Tax Authorities within a period of 60 months. As most of the developers have not been able to meet the above condition, Government of India has extended the above time frame from 60 months to 120 months.

..........2.

Page 11: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 2 -

Apart from the above, following measures have been taken to ease out the stress in power sector:

i. Ujwal DISCOM Assurance Yojana (UDAY) scheme for Financial and Operational

Turnaround of power distribution utilities (DISCOMs) of the country.

ii. Augmenting Transmission capacity to remove transmission constraints.

iii. Flexibility in utilisation of domestic coal for reducing the cost of power generation.

iv. Power For All (PFA) initiative with 36 States and UTs for bringing uninterrupted quality of power to each household, industry, commercial business, small & medium enterprise and establishment, any other public needs and adequate power to agriculture consumer as per the state policy.

v. Deen Dayal Upadhyaya Gram JyotiYojana (DDUGJY) for:

Separation of agriculture and non-agriculture feeders;

Strengthening of sub-transmission and distribution networks in the rural areas;

Metering of distribution transformers / feeders / consumers in the rural area;

Rural Electrification.

vi. Integrated Power Development Scheme (IPDS) for:

Strengthening of sub-transmission and distribution networks in the urban areas;

Metering of distribution transformers / feeders / consumers in the urban areas;

IT enablement of distribution sector and strengthening of distribution network.

 

**************

   

Page 12: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.80

ANSWERED ON 17.07.2017

SEGREGATION OF TECHNICAL AND COMMERCIAL LOSSES 80. DR. R. LAKSHMANAN: Will the Minister of POWER be pleased to state:

(a) whether any proposal is pending with Government to introduce segregation of technical and commercial losses on pan- India basis; (b) if so, the details thereof; (c) whether Government undertook any consultation in this regard with all stake holders; (d) if so, the details thereof; and (e) if not, the reasons therefor?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )   

(a) to (e) : Standing Committee of Parliament on Energy, in its twelfth report,

recommended that concept of segregation of commercial and technical losses should be

applied to all these cities where the erstwhile Restructured Accelerated Power

Development & Reforms Programme (R-APDRP), was implemented for Computerized

Data Collection, as well as follow-up remedial measures for detecting and plugging

leakages in electricity supply. Accordingly, all State Governments have been advised to

take necessary steps for segregation of Technical and Commercial Losses in all Go-Live

towns.

****************

 

Page 13: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.81

ANSWERED ON 17.07.2017

24 HOURS ELECTRICITY TO HOUSEHOLDS IN WEST BENGAL 81. SHRI VIVEK GUPTA: Will the Minister of POWER be pleased to state:

(a) whether the definition 'electrification of villages' as per Government's database does not in reality ensure 24 hours electricity to all households of the village; (b) the details of the percentage of households, in rural and urban areas, that enjoyed 24 hours electricity during the last three years, State-wise; (c) the details of percentage of households that enjoy 24 hours electricity in each district in West Bengal; and (d) the steps taken by Government to provide 24 hours electricity to all households?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a) : According to Rural Electrification Policy 2006, a village is reported as electrified, if

(i) basic infrastructure such as Distribution Transformer and Distribution Lines are provided in the inhabited locality as well as the locality inhabited by weaker sections of the society/hamlet where it exists, (ii) electricity is provided to public places like Schools, Panchayat Office, Health Centres, Dispensaries, Community Centres etc., and (iii) the number of household electrified should be at least 10% of the total number of households in the village.

A village is reported to be electrified by the States, if it fulfills the above mentioned norms. However, level of infrastructure may vary in different habitations of the same village.

..........2.

Page 14: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 2 - (b) to (d): Providing 24 hours’ electricity to all households is the responsibility of concerned State Government/Power Utility. Following states have reported almost full household electrification hence available for 24 hours supply of Power :

State %age electrified HHs 1 Gujarat 98% 2 Himachal Pradesh 99% 3 Punjab 100% 4 Tamil Nadu 100% 6 West Bengal 99%

To supplement the efforts of the States, Government of India has taken up a

joint initiative with all States/UTs for preparation of State specific documents for providing 24x7 power supply to all households/homes, industrial & commercial consumers and adequate supply of power to agricultural consumers as per State policy. All the State Governments and Union Territories have signed the “24X7 Power For All” agreement with the Union Government.

Government of India supplements the efforts of State through its schemes including Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY), Integrated Power Development Scheme (IPDS), Ujwal DISCOM Assurance Yojana (UDAY) etc.

********  

   

Page 15: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.82

ANSWERED ON 17.07.2017

EMPLOYMENT TO PEOPLE AFFECTED BY LAND ACQUISITION BY POWER COMPANIES

†82. SHRI P.L. PUNIA: Will the Minister of POWER be pleased to state:

(a) whether power companies give preference to farmers and their families, affected by land acquisition, for working in their projects and if so, the number of affected families and the number of such families who were provided with employment; (b) the number of affected farmers who have been regularized and the number of farmers families that are still dependent on irregular employment; and (c) whether arrangement for quality education has been made for educating the children of workers, if so, the details thereof?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES

( SHRI PIYUSH GOYAL )   (a) : Central Public Sector Enterprises give preference to project affected farmers and their families affected by land acquisition for their project subject to availability of vacancies and suitability of the affected persons. CPSEs also facilitate giving indirect employment to project affected persons through contracting agencies, petty contracts, PAP Cooperative Societies and other self employment avenues during construction and operation phases as per company policy. (b) : As per information provided by NTPC, NHPC, THDC, SJVN, PGCIL and NEEPCO, 5658 project affected persons, including farmers, have been provided regular employment in the projects by these CPSEs. 48 persons belonging to the land affected families of Pare Hydro Electric Project are engaged on contract basis by NEEPCO.

(c) : The power sector CPSEs establish schools in the project area where children belonging to land affected families are also extended schooling facilities. Besides under their CSR initiative, the CPSEs also provide infrastructure for nearby schools, free transportation, uniforms, books, stationery etc.

*********

Page 16: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.83

ANSWERED ON 17.07.2017

SETTING UP OF A "HOLDING COMPANY" TO RESCUE STRESSED PRIVATE POWER PLANTS

83. SHRI DHARMAPURI SRINIVAS:

SHRI T.G. VENKATESH: Will the Minister of POWER be pleased to state:

(a) whether the Ministry has reviewed the status of debt-laden private power plants in the country; (b) if so, the details thereof; (c) whether it is a fact that Government is contemplating on setting up of a holding company with the help of NTPC, PFC, REC and banks to acquire the debt-laden private power plants and run the companies and if so, the details thereof; and (d) the details of outcome of the review meeting in this regard?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a), (b) & (d) : Government has reviewed the status of 34 stressed Thermal Power Projects, as per the list provided by Department of Financial Services. During the review meeting, Government has identified the major reasons for stress in the Power Sector, which are as follows:

(i) Non-availability of regular fuel supply arrangements - For grant of regular coal linkages, Govt. of India has approved New coal allocation policy, 2017 for Power sector on 17.05.2017 viz. SHAKTI (Scheme for Harnessing and Allocating Koyala Transparently in India) under which inter-alia, coal is made available to Independent Power Producers (IPPs) against long-term Power Purchase Agreements (PPAs) and medium-term PPAs to be concluded in future in a transparent bidding process.

...........2.

Page 17: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 2 -

(ii) Lack of Power Purchase Agreement (PPA) tie-ups - To improve the demand of

Power, following measures have been taken:

a. Ujwal DISCOM Assurance Yojana (UDAY) scheme for Financial and Operational Turnaround of power distribution utilities (DISCOMs) of the country.

b. Power For All (PFA) initiative with States and UTs for bringing uninterrupted quality of power to each household, industry, commercial business, small & medium enterprise and establishment.

c. Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY) for Rural Electrification;

strengthening of sub-transmission and distribution networks in the rural areas; separation of agriculture and non-agriculture feeders and metering of distribution transformers/ feeders/consumers in the rural area.

d. Integrated Power Development Scheme (IPDS) for strengthening of sub-

transmission and distribution networks in the urban areas; Metering of distribution transformers/feeders/consumers in the urban areas and IT enablement of distribution sector.

e. Augmenting Transmission capacity to remove transmission constraints.

f. Flexibility in utilisation of domestic coal for reducing the cost of power generation.

(iii) Inability of the Promoter to infuse the equity and service debt.

(iv) Regulatory and Contractual issues. (c) : The issue of setting up of a fund has been discussed among other options with stakeholders.

************

Page 18: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.84

ANSWERED ON 17.07.2017

TARGETS UNDER DDUGJY 84. SHRI NARAYAN LAL PANCHARIYA: Will the Minister of POWER be pleased to state:

(a) the details of the targets set for Rajasthan under the Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY); (b) how much amount Government proposes to spend on electrification in rural areas, especially in Rajasthan, during the current fiscal year; (c) whether any specific assistance is provided to BPL households in rural areas for electrification; and (d) how many households are likely to benefit from the scheme during the current year and how many of them will be below the poverty line?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a): The targets set for Rajasthan during the financial year 2017-18 under Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY), are as under:

Electrification of un-electrified village (UEV) - One Intensive Electrification of villages - 5,996. Free Electricity connection to BPL HHs - 85,686

(b): There is no upfront allocation of funds to any State/District under DDUGJY. Funds are released against sanctioned projects in installments based on the reported utilisation of amount in the previous installment(s) and fulfillment of other conditionalities as per DDUGJY guidelines. However, Government of India has allocated budgetary support of Rs.4814 crore for the year 2017-18 for DDUGJY projects in the country. (c) & (d): Under DDUGJY, access to electricity is provided to all the rural households and free electricity service connection is provided to all eligible Below Power Line (BPL) households in the country. Under the scheme, free electricity service connections to 40 lakh BPL Households are targeted in the country during the financial year 2017-18.

*********

Page 19: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.85

ANSWERED ON 17.07.2017

IMPACT OF SURPLUS POWER ON BIO-MASS PLANTS IN ANDHRA PRADESH

85. DR. K.V.P. RAMACHANDRA RAO: Will the Minister of POWER be pleased to state:

(a) whether it is a fact that several biomass plants were on the verge of closure due to availability of surplus power in Andhra Pradesh as it had stopped supply to Telangana; (b) if so, the details thereof; and (c) the details of the installed capacity of power generation and demand in Andhra Pradesh and Telangana during the last three years?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )   

(a) & (b) : No, Sir.

(c) : The details of the installed capacity of power generation and demand in

Andhra Pradesh and Telangana during the last three years is given at Annex.

*************

   

Page 20: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEX

ANNEX REFERRED TO IN REPLY TO PART (c) OF UNSTARRED QUESTION NO. 85 ANSWERED IN THE RAJYA SABHA ON 17.07.2017.

***********

The installed capacity of power generation in Andhra Pradesh and Telangana as on 30.06.2017

(All figure in MW) State Conventional RES* Total Andhra Pradesh 15658.67 6164.42 21823.09Telangana 10280.61 1545.88 11826.49

* Installed capacity in respect of RES (MNRE) as on 31.03.2017

Demand of electricity in Andhra Pradesh and Telangana during the last three years:

(in MW)

************    

State 2014-15 2015-16 2016-17 April to June, 2017 (provisional)

Andhra Pradesh 7144 7400 7969 8024 Telangana 7884 6854 9187 7240

Page 21: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.86

ANSWERED ON 17.07.2017

STATUS OF KAYAMKULAM THERMAL POWER PLANT 86. SHRI K.K. RAGESH: Will the Minister of POWER be pleased to state:

(a) whether the Central Government is considering to handover the Kayamkulam thermal power plant to Kerala; and (b) if so, the details thereof?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )   

(a) : No, Sir.

(b) : In view of reply to (a) above, question doesn’t arise.

*********

 

   

Page 22: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.87

ANSWERED ON 17.07.2017

STATUS OF POWER GENERATION AND PROJECT IMPLEMENTATION IN THE COUNTRY

†87. SHRI MEGHRAJ JAIN: Will the Minister of POWER be pleased to state:

(a) the details of the demand and supply of power in the country including Madhya Pradesh, State-wise; (b) the quantum of power generated by each State using its own resources during the last two years and the current financial year and the details of the quantum of power provided to each State from central power generating stations during the said period; and (c) whether the Central Government has sanctioned any power project for various States during the last two years and if so, the details of the said projects, State-wise?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL ) (a) : The State-wise details of demand and supply of power including Madhya Pradesh during the current year (April, 2017- June, 2017) are given at Annex-I. (b) : The quantum of power produced by each State/UT with its own resources and the quantum of power given from central generating stations (schedule) to each State/UT, during the last two years and the current year is given in Annex-II & III respectively. (c) : Electricity is a concurrent subject. As per Electricity Act, 2003, electricity generation is a delicensed activity and any State or generating company may establish a generating station.

However, hydro projects need Techno-economic Clearance. Detailed Project Reports (DPRs) of 14 nos. of Hydroelectric Projects with aggregate installed capacity of 9,632 MW have been concurred by CEA since April, 2015. State-wise details of the same are given at Annex-IV.

**************    

Page 23: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEX-I

ANNEX REFERRED TO IN REPLY TO PART (a) OF UNSTARRED QUESTION NO. 87 ANSWERED IN THE RAJYA SABHA ON 17.07.2017.

***********   

Power Supply Position for 2017-18 (Provisional)

Energy Peak

State / April, 2017 - June,2017 April, 2017 - June,2017

System / Energy

Requirement Energy

Supplied Energy not Supplied

Peak Demand

Peak Met

Demand not Met

Region ( MU ) ( MU ) ( MU ) ( % ) ( MW ) ( MW ) ( MW ) ( % ) Chandigarh 487 478 9 2 340 340 0 0 Delhi 9,345 9,338 7 0.1 6,553 6,526 27 0.4 Haryana 12,875 12,875 0 0.0 8,912 8,912 0 0.0 Himachal Pradesh 2,326 2,317 9 0.4 1,377 1,377 0 0.0 Jammu & Kashmir 4,597 3,669 928 20.2 2,768 2,214 554 20.0 Punjab 14,015 14,015 0 0.0 10,786 10,786 0 0.0 Rajasthan 16,829 16,723 106 0.6 10,347 10,347 0 0.0 Uttar Pradesh 31,942 31,575 367 1.1 18,827 18,061 766 4.1 Uttarakhand 3,500 3,493 7 0.2 2,027 2,027 0 0.0 Northern Region 95,915 94,481 1,434 1.5 53,382 52,429 953 1.8 Chhattisgarh 6,829 6,829 0 0.0 3,888 3,887 1 0.0 Gujarat 29,192 29,192 0 0.0 15,693 15,693 0 0.0 Madhya Pradesh 16,166 16,166 0 0.0 8,402 8,402 0 0.0 Maharashtra 40,054 40,003 51 0.1 22,542 22,494 48 0.2 Daman & Diu 630 630 0 0.0 342 342 0 0.0 Dadra Nagar Haveli 1,525 1,525 0 0.0 771 771 0 0.0 Goa 1,036 1,036 0 0.0 558 557 1 0.2 Western Region 95,433 95,382 51 0.1 49,860 49,788 72 0.1 Andhra Pradesh 14,384 14,377 7 0.0 8,024 8,000 24 0.3 Telangana 13,291 13,286 5 0.0 9,009 9,001 8 0.1 Karnataka 16,640 16,634 6 0.0 9,992 9,987 5 0.1 Kerala 6,394 6,388 6 0.1 3,889 3,862 27 0.7 Tamil Nadu 27,986 27,977 9 0.0 15,001 14,975 26 0.2 Puducherry 703 703 0 0.0 388 387 0 0.1 Lakshadweep# 12 12 0 0 8 8 0 0 Southern Region 79,399 79,365 34 0.0 42,770 42,535 235 0.5 Bihar 6,797 6,606 191 2.8 4,122 4,021 101 2.5 DVC 5,230 5,221 9 0.2 2,770 2,770 0 0.0 Jharkhand 1,969 1,962 7 0.4 1,211 1,211 0 0.0 Odisha 7,285 7,283 2 0.0 4,227 4,227 0 0.0 West Bengal 13,627 13,571 56 0.4 7,828 7,828 0 0.0 Sikkim 106 106 0 0.0 91 91 0 0.0 Andaman- Nicobar# 60 45 15 25 40 32 8 20 Eastern Region 35,015 34,751 264 0.8 19,238 19,191 47 0.2 Arunachal Pradesh 183 180 3 1.6 145 145 0 0.2 Assam 2,227 2,111 116 5.2 1,744 1,623 121 6.9 Manipur 184 181 3 1.6 163 161 2 1.2 Meghalaya 407 407 0 0.0 304 304 0 0.1 Mizoram 124 122 2 1.6 86 85 1 0.8 Nagaland 187 184 3 1.6 147 146 1 0.7 Tripura 605 592 13 2.1 280 276 4 1.4 North-Eastern Region

3,918 3,777 141 3.6 2,499 2,391 108 4.3

All India 3,09,680 3,07,755 1,925 0.6 1,59,816 1,58,393 1,423 0.9 #Lakshadweep and Andaman & Nicobar Islands are stand- alone systems, power supply position of these, does not form part of regional requirement and availability

Page 24: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEX-II

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO. 87 ANSWERED IN THE RAJYA SABHA ON 17.07.2017.

***********

State’s Own Gross Generation State Generation (Million Units)

2017-18 (April-June)* 2016-17 2015-16 DELHI 1118.13 4548.41 3964.66HARYANA 2103.7 9486.92 10396.08HIMACHAL PRADESH 605.99 1293.51 1161.81JAMMU AND KASHMIR 2078.7 4789.6 3980.3PUNJAB 2872.31 9747.67 12343.39RAJASTHAN 5777.3 27249.38 27399.94UTTAR PRADESH 9257.45 30963.85 28153.73UTTARAKHAND 1246.74 4201.44 4762.86CHHATTISGARH 5265.65 18217.32 15603.8GOA 0 0 0GUJARAT 7039.66 21370.76 23101.99MADHYA PRADESH 4123.37 17212.15 20538.42MAHARASHTRA 14925.1 49921.11 47213.52ANDHRA PRADESH 6547.37 29085.32 25049.76KARNATAKA 5466.85 24916.93 25037.87KERALA 1184.07 4115.21 6510.59PUDUCHERRY 56.25 246.84 227.59TAMIL NADU 7470.13 29112.29 34543.58TELANGANA 7101.43 23793.71 16617.61ANDAMAN NICOBAR 46.4 215.56 182.85BIHAR 36.04 131.42 0JHARKHAND 368.09 1453.43 2687.98ODISHA 2660.89 8348.87 8027.67SIKKIM 1133.53 309.42 0WEST BENGAL 7285.53 27222.58 23430.87ARUNACHAL PRADESH 0 0 0ASSAM 368.18 1640.2 1864.37MANIPUR 0 0 0MEGHALAYA 221.83 719.6 860.94NAGALAND 0 0 0TRIPURA 155.7 624.19 739.22* PROVISIONAL BASED ON ACTUAL-CUM-ASSESMENT Note: 1 Generation from conventional sources (Thermal, Hydro and Nuclear) stations of 25 MW and

above only. 2. Figures given above indicate gross generation of the power stations located geographically in the

respective State/UT.  

************* 

   

Page 25: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEX-III

ANNEX REFERRED TO IN REPLY TO PART (b) OF UNSTARRED QUESTION NO. 87 ANSWERED IN THE RAJYA SABHA ON 17.07.2017.

***********

State-wise Quantum of Power from Central Generating Stations (Figures in Million Units)

States/System 2016-17 2015-16Northern Region Chandigarh 1036.29 991.57Delhi 19323.06 19520.72Haryana 14471.50 13225.44H.P. 6879.98 6800.19J & K. 10627.99 10636.01Punjab 18971.96 18790.36Rajasthan 17734.24 17800.98U.P. 37021.07 39718.29Uttarakhand 5443.20 5536.44Western Region Chhattisgarh 7491.32 7474.19Gujarat 26134.32 32370.59Madhya Pradesh 26932.74 35878.95Maharashtra 33100.10 33618.60DD 1586.63 1868.65DNH 3412.69 3811.64Goa 3292.07 3423.26Southern Region Andhra Pr. 11598.87 12476.72Telangana 12813.12 14890.68Karnataka 19480.65 15666.53Kerala 10574.77 11595.43Tamil Nadu 33062.04 29716.64Puducherry 2587.65 2423.49Eastern Region Bihar 18252.19 15949.85Jharkhand 3817.31 3096.47Odisha 8280.89 7448.19W. Bengal 7108.90 6809.62Sikkim 817.89 773.25North Eastern Region Arunachal Pr. 727.09 601.71Assam 5929.27 4231.95Manipur 968.36 747.60Meghalaya 793.25 937.15Mizoram 542.94 409.57Nagaland 658.42 532.42Tripura 1624.03 1360.63

 

************* 

   

Page 26: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

ANNEX-IV

ANNEX REFERRED TO IN REPLY TO PART (c) OF UNSTARRED QUESTION NO. 87 ANSWERED IN THE RAJYA SABHA ON 17.07.2017.

***********

List of Hydro Electric Schemes concurred/ appraised by CEA since April, 2015

S. No.

Name of Scheme Sector Developer Installed Capacity (MW)

Jammu & Kashmir 1. Kiru Joint- Venture CVPPL 624 2. Sawalkot State JKPDC 1856 3. Kirthai-II State JKPDC 930 4. Kwar Joint-Venture CVPP 540

Sub-Total 3950

Himachal Pradesh

5. Seli Private SHPCL 400 6. Sach Khas Private L&T HHPL 267 7. Dugar Private DHPL 449

Sub-Total 1116 West Bengal

8. Turga PSP State WBSEDCL 1000 Sub-Total 1000 Arunachal Pradesh

9. Heo Private HHPPL 24010. Tato-I Private SHPPL 186 11. Tagurshit Private L&T 74

12. Dibang Central NHPC 2880

Sub-Total 3380

Assam

13. Lower Kopili State AGPCL 120

Sub-Total 120 Manipur

14. Loktak Downstream Central LDHCL 66 Sub-Total 66 Total 9632

 

**************   

Page 27: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.88

ANSWERED ON 17.07.2017

WAIVER OF INTER-STATE SUPPLY CHARGES ON SOLAR POWER PROJECTS

88. SHRI N. GOKULAKRISHNAN:

DR. PRADEEP KUMAR BALMUCHU: Will the Minister of POWER be pleased to state:

(a) whether it is a fact that Government has taken a decision to waive inter-State supply charges on solar power projects to make them feasible and to compete with thermal power projects; and (b) if so, the details thereof?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )

(a) & (b) : Ministry of Power, Government of India, vide Order dated 14th June 2017,

has extended the waiver of the inter-State transmission charges and losses for the

generation project based on solar resources for use of inter-state transmission system

(ISTS) network by such Projects commissioned till 31.12.2019, for a period of 25 years

from the date of commissioning of such projects.

Such waiver shall be available only for those projects entering into PPA with

Discoms for compliance of their renewable purchase obligation (RPO) and are awarded

through competitive bidding process.

***************

 

Page 28: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.89

ANSWERED ON 17.07.2017

VIABILITY OF THERMAL POWER PLANTS

89. SHRI D. KUPENDRA REDDY: Will the Minister of POWER be pleased to state:

(a) whether it is a fact that the country's thermal power plants would become economically unviable as reported in the media recently; (b) if so, the details thereof; and (c) the steps taken/being taken by Government to keep the thermal power plants of the country economically viable and productive?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )

(a) : No, Sir. (b) : Does not arise. (c) : The Government has taken the following measures to support thermal power plants: i. Ensuring Coal supply through a more Transparent Coal Allocation Policy for Power

Sector, 2017 namely Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India (SHAKTI).

ii. Amended Mega Power Policy for Provisional Mega Power Projects

iii. Ujwal DISCOM Assurance Yojana (UDAY) scheme for Financial and Operational

Turnaround of power distribution utilities (DISCOMs) of the country.

iv. Augmenting Transmission capacity to remove transmission constraints.

v. Flexibility in utilisation of domestic coal for reducing the cost of power generation.

**********

Page 29: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.90

ANSWERED ON 17.07.2017

IMPACT OF DEMONETISATION ON POWER SECTOR 90. SHRI A.K. SELVARAJ: Will the Minister of POWER be pleased to state:

(a) whether demonetisation has turned out to be a positive event for the power sector with the distribution companies recovering pending power bills from their customers; (b) whether power sector could also benefit from relaxed lending and lower rates of interest among others; (c) whether banks are suddenly flushed with funds, all of which could relax lending to the power sector and potentially bring down interest rates beneficial to power sector; and (d) if so, the details thereof?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )   

(a) : As per the information collated by Power Finance Corporation (PFC), the

collection of electricity dues for the period from 10th November 2016 to 15th December

2016 was approximately Rs.29,111.70 Crore against Rs.26,722.01 Crore of the

corresponding period of the previous year.

(b) to (d) : Lending rates are commercial decisions of Banks depending upon several

factors including liquidity, sectoral risks and the investment environment.

**************

 

   

Page 30: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA

MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.91

ANSWERED ON 17.07.2017

REPLACEMENT OF OUTDATED PLANTS BY NTPC 91. SHRI A.K. SELVARAJ: Will the Minister of POWER be pleased to state:

(a) whether the National Thermal Power Corporation (NTPC) would spend Rs.50,000 crore to replace outdated plants which are more than 25 years old; (b) if so, the details thereof; (c) whether NTPC is considering to replace the old and outdated plants by more efficient and less polluted modern units to reduce carbon emission; and (d) if so, the details thereof?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )

(a) to (d) : Ordinarily the life of thermal power generating stations is taken as 25 years

and can operate for a longer period depending on the condition of the plant. Review and

decommissioning of old plants is a continuous process. NTPC sets up new plants based on

the criteria of electricity demand from the states. Currently, NTPC is in the process of

setting up new high efficiency ultra supercritical plants at Patratu, Talcher Thermal and

Singrauli.

**************

 

   

Page 31: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

GOVERNMENT OF INDIA MINISTRY OF POWER

RAJYA SABHA UNSTARRED QUESTION NO.92

ANSWERED ON 17.07.2017

SCHEME FOR REVIVAL OF STALLED POWER UNITS 92. SHRI ANAND SHARMA: Will the Minister of POWER be pleased to state:

(a) whether the majority of assets in the power generation sector have been categorised as Non-Performing Assets (NPAs); (b) whether Government proposes to introduce a scheme to revive the stalled power units; and (c) if so, the details of the scheme and the target period by which the scheme would be implemented?

A N S W E R

THE MINISTER OF STATE (INDEPENDENT CHARGE) FOR POWER, COAL, NEW & RENEWABLE ENERGY AND MINES ( SHRI PIYUSH GOYAL )

(a) : No, Sir.

(b) & (c) : Government has taken following measures to address stress in the power

sector:

i. Ensuring Coal supply through a more Transparent Coal Allocation Policy for

Power Sector, 2017 namely Scheme for Harnessing and Allocating Koyala (Coal) Transparently in India (SHAKTI).

ii. Ujwal DISCOM Assurance Yojana (UDAY) scheme for Financial and Operational Turn-around of power distribution utilities (DISCOMs) of the country.

iii. Augmenting Transmission capacity to remove transmission constraints.

………..2.

Page 32: RAJYA SABHA STARRED QUESTION NO.04 …powermin.nic.in/sites/default/files/uploads/RS_17072017...GOVERNMENT OF INDIA MINISTRY OF POWER RAJYA SABHA STARRED QUESTION NO.04 ANSWERED ON

- 2 -

iv. Flexibility in utilisation of domestic coal for reducing the cost of power generation.

v. Power For All (PFA) initiative with 36 States and UTs for bringing uninterrupted quality of power to each household, industry, commercial business, small & medium enterprise and establishment, any other public needs and adequate power to agriculture consumer as per the state policy.

vi. Deen Dayal Upadhyaya Gram Jyoti Yojana (DDUGJY) for:

Separation of agriculture and non-agriculture feeders.

Strengthening of sub-transmission and distribution networks in the rural areas;

Metering of distribution transformers / feeders / consumers in the rural areas.

Rural Electrification

vii. Integrated Power Development Scheme (IPDS) for:

Strengthening of sub-transmission and distribution networks in the urban areas;

Metering of distribution transformers / feeders / consumers in the urban area.

IT enablement of distribution sector and strengthening of distribution network.

 

**************