QA QC PLAN for CNG

Embed Size (px)

Citation preview

  • 7/24/2019 QA QC PLAN for CNG..

    1/21

    QA / QC PLAN

    Rev.No. Date Description Reference No. Approved

    0 October 2015 Issued for Approved

    CLIENT :

    PROJECT :PROJECT NO.:

    WORK/SCOPE

    :

    Page1 of 21

  • 7/24/2019 QA QC PLAN for CNG..

    2/21

    QA/QC PLAN

    Page no. : 0 Page

    2 of 21Rev. date :

    Date :

    TABLE OFCONTENTS

    PART TI TLEPAGE

    1 PART-1 GENERAL. 3

    1.1 Purpose. .. 4

    1.2 Extent . .. 4

    1.3 Definition of Term 4-6

    2 PART-2 ORGANIZATION . 7

    2.1 Project Organization . 8

    3 PART-3 DESIGN .. 9

    3.1 Design and Relevant Quality Control ... 10

    3.2 Changes Control 10

    4 PART-4 PROCUREMENT CONTROL . 11

    4.1 General . 12

    4.2 Vendors Evaluation .. 12

    4.3 Purchasing Control .. 12-13

    4.4 Shop Inspection and Control 13-14

    4.5 Non-Conformance Control .. 14-15

    4.6 Sub contracting .. 15-16

    5 PART 5 SITE CONSTRUCTION AND INSTALLATION 17

    5.1 Scope . 18

    5.2 Document Control . 18-19

    5.3 Material Receipt, Storage and Trace ability ... 19

    5.4 Field Quality Control 20

    5.5 Construction Equipment and Test/Inspection Equipment Control 205.6 Non-Conformance Control 20-21

    5.7 Final Documentation and Records 21

  • 7/24/2019 QA QC PLAN for CNG..

    3/21

    QA/QC PLAN

    Page no. : 0 Page

    3 of 21Rev. date :

    Date :

    1. PART 1 - GENERAL

    1.1. PURPOSE

    1.2. EXTENT

    1.3. DEFINITION OFTERMS

  • 7/24/2019 QA QC PLAN for CNG..

    4/21

    QA/QC PLAN

    Page no. :0 Page

    4 of 21Rev. date :

    Date :

    1.1. PURPOSE

    The main purpose on this QA/QC Plan is to ensure in achieving the desired level of

    quality of a completed facility.

    1.2. EXTENT

    1.2.1. The requirements in this QA/QC Plan pertains to the contract activities effecting

    quality including Design, Procurement .Fabrication, Transportation, Storage,

    Installation and Testing.

    1.2.2. Any organization, firm, sub-contractor or party who carries-out any of the above

    activity shall conform to the requirement of this QA/QC Plan. In such cases, the

    interfacing between different parties shall be defined and controlled.

    1.3. DEFINITION OF TERMS

    In this QA/QC Plan the following term are mentioned and defined as follows;

    Acceptance Criteria - Specified limits mentioned which characterizedan item, process, or service defined codes,

    standards or other requirement document.

    Approval - An act of endorsing or adding positive

    authorization of both.

    Certificate of Conformance - A document signed by an authorized individual,

    certifying the degree to which items or services

    meet specified requirements at the time of

    assessment.

    Certification - The authoritative act of documenting compliance

    with requirements.

    Contractor -

    Client -

    Document - Any written or pictorial information describing,

    defining, specifying, reporting, or certifying

    activities, requirements, procedures, or result.

    Inspection - Examination of measurement to verify whether

    an item or activity conforms to specified

    requirement

    Inspection Authority - Clients own inspection department and or

  • 7/24/2019 QA QC PLAN for CNG..

    5/21

    QA/QC PLAN

    Page no. :0 Page

    5 of 21Rev. date :

    Date :

    Nationality or internationally recognized Inspecification agency.

    Inspection Level - Specified amount of inspection coverage deemednecessary to assure that a product or services

    conforms to specifications.

    Interface (Interfacing) - Interrelationship between the different

    organization participating to the same project and

    also relating to define communication and

    physical boundary.

    Item - Any level of unit assembly, including structure

    system, subassembly, component, part or

    material.

    Non Conformance - A deficiency in characteristics documentation of

    procedure that renders the quality of an item or

    activity unacceptable or indeterminate.

    Objective Evidence - Any documented statement or fact, information

    or record, quantitative or qualitative, pertaining to

    the quality of an item or activity, based on

    observations, measurements, or tests which can

    be verified.

    Procedure - A document that specifies or describes show an

    activity is to be performed.

    It may include methods to be employed or

    materials to be used and sequence of operations.

    Qualification (Personnel) - The characteristics or abilities gained through

    education, training, or experience as measured,

    such as standards or tests, that quality of an

    individual to perform a required function.

    Quality Assurance (QA) - All these planned, systematic actions, and

    detailed schemes developed and documented

    before hand necessary to provide adequate

    confidence that a product, processor service will

    be satisfied.

    Quality Control (QC) - That pasta QA which through checks, review,

    measurements, tests, and inspection determines

    that specifications are met.

  • 7/24/2019 QA QC PLAN for CNG..

    6/21

    QA/QC PLAN

    Page no. :0 Page

    6 of 21Rev. date :

    Date :

    Repair - The process of correcting and/or rectifying aNon conforming characteristics to a condition

    such that the capability of an item to functionreliably and safety is unimpaired even conform to

    the original requirement.

    Surveillance - The act if monitoring or observing to verify

    whether any item or activity conforms to

    specified requirements.

    Testing - An element of verification for the determination

    of the capability of an item to meet specified

    requirements by subjecting the item to set of

    physical, chemical, environmental or operating

    conditions.

    Traceability - The ability to trace the history, application, or

    location of an item an like items or activities by

    means of recorded identification.

    Use-as-is - A disposition permitted for a non conforming

    item when it can be established that the item is

    satisfactory for its intended use.

    Verification - The act of reviewing, inspecting, testing,

    looking, auditing or other wise determining and

    documenting whether items, process, services, or

    documents conform to specified requirements.

    Waiver - Documented authorization to deviate from

    specified requirements.

  • 7/24/2019 QA QC PLAN for CNG..

    7/21

    QA/QC PLAN

    Page no. :0 Page

    7 of 21Rev. date :

    Date :

    2. PART2 - ORGANIZATION

    2.1. PROJECT ORGANIZATION

  • 7/24/2019 QA QC PLAN for CNG..

    8/21

    QA/QC PLAN

    Page no. :0 Page

    8 of 21Rev. date :

    Date :

    2.1. PROJECT ORGANIZATION

    2.1.1. The Project Organization, de line at as the authority and responsibility of theappointed persons and parties performing project activities.

    The Organization Chart indicates the key positions both at home office and on

    site engaged in the project. While other engineering groups from the permanent

    organization will be assigned to the project team in relation to the needs defined

    and scheduled by the Project Management.

    2.1.2. The structure of the Quality Assurance team in the Project Organization and the

    relation ship with the Project Management, the QA/QC team and the other

    functions.

    2.1.3. The overall responsibility for site construction is of the Site Manager who reports

    to the Project Manager.

    The execution of the works is the responsibility of the Construction Manager

    while field it the responsibility of the Construction Manager while field quality

    control activities are the responsibility of Field QC Engineer.

    2.1.4. The execution of the work on site in accordance with the drawings and

    specifications shall be ensured by the Field Erection Superintendents and

    Supervisors who report to the Construction Manager.

    2.1.5. At Site, the engineering activities shall be carried out be the Engineering Team

    headed by the Field Engineering Manager. On Site, the quality control activities

    shall be ensured by the QC team under the coordination of the Field QC

    Engineer who reports to the Site Manager.

    The Site Quality Control is included but not limited to the activities for materials

    and equipment at their arrival at Site. Special process used during construction

    and completed testing and examination of items and systems during and after

    installation.

    2.1.6. The Field QC Team will act as a separate entity from construction team and

    therefore free of conflicts with progress and construction restraints.

    2.1.7. The Clients representative and Inspection Authority, acting on be half of the

    Client, witness to ensure that the project is carried out in accordance with the

    contract requirements. The Quality Assurance Plan, system or program which

    either during site construction clearly shows the relevant witnessing points.

  • 7/24/2019 QA QC PLAN for CNG..

    9/21

    QA/QC PLAN

    Page no. :0 Page

    9 of 21Rev. date :

    Date :

    3. PART3 - DESIGN

    3.1. DESIGN AND RELEVANT QUALITY CONTROL

    3.2. CHANGES CONTROL

  • 7/24/2019 QA QC PLAN for CNG..

    10/21

    QA/QC PLAN

    Page no. :0 Page

    10 of 21Rev. date :

    Date :

    3.1. DESIGN AND RELEVANT QUALITY CONTROL

    3.1.1. Measures are established to ensure that the Design activities are planned, carriedand reviewed in a controlled manner in accordance with the established project

    requirements. The Engineering documents to be produced in the project will be

    controlled with document list which indicate the date of issuing for project use

    (inquiry, purchase, construction, etc.) and those which are subject to clients, etc.)

    And those which are subject to clients approval/comment.

    3.1.2. Responsibilities for preparation, checking, reviewing, and approval of technical

    documents shall be clearly defined. Design reviews are planned, performed and

    recorded under the coordination of the Project Engineering Manager.

    3.1.3. The drawings and specifications to be issued must be approved and signed by the

    responsible Engineer concerned or other relevant position after verification that

    the established checks and design review shave been satisfactorily performed.

    When a document needs to be modified following a design/field change, the

    revisions shall be signed for approval by the same positions the approved the

    original document.

    Status and reason for document revisions is to be clearly indicated in the

    document front sheet.

    3.2. CHANGES CONTROL

    3.2.1. The design document may be revised for completion or for change purpose.

    The changes may result mainly from Client request, design requirements, shop or

    site exigencies. In any case it must be basic solution previously established or the

    project quality requirements.

    3.2.2. The document from required change shall be sent by the Engineer concerned to

    the Project Management for evaluation. If accepted copies of the change order

    are sent to all the involved persons and organizations. The technical documentsreflecting the design change shall be approved using the same procedure and by

    the same personnel as ones who approved the original design documents.

    3.2.3. Changes with multi disciplinary implications shall be examined by all the

    positions concerned. If necessary design review meetings shall be repeated as

    appropriate.

  • 7/24/2019 QA QC PLAN for CNG..

    11/21

    QA/QC PLAN

    Page no. :0 Page

    11 of 21Rev. date :

    Date:

    4. PART4 - PROCUREMENT CONTROL

    4.1. GENERAL

    4.2. VENDOR EVALUATION

    4.3. PURCHASING CONTROL

    4.4. SHOP INSPECTION AND TESTING

    4.5. NON- CONFORMANCE CONTROL

    4.6. SUB CONTRACTING

  • 7/24/2019 QA QC PLAN for CNG..

    12/21

    QA/QC PLAN

    Page no. :0 Page

    12 of 21Rev. date :

    Date :

    4.1. GENERAL

    4.1.1. The Procurement Control System is organized to give assurance that purchaseditems, whether directly or through vendors, meet the contractual requirements for

    quality, delivery schedule and economy.

    4.1.2. This system requires that Vendors meet the standards and specifications of the

    contract.

    4.1.3. The Procurement Control System includes provisions for source evaluation and

    selection, surveillance of the vendors and inspection of items and examination of

    documentation upon delivery.

    4.2. VENDOR EVALUATION

    4.2.1. Inquiries shall only be sent to qualified Vendors included in the Project Vendor

    Lists.

    4.2.2. For the vendors not included in the Project Vendor List, a prevention evaluation

    and qualification shall be carried out before the purchase order issue. The

    qualification is carried out by the Procurement Group in cooperation with the

    relevant technical and QA group as required.

    4.3. PURCHASING CONTROL

    4.3.1. The established procedures shall be implemented to make sure that all the

    applicable prescription, regulatory requirements, design basis and inspection

    requirements necessary to assure adequate quality of the bids are included or

    referenced in the documents for requisition of items and service. A said

    procedure defines the type documentation to be included in the inquiries and the

    responsibilities for their preparation, control and approval.

    4.3.2. Bid Evaluation

    The evaluation of the received bids shall be performed according to the

    established procedure. All the bids are compared in a bid summary.

    Technical bid evaluation is carried out buy the Engineering Group concerned to

    assess the adherence to the inquiring documents, the soundness of the proposed

    solutions and to evaluate the proposed deviations. Bid clarification meeting will

    be held with the Bidder son the short List. A survey may be carried out in

    connection with bid clarification meeting depending on previous experience with

    theBidder.

  • 7/24/2019 QA QC PLAN for CNG..

    13/21

    QA/QC PLAN

    Page no. :0 Page

    13 of 21Rev. date :

    Date :

    4.3.3. Purchase Orders

    The preparation and issuance of the purchase orders to the selected vendors/

    subcontractors shall follow the established procedures. Before orders for major

    items are issued, verifications will be carried out by the Engineering Group on

    the purchase order documentation to check that the following conditions are met;

    a. The Technical Bid Evaluation has been properly carried out by the

    Engineering Group concerned according to the procedures.

    b. The selected Vendor is included in the Project Vendor List and/or has been

    duly qualified.

    c. The documents attached there to are complete, updated, consistent to each

    other and include the approved drawing sand specifications.

    4.3.4. Vendor Documentation

    Vendors drawing sand data will be described in a Vendor Document List

    included in the Inquiry. Such list will specify in detail which documents will be

    apart of the supply and those to be submitted to Contractor (for

    approval/review/information) according to the delivery program.

    4.4. SHOP INSPECTION AND TESTING

    4.4.1. The vendor shall carry out the checks, inspection and tests required by the

    purchase order and inspection requirements.

    4.4.2. The minimum requirements for shop inspections and test for main equipment are

    detailed in the Inspection Requirements of the Contract.

    4.4.3. The Inspection will perform, as specified in the appropriate procedure;

    a. Pre inspection meeting with Vendors of major or critical equipment to clarifycontract requirement, coordination procedures and interfaces.

    b. Approval of the shop fabrication.

    c. Qualification of Welding Procedures.

    d. Qualification of Welders.

    e. Verification of Material Identification and Traceability.

    f. Check of material source certificates.

  • 7/24/2019 QA QC PLAN for CNG..

    14/21

    QA/QC PLAN

    Page no. :0 Page

    14 of 21Rev. date :

    Date :

    g. Witness shop inspection and testing and/or review relevant results in

    accordance with contract and/or relevant specification requirements.

    h. Check and validation of examination and test reports and certificates.

    4.4.4. The Project QA personnel will at tend the pre-inspection meetings with major

    supplies to verify their quality organization to clarify, Final Test Report will be

    prepared by vendor.

    4.4.5. On completion of inspection, Final Test Report will be prepared by vendor.

    4.4.6. Only after checking that all the established inspections, examinations and tests

    have been properly carried out, witnessed, evaluated documented, incompliance

    with the P.O., the inspector will review and approve with signature on the final

    inspection report to release for shipment.

    4.4.7. A final check of the documentation of inspections and test shall be carried out by

    the Project QA Team to verify completeness and adequacy.

    4.5. NON-CONFORMANCECONTROL

    4.5.1. Materials, components, equipment or system at deviate from approved

    specifications, drawings or other applicable documents or due to document

    deficiencies are indeterminate are considered as Non-Conforming Items andshall be properly marked and/or segregated in order to avoid the in advertent use.

    The Non-Conformance shall be documented by the inspector and the due course

    of action shall be initiated according to the concerned procedure.

    4.5.2. A Non-Conformance will be classified as;

    a. Minor Non-ConformanceWhen it can be solved with in the contractors

    QA Group, such as accepting;

    - Item replacement which affects the Project Schedule.

    - Complete repair in compliance with the applicable codes andspecifications.

    - Additional documentation (in case of document deficiency).

    b. Major Non-ConformanceWhen it is necessary to involve other Group such

    as;

    - Repair with a procedure to be approved.- Repair not leading to full conformance.

    - Replacement delaying the project schedule.

    - Use-as-is of the item.

  • 7/24/2019 QA QC PLAN for CNG..

    15/21

    QA/QC PLAN

    Page no. :0 Page

    15 of 21Rev. date :

    Date :

    4.5.3. There solution of major non-conformance shall involve all concerned Project

    function sand the Project QA Manager. The later will verify that all implications

    concerning the quality are duly considered and that there solution of the non-conformance is effective and documented.

    The above shall be applied also is the case of vendor, should propose a change

    not in compliance with the requirements of purchase specifications.

    4.5.4. The Non-conformance resolution such as Use-as-is or a Repair not leading to

    full conformance to governing specifications, drawings or Contract

    Documents but not effecting the suitability for service of materials, shall be

    exhaustively documented in the non-conformance report by the Contractors

    Inspector.

    In both cases the documents non-conformance resolution shall be submitted to

    the Project Manager for evaluation and disposition.

    4.5.5. As soon as a major non-conformance is found, a copy of the relevant Quality

    Control Report shall be sent to the Project QA Manager who will verify the

    effectiveness of the corrective action.

    4.5.6. There solution of a major non-conformance shall be documented by the Project

    QA Manager and the relevant report shall be signed by all individual concerned,

    A copy of this report will be filed by the Project QA Manager as QA Record.

    4.6. SUBCONTRACTING

    4.6.1. General

    This describes the measures which are established and documented to assure that

    services, complete assemblies or constructions are supplied in a controlled way

    with the aim to satisfy the Project requirements for quality, delivery schedule and

    cost.

    4.6.2. Instructions of Tendering Subcontractors

    The Contracts Department is responsible for collecting all documents to be

    included in the Tender Invitation such as;

    - Scope of Work.

    - Technical Requirement (including Inspection and Test Requirements).- Commercial Conditions.

  • 7/24/2019 QA QC PLAN for CNG..

    16/21

    QA/QC PLAN

    Page no. :0 Page

    16 of 21Rev. date :

    Date :

    4.6.3. Tender Evaluation

    The Evaluation of the received tenders shall be preformed by the Engineeringgroup concerned to assess the adherence to the inquiry documents.

    The Final Tender Evaluation will end up with a Tender Evaluation Report where

    the contractors are ranked and all necessary documents to be included in the

    contract are listed.

    4.6.4. Contract Award

    Contract commitments are made only the Tender Evaluation Report has been

    approved according to the Project provisions. The Procurement Group in

    cooperation with the Engineering Group shall prepare the Contract clearly

    stating all the requirements of quality related, technical and commercial nature,

    including what has been agreed upon during the clarification meetings.

  • 7/24/2019 QA QC PLAN for CNG..

    17/21

    QA/QC PLAN

    Page no. :0 Page

    17 of 21Rev. date :

    Date :

    5. PART5 - SITE CONSTRUCTION AND INSTALLATION

    5.1. SCOPE

    5.2. DOCUMENT CONTROL

    5.3. MATEIALRECEIPT, STORAGE AND TRACEABILITY

    5.4. FIELD QUALITY CONTROL

    5.5. CONSTRUCTION EQUIPMENT AND TEST INSPECTIONEQUIPMENT CONTROL

    5.6. NON - CONFORMANCE CONTROL

    5.7. FINAL DOCUMENTATION AND RECORDS

  • 7/24/2019 QA QC PLAN for CNG..

    18/21

    QA/QC PLAN

    Page no. :0 Page

    18 of 21Rev. date :

    Date :

    5.1. SCOPE

    5.1.1. The purpose of this section is to provide a formalized and systematic means for

    the implementation of the Quality Control for Construction to ensure that the

    contracted facilities installed by the Field Project Organization are fully

    compliant with are relevant specifications, procedures, drawings, applicable

    codes, rules and regulations.

    5.1.2. The working procedures state the activities, for the relevant responsibilities, the

    quality control activities, the reports to be prepared, the communication lines to

    be maintained and the required recording system.

    5.1.3. This section includes the requirements pertaining to the administration and control

    of the technical documentation on site.

    5.1.4. It is also specified how the same requirements are imposed on subcontractors.

    5.1.5. Although the construction subcontractor is responsible for the execution, testing

    and documentation of the work, the Site Organization has as advisory function

    and is given the responsibility to provide a close follow-up subcontractor

    activities.

    5.2. DOCUMENT CONTROL

    5.2.1. Recording, filing and distribution of design documentation received from home

    office shall been sure by the Site Drawing Controller.

    5.2.2. The document will be distributed to the personnel concerned so as to be available

    at the location where the activity is to be performed prior to commencement of

    the activity it self.

    All obsolete documents must be marked OBSOLETE to prevent their

    misapplication.

    5.2.3. On working site, the Field Engineer concerned receives the construction

    specifications and drawings and review them, also taking into account any field

    requirements. Where necessary, he will ensure that modifications/additions to

    said documents are performed in compliance with the procedures.

    In case of change effecting the basic design, he ensures through the Field

    Engineering Manager the approval of home office Engineer concerned and,

    when necessary of the Customer Representative. The data necessary for the As

    Built Drawings will be collected by the Field Engineers.

    5.2.4. The documents which are prepared on site (or modified without needing the homeoffice approval as per part5.2.3) will be signed by the Field Engineer concerned

    and by the Field Engineering Manager for check and approval.

  • 7/24/2019 QA QC PLAN for CNG..

    19/21

    QA/QC PLAN

    Page no. :0 Page

    19 of 21Rev. date :

    Date :

    A copy of said documents will be sent to the relevant home office the Engineer

    who provides for the relevant recording, distribution and filing.

    5.2.5. Documentation relevant to fabrication and testing of purchased items and

    materials (mill certificates, test reports, manufacturers drawings, specifications,

    data reports, instruction manuals) will be received and filed by the Site Drawing

    controller.

    5.2.6. Recurrent in sections will be carried out at the working are as by the Field

    Engineers, to as certain that the latest revisions of construction drawings and

    specifications are be ingused.

    5.3. MATERIAL RECEIPT, STORAGE AND TRACEABILITY

    5.3.1. Material receipt, unloading, check registration, storage and traceability will be

    ensured by the material controller in accordance with the relevant procedure.

    5.3.2. Only after a satisfactory check, the received material may be release for the final

    registration and storage.

    Irregularity on the concerning document be found such as to identify anon-

    conformity, the Construction Manager shall be informed.

    He shall evaluate the non-conformity, informing when necessary, the concerned

    Engineer at home office.When contractual requirements are effected the client representative is to be

    informed.

    5.3.3. The Construction Managers evaluation of a non-conformity can be Rejection

    or Repair or Use-as-is and shall in any case be documented.

    In case of Repair, the relevant repair procedure is the responsibility of the

    Construction Manager concerned which, after repair will evaluate the results and

    issues the acceptance certificate.

    Should any deviation from design documents be accepted, the written approval

    of the concerned Engineer is necessary, before the acceptance certificate.

    Incase of deviations from contractual requirements, the customer writtenapproval will be required.

    These reports are to be filed as Quality Control Records.

    5.3.4. All the materials which have not passed the receiving control are to be marked

    HOLD and held being separated from the others, until they are accepted or

    rejected. In case rejection they must be marked REJECTED and kept

    segregated.

    5.3.5. For the released items or materials the Material Controller will provide for the

    project registration, storage, preservation and maintenance (to prevent any

    damage or deterioration) ensuring the traceability of stored items and materialsby painting or stamping project, identification symbols or marks, all in

    accordance with the procedures.

  • 7/24/2019 QA QC PLAN for CNG..

    20/21

    QA/QC PLAN

    Page no. :0 Page

    20 of 21Rev. date :

    Date :

    5.4. FIELD QUALITY CONTROL

    5.4.1. The site installation and construction work shall be performed in a planned andcoordinated manner using construction drawings and specifications.

    5.4.2. The inspection and test activities shall be planned in order to maintain overall

    project scheduling and shall be supported by the applicable procedures.

    The status of inspections and tests in every stage of the construction work shall

    be maintained by the Quality Control Engineer.

    5.4.3. The purpose of the Field Quality Control Plan is to define all the mandatory tests

    and examination to be carried out during the installation work to verify the work

    is carried out in conformity to specify prescriptions and to provide for the

    relevant documentary evidence.

    TheplanwillalsoshowthewitnesspointsandthetimingwhenQualityControl

    Engineer shall notify the customer and/or the Inspection Authority.

    5.4.4. Quality Control Team Construction Team will have meetings when ever QC

    Matter requires coordination or instruction prior to installation activity.

    5.4.5. The Client Inspection Group may witness the inspections and tests made in

    accordance with the Field QA Plan.

    This Plan will show the Clients witnessing points while the coordination between

    the Contractor and the Client is defined in the established procedure.

    5.5. CONSTRUCTION EQUIPMENT AND TEST/ INSPECTION EQUIPMENT

    CONTROL

    5.5.1. In general, using equipment (i.e. welding equipment, grinder etc.) the supervisor

    and warehouse staff confirm the condition of equipment and make a proper

    suggestion to prevent damage and maintain its original quality.

    5.5.2. The Field QC engineer nominates for a test and inspection equipment controller

    and let him control these equipment.

    5.6. NON - CONFORMANCECONTROL

    5.6.1. Any deficiency or deviation in characteristic, documentation, procedure or work

    which renders the quality of an item or work un acceptable or in determinate

    shall be considered as anon-conforming.A defined course of action shall be applied according to the concerned

    procedure.

    5.6.2. The finding of a Non-conforming may occur at any time during the installation

    work or routine inspection and may be made by any one. All field staff are awarethat it must be reported both to the Construction Manager and Field QC

    Engineer.

  • 7/24/2019 QA QC PLAN for CNG..

    21/21

    QA/QC PLAN

    Page no. :0 Page

    21 of 21Rev. date :

    Date :

    5.6.3. The Construction Manager and Field QC Engineer convene a discussion with the

    relevant personnel, to discuss the counter measures and make the final decision.

    5.6.4. When the disposition plan of non-conformities is considered to effect the original

    design, the Field Engineer shall re-evaluate and inform the result to the

    Construction Manager and Field QC Engineer.

    5.6.5. If repaired, Field QC Engineer confirms the passing of the Final Inspections,

    removes the non-conformities identification and sends it to next process.

    5.6.6. If scrapping the non- conformities product, the Construction Manager, together

    with relevant personnel, separate it from others.

    5.7. FINAL DOCUMENTATION AND RECORDS

    5.7.1. All reports of examination, inspection, tests, non-conformities and changes issued

    during installation works will be collected, checked and signed by the concerned

    Field QC Engineer and/or Superintendent.

    The documents are to be prepared shall be taken to prevent deterioration,

    damages and losses.

    5.7.2. The above documents will be checked by the Field QC Team for completeness

    and adequacy with the QA Plan prescription and Contract requirements.