Purple Line Extension Updates on La Cienega and Rodeo Stations November 8, 2017 1

Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

  • Upload
    others

  • View
    10

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Purple Line Extension Updates on La Cienega and Rodeo Stations November 8, 2017

1

Page 2: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Agenda

2

• Project Overview

• Section 1 Construction Updates

• Wilshire/La Cienega Station

• La Cienega Decking

• Decking Overview

• Schedule

• Detours

• Safety

• Section 2 Pre-Construction Updates• Rodeo Drive Station

• Advance Utility Relocation (AUR)• SCE Phase I, underway• SCE Phase II, future

power outage• SoCal Gas and AT&T

• Geotechnical Investigation• Demolition of former Ace

Gallery• Proposed MOA for AUR

• Business Interruption Fund

• Questions & Answers

Page 3: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Purple Line ExtensionProject Alignment

3

Page 4: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Sections 1, 2 & 3 Status

4

Under Construction Forecasted ScheduleSection Section 1 Section 2 Section 3

Length 3.92 Miles 2.59 Miles 2.59 Miles

New Stations Wilshire/La BreaWilshire/FairfaxWilshire/La Cienega

Wilshire/RodeoCentury City/ Constellation

Westwood/UCLAWestwood/VA Hospital

Pre-Construction Activities

Current - 2016 2016 - 2018 2016 – 2018*

Construction 2015 - 2023 2018 – 2024* 2018 – 2024*

Operations 2023 2024* 2024*

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

*Metro’s goal is to complete the entire Purple Line Extension by 2024 if Federal matching funds for Section 3 are secured.

Page 5: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Section 1Wilshire/La Cienega Station

5

Page 6: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega Station

6

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

Page 7: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega Station*As of November 2017, subject to change

7

Page 8: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega Station Decking Overview

8

• Construction of a concrete deck on Wilshire Bl, which will serve as a temporary roadway while construction proceeds underground. This construction spans the width of Wilshire Bl

• Location: Wilshire Bl between La Cienega Bl and San Vicente Bl, and in the Wilshire/La Cienegaintersection

• This work occurs under full weekend closures of Wilshire Bland La Cienega Bl

Page 9: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega DeckingWork zone

9

Approximate location of decking work zone at Wilshire Bl/La Cienega Bl

GALE LAYDOWN

YARDLA CIENEGALAYDOWN

YARD

Page 10: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega StationWeekend Closures Schedule

Wilshire Bl/La Cienega Bl Weekend Closures Schedule• Approximately 17 weekend closures• Scheduled in 3 phases• Started September 8, 2017

Phase 1: Wilshire Bl between La Cienega Bl and San Vicente Bl – COMPLETE

Phase 2: Wilshire/La Cienega intersection – COMPLETE• 4 weekends

Phase 3: Wilshire Bl between La Cienega Bl and San Vicente Bl• 11 weekends • Started November 3rd

10

Page 11: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/La Cienega StationDecking Construction

11

Placing deck beams on Wilshire Bl

Page 12: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Phase 3: East/West DetourWilshire Bl between La Cienega Bl and San Vicente Bl

12

Closures:• Westbound Wilshire Bl

will be closed at San Vicente Bl

• Eastbound Wilshire Bl will be closed at Robertson Bl

Local Access:

• Maintained to Wilshire Bl,La Cienega Bl open during this phase

Detours:

• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente BlWilshire Bl

• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson BlWilshire Bl

Page 13: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Bus DetoursWeekend Full Closures

Bus Detour Route will follow Traffic Detour:

• Eastbound: Wilshire Bl Robertson Bl Burton Way San Vicente BlWilshire Bl

• Westbound: Wilshire Bl San Vicente Bl Burton Way Robertson BlWilshire Bl

13

For information regarding changes to Metro service, please call 323.GoMetro or visit: https://www.metro.net/service/advisories/

720/20 Wilshire bus stops for Wilshire/La Brea, Wilshire/Fairfax and Wilshire/La Cienegahave been relocated to temporary locations away from the construction zone and will remain in place until construction is completed

Page 14: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Help Us Keep You Safe

14

Purple Line Extension24/7 Project Hotline - 213.922.6934Email – [email protected]

On Metro TransitSee Something, Say Something888-950-SAFE (7233)

Construction Safety Awareness ProgramGlyssa Alcazar, Community Relations OfficerEmail: [email protected]: 323.900.2192

City of Beverly [email protected] Works Customer Service: (310) 285-2467

Page 15: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Section 2Wilshire/Rodeo Station

1515

Page 16: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Purple Line ExtensionSection 2 Agenda

16

• Rodeo Drive Station• Advance Utility Relocation (AUR)

• SCE Phase I, underway• SCE Phase II, future power outage• SoCal Gas and AT&T

• Geotechnical Investigation• Demolition of former Ace Gallery• Proposed MOA for AUR

Page 17: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Purple Line ExtensionSection 2 Alignment

17

Page 18: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wilshire/Rodeo Station

Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr

18

Page 19: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Advanced Utility Relocation

Page 20: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Southern California EdisonRed=power

Page 21: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

• Sunday 10am-6pm, Monday-Friday 9am-4pm

• Sun – Wed: Wilshire with turn restrictions

• Thurs-Fri: Reeves or Wilshire with no turn restrictions

• City of Beverly Hills/Metro traffic engineers will monitor traffic

• Local Access Only signs

• Signal and crosswalk timing adjustments

• Traffic Control Officers (TCO)

• Beverly Hills Police Department support

• Any other adjustments as needed to work plans, traffic plans or detours

• Monitor bus stops and zones

SCE Advanced Utility RelocationMonitoring and Adjustment

21

Page 22: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Wayfinding Signage

22

Page 23: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

• SCE Phase 1: September 5, 2017

• SCE Phase 2: January 2018

• SCG: February 2018

• AT&T: February 2018

Advanced Utility RelocationWilshire/Rodeo Station

Rendering of AUR work23

Page 24: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

• Cable Pulling: 3 weeks, anticipated January 2018

• Utility Interruption: Two 8-hour outages per circuit

• Anticipated January 2018

• 3 separate circuits impacted

• Direct engagement to impacted businesses and one residential

unit

• Same traffic plans as SCE Phase 1

SCE Phase 2

24

*Pending City Council Approval

Page 25: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationCombined Traffic Control

Starting February 2018

• SCG and AT&T will work simultaneously within work zone• Will reduce overall duration of work• Work is scheduled from February through August 2018

• Stage 1-3 will look similar to SCE• Work is set up in morning and taken down each night• Will accommodate awards season

• Stage 4 -8 will take place behind K-rail• K-rail to remain 24/7 and work will take place behind it during approved

working hours• Set up will take place after awards season (March 5, 2018)

25

*Pending City Council Approval

Page 26: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 1: 16 days / Sun.: 10am-6pm, Mon.-Wed.: 9am-4pm

26

Page 27: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 4-7 Traffic Proposal

• Medians and parking removed from work zone

• Buses relocated outside of work zone

• Wilshire Bl two lanes each direction from west of Beverly Dr to east of Canon Dr

Example on Wilshire Bl

27

Page 28: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 4: 34 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

28K-Rail 24/7

Page 29: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Purpose of Memorandum of Agreement (MOA)

• Establish conditions and procedures for construction

• Minimize impacts to the Community

• Establish compliance monitor and enforcement process

29

Page 30: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

30

Key Terms of the MOA

• Enforcement of Conditions

• Independent Compliance Monitor

• Allowable Work Hours

• Holiday Moratorium

• Service Interruptions

• Traffic Impacts

• On-Street Parking

• Noise Standards

• Light Mitigation

• Traffic Mitigation Conditions

• Business Mitigation Assistance

• Notifications Process

Page 31: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Proposed Memorandum of Agreement (MOA)AUR

Legally binding document between City and Metro• Sets allowable work hours for each activity

• Mostly day work

• Service interruptions at night

• Provides details on required mitigations

• Holiday Moratorium

• Noise Limits

• Parking Replacement

• Business Mitigation Assistance

• Aesthetics of signage and construction fencing

• Bus Relocation – for duration of construction, installed before Phase 4 of SCE/AT&T (krail)

• Details violations and penalties

31

*Pending City Council Approval

Page 32: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AURHoliday Moratorium

• New Year’s Day

• Martin Luther King Jr. Day

• President’s Day

• Mother’s Day

• Memorial Day

• Father’s Day

• Easter Sunday

• The First Two Days of Passover

32

Utility cutover or surface work in the City Rights-of-Way shall be prohibited between the Saturday after Thanksgiving Day through New Year’s Day, except that cable pulling activities during the work hours provided above may occur through December 14th during this holiday moratorium period.

• Independence Day

• Labor Day

• Rosh Hashanah

• Yom Kippur

• Thanksgiving Day

• The Friday after Thanksgiving

• Christmas Day

Page 33: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AUR5 Step Noise Plan

33

Metro 5 Step Noise Plan

• Training

• Scheduling

• Noise Control Measures• Movable noise barriers

• Low impact back up alarms

• Stage equipment away from residences and hotels

• Solar powered equipment

• Noise barrier fencing at staging yards

• Monitoring

• Response

Page 34: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AURNoise Mitigation

34

Except by written permission from the City during emergencies, sawcutting, jackhammering, and the use of vacuum trucks are prohibited at the following times and locations:

• 12pm to 2:30pm, Monday through Saturday, on N Canon Dr

• 6pm to 9am, Monday through Friday, on all streets

• 6pm to 10am, Saturday through Sunday, on all streets

Page 35: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AURParking Mitigations

35

Replacement parking – provide 1 parking spot for each parking spot Metro takes for construction:

• Replacement parking will be in suitable distance from removed spot

• On-street signage

• Postcards provided to local businesses

• Web and social media campaign

• Advertisement in local papers

Page 36: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AURBusiness Mitigation Assistance (BMA)

36

• 24/7 Hotline with live-person

• Advertising

• Eat Shop Play Beverly Hills

• Coordination with BH Chamber of Commerce and My Beverly Hills campaign

• Coordination with BH Tourism and Visitors Bureau and Love Beverly Hills campaign

• Parking Mitigation

• Banners and signage (Aesthetic Treamtment)

• Communications, Outreach and Engagement

Page 37: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

MOA – AURNorth Canon Traffic Study

37

• Feasibility analysis of options to promote traffic flow to North Canon businesses

• Administered by City of Beverly Hills, paid for my Metro

• Includes study of temporary closure of N. Canon at Wilshire

• Two community meetings required before recommendations implemented

• Requires recommendation to City Council by March 2018

Page 38: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

8

• Gather additional soil information to validate existing data and characterize subsurface conditions for the design and construction of stations, tunnels, and cross passages• Cross passages connect the two tunnels and house mechanical and electrical

equipment along the alignment

• Install groundwater monitoring wells and gas probes to be used for monitoring prior to and during construction

Geotechnical Site InvestigationPurpose of Investigation

Page 39: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Geotechnical Site InvestigationSchedule

• Begin work on Monday November 13, 2017

• Completion of work by February 2018

• Schedule: 3 to 5 days per boring location

• Each shift: 2 to 3 hours spent on set-up and breakdown (including traffic control and noise mitigation efforts)

• Proposed work hours:

• Nighttime: 8pm – 6am

• Daytime: 9am – 4pm

39

Page 40: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Geotechnical Site InvestigationTraffic Control

ALL TURN LANES OPEN FOR USE

Typical Traffic Control for Work Zone in Outside Lanes

40

Page 41: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Demolition of 9430 Wilshire BlFormer Ace Gallery, future Construction Staging Yard

41

Page 42: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Demolition of 9430 Wilshire BlFormer Ace Gallery

Site Address: 9430 Wilshire Blvd

• 2-Story Building on the corner of Wilshire Bl and Reeves Dr

Schedule

• Anticipated Start in January 2018

• Estimated Duration of Demolition Activities: 5-7 weeks

Traffic Impacts

• Temporary Lane Closure along Wilshire Bl (approximately 2 weeks)

• Temporary Turn Restriction on Reeves Dr

• Sidewalk/Partial Lane Closure along Reeves Dr (duration of demolition)

• Pedestrian protection to be installed

42

*Pending City Council Approval

Page 43: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Dust Mitigation• Water used to spray demo

area

Noise Mitigation• Equipment installed with

low-noise mufflers and noise blankets on fencing around work area

Protection of the Park• Fencing/barrier around work

area including noise control measures.

Demolition of 9430 Wilshire BlFormer Ace Gallery

Example of noise mitigation blanket

43

Page 44: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Next StepsWilshire/Rodeo Station

44

City Council on November 21, 2017

• Approval of remaining AUR work

– SCE Phase II

– SCG/AT&T

• Approval of AUR Memorandum of Agreement

City Council on January 9, 2018

• Ace Gallery Demo permit

Notification process

• Hand delivered, email, website, social media

Continued Outreach and Communication

• Monthly meeting – 2nd Wednesday of each month at City of Beverly Hills City Hall

• “Traffic Alert” in local newspapers

• Construction notices

• Online and social media ads

Page 45: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Helping local businesses as we build.Update as of 11/3/17

Page 46: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas

> Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements

> Grant amount determined by loss of business revenue related to period of construction disruption

> To date, more than $11.4 million awarded to 252 small businesses along all three project areas

Page 47: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

BIF Grant Award Update

> Purple Line Extension, Section 1

> BIF Grants Awarded: 125

> BIF Grant Amount Awarded: $2,982,547.49

> Number of small businesses awarded: 54

> BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

> Purple Line Extension, Section 2

> BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

Page 48: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Updates on La Cienega and Rodeo Stations

Wednesday, December 13, 2017

6:30pm – 8pm

Beverly Hills City HallMunicipal Gallery455 N Rexford Dr

Beverly Hills, CA 90210

48

Next Community MeetingBeverly Hills

Page 49: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

Stay in Touch

49

Page 50: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 2: 20 days / Sun: 10am-6pm, Mon-Wed: 9am-4pm

5050

Page 51: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 2A: 3 days / Sun: 10am-6pm, Mon-Wed: 9am-4pm

51

Page 52: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 3: 9 days / Sun: 10am-6pm, Mon-Wed: 9am-4pm

52

Page 53: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 5: 5days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

53

K-Rail 24/7

Page 54: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

54

Page 55: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

55

K-Rail 24/7

Page 56: Purple Line Extension - Metro · 2017. 11. 9. · 2015 - 2023. 2018 – 2024* 2018 – 2024* Operations. 2023. 2024* 2024* ... • Started September 8, 2017 Phase 1: Wilshire Bl between

SCG and AT&T Utility RelocationStage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

K-Rail 24/7

56