Project Status Report (Weekly)

Embed Size (px)

DESCRIPTION

Subject: Project ManagementProject Status Report (Weekly) during Progress Meeting, Site Meeting

Citation preview

  • PROJECT STATUS REPORT (WEEKLY)

    Project Name 99-Storey Mixed-Use Development Skyscraper

    Project Summary The quality assurance is delayed as the tester is on vacation. The development is on track.

    Project Code AR13B

    Project Manager Ling Hua Yin

    Status Date 10-July-2015

    Project Key Parameters Comments

    Schedule On-Track / At-Risk / Off-track The project is 45% complete.

    Quality On-Track / At-Risk / Off-track Test case prep is done. Execution in progress.

    Scope On-Track / At-Risk / Off-track All ok.

    Budget On-Track / At-Risk / Off-track Total : RM99,000,000 Spent : RM200,000 Remaining : RM98,800,000

    Risks On-Track / At-Risk / Off-track No major risks.

    Issues On-Track / At-Risk / Off-track No major issues.

    Project Schedule 3 July 27 July

    Analysis Fri 26 Jun Thurs 2 July

    Build Fri 3 July -

    Thurs 23 July

    Test Case

    Testing Fri 24 July

    Thurs 30 July

    Implement Fri 31 July - Thurs 6 Aug

    Close Fri 7 Aug

    Thurs 13 Aug

    Project Risks and Issues Risk / Issue Risk / Issue Description Owner Status

    Risk 1 No major risk / issue Open

    Today