Upload
alina-cristina-vranceanu
View
227
Download
0
Embed Size (px)
Citation preview
8/3/2019 Product Cost Process
1/48
ChapterChapter1717
Process Cost SystemsProcess Cost Systems
Financial and Managerial Accounting
8th Edition
Warren Reeve Fess
PowerPoint Presentation by Douglas CloudProfessor Emeritus of Accounting
Pepperdine University
Copyright 2004 South-Western, a divisionof Thomson Learning. All rights reserved.
Task Force Image Galleryclip art included in this
electronic presentation is used with the permission ofNVTech Inc.
8/3/2019 Product Cost Process
2/48
Some of the action has been automated,
so click the mouse when you see this
lightning bolt in the lower right-handcorner of the screen. You can point and
click anywhere on the screen.
8/3/2019 Product Cost Process
3/48
1. Distinguish between job order costing
and process costing systems.
2. Explain and illustrate the physical flows
and cost flows for a process
manufacturer.
3. Calculate and interpret the accounting
for completed and partially completedunits under the fifo method.
4. Prepare a cost of production report.
ObjectivesObjectives
After studying thisAfter studying this
chapter, you shouldchapter, you should
be able to:be able to:
8/3/2019 Product Cost Process
4/48
5. Prepare journal entries for transactions
of a process manufacturer.
ObjectivesObjectives
6. Use cost of production reports fordecision making.
7. Contrast just-in-time processing with
conventional manufacturing practices.
8/3/2019 Product Cost Process
5/48
Job Order Cost System
Job CostSheets
Dept. A and
Dept. B
Comparing Job OrderComparing Job Order
Costing and Process CostingCosting and Process Costing
Direct materialsDirect materials
Factory overheadFactory overhead
Direct laborDirect labor
Work in ProcessWork in Process
AccountAccount to Finishedto FinishedGoodsGoods
8/3/2019 Product Cost Process
6/48
Process Cost System
DirectDirect
materialsmaterials
Work in ProcessWork in Process
AccountAccount
Work in ProcessWork in Process
AccountAccount
DEPT. A DEPT. B
FactoryFactory
OverheadOverhead
DirectDirect
LaborLabor
FactoryFactory
OverheadOverhead
DirectDirect
LaborLabor
to Finishedto Finished
GoodsGoods
Comparing Job OrderComparing Job Order
Costing and Process CostingCosting and Process Costing
8/3/2019 Product Cost Process
7/48
determine aproduct costby measuring the amount
of direct materials and direct labor used andallocating overhead costs.
allocate overhead using apredetermined overheadrate (or activity-based costing).
maintain perpetual inventory records with subsidiaryledgers forMaterials, Work in Process, andFinished Goods.
Both systems:Both systems:
Comparing Job OrderComparing Job Order
Costing and Process CostingCosting and Process Costing
8/3/2019 Product Cost Process
8/48
Physical Flows for a Process ManufacturerPhysical Flows for a Process Manufacturer
ScrapMetal
Materials
MeltingMelting
DepartmentDepartment
CastingCasting
DepartmentDepartment
8/3/2019 Product Cost Process
9/48
Molten
metal
transferred
fromMelting
To finished goods
CastingCasting
DepartmentDepartment
MeltingMelting
DepartmentDepartment
Physical Flows for a Process ManufacturerPhysical Flows for a Process Manufacturer
8/3/2019 Product Cost Process
10/48
Materials WIP Melting
Factory OH Melting
DMDMPurchases ofdirect and
indirectmaterials
Direct materials used in productionDMDM
DMDM
Finished Goods
Cost of Goods Sold
Factory OH Casting
WIP Casting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
11/48
Materials WIP Melting
DMDM
DLDL
DMDM
Direct labor used in productionDLDL
Purchases ofdirect and
indirectmaterials
Finished Goods
Cost of Goods Sold
Factory OH Casting
Actualcosts
incurred
WIP Casting
Factory OH Melting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
12/48
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDM
Indirect materials used in productionIMIM
Purchases ofdirect and
indirectmaterials
IMIM
Factory OH CastingFactory OH Melting
Actualcosts
incurred
Actualcosts
incurred
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
13/48
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDM
Factory overhead appliedFOAFOA
Purchases ofdirect and
indirectmaterials
IMIM
Factory OH Casting
Actualcosts
incurred
FOAFOA Actualcosts
incurred
FOAFOA
Factory OH Melting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
14/48
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDM
Cost transferred out/transferred inTO/TITO/TI
Purchases ofdirect and
indirectmaterials
IMIM
Factory OH Casting
Actualcosts
incurred
FOAFOA Actualcosts
incurred
FOAFOA
TOTO TITI
Factory OH Melting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
15/48
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDMPurchases ofdirect and
indirectmaterials
IMIM
Factory OH Casting
Actualcosts
incurred
FOAFOA Actualcosts
incurred
FOAFOA
TOTO TITI
DLDL
Factory overhead appliedFOAFOA
Direct labor used in productionDLDL
FOAFOA
FOAFOA
Factory OH Melting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
16/48
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDMPurchases ofdirect and
indirectmaterials
IMIM
Factory OH Casting
Actualcosts
incurred
FOAFOA Actualcosts
incurred
FOAFOA
TOTO TITI
DLDL
FOAFOA
FOAFOA
Cost transferred out/transferred inTO/TITO/TI
TOTO
TITI
Factory OH Melting
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
8/3/2019 Product Cost Process
17/48
Cost Flows for a Process ManufacturerCost Flows for a Process Manufacturer
Materials WIP Melting
Finished Goods
WIP Casting
Cost of Goods Sold
DMDM
DLDL
DMDMPurchases ofdirect and
indirectmaterials
IMIM
Factory OH Casting
Actualcosts
incurred
FOAFOA Actualcosts
incurred
FOAFOA
TOTO TITI
DLDL
FOAFOA
FOAFOA
Cost of goods soldCOGSCOGS
TOTO
TITI COGSCOGS
COGSCOGS
Factory OH Melting
8/3/2019 Product Cost Process
18/48
8/3/2019 Product Cost Process
19/48
Melting Department of McDermott Steel Inc.
Inventory in process, July 1, 500 tons:
Direct materials cost, 500 tons $24,550
Conversion costs, 500 tons, 70% completed 3,600
Total inventory in process, July 1 $28,150Direct materials cost for July, 1,000 tons 50,000
Conversion costs for July 9,690
Goods transferred to Casting in July, 1,100 tons ?
Inventory in process, July 31, 400 tons, 25%complete as to conversion costs ?
8/3/2019 Product Cost Process
20/48
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
8/3/2019 Product Cost Process
21/48
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
Transferred
1,100 Tons
In a perpetual
inventory system,
outflows are recorded
as they occur.
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
8/3/2019 Product Cost Process
22/48
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
Transferred
1,100 Tons
Ending
Inventory
400 Tons
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
Beginning InventoryBeginning Inventory 500 Tons500 Tons11
8/3/2019 Product Cost Process
23/48
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
Transferred
1,100 Tons
Ending
Inventory
400 Tons
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
Beginning InventoryBeginning Inventory 500 Tons500 Tons11
Started & Completed ? Tons+22
8/3/2019 Product Cost Process
24/48
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
Transferred
1,100 Tons
Ending
Inventory
400 Tons
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
Beginning InventoryBeginning Inventory 500 Tons500 Tons11
Started & Completed 600 Tons+22
8/3/2019 Product Cost Process
25/48
BeginningBeginning
InventoryInventory
500 Tons500 Tons
Work in Process Melting
StartedStarted
1,000 Tons1,000 Tons
Transferred
1,100 Tons
Ending
Inventory
400 Tons
Beginning InventoryBeginning Inventory 500 Tons500 Tons11
Started & Completed 600 Tons+22
=
Transferred OutTransferred Out 1,100 Tons1,100 Tons
+
Ending Inventory 400 Tons33
Total units 1,500 Tons=
Step 1: Determine the Units to be Assigned CostsStep 1: Determine the Units to be Assigned Costs
Total tons to beTotal tons to be
assigned costsassigned costs
8/3/2019 Product Cost Process
26/48
The equivalent units ofproduction are the number of
units that could have beencompleted within a given
accounting period.
Step 2: Calculate
equivalent
units ofproduction
8/3/2019 Product Cost Process
27/48
Step 2: Calculate Equivalent Units of ProductionStep 2: Calculate Equivalent Units of Production
Materials Equivalent UnitsMaterials Equivalent UnitsTotal Percent Equivalent
Units Added Units
Inventory in process, July 1 500 0% 0
Started and completed in July 600 100% 600Transferred out to Casting Dept. 1,100 600
Inventory in process, July 31 400 100% 400
Total tons to be assigned cost 1,500 1,000
8/3/2019 Product Cost Process
28/48
Step 2: Calculate Equivalent Units of ProductionStep 2: Calculate Equivalent Units of Production
500500EU ofEU ofmaterialsmaterials
500500 tons beginning inventorytons beginning inventory
100% materials added in June100% materials added in June
JULY 1
600600 EU ofEU ofmaterialsmaterials
600 tons started and completed
100% materials added in July
JULY 31
400 EU ofmaterials
400 tons ending inventory
100% materials added in July
1,000 Equivalent Units
Inventory in
process, July 1
Note: Startedand completed
Inventory inprocess, July 31
No materialsequivalent units
added to beginninginventory for July
8/3/2019 Product Cost Process
29/48
Step 2: Calculate Equivalent Units of ProductionStep 2: Calculate Equivalent Units of Production
Conversion Equivalent UnitsConversion Equivalent Units
Inventory in process, July 1 500 30% 150
Started and completed in July 600 100% 600
Transferred out to Casting Dept. 1,100 750
Inventory in process, July 31 400 25% 100
Total tons to be assigned cost 1,500 850
Total Percent Equivalent
Units Added Units
8/3/2019 Product Cost Process
30/48
350350 EUEU
500 tons beginning inventory
70% completed for70% completed forconversion in Juneconversion in June
JULY 1
600600 EUEU
600 tons started and
completed
100% completed for
conversion in July
JULY 31
100100EUEU
400 tons ending inventory
25% completed for25% completed forconversion in Julyconversion in July
850 Equivalent Units
Inventory inprocess, July 1
Step 2: Calculate Equivalent Units of ProductionStep 2: Calculate Equivalent Units of Production
150150EUEU
300300 EUEU
Inventory in
process, July31 (75% to becompleted forconversion in
August)
30%
completed
for
conversion
in July
8/3/2019 Product Cost Process
31/48
Step 3: Determine the Cost per Equivalent UnitStep 3: Determine the Cost per Equivalent Unit
Equivalent UnitsDirect Materials Conversion
Inventory in process, July 1 0 150
Started and completed in July
(1,100 500) 600 600Transferred out to Casting Dept.
in July 600 750
Inventory in process, July 31 400 100
Total tons to be assigned cost 1,000 850
8/3/2019 Product Cost Process
32/48
Beginning
Inventory
$28,150
Work in Process Melting
Materials
$50,000Conversion
Costs
$9,690
Conversion Equivalent Unit CostConversion Equivalent Unit Cost
Direct Materials Equivalent Unit CostDirect Materials Equivalent Unit Cost
$11.40
per EUof con-
version
=
$50,000 direct materials cost
1,000 direct materials equivalent units
$9,690 conversion cost
850 conversion equivalent units
Step 3: Determine the Cost per Equivalent UnitStep 3: Determine the Cost per Equivalent Unit
$50.00
per EU of
DM
=
8/3/2019 Product Cost Process
33/48
Inventory in process, July 1
beginning balance $28,150
Equivalent units for completing
the July in-process inventory 0 150
Equivalent unit cost x $50.00 x $11.40
Cost of completed July 1 in-
process inventory $0 $1,710 1,710
Cost of July 1 in-process
inventory transferred to
Casting Department $29,860
Step 4: Allocate Costs to Transferred andStep 4: Allocate Costs to Transferred and
Partially Completed UnitsPartially Completed Units
Direct Materials Conversion TotalCosts Costs Costs
8/3/2019 Product Cost Process
34/48
Units started and completed
in July 600 600
Equivalent unit cost x $50.00 x $11.40
Cost to complete the units
started and completed in
July $ 30,000 $ 6,840 $36,840
Direct Materials Conversion TotalCosts Costs Costs
Step 4: Allocate Costs to Transferred andStep 4: Allocate Costs to Transferred and
Partially Completed UnitsPartially Completed Units
8/3/2019 Product Cost Process
35/48
Equivalent units in ending
inventory 400 100
Equivalent unit cost x $50.00 x $11.40
Cost of ending inventory $ 20,000 $ 1,140 $21,140
Direct Materials Conversion TotalCosts Costs Costs
Step 4: Allocate Costs to Transferred andStep 4: Allocate Costs to Transferred and
Partially Completed UnitsPartially Completed Units
8/3/2019 Product Cost Process
36/48
Beginning
Inventory
$28,150
Materials
Costs
$50,000
Started and
Completed
$36,840
Beginning
Inventory
$29,860
Work in Process Melting
Total Costs
Charged
$87,840
Ending
Inventory$21,140
Conversion
Costs
$9,690
Total Costs
Assigned
$87,840
M 600 x 100% x $50.00 = $30,000
C 600 x 100% x $11.40 = 6,840
$36,840
M 400 x 100% x $50.00 = $20,000
C 400 x 25% x $11.40 = 1,140$21,140
Beginning cost $28,150
M 500 x 0% x $50.00 = 0
C 500 x 30% x $11.40 = 1,710
$29,860
Total Costs Assigned $87,840
Costs
Step 4: Allocate Costs to Transferred andStep 4: Allocate Costs to Transferred and
Partially Completed UnitsPartially Completed Units
8/3/2019 Product Cost Process
37/48
A cost of production reportis
prepared for each processingdepartment at periodical intervals.
8/3/2019 Product Cost Process
38/48
Cost of Production ReportCost of Production Report
The cost of production report provides thefollowing production quantity and cost data:
The units for which the department
is accountable and the deposition ofthose units.
The production costs incurred by thedepartment and the allocation ofthose costs between completed and
partially completed units.
8/3/2019 Product Cost Process
39/48
A cost of production reportalso is used to control costs.
8/3/2019 Product Cost Process
40/48
UnitsUnits
Step 1 Step 2
Units charged to production:
Inventory in process, July 1 500
Received from materials 1,000
Total units accounted for 1,500Units to be assigned cost:
Inventory in process, July 1
(70% complete) 500 0 150
Started and completed in July 600 600 600
Transferred to CastingDept. 1,100 600 750Inventory in process, July 31
(25% complete) 400 400 100
Total units to be assigned cost 1,500 1,000 850
Whole DirectUnits Materials Conversion
Equivalent Units
Cost of Production ReportCost of Production ReportMeltingDepartmentMeltingDepartment
8/3/2019 Product Cost Process
41/48
CostsCosts
Direct Materials Conversion Total Costs
Costs
Step 3
Unit costs:
Total costs for July in
Melting Department $50,000 $9,690
Total equivalent units
(from Slide 43) 1,000 850Cost per equivalent unit $ 50.00 $11.40
Cost of Production ReportCost of Production ReportMeltingDepartmentMeltingDepartment
8/3/2019 Product Cost Process
42/48
CostsCosts Direct Conversion TotalMaterials Costs Costs
Step 4
Costs charged to production:
Inventory in process, July 1 $28,150
Cost incurred in July 59,690
Total costs accounted for $87,840
Costs allocated to completed and
partially completed units
Inventory in process, July 1 $28,150
To complete inventory of July 1 $ 0 $1,710 1,710
Started and completed in July 30,000 6,840 36,840
Transferred to CastingDept. $66,700Inventory in process, July 31 $20,000 $1,140 21,140
Total costs assigned $87,840
Cost of Production ReportCost of Production ReportMeltingDepartmentMeltingDepartment
8/3/2019 Product Cost Process
43/48
Journal Entries for a Process Cost SystemJournal Entries for a Process Cost System
Materials 62,000
Accounts Payable 62,000
Work in ProcessMelting 50,000
Factory OverheadMelting 4,000Factory OverheadCasting 3,000
Materials 57,000
Work in ProcessMelting 5,000
Work in ProcessCasting 4,500
Wages Payable 9,500
Factory OverheadMelting 1,000
Factory OverheadCasting 7,000
Accumulated Depreciation 8,000
a. Materials
purchased on
account.
b. Direct and indirect
materialsrequisitioned.
c. Direct labor
used.
d. Depreciation
expenses.
Transaction Journal Entry Debit Credit
8/3/2019 Product Cost Process
44/48
Work in ProcessMelting 4,690
Work in ProcessCasting 9,640
Factory OverheadMelting 4,690
Factory OverheadCasting 9,640
Work in ProcessCasting 66,700Work in ProcessMelting 66,700
e. Factory overhead
applied.
f. Costs transferred toCasting
Department
g. Casting
Department
transferred toFinished Goods
h. Goods sold.
Journal Entries for a Process Cost SystemJournal Entries for a Process Cost System
Finished Goods 78,600
Work in ProcessCasting 78,600
Cost of Goods Sold 73,700
Finished Goods 73,700
Transaction Journal Entry Debit Credit
8/3/2019 Product Cost Process
45/48
JustJust--inin--Time Processing (JIT)Time Processing (JIT)
JIT is a business philosophy that focuses onreducing time and cost and eliminating poorquality.
JIT organizes work cells that perform several
manufacturing steps.Workers are cross-trained to perform more than
one task. This provides flexibility and workerpride and involvement in the final product.
Because products have limited movementbetween departments, the nonvalue-added costof transporting products and parts is reduced.
8/3/2019 Product Cost Process
46/48
UpholsteryUpholstery
Dept.Dept.
AssemblyAssembly
Dept.Dept.
JustJust--inin--Time Processing (JIT)Time Processing (JIT)
CuttingCuttingDept.Dept.
Traditional Production Line
DrillinDrilling Dept.g Dept.
SandingSandingDept.Dept.
StainingStainingDept.Dept.
VarnishingVarnishing
Dept.Dept.
8/3/2019 Product Cost Process
47/48
JustJust--inin--Time Processing (JIT)Time Processing (JIT)
Just-in-Time Production Line
Work Center OneWork Center OneCutting drilling
and sanding
Work Center TwoWork Center TwoStaining and
varnishing
Work Center ThreeWork Center ThreeUpholstery and
assembly
8/3/2019 Product Cost Process
48/48
The EndThe End
Chapter 17Chapter 17