Upload
dotuyen
View
218
Download
0
Embed Size (px)
Citation preview
Presented by John Augustyn Reclamation Approval Coordinator with
Alberta Environment and ParksSeptember 27, 2017
Income
Product
Continued value of land (equivalent land capability by means of conservation and reclamation)
Integrity of water
Something new(alternative end land uses)
Environmental Protection and Enhancement Act (1992 origin) – defines pits and reclamation; to construct, operate or reclaim a pit is an activity under the Act.
Activities Designation Regulation –registrations are required for any pit 5 hectares or larger (includes infrastructure and stockpiles) (aka Class I pit)
Conservation and Reclamation Regulation – any land being used for construction, operation or reclamation of a pit is “specified land” (no distinction of Class I or II); an operator must conserve specified land and reclaim specified land.
Code of Practice for Pits – standards and process (Activities Plans, full cost reclamation security, and reporting requirements)
Guide to the Code of Practice for Pits- detailed information for plans guiding conservation and reclamation.
Applications:◦ Activity plan
◦ Pre-disturbance assessment
◦ Soils
◦ Groundwater evaluation
◦ Current status if an operating pit
◦ Full cost security estimate representing next 5 years operations.
◦ Proposed end land uses
◦ Authorizations from municipalities
An activity within the water requires an approval. (Wet pit excavation, construction of end pit lakes)
A use of water will typically require a licence. (gravel washing, dust control)
Disturbance of wetlands requires authorization, but re-creation of wetlands through reclamation is a valid option.
No distinction for Class I or II pits.
Thorough assessment of site before disturbance guides conservation of soil.
Conservation of soil at the beginning allows reclamation of pit by maximizing soil placement.
Focus on topsoil (All of L, F, H & A horizons) & subsoil (B and C horizons to a maximum of 1.2 meters)
Stripping of topsoil for at least 5 meters from pit faces and stockpiled.
3m separation from other stockpiles
All topsoil is to be used strictly for reclamation of the pit.
Material movement to be complete
Site re-vegetated
Weeds have been managed
Water bodies constructed as authorized
Initiated by the registration holder by application.
Assessed by a reclamation inspector.
Target is minimum of 80% productivity of pre-site landbase.
AEP focus: Soil
Land
Water (surface and ground water)
Reclamation Security
Municipality focus: Land use / zoning (critical component)
Resident consideration such as noise and traffic